This is a Statement of Work for a federal construction contract to repair and pave access roads and parking lots at Yatesville Lake and Paintsville Lake in Kentucky. The work includes repaving over 1.5 miles of dam access road and repairing additional areas at Yatesville Lake, such as repaving an office parking lot, filling and milling other lots, and paving shoulder areas and a road. At Paintsville Lake, requirements involve repaving additional roads and lots, including a dam access road, office and bus parking areas, intake roads, and downstream access points. Some areas require full depth repair and resurfacing. The contract will be awarded by the Department of the Army Corps of Engineers Huntington District. The response due date is not provided.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Specifications for

Repair and Paving of Yatesville Access Road, Yatesville Lake, Kentucky/ Repair and Paving of Paintsville Access Road, Paintsville Lake, Kentucky

DEPARTMENT OF THE ARMY

HUNTINGTON DISTRICT, CORPS OF ENGINEERS

HUNTINGTON, WEST VIRGINIA

July 2022

Certified Final Documents - RTA

IFB No.

This page was intentionally left blank for duplex printing.

Yatesville/Paintsville Paving YBCPS01

PROJECT TABLE OF CONTENTS

DI VI SI ON 01 - GENERAL REQUI REMENTS

01 11 00 SUMMARY OF WORK

01 14 00 WORK RESTRICTIONS

01 30 00 ADMINISTRATIVE REQUIREMENTS

01 32 01.00 10 PROJECT SCHEDULE

01 33 00 SUBMITTAL PROCEDURES

01 35 26 GOVERNMENTAL SAFETY REQUIREMENTS

01 45 00.00 10 QUALITY CONTROL

01 45 00.15 10 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 50 00 TEMPORARY CONSTRUCTION FACILITIES AND CONTROLS

01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS

01 58 00 PROJECT IDENTIFICATION

01 74 19 CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

01 78 00 CLOSEOUT SUBMITTALS

DI VI SI ON 32 - EXTERI OR I MPROVEMENTS

32 01 00 PAVEMENT AND MISCELLANEOUS SITE WORK

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUBMITTALS

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

1.2.2 Location

1.3 OCCUPANCY OF PREMISES

1.4 EXISTING WORK

1.5 CONTRACT CONSIDERATION

1.5.1 Protection of Government Property

1.5.2 Cooperation With Government Personnel

1.6 PAYMENT

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 11 00 Page 1

SECTION 01 11 00

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Salvage Plan; G|CM

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

This work involves repair and paving of access roads and parking lots at Yatesville Lake and Paintsville Lake locations.

The Base Contract consists of repair and paving of 1.55 miles of dam access roadway at Yatesville location. The access roadway shall be overlaid with asphalt surface course. There are also additional identified repairs such as scratch course repair, pothole repair, and full depth repairs are required.

The Option 1 Contract consists of repair and paving of office building parking lot, maintenance shop parking lot, shoulder areas, intake access road at Yatesville Lake location. Office parking lot requires milling and filling of surface course. Maintenance shop parking lot requires surface course, and there is an adjacent area where new pavement is required. In addition, there are three shoulder areas identified where new pavement is required, and two shoulder areas where shoulder shall be leveled with new aggregate. Finally, the intake access road shall be paved with a surface course.

The Option 2 Contract consists of repair and paving of dam access roadway, office building parking lot, bus turn-around, end of the dam parking lots, intake access road and parking lot, and access roads and parking lots in downstream area at Paintsville Lake location. Dam access roadway, office building parking lots, bus turn-around, end of the road parking lots and intake access road and parking lots shall be paved with surface course.

Also, there are two pothole repairs required at the dam access roadway.

Downstream area requires surface course, some areas require scratch course, and another area requires full depth repair.

The Option 3 Contract consists of repair and paving of maintenance shop access road and parking lot at Paintsville Lake location. This repair requires milling and filling of the surface course.

In order to fulfill the requirements of this contract, the Contractor must

SECTION 01 11 00 Page 2 complete the above mentioned general project features.

1.2.2 Location

Yatesville Lake work is located in Louisa, Kentucky and Paintsville Lake work located in Staffordsville, Kentucky. The exact location will be shown by the Contracting Officer.

1.3 OCCUPANCY OF PREMISES

Building(s) will be occupied during performance of work under this Contract. Occupancy notifications will be posted in a prominent location in the work area.

Before work is started, arrange with the Contracting Officer a sequence of procedure, means of access, space for storage of materials and equipment, and use of approaches, corridors, and stairways.

1.4 EXISTING WORK

In addition to FAR 52.236-9 Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements:

a. Remove or alter existing work in such a manner as to prevent injury or damage to any portions of the existing work which remain.

b. Repair or replace portions of existing work which have been altered during construction operations to match existing or adjoining work, as approved by the Contracting Officer. At the completion of operations, existing work must be in a condition equal to or better than that which existed before new work started.

1.5 CONTRACT CONSIDERATION

1.5.1 Protection of Government Property

The Contractor shall take whatever measures are necessary or required for protection of the existing features, buildings, grounds, parking areas and other Government facilities. The Contractor is responsible for protecting the adjacent features, machineries and facilities from any damage resulting from work performed. The adjacent features and facilities will be inspected by the Contractor and Government personnel before and after each major milestones.

