A.02PWS Yaquina FY22 Dockside Repairs Rev.pdf
PDF 335 KB Posted
- Attached to
- Dredge YAQUINA Pier Side Repair
- Solicitation number
- W9127N22Q0005
About this file
This performance work statement outlines repair and maintenance requirements for the USACE dredge Yaquina. Key work includes replacing sluice valves, pipe spool pieces, S-pipes, and jetting system piping. Additional tasks involve overhauling anchor windlasses, auxiliary machinery room ventilation fans, and providing staging in the hopper space. The contractor must furnish all necessary labor, equipment, materials, and incidentals to complete repairs by February 28, 2022 in accordance with specifications. The statement also defines contractor safety, quality control, and anti-terrorism requirements, as well as a level of effort and schedule of fully burdened labor rates for negotiating growth work.
View the file
Other files
Show all 19
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PWS – Yaquina Pier Side Repair 23 November 2021
1.0 General
The Contractor shall furnish all management, supervision, labor, equipment, tools, lubricants, fuels, materials, articles (excluding Government furnished items), subcontracting services of manufacturer’s representatives, technical, procurement, production, testing and quality assurance necessary to prepare and fully execute the maintenance and repairs of the USACE Dredge YAQUINA, hereinafter referred to as the vessel.
1.1 Description of Vessel
USACE YAQUINA is a trailing arm suction Hopper Dredge built in 1980.
It has the following characteristics:
Length Overall 200 Feet Length B.P. 188 Feet Beam Molded 58 Feet Beam Overall (With Drag Arms Lowered) 70 Feet
1.2 Period of Performance
The anticipated period of performance (POP) shall start upon award of contract. The Contractor shall commence work no later than January 3, 2022 and complete work no later than February 28, 2022.
1.3 Location
The required place of performance shall be onboard the vessel which will be berthed at:
USACE Portland Terminal 2 3556 NW Front Avenue Portland, OR. 97210
2.0 Definitions
Throughout this contract, terms are defined as follows:
Contracting Officer (KO): Government employee who is authorized to enter into, administer and / or terminate contracts and make related determinations and findings.
Contracting Officer’s Representative (COR): Government employee who has been authorized in writing as the COR by the KO, acting within the limits of their authority.
Quality Assurance Evaluator (QAE): Government employees responsible for checking Contractor’s performance.
Regulatory Bodies: These include American Bureau of Shipping (ABS), United States Coast Guard (USCG) and other agencies having jurisdictions on certain matters, such as United States Public Health Service (USPHS).
Vessel’s/Ship’s Crew: Government employees assigned to work on the vessel.
3.0 Government Furnished Equipment, Facilities, Materials
Government furnished equipment, property, facilities, materials, and utilities will be provided as follows.
Electrical power:400 Amps, 480V AC, 3-phase, 60 cycle continuous electrical service.
Connections shall be cable lug, individually bolted, by each phase.
Lay Down Area: 100 feet x 200 feet clear lay down are on the pier adjacent to the vessel.
Contractor shall be responsible for providing all material handling equipment and operators to transfer shipboard equipment and materials to and from the vessel to the lay down area.
PROPOSED LIST OF GOVERNMENT FURNISHED PROPERTY (GFP)
Name Quantity Value
Per Unit Serial Number Manufacturer PWS
Sluice Valve (20”) 2 $24,373 N/A IHC Systems B.V. 5.4 20” S-Pipe 2 $25,000 N/A N/A 5.6 Overflow Trough 2 $ 25,000 N/A N/A 5.8
4.0 Contractor Requirements
4.1 General Statement
The Contractor shall furnish all management, supervision, labor, equipment, tools, lubricants, fuels, materials, articles (excluding Government furnished items), subcontracting services of manufacturer’s representatives, technical, procurement, production, testing and quality assurance necessary to prepare and fully execute the maintenance and repairs of the vessel.
The Contractor shall perform to the standards in the contract and shall comply with all federal, state, and local regulations during the performance of services.
4.1.1 Approved Material and Equipment
Contractor shall ensure all furnished materials and equipment used for repairs to, replacement of, or installation of new items, shall comply with all applicable American Bureau of Shipping (ABS) and United States Coast Guard (USCG) requirements.
4.1.2 Spare Parts, Tooling, and Equipment
Contractor shall not use the vessel’s spare parts, materials, tools, or equipment for the repair of, replacement of, or installation of new items unless specifically approved in writing by the COR. If vessel spare parts, materials, tools, or equipment are approved for Contractor use, the Contractor shall replace any/all materials and/or damaged tooling or equipment at no cost to the Government.
4.2 Meetings
4.2.1 Arrival Conference
An arrival conference shall be held between the Contractor’s Contract Administrator, Ship Superintendent, Safety Director, Subcontractors (if requested by Government), and the Government’s COR at a time mutually acceptable to all parties but no later than four (4) hours after the start of the period of work. Contractor shall submit a list of all Subcontractors proposed to do work and the extent and character of the work to be performed by each Subcontractor.
All work submittals stated in the PWS shall be required at this time. An outline of events for the arrival conference shall be prepared by the COR and provided to the Contractor for distribution prior to the arrival conference.
4.2.2 Daily Production Meetings
Daily production control meetings shall be led by the Contractor at a time and location mutually agreeable between the Contractor and COR.
