This document is a Notice of Intent to Award a Sole Source contract for the supply of new switchgear assemblies and replacement of existing 80+ year old main unit oil circuit breakers at Powerhouse 1 at Bonneville Lock and Dam.

The scope of the project is the manufacturing of custom 15 kV switchgear to fit within the existing space at Bonneville Powerhouse 1 on Elevation 65. The contract will include supplying ten (10) Main Unit Breaker Switchgear Assemblies. Eaton Corporation is the designer of record and the government intends to solicit and negotiate with only Eaton Corporation under the authority of FAR 6.302-1 as the only responsible source. The North American Industry Classification System (NAICS) code for this acquisition is 335313, with a small business size standard of 1,250 employees. All responsible sources may submit capability statements, proposals, or exceptions within 5 days of this notice, which will be considered by the government.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOLICITATION

W9127N24R0036

Bonneville Lock and Dam Multnomah County, OR

Powerhouse One Main Unit Breaker Replacement

Project Manual

CODE

(Hour)

PAGE(S)

until 03:00 PM local time 24 May 2024

X

A X B

C D

EX

X G F 35 - 49

X H

Cory.R.Pfenning@usace.army.mil

RATING PAGE OF PAGES

7. ISSUED BY

(Date)

IMPORTANT - Award will be made on this Form, or on Standard Form 26, or by other authorized official written notice.

Previous Edition is Unusable 33-134 STANDARD FORM 33 (REV. 9-97)

Prescribed by GSA FAR (48 CFR) 53.214(c)

1 49

(If other than Item 7)

15A. NAME 16. NAME AND TITLE OF PERSON AUTHORIZED TO

AND

ADDRESS

SIGN OFFER (Type or print)

OF

OFFEROR

AMENDMENT NO. DATE

15B. TELEPHONE NO (Include area code) 17. SIGNATURE15C. CHECK IF REMITTANCE ADDRESS

IS DIFFERENT FROM ABOVE - ENTER

SUCH ADDRESS IN SCHEDULE.

18. OFFER DATE

1. THIS CONTRACT IS A RATED ORDER

UNDER DPAS (15 CFR 700)

2. CONTRACT NO.

W9127N 8. ADDRESS OFFER TO

See Item 7

9. Sealed offers in original and 1 copies for furnishing the supplies or services in the Schedule will be received at the place specified in Item 8, or if handcarried, in the depository located in

CAUTION - LATE Submissions, Modifications, and Withdrawals: See Section L, Provision No. 52.214-7 or 52.215-1. All offers are subject to all terms and conditions contained in this solicitation.

10. FOR INFORMATION

CALL:

A. NAME (NO COLLECT CALLS)

CORY R PFENNING 503-808-4398

11. TABLE OF CONTENTS

SOLICITATION/ CONTRACT FORM

SUPPLIES OR SERVICES AND PRICES/ COSTS

2 - 3

X I CONTRACT CLAUSES

DESCRIPTION/ SPECS./ WORK STATEMENT

PACKAGING AND MARKING

J LIST OF ATTACHMENTS

INSPECTION AND ACCEPTANCE

DELIVERIES OR PERFORMANCE

X K

REPRESENTATIONS, CERTIFICATIONS AND

OTHER STATEMENTS OF OFFERORS

CONTRACT ADMINISTRATION DATA 6

SPECIAL CONTRACT REQUIREMENTS

OFFER (Must be fully completed by offeror) 7 - 11 M

L INSTRS., CONDS., AND NOTICES TO OFFERORS

EVALUATION FACTORS FOR AWARD

NOTE: Item 12 does not apply if the solicitation includes the provisions at 52.214-16, Minimum Bid Acceptance Period.

is inserted by the offeror) from the date for receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified in the schedule.

13. DISCOUNT FOR PROMPT PAYMENT

(See Section I, Clause No. 52.232-8)

14. ACKNOWLEDGMENT OF AMENDMENTS

(The offeror acknowledges receipt of amendments

AMENDMENT NO. DATE

to the SOLICITATION for offerors and related documents numbered and dated):

FACILITY

12. In compliance with the above, the undersigned agrees, if this offer is accepted within calendar days (60 calendar days unless a different period

SOLICITATION, OFFER AND AWARD

X

(X) SEC. DESCRIPTION (X) SEC. DESCRIPTION PAGE(S)

PART I - THE SCHEDULE

26. NAME OF CONTRACTING OFFICER (Type or print) 27. UNITED STATES OF AMERICA 28. AWARD DATE

EMAIL:TEL: (Signature of Contracting Officer)

CODE CODE

B. TELEPHONE (Include area code) C. E-MAIL ADDRESS

AWARD (To be completed by Government)

19. ACCEPTED AS TO ITEMS NUMBERED 20. AMOUNT 21. ACCOUNTING AND APPROPRIATION

22. AUTHORITY FOR USING OTHER THAN FULL AND OPEN COMPETITION:

10 U.S.C. 2304(c)( ) 41 U.S.C. 253(c)( ) (4 copies unless otherwise specified)

23. SUBMIT INVOICES TO ADDRESS SHOWN IN ITEM

24. ADMINISTERED BY (If other than Item 7) CODE 25. PAYMENT WILL BE MADE BY CODE

PART IV - REPRESENTATIONS AND INSTRUCTIONS

PART III - LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS

12 - 34

PART II - CONTRACT CLAUSES

USACE, PORTLAND DISTRICT

333 SW 1ST AVE

PORTLAND OR 97204

503-808-4510

FAX:

TEL:

FAX:

TEL:

NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid" and "bidder".