1.5.2 Cooperation With Government Personnel

The Contractor shall conduct their operations in such manner so as not to interfere with the daily operational functions that Government personnel will have to perform in connection with their duties. Contractor storage of materials and equipment shall be located where approved by the Contracting Officer.

1.6 PAYMENT

No separate payment will be made for the work covered under this section and all costs in connection therewith shall be included in the applicable line item contract price to which the work pertains.

SECTION 01 11 00 Page 3

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 11 00 Page 4

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 14 00

WORK RESTRICTIONS

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Project Regulations

1.3.1.1 Subcontractors and Personnel Contacts

1.3.1.2 No Smoking Policy

1.3.2 Working Hours

1.3.3 Work Outside Regular Hours

1.3.4 Occupied Buildings

1.4 SECURITY REQUIREMENTS

1.4.1 General

1.4.2 Pre-Bid Meetings

1.4.3 For All Contracts 1-Year and Subsequent Option Years:

1.4.4 For Contractors Requiring DOD Common Access Cards (CAC)

1.4.5 Foreign Nationals

1.4.6 OPSEC/AT

1.5 PAYMENT

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 14 00 Page 1

SECTION 01 14 00

WORK RESTRICTIONS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with SECTION 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

Personnel List; G|CM

1.3 CONTRACTOR ACCESS AND USE OF PREMISES

1.3.1 Project Regulations

Ensure that Contractor personnel employed on the project become familiar with and obey regulations including safety, fire, traffic and security regulations. Keep within the limits of the work and avenues of ingress and egress. Wear appropriate personal protective equipment (PPE) in designated areas. Do not enter any restricted areas unless required to do so and until cleared for such entry. Mark Contractor equipment for identification.

1.3.1.1 Subcontractors and Personnel Contacts

Provide a Personnel List of the Contractor and subcontractors including addresses and telephone numbers for use in the event of an emergency. As changes occur and additional information becomes available, correct and change the information contained in previous lists.

1.3.1.2 No Smoking Policy

Smoking is prohibited within and outside of all buildings, except in designated smoking areas. This applies to existing buildings, buildings under construction and buildings under renovation. Discarding tobacco materials other than into designated tobacco receptacles is considered littering and is subject to fines. The Contracting Officer will identify designated smoking areas.

SECTION 01 14 00 Page 2

1.3.2 Working Hours

Regular working hours shall consist of an 8 1/2 hour period established by the Contracting Officer, between 7 a.m. and 3:30 p.m., Monday through Friday, excluding the following Government holidays:

New Year's Day (January 1) Martin Luther King Day (3rd Monday in January) President's Day (3rd Monday in February) Memorial Day (Last Monday in May) Juneteenth (June 19th) Independence Day (July 4) Labor Day (1st Monday in September) Columbus Day (2nd Monday in October) Veteran's Day (November 11) Thanksgiving Day (4th Thursday in November) Christmas Day (December 25)

When one of the above designated holidays falls on a Sunday, the following Monday is observed as a legal holiday. When a legal holiday falls on a Saturday, the preceding Friday is observed as a holiday. The last two weeks of the calendar year shall not be considered when scheduling review or meeting times.

1.3.3 Work Outside Regular Hours

If work is required to be performed outside regular hours, the Contractor shall submit a request to the Contracting Officer for Government review.

No work shall occur outside regular hours, unless approved by the Contracting Officer. During periods of darkness, the different parts of the work shall be lighted in accordance with the requirements of EM 385-1-1 , and in a manner approved by the Contracting Officer.

1.3.4 Occupied Buildings

The Contractor shall be working around existing buildings which are occupied. Do not enter the buildings without prior approval of the Contracting Officer.

1.4 SECURITY REQUIREMENTS

Contract Clause FAR 52.204-2 Security Requirements and Alternate II and the following apply.

1.4.1 General

All Contractors and subcontractor employee(s) working on any contract who require access in and/or around any Huntington District facilities, projects, owned or leased facility/space shall receive authorization to be on site at these areas based upon a favorable background investigation in accordance with "Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors" (HSPD 12). The Huntington District Security Management Office shall submit contractor(s) personal information to complete the basic background investigation in order to make a recommendation to the Contracting Officer of an employee's suitability for work on Government property. The Procuring Contracting Officer (PCO) has the right to deny any contractor or subcontractor employee from working on any contract based upon the results of the background investigation provided by the Huntington

SECTION 01 14 00 Page 3

District Security Management Office. The Government, Contractor, and subcontractors shall not permit any employee(s) access to drawings, blueprints, records, photos, sites, or projects until the Huntington District Security Management Office has completed an Operations Security (OPSEC) review of such items and determined they can be released.

Contractors shall submit a complete investigation packet for each contractor and subcontractor employee to the Huntington District Security Management office within 10 working days after award of any contract, or prior to the individual being permitted unescorted access in or on District facilities. The Contractor shall also provide the following: (1) Name of the Contract Specialist with whom he/she is working, (2) Project Name, (3) Contract Number and (4) Task Order Number when applicable.