4.3 Schedules
4.3.1 Production Schedule
The Contractor shall submit a Production Schedule within 10 days of receiving the notice of award. The Production Schedule shall illustrate the sequence the Contractor proposes to perform the work and the dates the Contractor contemplates commencement and completion of each schedule activity.
The schedule shall consist of all work items listed in Section 5 and demonstrate completion within the stated period of performance. The schedule shall include a sufficient level of detail to denote work overlaps, commence and completion dates of all activities, predecessor/successor relationships, milestones, critical path, and the logical and efficient order the contractor proposes to accomplish all work. Activities shall be scheduled for earliest possible completion, commensurate with the best commercial marine practices and availability of materials.
The Production Schedule shall be based on the following: date of start of work (refer to paragraph
1.2 above); date of completion for each work item; and anticipated completion date of all contract work.
4.3.2 Weekly Production Schedule Update Meeting
The weekly production schedule update meeting shall be held on weekly basis at a location agreeable by all parties.
The Contractor shall update the production schedule on a weekly basis reflecting actual progress attained (percentage of work completed for each activity) and identify the current critical path through remaining work activities. Contractor management personnel, subcontractors, and suppliers shall actively participate in developing an accurate production schedule.
The weekly updated production schedule shall be accompanied with a written narrative describing (1) amount of progress on major work items during the reporting period, (2) problems uncovered, (3) known or anticipated delays, and causes thereof, together with the impact on the schedule, and (4) corrective actions taken or planned in connection with the latter. Work reported shall be inclusive of Contractor and subcontractor’s performance and should be coordinated with the COR. The Contractor shall provide a production schedule and written narrative in both a hard copy and electronic copy.
The weekly production schedule update meeting provides an opportunity to discuss progress, problems and forthcoming schedule requirements. If the event the Contractor falls behind the production schedule, the Contractor shall take steps necessary to improve its progress, including those that may be required by the Contracting Officer, without additional cost to the Government.
In this circumstance, the Contracting Officer may require the Contractor to increase the number of shifts, overtime operations, days of work, and/or equipment and to submit for approval any supplementary schedule or schedules as the Contracting Officer deems necessary to demonstrate how the approved rate of progress will be regained.
Failure of the Contractor to comply with the requirements of the Contracting Officer shall be grounds for determination by the Contracting Officer that the Contractor is not prosecuting the work with sufficient diligence to ensure completion within the time specified in the job order. Upon making this determination, the Contracting Officer may terminate the Contractor’s right to proceed with the work, or any severable part of it, in accordance with DFARS 252.217-7009, Default.
4.4 Submittals
4.4.1 Pre-Work Submittals
Within ten (10) days prior to the start of work, Contractor shall submit the following documents to the COR for review and approval:
Submittal Item PWS Paragraph
Production Schedule 4.3.1 QC Program / Plan 4.6 List of ABS / USCG Qualified Welders with Proof of Certification 4.5.9.1 Accident Prevention Plan 4.7 Fire Prevention Plan 4.7
4.4.2 Material Procurement Submittals
Certain work items may specify submission of procurement information in support of contractor provided material. A pre-procurement submittal containing product data, technical specifications, testing information, and MSDSs, etc. shall be provided to the COR for review and approval in advance of procurement.
4.5 Standards and General Requirements for Repairs
All work shall be completed in accordance with DFARS 252.217-7005, Inspection and Manner of Doing Work, to the satisfaction of the COR or QAE and representatives of USCG and/or ABS and meet all requirements and regulations of the ABS, USCG, and the Institute of Electrical and Electronic Engineers.
4.5.1 Standards
All design, engineering, modifications, and repairs to the vessel shall be performed in accordance with the criteria set forth in the latest issues of the following standards or regulations:
a) U.S. Army Corps of Engineers, Engineer Manual (EM) 385-1-1, “Safety and Health
Requirements Manual.”
b) USCG, Navigation Rules - Inland/International.
c) Title 29 Code of Federal Regulations (C.F.R.) part 1915, Occupational Safety and Health
Standards for Shipyard Employment. (Also found in Occupational Safety and Health Administration publication no. 2268, Shipyard Industry Standards.)
d) 33 C.F.R. chapters I-II.
e) 46 C.F.R. parts 41-69, 90-105, 110-13, 159-65, 170-74.
f) American Bureau of Shipping, “ABS Rules for Building and Classing Steel Vessels”
g) Institute of Electrical and Electronic Engineers Standards, Publication No. IEEE-45 –
“Recommended Practice for Electrical Installation on Shipboard”
h) Illuminating Engineering Society, “Recommended Practice for Marine Lighting” National
Electric Code (NEC). National Electrical Manufacturer Association (NEMA). National Fire Protection Association (NFPA).
Any other standards not listed above that are incorporated by reference under these standards shall also apply to the work being performed under this contract.
4.5.2 General Requirements for Access Cuts and Interferences
The Contractor shall request COR approval prior to cutting and/or removing the plating or framing members from the vessel for access to machinery, piping, wiring, and equipment.
The Contractor shall request COR approval prior to the removal of any piping, wiring, fixtures, fittings, etc., for access and clearance to perform required work.
Upon the completion of required work, all removals and/or cutting shall be replaced/restored and all removed interferences shall be returned to their original operating condition and position. All damaged or missing fasteners shall be replaced with new fasteners of the same grade and size as original. New gaskets, packing or seals shall be installed on all disturbed joints and demonstrated leak-free where applicable. Damaged paint shall be renewed at no additional cost to the Government.
The cost for all removals and reinstallations shall be included in the cost of the respective task.
