A.03_Drawings Specifications for W912ER22R0017 - 1 SECTION 01 11 00 ATCT Iraq.pdf
PDF 18 KB Posted
- Attached to
- Air Traffic Control Tower, Iraq
- Solicitation number
- W912ER22R00170002
About this file
This document provides specifications for the repair, restoration, and upgrade of an air traffic control tower at Imam Ali Air Base in Iraq under solicitation number W912ER22R00170002 issued by the Department of the Army Corps of Engineers Engineering District Middle East. The project scope involves restoring the structural integrity of the existing tower facility and upgrading its electrical, HVAC, fire suppression, plumbing, conveyance, and lightning protection systems. The contractor will be responsible for procuring all materials locally or from the Gulf Region and delivering them to the project site. The contractor must also provide security for its worksite and laydown areas within the base until beneficial occupancy is achieved. Notifications must be given for excavation work, material delivery times, and any salvage of existing equipment.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| B.08_Solicitaion Amendment(s) 0002 W912ER22R0017 Air Traffic Control Tower, Iraq.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Air Traffic Control Tower, Imam Ali Air Base, Iraq 460093
SECTION TABLE OF CONTENTS
DIVISION 01 - GENERAL REQUIREMENTS
SECTION 01 11 00
SUMMARY OF WORK -- REVISED BY AMENDMENT NO. 0002
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
1.1.2 Location
1.2 OCCUPANCY OF PREMISES
1.3 EXISTING WORK
1.4 LOCATION OF UNDERGROUND UTILITIES
1.4.1 Notification Prior to Excavation
1.5 DELIVERY SCHEDULE
1.5.1 Delivery Location
1.6 NOTIFICATION PRIOR TO EXCAVATION
1.7 SITE SECURITY
1.8 SALVAGE MATERIAL AND EQUIPMENT
PART 2 PRODUCTS
PART 3 EXECUTION
-- End of Section Table of Contents --
SECTION 01 11 00 Page 1
SECTION 01 11 00
SUMMARY OF WORK -- REVISED BY AMENDMENT NO. 0002
PART 1 GENERAL
1.1 WORK COVERED BY CONTRACT DOCUMENTS
1.1.1 Project Description
This effort shall provide for the repair, restoration and upgrade of the existing ATCT at Imam Ali Air Base, Iraq. The existing ATCT has been in various states of disrepair since 2011 with limited to no maintenance performed on the facility since that time. The repair, restoration and upgrade of the ATCT will include but is not limited to: complete structural integrity, electrical power, backup electrical power including diesel generators, Heating, Ventilation, and Air Conditioning (HVAC) systems, fire suppression systems, plumbing systems, conveyance systems, lightning grounding protection, doors, windows, floors and other building systems as required. The USACE intends to issue a design bid build (D-B-B) full and open, Firm Fixed Price contract to execute the restoration, repair and upgrade of the ATCT.
1.1.2 Location
This project is located at the Imam Ali Air Base located near Nasiriyah, Iraq, in southern Iraq, approximately 120 miles northeast of the city of Basra. The exact location will be shown by the Contracting Officer.
1.2 OCCUPANCY OF PREMISES
Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area. Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.
1.3 EXISTING WORK
In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:
a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.
b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.
1.4 LOCATION OF UNDERGROUND UTILITIES
Obtain digging permits prior to start of excavation, and comply with Installation requirements for locating and marking underground utilities.
Verify existing utility locations indicated on contract drawings, within
SECTION 01 11 00 Page 2 area of work. Contact local utility locating service a minimum of 48 hours prior to excavating, to mark utilities, and within sufficient time required if work occurs on a Monday or after a Holiday. Verify existing utility locations indicated on contract drawings, within area of work.
Identify and mark all other utilities not managed and located by the local utility companies. Scan the construction site with Ground Penetrating Radar (GPR), electromagnetic, or sonic equipment, and mark the surface of the ground, pier deck] or paved surface where existing underground utilities or utilities encased in pier structures are discovered. Verify the elevations of existing piping, utilities, and any type of underground or encased obstruction not indicated, or specified to be removed, that is indicated or discovered during scanning, in locations to be traversed by piping, ducts, and other work to be conducted or installed. Verify elevations before installing new work closer than nearest manhole or other structure at which an adjustment in grade can be made.
1.4.1 Notification Prior to Excavation
Notify the Contracting Officer at least 48 hours prior to starting excavation work.
1.5 DELIVERY SCHEDULE
Notify the Contracting Officer in writing at least 3 calendar days in advance of the date on which the materials and equipment are required.
Pick up materials and equipment no later than 30 calendar days after such date. When materials and equipment are not picked up by the 30th day, the Contractor will be charged for storage at the rate of $336.00 per 45 kg 3 cubic meters per month or fraction thereof. Materials and equipment will be available on or after 15 calendar days after the award of contract.
1.5.1 Delivery Location
The materials and equipment will be locally procured or from the Gulf Region and will be delivered to the project site at BIA. If the Iraqi Government has no need of the exiting furniture or shelving, then belongs to the contractor for salvage value or accepted disposal.
1.6 NOTIFICATION PRIOR TO EXCAVATION
Notify the Contracting Officer at least 15 days prior to starting excavation work.
1.7 SITE SECURITY
The contractor will need to provide their own site security at Imam Ali Airbase. The Iraqi Air Force will not be responsible for providing contractor site security), the mobilization area for the KTR will be inside the Imam Ali AB perimeter and near the project site (Air Traffic Control Tower). Ima Ali AB is secured by the Iraqi AF Security Force, however the KTR will be responsible to provide the security for his own site/laydown area within Imam Ali AB. The KTR will responsible to provide light security (guards who have been vetted & cleared without weapon authorization) for two locations (1 - mobilization area and 2 - the project site) until the work is completed and beneficial occupancy date (BOD) is achieved.
SECTION 01 11 00 Page 3
] 1.8 SALVAGE MATERIAL AND EQUIPMENT
Items designated by the Contracting Officer to be salvaged remain the property of the Government. Segregate, itemize, deliver and off-load the salvaged property at the storage area as designated by Contracting Officer.
Provide a salvage plan, listing material and equipment to be salvaged, and their storage location. Maintain property control records for material or equipment designated as salvage. Use a system of property control that is approved by the Contracting Officer. Store and protect salvaged materials and equipment until disposition by the Contracting Officer.
PART 2 PRODUCTS
Not used.
PART 3 EXECUTION
Not used.
-- End of Section --