The following documents listed below are required: SF 85, Questionnaire for Non-Sensitive Positions (see http://www.opm.gov/forms/ to print form).

FD 258, Contractor Fingerprint Card (one card for digital prints, two for ink prints) (NOTE: a trained/qualified individual shall take prints, ORI block on the FD 258 shall be USOPM000Z) (Contractor Fingerprint Cards (FD-258) may be obtained by Contracting Division by contacting the Huntington District Security Management office). Contractor shall report any changes in personnel or at any time conditions change at least 5 working days prior to individual(s) need to have access to the site. The Contractor shall provide the same information as listed above for all new employees.

Following submission of paperwork, the Security Management Office will conduct an initial criminal check based upon the information provided. If there are no issues, Security Management Office will make recommendations to the PCO or their Designated Representative. The Security Management Office cannot give approval due to unfavorable report(s). The Security Management Office shall coordinate with Office of Counsel and will jointly make recommendations to the PCO and/or the Designated Representative should a background investigation come back with derogatory information.

The PCO will make the determination whether to allow the Contractor personnel to work on the site based on Security and Office of Counsel recommendations, and the PCO will advise Contractor of the decision.

1.4.2 Pre-Bid Meetings

Any Contractor or Sub Contractor who plans to attend a pre-bid site visit to any Huntington District facilities, projects, owned or leased facility/spaces shall be vetted by having a background investigation conducted by the Security Management Office prior to the site visit.

Information for the background investigation shall contain the following:

a full legal name, complete SSN#, Date of Birth, Place of Birth (City and State). It is the Contractor's responsibility to ensure the above information is accurate and legible, otherwise delays may occur.

1.4.3 For All Contracts 1-Year and Subsequent Option Years:

Contractors shall submit a complete investigation packet for each contractor and subcontractor employee to the Huntington District Security Management office within 10 working days after award of any contract, or prior to the individual being permitted unescorted access in or on District facilities.

The Contractor shall also provide the following: (1) Name of the Contract

SECTION 01 14 00 Page 4

Specialist with whom he/she is working, (2) Project Name, (3) Contract Number (4) Task Order Number when applicable, and (5) Security Information Sheet on each employee working on site shall be submitted directly to the Huntington District Security Management Office.

The Contractor shall provide a full legal name, complete SSN#, Date of Birth, Place of Birth (City and State) and Driver's license number if available. It is the Contractor's responsibility to ensure the above information is accurate and legible, otherwise delays may occur.

Contractors shall have background checks completed for their employees annually in the case of Contracts with option periods. For instance, if the employee was cleared in May of 2019, they shall be cleared again in May of 2020. It is the Contractor's responsibility to ensure that each employee's security is up to date. Failure to comply may lead to possible removal from the project/jobsite.

The Contractor shall ensure if new employees are brought in to work on an existing Contract with the U.S. Army Corps of Engineers (USACE), they shall process the employee through the Huntington District USACE Security Management Office for background purposes.

1.4.4 For Contractors Requiring DOD Common Access Cards (CAC)

The documents listed below are required:

SF 85, Questionnaire for Non-Sensitive Positions (see http://www.opm.gov/forms/ to print form). FD 258, Contractor Fingerprint Card (one card for digital prints, two for ink prints) (NOTE: a trained/qualified individual shall take prints, ORI block on the FD 258 shall be USOPM000Z) (Contractor Fingerprint Cards (FD-258) may be obtained by Contracting Division by contacting the Huntington District Security Management Office).

Contractor shall report any changes in personnel, or at any time conditions change at least 5 working days prior to individual(s) need to have access to the site. The Contractor shall provide the same information as listed above for all new employees.

Following submission of paperwork, the Huntington District Security Management Office will conduct an initial criminal check based upon the information provided. If there are no issues, the Huntington District Security Management Office will make recommendations to the PCO or their Designated Representative. The Huntington District Security Management Office cannot give approval due to unfavorable report(s). The Huntington District Security Management Office shall coordinate with Office of Counsel and will jointly make recommendations to the PCO and/or the Designated Representative should a background investigation come back with derogatory information. The PCO will make the determination whether to allow the Contractor personnel to work on the site based on Security and Office of Counsel recommendations, and the PCO will advise the Contractor of the decision.

1.4.5 Foreign Nationals

The Contractor shall provide the package listed above, as well as additional materials noted below for all Foreign Nationals. The Contractor is to expect additional time in the approval process for all Foreign Nationals due to the level of review and elevation of the review to

SECTION 01 14 00 Page 5

Headquarters staff to complete. All Foreign Nationals shall be cleared 30 to 45 calendar days in advance of any site visit, tour or work on USACE owned/leased property. All Foreign Nationals shall comply with the following paragraph:

In accordance with Engineering Regulation 380-1-18, "Technology Transfer, Disclosure of Information and Contacts with Foreign Representatives" dated 1 August 1996, Section 4, all foreign nationals who work on Corps of Engineers' contracts shall be approved by the Headquarters US Army Corps of Engineers (HQ USACE) Foreign Disclosure Officer before beginning work on this contract; this regulation includes subcontractor employees. The Contractor shall submit to the Security Management Office, the names of all foreign nationals proposed for performance under this contract, along with documentation to verify legal admittance into the United States. Such documentation shall include at least one of the following: a U.S.

passport, Certificate of U.S. Citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), Alien Registration Card with photograph (INS Form I-151 or I-551), Employment Authorization Card (INS Form I-688A), etc.

