This document appears to be a Performance Work Statement (PWS) for a carpet installation contract opportunity. The key details are:

The 355th Training Squadron (355 TRS) at Davis-Monthan Air Force Base (DMAFB) requires the removal and installation of carpet tiles in building 4413, 2nd and 3rd floor hallways. The contractor shall provide and install an estimated 196 square yards of new carpet tile, 10 linear yards of new transition, and 250 linear yards of 4-inch wall base. The contractor must also skim coat the entire floor, provide maintenance manuals and warranty documents, and comply with various security, environmental, and safety requirements outlined in the PWS. The contract opportunity is identified as Solicitation Number FA487724QA316, with a required site visit and proposal submission timeline. No additional details are provided about pricing terms, set asides, or incumbent contractors.

View the file

Other files for this federal contract opportunity

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

20 May 2024 service(s). Measurements provided by the Government are estimated and the contractor is ultimately responsible for determining exact measurements.

1.1.7.1.1. Skim Coating. The contractor shall skim coat entire floor with cementitious floor patch to provide barrier from any remaining abatement chemicals and to give the floor the smoothness required for carpet installation.

1.1.7.2. New Flooring Requirement. The contractor shall provide and install an estimated 196 square yards of carpet tile from one of the approved Tier I carpet vendors.

1.1.7.2.1. Transition and Wall Base. The contractor shall install estimated 10 linear yards of new transition and 250 linear yards of 4 inch wall base. Color is dependent on which preference is selected for contract award, and will be selected by Government personnel upon contract award. No transition or wall base shall be reused.

1.1.7.3. Manual and/or Warranty Documents. Upon installation completion the contractor shall provide the building 4413 Facility Managers with two copies of all necessary maintenance manuals and warranty documents.

1.1.7.4. Equipment. Any equipment brought into the facility by the contractor shall remain secured in the facility or a suitable area within DMAFB, to include the patio, after each work day until the installation process is complete.

1.2. General Information

1.2.1. Quality Standards. All equipment, materials, and installation methodology shall conform to the requirements of all applicable laws and regulations, and manufacturer’s recommendations. All products and materials provided by contractor shall be new, of high quality, and free of faults and defects. All work related to this Performance Work Statement shall be completed in a professional manner by fully qualified contractor personnel.

1.2.1.1. Inspection of Services. The contractor’s work shall be subject to inspection at any time. The presence or absence of a Government inspector shall not relieve the contractor from strict compliance with the requirements in this performance work statement, nor shall the presence of an inspector relieve the contractor from any deficiency that may be noted during the final inspection. Upon completion of work, the contractor shall notify the Facility Managers so an inspection can be accomplished.

1.2.4. Safety. The contractor shall comply with all local, state and federal laws and safety regulations. Compliance with OSHA and other applicable laws and regulations for the protection of contractor employees is exclusively the obligation of the contractor, and the Government will assume no liability or responsibility for the contractor’s compliance or noncompliance with such responsibilities.

1.2.4.1. Safety Equipment. The contractor is responsible for providing all safety equipment for contractor employees. Contractor employees shall use proper safety equipment at all times during the performance of this contract, and shall perform all tasks in a safe manner. The Government has the right to terminate work if the contractor is practicing unsafe work practices or lacks proper safety equipment, at no cost to the Government. The Government may also terminate work if unsafe weather conditions exist during the contract.

1.2.4.2. Work Areas. The contractor shall, at all times, keep work areas free from accumulations of waste material, rubbish, tools, scaffolding, equipment, and materials. Upon completion of the job or when away from the work site, the contractor shall leave the work area and premises in a clean, neat, safe and workmanlike condition. The contractor is responsible for removal and proper disposal of all job related waste material at a permitted site.

1.2.4.3 Fire Prevention and Safety. Contractor employees shall comply with DMAFB Fire Protection Program, Air Force Occupational Safety & Health (OSHA), Air Force Occupational Safety, and the Fire Prevention and Health Program. Compliance with OSHA and other applicable laws and regulations for the protection of employees is exclusively the obligation of the contractor, and the government will assume no liability or responsibility for the contractor’s compliance or noncompliance with such responsibilities.