If parts, components, or equipment are damaged during interference removal or access cutting, the Contractor shall replace them in kind at no additional cost to the Government.
Horizontal openings, such as those on the deck, shall be protected with Contractor-furnished temporary combing and safety netting around the entire perimeter of the deck opening when such opening is not in use.
4.5.3 General Requirements for Structural Work
Contractor shall pay close attention to details in both the design and construction of all new and/or modified structures, to prevent structural discontinuities and other stress concentrations.
Where openings must be provided in the structure to gain access internally, the Contractor shall provide adequate compensation to maintain the original structural integrity while the opening is present. All compensation shall be approved by the ABS.
Watertight and oil tight integrity of all bulkheads and decks not affected by the execution of contract work items, shall be maintained throughout the period of performance of this job order.
Openings created by permanent removal or addition of piping, wiring or other materials shall be closed by means of Watertight penetrations or insert plates of equal thickness flush-welded to the bulkheads.
All welds shall be ground flush and smooth.
Sections of stiffeners, beams, girders, etc., shall be welded to the bulkheads to maintain continuity of structure. Openings cut into decks and bulkheads shall be adequately compensated in accordance with ABS requirements to maintain original strength, unless the opening is cut in such a manner that it can be re- welded to existing framing members.
4.5.4 General Requirements for Foundations and Supports
Contractor shall provide suitable foundations under all new units of machinery. Foundations shall be built up of plates and structural shapes to the dimensions required for satisfactory support, assuring rigidity, freedom from vibration, and designed for secure containment of the equipment in event of crash stops.
Foundations shall be constructed to the machinery manufacturer’s requirements, unless otherwise specified in technical specifications or modification.
Where dripping water or oil can be expected, the top plates of foundations shall project beyond the edges of the bedplates or bases of units being supported and formed into spill containment/drip pans. Flat bars welded around the edges of the top plates, or combing welded around the deck near the foundation, may be used to retain any leakage. Valve drains shall be provided at the ends or corners of the pans to facilitate fluid removal or recovery.
Foundations shall extend beyond the equipment fore and aft or transversely to distribute the load and to avoid excessive weight concentrations.
Insert plates, girders, headers, and stanchions shall be fitted and under-deck framing shall be reinforced to support units mounted on deck.
4.5.5 General Requirements for Piping
All piping required shall be designed and installed to obtain optimum operating conditions and shall be compatible with the machinery or equipment serviced, including pressure, volume, and temperature requirements. All piping, valves and fittings shall comply with material specifications required by the USCG and ABS standards.
New piping added to or replacing an existing system shall duplicate that system, both in size, material, and routing, unless otherwise specified. New piping, where installed in coordination with new equipment or machinery, shall be installed in a manner that does not adversely impact personnel with tripping or overhead hazards.
New fuel oil, lube oil, or hydraulic piping shall be seamless steel, Schedule 80, to match existing pipe material. Pipe shall be pickled prior to installation. Seamless stainless-steel tubing may be used as appropriate in Hydraulic systems.
New raw, jacket or sanitary water piping shall be with 90-10 copper-nickel, Schedule 80.
New drain piping shall be replaced in kind. Piping shall be led directly as per existing application.
The finished installation shall include the pipe, valves, unions, elbows, reducers, tees and fittings and all necessary subparts. Unions and flanges shall be required to facilitate installation and subsequent removal. High-pressure flanges shall be used where originally provided.
Flexible connections to machinery components shall be required where vibration may be anticipated. Piping shall not pass over switchboards and be kept clear of switchgear, wiring, etc.
All work shall be templated from the vessel.
Piping shall be secured by supports and hangers to avoid excessive strains; avoid the weight of the piping being transmitted to valves and fittings; minimize the effects of vibration, shock, pitching and rolling of the vessel; and permit proper thermal expansion and contraction.
Provision may be made for expansion and contraction by changes in direction of pipe runs or by use of expansion bends, joints, loops, or offsets.
Galvanizing destroyed by welding or other activity shall be restored to original. All new steel galvanized pipe shall be hot dipped galvanized.
All burrs shall be removed from the ends of all piping after any cutting or threading. Pipe ends shall be dressed before installation.
Valve type shall be consistent with the service. All valve materials shall match existing. New valves shall be approved by the COR.
All valves are to be pressure-tested in the presence of the COR or the QAE, and if necessary, the USCG, prior to installation on the vessel. Where three or more valves are located together for the same service, they shall be combined into a manifold.
Any new fuel supply lines shall include a new shut-off valve, one at each tank and one at each fuel pump. A brass or aluminum label plate shall be attached to the hand-wheel of all new valves to indicate its function.
New valves for seawater service shall be stainless steel or bronze and have a pressure rating appropriate for that service. Valves and operating mechanism shall be readily accessible.
Watertight integrity shall be maintained where pipes are carried through watertight bulkheads, decks, or tank tops.
Heat sensitive materials shall not be used in piping systems that penetrate watertight subdivisions.
Where overboard discharge lines or valves are attached to the inside of the hull, the hull shall be reinforced to maintain the original strength and integrity.
Spool pieces with flanges shall be used for all galvanized pipe deck and bulkhead penetrations to prevent damage to galvanizing due to welding.
Pipe penetrations through watertight bulkheads and decks shall be accomplished by welding pipe to a sleeve that is then welded to the bulkhead or deck. All fastenings used to connect valves to shell connections shall be stainless steel. Where dissimilar metals occur, the Contractor shall insulate to prevent electrolytic action. Any new piping shall be color-coated in accordance with the vessel’s current scheme.
