A.02.13 NAB_COVID ACF PH2 J&A Hagerstown Correctional ACF.pdf
PDF 2 MB Posted
- Solicitation number
- W912DR20C0019
About this file
This document provides a justification for a sole-source contract awarded to address an urgent need arising from the COVID-19 national emergency declaration. The U.S. Army Corps of Engineers Baltimore District awarded a letter contract on an other than full and open competition basis to Clark Construction Group on April 10, 2020. The contract was for design-build services to retrofit an existing building at the Hagerstown Correctional Facility in Maryland into a temporary non-acute Alternate Care Facility to support COVID-19 response efforts. The estimated value was $5 million to be completed within three weeks. However, the requirement was subsequently canceled by the State of Maryland and the contract terminated for convenience on April 23, 2020. Negotiation of the termination settlement is underway.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Digitally signed by
BECK.PAULA.M.1041789456
Date: 2020.05.01 14:47:20 -04'00'
BROWN.TRISTA
N.S.1394813717
Digitally signed by
BROWN.TRISTAN.S.13948137
Date: 2020.05.05 12:35:10 -04'00'
SEE APPROVAL PAGE
30 APR 20
1 May 20
29 APR 20
29 APR 20
NAB20-0031
After-the-Fact Justification and Approval for
Other than Full and Open Competition
1. CONTRACTING AGENCY: U.S. Army Corps of Engineers (USACE), Baltimore District (CENAB), Contracting Division, Baltimore, MD
2. DESCRIPTION OF ACTION: In support of Presidential National Emergency Declaration Concerning the Novel Coronavirus Disease (COVID-19) Outbreak, dated 13 March 2020, after the-fact approval is requested for a Justification and Approval (J&A) for a two-phase design build construction, firm fixed price (FFP) Letter Contract awarded to Clark Construction Group, 7500 Old Georgetown Rd, Bethesda, MD 20814-6133, on an other than full and open competition/sole-source basis under circumstances of Unusual and Compelling Urgency. The action was awarded as an Undefinitized Contract Action (UCA) and will be definitized as a FFP "C-type" contract. This contract was terminated for convenience on April 23, 2020 due to the State of Maryland cancelling this requirement. The type of funds utilized are Federal Emergency Management Administration (FEMA) Disaster Relief funds. There were no options identified for the contract.
3. DESCRIPTION OF SUPPLIES/SERVICES: The purpose of this contract was to provide design-build construction services in accordance with the Presidential National Emergency Declaration. The work effort consisted of the design and construction to retrofit Building 192 of the Hagerstown Correctional Facility in Hagerstown, Maryland into a Non-Acute Alternate Care Facility (ACF) that can meet basic healthcare functions with an emphasis on patient care, infection control, fire protection, and life safety. The temporary ACF shall also serve as a satellite patient ward supported by an on-site infirmary and a nearby full service hospital. The on-site infirmary and full service hospital would, however, provide the logistics, materials, waste management support, and nutrition care. This Justification is for the temporary Non-Acute ACF in Hagerstown, MD. The estimated total value of the contract awarded under this J&A was $5,000,000.00 based on the Government's estimate for the project and the not-to-exceed (NTE) amount for the awarded UCA. The period of performance for the design-build contract was anticipated to be three weeks in total and performance began immediately upon award of the UCA in order to meet this aggressive schedule. The requirement was subsequently canceled and the contract is being terminated for convenience. Negotiation of a termination settlement is underway.
4. AUTHORITY CITED: lOU.S.C. § 2304(c)(2), as implemented by Federal Acquisition Regulation (FAR) 6.302-2, Unusual and Compelling Urgency.
5. REASON FOR AUTHORITY CITED: Consistent with Defense Federal Acquisition Regulation Supplement (DF ARS) Procedures, Guidance and Information (PGI) 206.302- 2(b ), "use of this [ unusual and compelling urgency] authority may be appropriate . . . [for] construction needed at once because of fire, flood, explosion, or other disaster." In support of the Presidential National Emergency Declaration, the agency's need for this construction was of such an unusual and compelling urgency that the Government would have been seriously injured unless the agency was permitted to sole-source a contract to the single firm selected from the group of firms that were down-selected after Phase I of this two-phase design-build acquisition.
MORROW.PATRI
CIA.1367939946
Digitally signed by
MORROW.PATRICIA.1367939946
Date: 2020.05.01 15:42:34 -04'00'
MORROW.PATRI
CIA.1367939946
Digitally signed by
MORROW.PATRICIA.1367939946
Date: 2020.05.01 15:43:29 -04'00'
5 May 2020