In order to assure forms are properly completed, and to minimize time delays, the Contractor is encouraged to work closely with the Huntington District Security Management Office. The Government will return for correction incomplete forms, illegible forms, etc. which will delay the contractor / subcontractor from beginning work. A scanned copy of a valid passport shall be sent to the Security Management Office in order to formally request a visit to any Huntington District facilities, projects, owned or leased facility/spaces.

Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, Engineering or Army regulation or policy changes, etc. The Government shall add any changes to security requirements by modification to the contract.

The Contractor shall contact the Huntington District Security Management Office by phone, letter, or email at the following numbers/addresses:

CELRH-SM

502 Eighth Street Huntington, WV 25701

Scott E. Grandon, phone (304) 399-5661; email scott.e.grandon@usace.army.mil Matthew D. Green, phone (304) 399-5294; email matthew.d.green@usace.army.mil Stephen R. Curry, phone (304) 399-5695; stephen.r.curry@usace.army.mil

1.4.6 OPSEC/AT

a) Access and General Protection/Security Policy and Procedures. All contractor and all associated sub-contractors employees shall comply with applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative). The contractor shall also provide all information required for background checks to meet installation/facility access requirements to be accomplished by installation Provost Marshal Office, Director of Emergency Services or Security Office. Contractor workforce shall comply with all personal identity verification requirements (FAR clause 52.204-9, Personal Identity Verification of Contractor Personnel)

SECTION 01 14 00 Page 6 as directed by DOD, HQDA and/or local policy. In addition to the changes otherwise authorized by the changes clause of this contract, should the Force Protection Condition (FPCON) at any installation or facility change, the Government may require changes in contractor security matters or processes.

b) For contractors who do not require CAC, but require access to a DoD facility or installation. Contractor and all associated sub-contractors employees shall comply with adjudication standards and procedures using the National Crime Information Center Interstate Identification Index (NCIC-III) and Terrorist Screening Database (TSDB) (Army Directive 2014-05 / AR 190-13), applicable installation, facility and area commander installation/facility access and local security policies and procedures (provided by government representative, as NCIC and TSDB are available), or, at OCONUS locations, in accordance with status of forces agreements and other theater regulations.

c) For Contracts that Require OPSEC Training. All new contractor employees will complete Level I OPSEC Training within 30 calendar days of their reporting for duty. Additionally, all contractor employees shall complete annual OPSEC awareness training. The contractor shall submit certificates of completion for each affected contractor and subcontractor employee, to the COR or to the contracting officer (if a COR is not assigned), within 5 calendar days after completion of training. OPSEC awareness training is available at the following websites:

https://www.iad.gov/ ioss/ or http://www.cdse.edu/catalog/operations-security.html ; or it can be provided by the RA OPSEC Officer in presentation form which will be documented via memorandum.

d) Pre-screen candidates using E-Verify Program. The Contractor shall pre-screen Candidates using the E-verify Program ( http://www.uscis.gov/e-verify ) website to meet the established employment eligibility requirements. The Vendor shall ensure that the Candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible Candidates shall be provided to the COR no later than 3 business days after the initial contract award.

*When contracts are with individuals, the individuals will be required to complete a Form I?9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.

1.5 PAYMENT

No separate payment will be made for the work covered under this section and all costs in connection therewith shall be included in the applicable line item contract price to which the work pertains.

PART 2 PRODUCTS

Not Used

PART 3 EXECUTION

Not Used

SECTION 01 14 00 Page 7

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

1.2 SUBMITTALS

1.3 PROGRESS AND COMPLETION PICTURES

1.4 MINIMUM INSURANCE REQUIREMENTS

1.5 SECURITY REQUIREMENTS

1.6 AT/OPSEC REQUIREMENTS

1.7 PERFORMANCE OF WORK BY CONTRACTOR

1.8 VALUE ENGINEERING CHANGE PROPOSAL

1.9 PERFORMANCE EVALUATION OF CONTRACTOR

1.10 SUPERVISION

1.10.1 Minimum Communication Requirements

1.10.2 Superintendent Qualifications

1.10.2.1 Duties

1.10.3 Non-Compliance Actions

1.11 PRECONSTRUCTION CONFERENCE

1.11.1 Minimum Agenda

1.12 PARTNERING

1.12.1 Partnering Process

1.13 ELECTRONIC MAIL (E-MAIL) ADDRESS

1.14 PROGRESS MEETINGS

1.14.1 Minimum Agenda

1.15 PREINSTALLATION CONFERENCES

1.16 CALLED MEETINGS

1.17 MOBILIZATION

PART 2 PRODUCTS

2.1 DIGITAL PHOTOGRAPHS

2.2 VIEW LOCATION MAP

2.3 PAYMENT

PART 3 EXECUTION

SECTION 01 30 00 Page 1

SECTION 01 30 00

ADMINISTRATIVE REQUIREMENTS

PART 1 GENERAL

1.1 REFERENCES

The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.