4.5.5.1 Hydraulic Hoses and Piping
All hydraulic systems opened as a result of work tasks or as interference shall be immediately fitted with appropriate caps or plugs that prevent contamination of the hydraulic system. Hydraulic systems contaminated as a result of the Contractor’s negligence shall require the Contractor to provide, at no additional cost to the Government, all materials, labor and equipment to perform system flushing to remove resultant contaminants.
4.5.6 General Requirements for Machinery Systems
Where new machinery and equipment is to be installed, or when existing machinery and equipment is relocated, the Contractor shall mount the items on foundations as specified elsewhere herein.
All fastenings, bolts, (fitted or otherwise) studs and nuts shall be installed using anti-seize compound. Any defective or missing standard, fasteners, washers, gaskets, grommets, shall be replaced with material that matches existing performance standards.
Bottoming taps shall be used whenever new holes are drilled and tapped.
When detailed disassembly, assembly, or installation procedures appear in the specifications, they are presented for the Contractor's information and convenience in estimating the possible extent of the work to be accomplished. The inclusion of these detailed procedures does not relieve the Contractor of responsibility for doing all work necessary and in the proper manner for satisfactorily accomplishing the specified objective.
4.5.7 General Requirements for Electrical Systems
All electrical installations as set forth elsewhere in these specifications shall comply with the referenced rules, regulations, and standards, especially regarding ambient and working temperature requirements.
Electric cable shall be commercial marine type cable or armored cable. All new cable installed on weather decks or exposed to seawater spray shall be bronze or stainless steel armored. All new interior cable installed shall be bronze or aluminum armored.
Electric cable shall be capable of handling the required amperage.
Electrical installations shall be accomplished in a manner which eliminates the possibility of mechanical injury or damage from the accumulation of dust, oil, vapors, steam, dripping liquids, etc.
New cable runs shall be supported at intervals of no more than 18” apart where installations are located vertically and 14” apart where installations are located horizontally. Straps, hangers, and standoffs shall be aluminum with stainless steel fasteners. Plastic type straps are permitted only behind sheathing/paneling. No cable runs will be permitted below the deck-plates, except for bilge pump wiring. Cable penetrations, when required to be watertight, shall have approved kick-plates, stuffing tubes, etc., and shall be filled with duct seal, or pitch where originally used. All electrical supplies and/or installations to meet CFR 46, as well as all applicable NEMA, IEEE and ANSI standards.
4.5.8 General Requirements for Hot Work
Prior to commencing any hot work, the Contractor shall take steps necessary to remove any flammable or combustible material from the affected area. The Contractor shall supply all personnel performing hot work operations with suitable breathing, clothing, vision, and hearing protection to protect personnel from fumes, sparks, bright light, and noise resulting from hot work operations.
The Contractor shall supply and post permits stating the spaces where hot work is being performed are Gas Free and Safe for Hot Work.
While Contractor personnel are performing fire watch services, no additional responsibilities or additional work shall be performed during this time. Fire Watch is required to be on station for 60 minutes after welding/cutting ceases.
4.5.9 General Requirements for Welding
The Contractor shall ensure only welders with proper certification through ABS and USCG may weld steel on this job. Certifications shall be provided to the COR.
The electrodes used throughout the work shall be suitable for use with the parent metal at each weld. Electrodes shall be received on the job in unbroken packages bearing the manufacturers' label or be otherwise marked.
Certified statements shall accompany each shipment of electrodes to the effect that sample pieces, representative of each kind and size in each shipment, have satisfactorily passed the tests required by ABS and USCG for welding on the parent material. The Contractor shall provide the COR documentation certifying compatibility of electrode with parent material.
The Contractor shall submit welding procedures to the COR prior to welding to a casting or forging. The procedure shall cover the type of weld process, welding electrode, pre-heat, welding sequence and stress relief required.
All welding shall be smooth, tight, and free from undercuts, porosity, craters, and gas inclusions.
Shell, deck butts, and flush seams shall be back chipped or gouged to sound metal from the closing side before welding.
All sharp and/or rough edges shall be ground smooth, and all weld splatter shall be removed.
All welds for temporary dogs used during modifications or to secure plate in place while welding shall be ground flush with the surrounding metal.
Assembly of all welded joints, before welding, shall be such as to secure proper gaps in butt welds and metal contact in fillet welds. Welding shall not be used to close openings larger than stipulated for each plate thickness by the ABS.
Welding procedures, as to direction, length, number, temperature, and sequence, shall be carefully planned to minimize distortion and locked-in stresses.
Any welding to or of hull shell plating, watertight and/or oil-tight bulkheads shall be inspected by ABS. This includes the removal of existing plate, examination of the remaining surrounding plate, examination of the fit-up, and examination of the final welding.
Any welding shall use local grounding on and forward of frame 48 and on and aft of frame 108 and in all machinery spaces. The Contractor shall maintain a log of all welders who worked on the vessel throughout the repair period, each welder’s certification, and the repair activities on each welder worked. This log shall be made accessible to the COR at any time during normal business hours throughout the period of performance of this job order.
Testing of welds, will apply where required.
4.5.9.1 Welders
Welders shall be qualified to the standards established by ABS and/or USCG shall perform all welding accomplished aboard the vessel or on any components intended for installation onboard the vessel.
