This sole source determination document identifies the need to procure transformer repair parts from a specific manufacturer, Powell, on a sole source basis. The U.S. Army Corps of Engineers, Walla Walla District requires iso-phase bellows and other parts from Powell to overhaul generators at the Lower Granite Powerhouse. The parts are needed to replace worn items and maintain critical transformers that support fish passage, water quality mitigation and power generation. No other manufacturer can produce parts that ensure proper fit and compatibility without reverse engineering the existing designs. Market research found no other sources that meet requirements. A price analysis will ensure fair and reasonable pricing from Powell. Two small business sources sought responses were received but only one bid in response to the solicitation, and additional time extensions could impact maintenance windows and revenue from lost power generation.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
- 1 -
Control Number 23-0015
SOLE SOURCE DETERMINATION
(POWELL)
FAR Subpart 13.106-1(b)
1. CONTRACTING AGENCY: US Army Corps of Engineers (USACE), Walla Walla District (CENWW- CT) 201 North 3rd, Walla Walla, WA 99362.
2. DESCRIPTION OF THE ACTION: This action is for a new Firm Fixed Price (FFP) contract to purchase HITACHI/ABB Generator Step Up (GSU) Transformer overhaul parts such as the transformer Powell T1 Iso-phase bellows. This action meets the definition of a commercial item as defined in FAR
2.101. This action will be funded by FY23 BPA NREX funding.
3. DESCRIPTION OF THE SERVICES/SUPPLIES: This action is for the procurement of POWELL T1
Iso-phase bellows for use on HITACHI merged with ABB Generator Step Up (GSU) Transformer, Westinghouse GSU Transformers. The POWELL components will be used as replacements during transformer maintenance at the Lower Granite Powerhouse. Below is a list of all the required items:
Manufacturer Part Number Description Qty
POWELL 1560950 Iso-Phase Baffles 12
The estimated total value of this action is below the simplified acquisition threshold (SAT).
Anticipated cost:
4. AUTHORITY CITED:
FAR 13.106-l (b) Soliciting from a single source. (1) For purchases not exceeding the simplified acquisition threshold, contracting officers may solicit from one source if the contracting officer determines that the circumstances of the contract action deem only one source reasonably available (e.g., urgency, exclusive licensing agreements, brand name, or industrial mobilization).
FAR 11.105(a)(1) the particular brand name, product, or feature is essential to the Government's requirements, and market research indicates other companies' similar products, or products lacking the particular feature, do not meet, or cannot be modified to meet, the agency's needs.
5. REASON FOR AUTHORITY CITED:
a. BACKGROUND:
• Lower Granite Project presently has 6 Westinghouse Generator Step Up (GSU) transformers. Lower
Granite utilizes three single-phase transformers to transmit 3-phase power to the BPA switchyard and power grid per bank (T1 & T2). The T1 bank, consists of T1A, T1B, and T1C and the T2 bank consists of T2A, T2B and T2C. T1A was overhauled in Nov. 2022-Jan 2023 but the worn-out bellows were not replaced on T1A.
• The scheduling and coordination of transformer maintenance represents over a year of effort by all parties to ensure a planned temporary outage create as little impact to normal operations as possible.
Coordinating parties include, but are not limited to, fish managers, BPA, and Operations at Lower Granite.
• Maintenance and outage timing is significant as any disruption(s) greatly impacts ESA listed fish and water quality, and power generation mission(s).
- 2 -
b. JUSTIFICATION:
• The remaining transformers (T1B, T1C and T2 bank) are leaking and need overhaul parts. The POWELL parts listed above are required since the existing parts have reached the end of their service life. The parts needed are critical and must be replaced in kind. The current bellows are produced solely by POWELL and no other manufacturer can make the parts without reverse engineering them.
• Moreover, as the market research will show, no other business, large or small, are able to meet our requirements.
• Therefore, procuring critical parts and replacing in kind through the sole source (POWELL) will remove unnecessary performance and compatibility risks, ultimately preventing additional costs and loss of production revenue.
c. IMPACT:
• There is no way to accurately estimate unforeseen labor time and costs associated with using another manufacturer regarding form, fit, and function as the products would be new. If alternative, non-Brand specific products are purchased, it is unknown how much each transformer will need to be retrofitted to enable use of a different manufacturer’s parts.
• T1 bank transformers service 4 generating units critical for adult fish passage, river total dissolved gas mitigation, and power generation. Outages of the named transformer(s), planned or otherwise, represent an extremely high-cost impact with the last similar outage costing in lost power generation revenue.
• Therefore, if parts are not able to be procured to meet mission needs, the resulting failure would have an extremely high-cost impact both in dollar value and mission function.
6. ALTERNATIVES:
a. No reasonable alternatives to named products are available. If Lower Granite cannot purchase named parts there is no way to predict the quality and or reliability of those manufactured parts. Not knowing the source of the parts, as well as, going with a manufacturing that doesn’t hold the prints for the Westinghouse bellows parts (POWELL) adds additional time, costs, and risk to these transformer repairs. Powell can provide known solutions and are replacing in kind items. The lost generation revenue can range up to per day, per unit. An unplanned transformer outage can cost upwards of per day in lost revenue.
b. Additionally, the market research shows that no other reasonable source is able to provide the necessary products apart from POWELL.
7. DETERMINATION OF FAIR AND REASONABLE COSTS: A price analysis will be completed after receipt of quotation on the basis of historical pricing and the IGE. No award will be made unless prices are determined fair and reasonable.
8. EFFORTS TO OBTAIN COMPETITION:
a. A full and open Sources Sought was completed and two eligible, small business responses were received.
However, no large business responses were received. This created a reasonable expectation for price competition among small businesses.
b. In response to the sources sought, a solicitation was issued as a 100% small business set-aside. Between the sources sought and interests expressed during the solicitation, there was a reasonable expectation to receive quotes from at least small businesses. However, only response was received after two extensions (Solicitation was public for 23 calendar days). Two additional requests for extension were received since.
However, due to strict service windows, projected lead times for required parts, and the critical nature of this project we were unable to accommodate the requests for extension. To do so would have placed the