U.S. ARMY CORPS OF ENGINEERS (USACE)

EM 385-1-1 (2014) Safety and Health Requirements Manual

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. When used, a designation following the "G" designation identifies the office that will review the submittal for the Government. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

View Location Map; G|CM Progress and Completion Pictures; G|CM

SD-07 Certificates

Authorized Change Document Individual; G|CM

a. Submit name of the individual authorized to receive change documents, and be responsible for informing others in Contractor's employ or Subcontractors of changes to the work.

b. Submit in accordance with Contract Clauses, CHANGES and

NOTIFICATION OF CHANGES.

1.3 PROGRESS AND COMPLETION PICTURES

Photographically document site conditions prior to start of construction operations. Provide monthly, and within one month of the completion of work, digital photographs, 16 meg apixal minimum resolution in JPEG file format showing the sequence and progress of work. Take a minimum of 30 digital photographs each month throughout the entire project from a minimum of ten views from points located by the Contracting Officer.

Submit as attachments to daily reports within RMS and as a monthly submittals. Indicate photographs demonstrating environmental procedures.

Name each file to indicate its location on the view location sketch. Also provide the view location sketch digital file. Include a date designator in file names. Cross reference submittals in the appropriate daily report. Photographs provided are for unrestricted use by the Government.

SECTION 01 30 00 Page 2

1.4 MINIMUM INSURANCE REQUIREMENTS

Provide the minimum insurance coverage required by FAR 28.307-2 LIABILITY, during the entire period of performance under this contract. Provide other insurance coverage as required by Kentuckylaw.

In reference to Contract Clause, INSURANCE--WORK ON A GOVERNMENT INSTALLATION, FAR 52.228-5, the Contractor shall procure and maintain, during the entire period of his performance under this contract, the following minimum insurance:

a. Workmen's Compensation. Workmen's Compensation and Occupational Disease Coverage, as legally required by the State wherein the work is being performed.

b. Comprehensive Automobile Liability Insurance. Bodily injury coverage with minimum limits of $200,000 per person and $500,000 per occurrence, and $100,000 per occurrence for property damage shall be required.

c. Comprehensive General Liability Insurance. Bodily injury coverage with minimum limit of $500,000 per occurrence shall be required. Property damage coverage with a minimum limit of $100,000 per occurrence shall be required.

d. Insurance Certification. Before commencing work under this contract, the Contractor shall certify to the Contracting Officer, in writing, that the required insurance has been obtained. The policies evidencing the required insurance shall contain an endorsement to the effect that any cancellation or any material change adversely affecting the Government's interest shall not be effective (1) for such period as the laws of the State in which this contract is to be performed prescribe or (2) until 30 calendar days after the insurer or the Contractor gives written notice to the Contracting Officer, whichever period is longer.

The Contractor shall be able to obtain bond/insurance and submit required plans (as stipulated in the terms of the contract) within 10 calendar days of receipt of Notice of Award.

1.5 SECURITY REQUIREMENTS

All Contractors and subcontractor employee(s) working on this contract who require access in and/or around any Huntington District facilities shall receive authorization to be on site at these facilities based upon a favorable background investigation in accordance with "Homeland Security Presidential Directive 12: Policy for a Common Identification Standard for Federal Employees and Contractors" (HSPD 12). The Huntington District Security Management Office shall submit contractor(s) personal information (List of Employees) to complete the basic background investigation in order to make a recommendation to the Contracting Officer of an employee's suitability for work on Government property. The Procuring Contracting Officer (PCO) has the right to deny any contractor or subcontractor employee from working on the contract based upon the results of the background investigation provided by the Huntington District Security Management Office. The Government, Contractor, and subcontractors shall not permit any employee(s) access to drawings, blueprints, records, photos, sites, or projects until the Huntington District Security Management Office has completed an Operations Security (OPSEC) review of such items and

SECTION 01 30 00 Page 3 determined they can be released.

For Contracts In Excess Of 1 Year Duration The Documents Listed Below Are Required:

The documents listed below are required (Investigation Package for Contractor and Subcontractor Employees):

SF 85, Questionnaire for Non-Sensitive Positions (see http://www.opm.gov/forms/ to print form). FD 258, Contractor Fingerprint Card (one card for digital prints, two for ink prints) (NOTE: a trained/qualified individual must take prints, ORI block on the FD 258 must be USOPM000Z) (Contractor Fingerprint Cards (FD-258) may be obtained by Contracting Division by contacting the Huntington District Security Management Office).

Contractor shall report any changes in personnel, or at any time conditions change at least 5 business days prior to individual(s) need to have access to the site. The Contractor shall provide the same information as listed above for all new employees.