Contractor shall bear the expense of certifying welding proficiency in the prescribed welding method for all welders assigned to the vessel and shall provide documentation of completed tests to the COR. Where the workmanship of any individual welder indicates a reasonable doubt of the welder’s proficiency, the Contractor shall be required to recertify or reassign the welder prior to that individual conducting additional welding on the vessel. Contractor shall provide welding certifications to the COR.
4.5.10 General Requirements for Surface Preparation & Coating Application Work covered under this specification requires the contractor to provide all labor, materials, supplies, and equipment necessary for the cleaning, preparation, and coating of surfaces. All exterior and interior surfaces of the vessel shall be prepped and coated in accordance with this specification.
Methods of surface preparation and coating application shall comply with all applicable State, Federal and Municipal Regulations.
Where conflict exists between this section and the work requirements of the PERFORMANCE WORK STATEMENT, this section shall govern.
4.5.10.1 Technical References
a) ASTM D5064 (Standard Practice for Conducting a Patch Test to Assess Coating
Compatibility)
b) ISO 8502 (Preparation of Steel Substrates Before Application of Paints and Related
Products)
c) MIL SPEC MIL-PRF-23236D (Coating Systems for Ship Structures)
d) MIL SPEC MIL-PRF-24647D (Paint System, Anticorrosive and Antifouling, Ship Hull)
e) MIL SPEC MIL-PRF-24667C (Coating System, Non-Skid, for Roll, Spray, or Self-Adhering
Application)
f) MIL SPEC MIL-PRF-32171B (Deck Coatings, High Durability)
g) SSPC-SP1 (Solvent Cleaning)
h) SSPC-SP3 (Power Tool Cleaning)
i) SSPC-SP6 (Commercial Blast Cleaning)
j) SSPC-SP10 (Near-White Blast Cleaning)
k) SSPC-SP11 (Power Tool Cleaning to Bare Metal)
4.5.10.2 Surface Preparation
Prior to any surface preparation, the Contractor shall ensure all adjacent equipment, materials and areas are adequately protected against mechanical damage resulting from the surface preparation methods used. Any mechanical damage caused directly or indirectly, by the accomplishment of surface preparation, shall be repaired at the contractor’s expense.
Throughout the process the contractor shall ensure dust and debris are contained within the immediate work area. Any areas contaminated with scale, blasting grit, dust, or other debris resulting from contractor’s activity shall be cleaned at contractor’s expense.
Contractor shall ensure all surfaces are free of sharp edges, weld spatter, laminations or other irregularities that would negatively impact coating adhesion. Prior to mechanical surface preparation, all metalwork shall be cleaned of grease, oil, salt, or other contamination. Cleaned surfaces shall be tested for surface contamination in accordance with paragraph 4.5.10.4.
Prior to coating application all prepared surfaces shall be cleaned to SSPC-SP1. COR shall visually inspect and approve prepared areas prior to application of the first coat. Prepared surfaces shall be maintained free of surface contamination that would negatively impact coating adhesion.
4.5.10.3 Coating Systems
All coating systems shall be specifically manufactured for heavy-duty marine applications and shall be made by the same manufacturer. Substitutions of coating materials that do not meet the prescribed specification shall not be made, unless approved by COR in writing.
Coating systems shall be compatible with existing coatings. Contractor shall provide documentation from the manufacturers of the existing and proposed coating system stating compatibility or conduct a patch test to assess coating compatibility in accordance with ASTM D5064.
All coating materials shall be transported, stored, prepared, and applied in accordance with the manufacturer’s recommendations.
Prior to application of any coatings, adjacent equipment, materials, and areas not to be coated shall be provided with protective coverings as necessary. Equipment, materials, and areas inadvertently coated shall be restored to its previous conditions at contractor’s expense.
Contractor shall be responsible for removal and proper disposal of all protective materials upon completion of the work.
Application equipment used by the Contractor shall be of a type suitable for the materials to be applied and shall be used and maintained in accordance with the manufacturer’s recommendations.
All painting shall be executed in a workmanlike manner and the finished coatings shall be free of holidays, pinholes, bubbles, runs, drops, ridges, laps and variations in color, texture, and gloss.
All coats shall be applied in such a manner to produce an even film of uniform thickness. Edges, corners, seams, joints, welds, and surface irregularities shall receive special attention to ensure adequate thickness of paint. Each coat shall be visually inspected and approved by the COR for runs, drips, sags, and holidays. Where multiple coats are required, each coat shall be of a unique color to enable differentiation between coats.
All noted defects shall be corrected and re-inspected prior to application of subsequent coats.
Contractor shall ensure areas to be coated are maintained under suitable environmental conditions within the range specified by the coating manufacturer for the entire duration of application and curing.
The following Federal Standard 595B (Paint Specification) colors shall be used to match existing:
Deck Red (100076); White (37925); Ivory (17855); Black (17038); or Grey (16187) Other Federal Standard colors may be substituted as necessary upon written approval by the
COR.
4.5.10.4 Weather Decks
All weather deck areas to be coated shall be cleaned / prepared to SSPC-SP3 or SSPC-SP6.
Cleaned and prepared areas shall receive two (2) coats of epoxy primer, MIL SPEC MIL-PRF- 32171B, Type I, Class 1, 4-6 mils DFT per coat and two (2) finish coats of acrylic polyurethane meeting MIL SPEC MIL-PRF-24667C, Types I, II, III & VIII to a thickness of 2-3 mils DFT per coat. Deck areas subject to foot traffic shall receive non-skid application of 40 grit garnet between finish coats. Non-skid application shall not be applied within 4” of adjacent foundations.