1.2.4.4. Smoking in Air Force Facilities. Contractors are advised that the Air Force has placed restrictions on the smoking of tobacco products in Air Force facilities. Air Force Instruction 40- 102, Tobacco Use in the Air Force, outlines the procedures used by the commander to control smoking in our facilities. Contractor employees and visitors are subject to the same restrictions as Government personnel. Smoking is permitted only in designated smoking areas.

1.2.5. Security Requirements

1.2.5.1. Pass and Identification Items. The contractor shall ensure the pass and identification items required for contract performance are obtained for employees and non-government owned vehicles.

1.2.5.2. Retrieving Identification Media. The contractor shall retrieve all identification media, including vehicle passes from employees who depart for any reason before the contract expires;

e.g. terminated for cause, retirement, etc., and turn them in to the issuing office.

1.2.5.3. Traffic Laws. Contractor employees shall comply with all base traffic regulations.

Contractor employees are subject to random vehicle speed control checks. Contractor personnel cited for speeding on the installation may suffer loss of base driving privileges, debarment from the base, or other administrative action.

1.2.5.4. Random Personnel and Vehicle Searches. Contractor personnel are subject to random personnel and vehicle searches. If contractor personnel refuse to be searched, they will be denied entry to the base, and may result in loss of base driving privileges, debarment from the base, or other administrative action.

1.2.5.5. Weapons, Firearms, and Ammunition. Contractor employees are prohibited from possessing weapons, firearms, or ammunition, on themselves or within their contractor owned vehicle or privately owned vehicle while on Davis-Monthan AFB.

1.2.5.6. For Official Use Only (FOUO). The contractor shall comply with DoD 5400.7-R, Chapter 4, DoD Freedom of Information Act (FOIA) Program requirements. This regulation sets policy and procedures for the disclosure of records to the public and for marking, handling, transmitting, and safeguarding FOUO material.

1.2.5.7. Reporting Requirements. Contractor personnel shall immediately report to an appropriate government authority any information or circumstances of which they are aware may pose a threat to the security of Department of Defense personnel, contractor personnel, resources, and classified or unclassified defense information.

1.2.6. Base Entry Requirements. The contractor shall obtain Government identification documents for all employees, by submitting an application to the Facility Managers. The contractor must provide the full name, social security account number (SSAN), driver’s license number (including state), and hours of required access, for each contractor employee. Any employee who does not have a driver’s license must provide another official form of picture ID, such as INS work permit or an Arizona ID (available through the Arizona Department of Transportation). Any employee desiring to bring a privately owned vehicle on Davis-Monthan AFB must provide proof of automobile registration and at least the minimum required liability insurance, as well as a valid driver’s license.

1.2.6.1. Contractor Vehicle Requirements. All vehicles used in the performance of the contract shall be properly registered and meet local, state, and federal safety and emissions requirements. The contractor shall operate vehicles to comply with base traffic regulations.

Vehicle-mounted communication equipment shall conform to all applicable base and federal frequency regulations and avoid conflict with existing frequencies.

1.3. Environmental Protection Compliance

1.3.1. Adherence to the Davis-Monthan Air Force Base Contractor Environmental Guide.

Adherence to this guide will help increase your company’s awareness of the installation’s Environmental Management System (EMS), and the environmental regulatory requirements that impact DMAFB. The environmental guide can be obtained from the Contracting Officer.

1.3.1.1. Environmental Management System (EMS) Awareness Training. The contractor shall comply with the DMAFB Contractor Environmental Guide in completing the required EMS Awareness Training prior to start of work.

1.3.1.2. Environmental Laws and Regulations. The contractor shall comply with all applicable Federal, State, and local laws, regulations, and requirements regarding environmental protection. In the event environmental laws/regulations/requirements change during the term of the contract, the contractor shall comply with such law/regulation as changed. The contractor is responsible for any penalties, fines, etc. resulting from violations. The contractor shall immediately notify the Facility Managers when violations occur, and cooperate fully with fire department personnel and Government investigators.