Following submission of paperwork, the Huntington District Security Management Office will conduct an initial criminal check based upon the information provided. If there are no issues, the Huntington District Security Management Office will make recommendations to the PCO or their Designated Representative. The Huntington District Security Management Office cannot give approval due to unfavorable report(s). The Huntington District Security Management Office shall coordinate with Office of Counsel and will jointly make recommendations to the PCO and/or the Designated Representative should a background investigation come back with derogatory information. The PCO will make the determination whether to allow the Contractor personnel to work on the site based on Security and Office of Counsel recommendations, and the PCO will advise the Contractor of the decision.

Foreign Nationals: The Contractor shall provide the package listed above, as well as, additional materials noted below for all Foreign Nationals.

In accordance with Engineering Regulation 380-1-18, "Technology Transfer, Disclosure of Information and Contacts with Foreign Representatives" dated 1 August 1996, Section 4, all foreign nationals who work on Corps of Engineers' contracts shall be approved by the Headquarters US Army Corps of Engineers (HQ USACE) Foreign Disclosure Officer before beginning work on this contract; this regulation includes subcontractor employees. The Contractor shall submit to the Security Management Office, the names of all foreign nationals proposed for performance under this contract, along with documentation to verify legal admittance into the United States. Such documentation shall include at least one of the following: a U.S. passport, Certificate of U.S. Citizenship (INS Form N-560 or N-561), Certificate of Naturalization (INS Form N-550 or N-570), Alien Registration Card with photograph (INS Form I-151 or I-551), Employment Authorization Card (INS Form I-688A), etc.

In order to assure forms are properly completed, and to minimize time delays, the Contractor is encouraged to work closely with the Huntington District Security Management Office. The Government will return for correction incomplete forms, illegible forms, etc., which will delay the contractor/subcontractor from beginning work.

SECTION 01 30 00 Page 4

Security requirements are subject to change in accordance with HSPD-12, Office of Personnel Management, regulation or policy changes, etc. The Government will add any changes to security requirements by modification to the contract.

The Contractor shall contact the Huntington District Security Management Office by phone, letter, or e-mail at the following numbers/addresses:

CELRH-SM

502 Eighth Street Huntington, WV 25701

Scott E. Grandon, phone (304) 399-5661;

email scott.e.grandon@usace.army.mil

Stephen R. Curry, phone (304) 399-5695;

e-mail stephen.r.curry@usace.army.mil

Matthew D. Green, phone (304) 399-5294;

e-mail matthew.d.green@usace.army.mil

1.6 AT/OPSEC REQUIREMENTS

Contractors are required to comply with the following: Pre-screen candidates using E-Verify Program. The Contractor must pre-screen candidates using the E-verify Program (http://www.uscis.gov/e-verify) website to meet the established employment eligibility requirements. The Vendor must ensure that the candidate has two valid forms of Government issued identification prior to enrollment to ensure the correct information is entered into the E-verify system. An initial list of verified/eligible candidates must be provided to the Contracting Officer's Representative no later than three business days after the initial contract award. When contracts are with individuals, the individuals will be required to complete a Form I-9, Employment Eligibility Verification, with the designated Government representative. This Form will be provided to the Contracting Officer and shall become part of the official contract file.

The Contractor and all associated sub-contractors shall receive a brief/training (provided by the RA) on the local suspicious activity reporting program. This locally developed training will be used to inform employees of the types of behavior to watch for and instruct employees to report suspicious activity to the project manager, security representative or law enforcement entity. This training shall be completed within 30 calendar days of contract award and within 30 calendar days of new employees commencing performance with the results reported to the COR NLT 5 calendar days after the completion of the training.

1.7 PERFORMANCE OF WORK BY CONTRACTOR

The Contractor shall perform on the site, and with its own organization, work equivalent to at least 15 percent of the total amount of work to be performed under the contract. This percentage may be reduced by a supplemental agreement to this contract if, during performing the work, the Contractor requests a reduction and the Contracting Officer determines that the reduction would be to the advantage of the Government.

1.8 VALUE ENGINEERING CHANGE PROPOSAL

The Government encourages the Contractor to develop, propose and submit value engineering change proposals (VECP's) with respect to materials, SECTION 01 30 00 Page 5 equipment, and systems that fall under the jurisdiction of this contract.

The proposal is to be made voluntarily in accordance with Contract Clause

52.248-3 VALUE ENGINEERING-CONSTRUCTION.

1.9 PERFORMANCE EVALUATION OF CONTRACTOR

It is the USACE standard operating procedure that the Contracting Officer evaluate the Contractor's performance and prepare a performance report using the web-based application CPARS (Contractor Performance Assessment Reporting System) for construction contracts of 700,000 or more. After an evaluation (interim or final) is written by the Corps, the Contractor has a 60-day period to access, review and comment on the evaluation.

Accessing and using CPARS requires having specific software, called PKI certification, installed on the user's computer. The certification, a Department of Defense requirement, was implemented to provide security in electronic transactions. The certification software could cost approximately $100-$125 per certificate, per year and is purchased from an External Certificate Authorities (ECA) vendor. Current information about the PKI certification process and for contacting vendors can be found on the web site: http://www.cpars.gov. The Contractor is encouraged to participate in the performance evaluation process, access to CPARS and PKI certification is the sole responsibility of the Contractor.