4.5.10.5 Aluminum House
All aluminum house areas to be coated shall be cleaned / prepared to SSPC-SP10, using Aluminum Oxide or Garnet Blast Grit, or SSPC-SP11. Copper-containing blast material is not allowed. The blasting process shall produce a uniform 2 to 3 mil surface profile. Cleaned and prepared areas shall receive two (2) coats of epoxy primer meeting MIL SPEC MIL-PRF-32171B, Type I, Class 1, 4-6 mils DFT per coat and two (2) finish coats of acrylic polyurethane meeting MIL SPEC MIL-PRF-24667C, Types I, II, III & VIII to a thickness of 2-3 mills DFT per coat.
4.5.10.4 Inspection
Cleaned, prepared, and coated surfaces and coatings shall be inspected and approved by the COR. DFT measurements of each coat shall be taken in the presence of the COR. A copy of all readings shall be provided to the COR within 24 hours of completion. Where the number of coats and DFT is specified, the mil thickness shall govern. Additional coats shall be applied as necessary to achieve the specified thickness.
COR shall be notified at least 24 hours in-advance of any required inspection. All noted defects shall be corrected and re-inspected prior to application of subsequent coats. Re-work shall be at the Contractor’s expense. Subsequent coats shall not be applied until each inspection has been completed and approved, unless specifically authorized by the COR in writing.
4.5.10.4 Testing
Prior to mechanical surface preparation, cleaned surfaces shall be tested for surface contamination in accordance with ISO 8502 in sufficient locations to ensure a representative sample of the cleaned area. Any areas where test results for soluble salt levels exceed 3 mcg / cm2 shall be re-cleaned and re-tested at the contractor’s expense until satisfactory results are obtained. Contractor shall provide a copy of all surface contamination test results to the COR within 72 hours of receiving results.
4.5.11 General Requirements for Materials
All materials provided by the Contractor shall be suitable for marine applications and shall be subject to COR approval prior to installation. Unless otherwise stated, contractor assumes all risks for incorporating unapproved materials into work tasks. If unapproved materials are discovered by the COR during inspection, contractor shall promptly submit product information for review and approval. If materials are found to be non-conforming to the minimum requirements of the specifications, contractor shall be required to remove all subject materials and rework at no additional cost to the Government.
4.5.11.1 Scrap Material
Unless otherwise specified in the PWS, all scrap material removed by the Contractor shall become the property of the Contractor and shall be reflected in the scrap value of the bid price submitted by the Contractor. The cost of removing, handling, transporting, and disposing of all scrap material shall be included in the price of the associated task.
4.6 Quality Control (QC) Program
Contractor shall provide and maintain a QC Program acceptable to the Government. At a minimum, it shall identify and include the following information.
a) Specification Work Item Number
b) Any testing and inspection requirements.
c) Sign off procedure for testing and inspections.
d) Sign off procedure for the COR to confirm item completion.
4.6.1 Tests
For all testing, Contractor shall coordinate the scheduled test date and time with the COR and Regulatory Bodies (where applicable). Notification of a required test schedule shall be provided to the COR at least 24 hours prior to conducting the test, unless stated otherwise.
4.6.2 Inspections
For all inspections, Contractor shall have assigned QC personnel inspect and approve prior to calling for an inspection by the COR and Regulatory Bodies (where applicable). Notification of a required inspection date and time shall be provided to the COR at least 24 hours prior to the inspection, unless stated otherwise.
4.6.2 Condition Found Reports (CFRs)
The contractor shall submit inspection reports, identify needed repairs, and recommend corrective action during contract performance for those deficiencies discovered which are not covered by the work specifications. Needed repairs and corrective action reported will be submitted to the Government in the form of a Condition Found Report (CFR). The CFR shall be in electronic format and shall be submitted with all supporting data by email to the COR. CFRs shall be submitted within 24 hours of issue discovery. As a minimum, the CFR will include the following:
a) Identify contract number, job order number, and ship
b) Serialized by CFR number
c) Identification of the applicable Work Item number
d) Date requirement was discovered
e) Description of work requirement
f) Specific location of the work
g) Recommendation for corrective action
h) Recommendation for the appropriate/best time to accomplish the work (with or without schedule change). Provide supporting rational for the recommendation, such as price efficiencies, availability of the work force, availability of material, premium expenditures etc.
i) Identification of related changes, if any, to the internal milestones and production and contract completion dates. If none, so state.
4.6.2.1 Government Review and Response to CFR
The Government will review all CFRs received. If a CFR is inadequate or incomplete, the Government will reject it and a corrected CFR must be returned within twenty-four (24) hours correcting the identified discrepancies.
When appropriate, the Government and contractor may meet to conduct ship checks and/or discuss the recommendation for corrective action further to determine the full scope of work required prior to final approval of the CFR. If growth work in response to a CFR is identified, the Government will submit an RFP to the contractor.