1.3.1.3. Environmental Permits. Contractors shall comply with all regulatory requirements to include permits if applicable. Pima County Department of Environmental Quality (PDEQ) and Arizona Department of Environmental Quality (ADEQ) require permits for asbestos removal or demolition as well as projects that require earth-moving or soil disturbance. These requirements may include storm protections. The contractor shall treat areas subject to dust producing activities with liquid palliatives which will not harm regrowth of vegetation, or other methods of dust control. The contractor shall also ensure methods to protect native plants, birds and wildlife are included in projects where required. All permit costs shall be considered as having been included as a factor in the contractor's bid price.

1.3.1.4. Hazardous Materials/Waste The contractor shall be responsible for the proper management of both hazardous and non-hazardous waste. The contractor shall segregate hazardous or regulated materials and non-hazardous or non-regulated materials and handle, transport, store, and dispose of those materials, in accordance with the Resource Conservation and Recovery Act, all applicable federal, state, and local statutes and regulations, and IAW Appendix C, Hazardous, PCB, and Universal Waste: Proper Management and Disposal, of the Contractor Environmental Guide. The contractor shall coordinate all hazardous shipments with the 355 Civil Engineer Squadron Hazardous Waste Program Manager (355 CES/CEIE) at 228- 4840.

1.3.1.5. Hazardous Material (HAZMAT) Handling. The contractor shall have approval from Hazardous Waste Program Manager (355 CES/CEIE) at 228-4840, in accordance with the Contractor Environmental Guide, prior to handling, using, and storing any chemicals, solvents, lubricants, and other products that require Safety Data Sheet (SDS) or Material Safety Data Sheet (MSDS) on the installation. The contractor shall plan, fill out, and submit a HAZMAT worksheet to the Facility Managers prior to bringing HAZMAT on the base - see Appendix A, Guidance For Submission Of Safety Data Sheets For Hazardous Material (HAZMAT) and Reporting of Hazmat Usage, and Attachment(s) A-1 to A-3 of the Contractor Environmental Guide for details. The contractor shall maintain one copy of the MSDS’s for each HAZMAT line item used within the work center.

1.3.1.6. Prohibited Substances/Chemicals. The contractor shall not use products that are, or contain Extremely Hazardous Substances (EHS), Ozone Depleting Substances (ODS), and/or Persistent Bio-accumulative and Toxic (PBT) chemicals. Any HAZMAT containing one of these banned substances will not be allowed on base. Contact the environmental office (355 CES/CEIE) at 228-7201 if you have any questions on materials.

1.3.1.7. Hazardous Materials/Waste Spills. The contractor shall take every reasonable precaution to prevent spills of HAZMAT, and immediately report any HAZMAT spills to the Facility Managers and base fire department by calling 228-3333, in accordance with Appendix J, HAZMAT Incident Response Procedures, of the DMAFB Spill Prevention, Control, and Countermeasure (SPCC) Plan. The contractor shall comply with this plan when handling and storing all oils and fuels. The Government will provide a copy of the SPCC Plan upon contract award. The contractor shall clean and dispose of all HAZMAT spills in accordance with local, state, and federal laws and regulations and the Contractor Environmental Guide. The contractor shall bear full financial obligation incurred from cleaning and disposing of HAZMAT spills, or release of HAZMAT within the confines of DMAFB by contractor employees.

1.3.1.7.1. Spill Containment Kits. The contractor shall ensure that all vehicles used for transport of HAZMAT on DMAFB, carry a spill containment kit capable of containing a spill, until first responders arrive. The contractor shall make spill containment kits available for inspection by Government personnel, upon request.

2.0. Government Provided Services

2.1. Physical Security. Government employees shall be responsible for safeguarding all government property and controlled forms provided for contractor use. At the end of each work period, all government facilities, equipment, and materials shall be secured by the provided escort.

2.1.1. Utilities. The Government will provide water and electricity inside of facility.

2.1.2. Conservation of Utilities. The contractor shall practice utility conservation and is responsible for operating under conditions that prevent the waste of utilities.

2.2. Emergency Services. The Government will provide security forces services (call 228-4444 for emergencies only), and fire protection services (call 228-3333). There are no emergency medical services available on DMAFB, therefore the contractor should call 911 for medical emergencies. If the contractor calls 911 from a Government phone, the contractor must tell the operator that they are calling from DMAFB.

3.0. Appendix