1.10 SUPERVISION

1.10.1 Minimum Communication Requirements

Have at least one qualified superintendent, or competent alternate, capable of reading, writing, and conversing fluently in the English language, on the job-site at all times during the performance of contract work. In addition, if a Quality Control (QC) representative is required on the contract, then that individual shall also have fluent English communication skills.

1.10.2 Superintendent Qualifications

The project superintendent shall have a minimum of ten years experience in construction with at least five of those years as a superintendent on projects similar in size and complexity. The individual shall be familiar with the requirements of EM 385-1-1 and have experience in the areas of hazard identification and safety compliance. The individual shall be capable of interpreting a critical path schedule and construction drawings. The qualification requirements for the alternate superintendent are the same as for the project superintendent. The Contracting Officer may request proof of the superintendent's qualifications at any point in the project if the performance of the superintendent is in question.

For routine projects where the superintendent is permitted to also serve as the Quality Control (QC) Manager as established in Section 01 45 00.00 10 QUALITY CONTROL, the superintendent shall have qualifications in accordance with that section.

1.10.2.1 Duties

The project superintendent is primarily responsible for managing and coordinating day-to-day production and schedule adherence on the project.

The superintendent is required to attend partnering meetings, and quality control meetings. The superintendent or qualified alternative shall be on-site at all times during the performance of this contract until the

SECTION 01 30 00 Page 6 work is completed and accepted.

1.10.3 Non-Compliance Actions

The Project Superintendent is subject to removal by the Contracting Officer for non-compliance with requirements specified in the contract and for failure to manage the project to insure timely completion.

Furthermore, the Contracting Officer may issue an order stopping all or part of the work until satisfactory corrective action has been taken. No part of the time lost due to such stop orders is acceptable as the subject of claim for extension of time for excess costs or damages by the Contractor.

1.11 PRECONSTRUCTION CONFERENCE

After award of the contract the Contractor shall attend a Pre-Construction Conference prior to commencement of any work at the site unless otherwise approved by the Contracting Officer. The Contracting Officer will schedule the conference after Notice of Award. The Contractor will meet with the Contracting Officer to discuss and develop a mutual understanding relative to the administration of the value engineering and safety program, preparation of the schedule of prices or earned value report, shop drawings, and other submittals, scheduling programming, prosecution of the work, and clear expectations of the "Interim DD Form 1354" Submittal.

Major subcontractors who will engage in the work shall also attend.

The Contractor shall be able to begin work at the project site within five calendar days from the date of the Pre-Cconstruction Conference. Depending on the complexities and size of the Contract, the Pre-Cconstruction Conference may be held by telephone conference or in person at the project location site. If acceptable to the Government, an alternate location may be used.

1.11.1 Minimum Agenda

a. Review of the Contractor's Quality Control (CQC) plan submitted in accordance with Section 01 45 00.00 10 QUALITY CONTROL.

b. Introduction and Outline of Conference.

c. Safety.

d. Design Briefing.

e. Scheduling.

f. User Coordination.

g. Labor Relations.

h. Defense Priorities and Allocations System (DPAS).

i. Environmental Protection.

j. Contractor Organization.

k. Discussion of Critical Items, problem areas and questions .

l. The Contracting Officer will issue the minutes of the meeting to

SECTION 01 30 00 Page 7 all participants.

m. Discussion of the processes for the Joint Risk Management between the Contractor and the Government.

1.12 PARTNERING

To most effectively accomplish this contract, the Government requires the formation of a cohesive partnership within the Project Team whose members are from the Government, the Contractor and their Subcontractors. Key personnel from the key site staff, the End User (who will occupy the facility), the Government Design and Construction team and Subject Matter Experts, the Installation, the Contractor and Subcontractors, and the Designer of Record will be invited to participate in the Partnering process. The Partnership will draw on the strength of each organization in an effort to achieve a project that is without any safety mishaps, conforms to the Contract, and stays within budget and on schedule.

The Contracting Officer will provide Information on the Partnering Process and a list of key and optional personnel who should attend the Partnering meeting.

1.12.1 Partnering Process

Provide and host the Partnering sessions with key personnel of the Project Team, including Contractor personnel and Government personnel. Pay all costs associated with the Partnering effort including the Facilitator, the meeting room, and other incidental items. In exception, each participant bears their own costs for meals, lodging, and transportation associated with the Partnering sessions.

Before a Partnering session, coordinate with the Facilitator all requirements for incidental items (such as audio-visual equipment, easels, flipchart paper, colored markers, note paper, pens/pencils, colored flash cards), and have these items available at the Partnering session. Provide copies of documents for distribution to all attendees. Provide a Facilitator experienced in conducting Partnering Workshops, and who is acceptable to both the Government and the Contractor. The Facilitator is responsible for leading the team in a timely manner and making sure that issues are identified and resolved. A list of Partnering Facilitators is available from the Contracting Officer.

a. Schedule the Initial Partnering Session for a duration of one day minimum. Locate this session at a place off the construction site, as agreed to by the Contracting Officer and the Contractor. It may take place concurrently with the Pre-Construction Meeting.

b. Schedule follow-on Partnering Session(s) for a maximum of four hours.