4.6.3 Request for Price (RFP)
The contractor shall provide all Contract Change Order (CCO) price proposals to the KO and Contract Specialist in response to RFPs within five (5) calendar days. A contractor’s CCO price shall remain valid for a minimum of fourteen (14) calendar days, unless otherwise specified on an individual RFP by the KO; if another timeframe is specified by the Government on an individual RFP, the contractor’s CCO shall remain valid for that amount of time. A CCO addressing a change to the FFP contract shall include:
a. Labor hours to be performed by the Prime Contractor $
b. Subcontractor Quote (If applicable) $
c. Material Quote (If applicable) $
d. Mark-up (If applicable) $
Subcontractor quotes shall include labor hours, labor rate, material (part number, description, unit cost, quantity, total cost, and vendor quotes for each line item), and tiered subcontractor quotes (if applicable).
Material quotes shall include the part number, description, unit cost, quantities, total cost, and vendor quotes for each line item.
The CCO shall include any specific terms and conditions related to completion of the new or growth work to include impact to milestones, sequencing of adjacent work items, and revised completion date(s) for impacted work item(s). Any proposed change to a schedule milestone shall include a proposed revised date.
Labor hours for both prime and subcontract shall be provided broken down by trade and labor mix.
The required documentation must accompany the CCO for the CCO to be considered submitted to the KO.
If circumstances arise where the contractor is unable to submit a CCO within five (5) calendar days, the contractor shall notify the KO in writing of the specific circumstances and provide a revised date in which a CCO proposal will be submitted. Additional time needed to complete a CCO may be granted solely at the discretion of the KO. The new timeframe granted may differ from the contractor’s requested time frame.
4.6.4 Open & Inspect Reporting
In the first 25% of the work performance period, conduct work and submit Condition Reports to the COR for all items involving:
a) Disassembling and inspection of equipment, machinery, systems, or components.
b) Opening, gas-freeing, and inspection of tanks.
No time extension of the work performance period will be granted for delays caused by failure to comply with this 25%-time requirement.
4.7 Safety and Environmental Requirements
In addition to applicable Local, State, Federal and OSHA requirements, the Contractor is required to adhere to all provisions of the most recent EM 385-1-1, 29 CFR Part 1910 (Occupational Safety and Health Standards), 29 CFR Part 1915 (Occupational Safety and Health Standards for Shipyard Employment) and FAR 52.236-13 Alt I (Accident Prevention). Where safety standards are conflicting, the most stringent standard shall apply. The requirements of EM 385-1-1, Section 1 (Program Management) will be strictly enforced.
The Contractor shall submit a written Accident Prevention Plan in conformance with EM 385-1-1, Appendix A, and a Fire Prevention Plan in conformance with EM 385-1-1, Section 09.A.01. Prior to commence of work, these plans shall be submitted to the COR for review and approval. No work shall be initiated until both plans are approved (refer to paragraph 4.4.1.).
A copy of the EM 385-1-1 can be found electronically at the following link:
http://www.publications.usace.army.mil/USACEPublications/EngineerManuals
4.7.1 Accident Protection
All work performed under this contract shall be in accordance with the requirements of EM 385-1- 1 and other safety requirements specified herein are further identified in standards in technical specifications.
4.7.2 Accident Investigations and Reporting
All accidents shall be reported IAW Section 01.D of the EM 385-1-1.
Records of exposures and accidents shall be maintained on an OSHA Form 300 or equivalent.
A log of reported accidents shall be kept and shall be available for review upon request from the
COR.
Accidents shall be investigated by the immediate supervisor of the employee(s) involved and reported to the COR within one (1) working day after accident occurs.
A report of all mishaps occurring on the project shall be submitted to the Contracting Officer within four (4) calendar days following the incident. All data reported must be complete, timely, and accurate. A follow up report shall be submitted when the estimated lost time days differs from actual lost time days. All accidents shall be reported on Engineering Form 3394.
4.7.3 Lockout / Tagout (LOTO) Policy and Procedures
Vessel’s policy for LOTO follows Section 12 of the EM 385-1-1. Contractor shall coordinate all work tasks requiring LOTO with the COR and designated LOTO personnel aboard the vessel prior to commencing work.
4.7.4 Marine Chemists Certifications
Provide gas free certificates, “Safe for Workers, Safe for Hot Work” IAW 29 CFR 1915.14 (OSHA
– Confined and Enclosed Spaces and Other Dangerous Atmospheres in Shipyard Employment) for all areas requiring access, burning or welding as required by the work tasks within the PWS.
Provide a Component Person to maintain the vessel in compliance with the Marine Chemist Certificate and OSHA rules for the duration the vessel is located in the Contractor’s Shipyard.
Marine Chemists shall recertify the vessel for all ongoing hot work permits in the event of vessel movement, changes in loading condition, spillage of any combustible liquid or other event which voids the currently issued gas free certificate. Inspections conducted by a Competent Person for the purpose of recertification will not be acceptable.
4.7.5 Hazardous Materials
http://www.publications.usace.army.mil/USACEPublications/EngineerManuals
4.7.5.1 Asbestos Containing Material (ACM)
Vessel is known to contain ACM. Contractor is required to perform all necessary inspections, tests and analysis of materials that may contain ACM prior to disturbing those areas referenced in the resultant contract and specifications. If testing indicates unspecified ACM abatement is required, the Contractor shall issue a Condition Found Report (CFR).
4.7.5.2 Lead Paint
Vessel is not certified to be free of lead-based paint. Contractor is required to perform all necessary inspections, tests, and analysis of existing coatings for lead prior to disturbing those areas referenced in the resulting contract and specifications. If testing indicates unspecified lead-based coating abatement is required, the Contractor shall issue a CFRPT IAW Paragraph 4.6.3.
4.8 Growth Work/New Work
It is the Government's intention to ensure that, where it is determined that the work will be performed by the private sector, any growth or new work identified during the overhaul will be awarded to the initial Prime Contractor only if a fair and reasonable price can be negotiated for such work. If a fair and reasonable price cannot be negotiated for the above actions, the Government may, at its election, pursue any of the following courses of action:
(1) defer the work to a repair period after completion of the instant contract.
(2) accomplish the work using Government employees during the original overhaul period.
(3) conduct a separate, competitive procurement for growth or new work. Performance will be during the original overhaul period. The initial prime Contractor and other capable contractors may enter this competition. If other than the initial prime Contractor is successful, the successful Contractor may engage in and complete the work while the ship is undergoing repairs for the base contract.
This requirement does not preclude the Government from using Government employees to perform new or growth work at any time during the availability provided the use of Government employees is in the best interests of the Government.
When growth work is incorporated into the Job Order via a bilateral modification, the Contractor is expected to perform the work within the POP identified in paragraph 1.3. The Contractor shall revise the Production Schedule accordingly no later than the following weekly production schedule update meeting.
4.9 Corrective Action Plan
If the projected completion date for any work task is unlikely to be met, the government may require the Contractor provide a corrective action plan that details what additional workforce and/or resources will be utilized to resolve the resulting schedule delays.
4.10 Final Inspection
Upon completion of all repairs and removal of all contractor equipment, the COR and the Contractor are to inspect all areas of the vessel to ensure work tasks were completed per the contract, the vessel is clean and free of all Contractor-generated debris, and all damaged coatings are repaired per the coating schedule.
5.0 Work Items
5.1 Hopper Staging; Provide
01. General Provide temporary staging and decking in the hopper space to allow for inspections and repairs. Staging shall be at heights of 7’ or 17’ as specified below. Total length is approximately 47’.
02. References Drawing NORSHIPCO Y-2494-3, Revision E, Sheets 1 to 2 – Hopper Plating &
Framing, Frames 32 to 53 NORSHIPCO Y-2496-2, Revision E, Sheets 1 to 3 – Arrangement & Details of Hopper Doors Operating Gear
03. GFM
None
04. Safety Precautions Follow all applicable state, local, and federal requirements including those specified in EM- 385-1-1 latest revision.
Prior to commencing work, follow vessel’s LOTO policy and procedures.
05. Specifications Install staging with two (2) levels of decking, extending from the starboard longitudinal bulkhead to the port longitudinal bulkheads at the following elevations:
a. 7’ above baseline, which is below the lower guide bearing support beam pads on the sloping longitudinal bulkheads; and
b. 17’ above baseline, which is near transition from sloping longitudinal bulkhead and vertical longitudinal bulkhead along the outboard sides of the hopper.
Decking at 17' above baseline shall extend in the longitudinal direction from the forward bulkhead of the hopper at Frame 32 to the aft bulkhead at Frame 53, with provisions made for lowering and raising overflow troughs and completing hopper door work.
Provisions for access to the staged areas shall be provided from two separate locations on the main deck. One at the forward most point of hopper; and one from the furthest aft point of hopper. Each point shall allow for access and egress at all levels of decking.
Remove staging upon completion of all hopper repairs. Hopper repairs will be identified and accomplished under separate work tasks.
06. Testing
07. Inspection / Documentation Staging shall be inspected and tagged for safe use daily, by a competent person, in the presence of the Government Representative IAW the Accident Prevention Plan. Inspections shall be held before each work shift. Inspections shall be documented daily by the Contractor.
5.2 Anchor Windlasses; Overhaul
General Furnish labor, materials, and equipment to overhaul the port and starboard anchor capstan windlass unit and wildcat assembly.
References Drawing Vertical Capstan- Model X-1445ASerial Numbers: 23091 & 23092 Manual: Yaquina Technical Manual 1505.02 Instruction Manual Capstan-
Windlass Power Unit Model X-1623 Drawings: New England Trawler Equipment Company Drawing R-12475 Rev.A, Electro-Hydraulic Capstan Windlass, General Arrangement NORSHIPCO Drawing Y-2272-3, Arrgt & Details Anchor Handling
GFM
Safety Precautions
Specifications NOTE - Only one capstan windlass unit can be removed from the ship at a time for repair.
For each capstan windlass unit repair requirements are as follows:
Prior to removal of capstan windlass unit, contractor shall disconnect and remove anchor from anchor chain and store securely in lay down area. Anchor chain shall be moved out of the way of windlass wildcat and secured on deck.
CHECK POINT – Contractor shall notify COR of anchor and chain securing and inspect with ship’s crew for adequacy before proceeding with work.
Disconnect and remove anchor capstan windlass unit. Unit is bolted to the foundation with 12 - 1 ¼inch ASTM-A354 Grade BC fasteners (125,000 PSI tensile strength). Mark capstan windlass unit to ensure re-installation will occur in the same location. All hydraulic lines and equipment shall be immediately capped and protected after capstan windlass removal to ensure foreign debris does not enter or contaminate the hydraulic system or equipment.
Transfer capstan windlass to a shop capable of performing the overhaul.
Remove and store the capstan windlass hydraulic motors under protection in a secure location. Disassemble, clean, and inspect the windlass, wildcat assembly, and gear.
Note for inspection: The wild cats on both windlasses are worn and the anchor chains occasionally catch. Contractor will specifically address any wear noted on each units and report as indicated below.
CONDITION FOUND REPORT –…