Schedule them at no more than three- to six-month intervals.

Participants are encouraged to utilize electronic means to expedite meetings. Meetings may be held at a location at the project site, or in a Government Facility. Follow-on meetings may be held concurrently with other scheduled meetings. Attendees need only be those required to resolve current issues. Recommend using the same Facilitator from the Initial Partnering session to achieve best results and for continuity.

SECTION 01 30 00 Page 8

1.13 ELECTRONIC MAIL (E-MAIL) ADDRESS

Establish and maintain electronic mail (e-mail) capability along with the capability to open various electronic attachments as text files, pdf files, and other similar formats. Within ten calendar days after contract award, provide the Contracting Officer a single (only one) e-mail address for electronic communications from the Contracting Officer related to this contract including, but not limited to contract documents, invoice information, request for proposals, and other correspondence. The Contracting Officer may also use email to notify the Contractor of base access conditions when emergency conditions warrant, such as hurricanes or terrorist threats. Multiple email addresses are not allowed.

It is the Contractor's responsibility to make timely distribution of all Contracting Officer initiated e-mail with its own organization including field office(s). Promptly notify the Contracting Officer, in writing, of any changes to this email address.

1.14 PROGRESS MEETINGS

Schedule and administer weekly construction progress meetings, coordination meetings, called meetings, and preinstallation conferences, throughout progress of work.

The Contractor shall preside at meetings, record minutes, and distribute copies within two calendar days after meeting to participants and to entities affected by decisions at meetings, with one digital copy to the Contracting Officer or Contracting Officer's Representative (COR). Upload a digital copy to RMS.

Make physical arrangements, prepare agenda, and distribute notice of each meeting to participants, and to the Contracting Officer, four calendar days in advance of meeting date.

Attendance shall include but not limited to: Contracting Officer, Contractor, job superintendent, Contractor's Quality Control Manager, Safety Manager, subcontractors, and suppliers as appropriate to agenda;

professional consultants and utilities and agencies may attend as appropriate.

Location of Meetings will be determined by Contracting Officer.

1.14.1 Minimum Agenda

a. Approval of minutes of previous meetings.

b. Review of work progress.

c. Field observations, problems, and decisions.

d. Identification of problems which impede planned progress.

e. Review of submittals schedule and status of submittals.

f. Review of off-site fabrication and delivery schedules.

g. Maintenance of progress schedule.

h. Corrective measures to regain projected schedules.

SECTION 01 30 00 Page 9

i. Planned progress during succeeding work period, including a two-week look ahead provided by the Contractor presented in bar chart format.

j. Coordination of project progress.

k. Maintenance of quality and work standards.

l. Effect of proposed changes on progress schedule and coordination.

m. Other business relating to work.

n. Safety.

o. Value Engineering Review.

p. Joint Risk Management.

1.15 PREINSTALLATION CONFERENCES

When required in individual specification sections, convene a preinstallation conference at work site prior to commencing work of the section.

The require attendance of entities directly affecting, or affected by, work of the section shall be in attendance.

Notify the Contracting Officer or Contracting Officer's Representative (COR) seven calendar days in advance of meeting date.

Prepare agenda, preside at conference, record minutes, and distribute copies within seven calendar days after conference to participants, with one digital copy to the Contracting Officer. Upload a digital copy to RMS.

Review conditions of installation, preparation and installation procedures, and coordination with related work.

1.16 CALLED MEETINGS

At any time during the construction period, the Contracting Officer may call for special meetings with the Contractor's staff to review the work.

The Contractor shall attend all called meetings, record minutes, and distribute copies within seven calendar days after the meeting, with one digital copy to the Contracting Officer. Upload a digital copy to RMS.

1.17 MOBILIZATION

Contractor shall mobilize to the jobsite within 60 calendar days of contract award unless otherwise directed by the terms of the contract.

Mobilize is defined as having equipment and having a physical presence of at least one person from the Contractor's team on the jobsite.

PART 2 PRODUCTS

2.1 DIGITAL PHOTOGRAPHS

Digital photographs shall be submitted at full resolution, not

SECTION 01 30 00 Page 10 compressed. The Contractor shall furnish, in Adobe PDF format, a document with each month's photographs which lists the following identifying information for each photographic image:

Name and Location of project Contract number Contractor (and subcontractor if applicable) Date taken File Name Orientation of view and brief description of work depicted

Each photograph shall be sequentially numbered and arranged with a consistent file naming convention (e.g. 2020_12 15 Time_Name_Orientation.jpg). The identifying data shall be placed in the document accompanying the photographs. No identifying data, except the date stamp, shall appear on the electronic digital photographs. Electronic images shall be recorded with a minimum of 24 bit color and no reduction in actual picture size.

2.2 VIEW LOCATION MAP

Submit, prior to or with the first digital photograph submittals, a sketch or drawing indicating the required photographic locations. Update as required if the locations are moved.

2.3 PAYMENT

A credit to the Government of $500.00 will be made each month the Contractor fails to submit photographs by the…