SOLICITATION

6. REQUISITION/PURCHASE NO.5. DATE ISSUED

30 Sep 2024

4. TYPE OF SOLICITATION

SEALED BID (IFB)

NEGOTIATED (RFP)

[ X ]

3. SOLICITATION NO.

W9127N24R0036

Section B - Supplies or Services and Prices

ITEM NO SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

0001 10 Each

Main Unit Breaker Switchgear Assemblies

FFP

Supply of ten (10) Main Unit Breaker Switchgear Assemblies. Measurement will be made on a per EACH basis for the Supply of 10 Main Unit Breaker Switchgear Assemblies. Each Main Unit Switchgear Assembly for includes all necessary Breakers (1XJ1 through 1XJ10), Disconnect Switches (1ZJ1D through 1ZJ10D), and necessary bus transitions FOB: Destination SHIP VIA: Best Way ( Shippers Option)

PSC CD: 6110

NET AMT

CONTRACT MINIMUM/MAXIMUM QUANTITY AND CONTRACT VALUE

The minimum quantity and contract value for all orders issued against this contract shall not be less than the minimum quantity and contract value stated in the following table. The maximum quantity and contract value for all orders issued against this contract shall not exceed the maximum quantity and contract value stated in the following table.

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

AMOUNT

$2,000,000.00 $12,000,000.00

CLIN DELIVERY/TASK ORDER MINIMUM/MAXIMUM QUANTITY AND CLIN ORDER VALUE

The minimum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not be less than the minimum quantity and order value stated in the following table. The maximum quantity and order value for the given Delivery/Task Order issued for this CLIN shall not exceed the maximum quantity and order value stated in the following table.

CLIN

MINIMUM

QUANTITY

MINIMUM

AMOUNT

MAXIMUM

QUANTITY

MAXIMUM

AMOUNT

Section B-1

0001 $ $

Section B-2

Bonneville Powerhouse I Main Unit Breaker Replacement

PROJECT TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

01 11 00.00 25 SUMMARY OF WORK

01 22 00.00 25 MEASUREMENT AND PAYMENT

01 33 00 SUBMITTAL PROCEDURES

01 42 00 SOURCES FOR REFERENCE PUBLICATIONS

01 45 00.15 25 RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

01 78 23.00 25 OPERATION AND MAINTENANCE DATA

01 78 39.00 25 PROJECT RECORD DOCUMENTS

DIVISION 26 - ELECTRICAL

26 13 13.00 26 METAL-ENCLOSED SWITCHGEAR

-- End of Project Table of Contents --

PROJECT TABLE OF CONTENTS Page 1

C-1

SECTION TABLE OF CONTENTS

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 11 00.00 25

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUMMARY

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

1.2.2 Location

1.3 CONTRACT DRAWINGS

1.4 OCCUPANCY OF PREMISES

1.5 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

PART 2 PRODUCTS

PART 3 EXECUTION

-- End of Section Table of Contents --

SECTION 01 11 00.00 25 Page 1

C-2

SECTION 01 11 00.00 25

SUMMARY OF WORK

PART 1 GENERAL

1.1 SUMMARY

This Section provides a summary of the various Contract work elements and their relationship to each other. This summary describes work activities within interim construction completion dates. This Section does not provide the technical detail for particular work activities, but describes the work as a whole, providing overall perspective to the separate tasks and their interrelationships. Use this Section in conjunction with all the Specification Sections and the Drawings to establish the total work requirements.

1.2 WORK COVERED BY CONTRACT DOCUMENTS

1.2.1 Project Description

This Section is a general summary of the required base Contract work and is not all-inclusive. The work described within these specifications include, but not necessarily be limited to the following:

Supply 10 Main Unit Breaker Switchgear Assemblies, each consisting of a breaker, internal bus, a disconnect switch, and bus transition sections.

1.2.2 Location

The work site is located at Bonneville Powerhouse No. 1. Contractor access to the work site will be from I-84/US-30.

1.3 CONTRACT DRAWINGS

a. The Drawings that accompany these Specifications are a part thereof.

b. One set of full size Contract drawings, maps, and Specifications will be furnished to the Contractor without charge per Section 00700 FAR 252.236-7001, CONTRACT DRAWINGS AND SPECIFICATIONS. Reference publications will not be furnished.

c. Immediately check furnished Drawings and notify the Government of any discrepancies.

1.4 OCCUPANCY OF PREMISES

Before any deliveries, arrange with the Contracting Officer a sequence of procedure of delivery, means of access, space for storage of materials.

1.5 GOVERNMENT-FURNISHED MATERIAL AND EQUIPMENT

a. Pursuant to FAR 52.245-1, GOVERNMENT PROPERTY, the Government will furnish the following materials:

SECTION 01 11 00.00 25 Page 2

C-3

ITEM NO. DESCRIPTION QUANTITY

0001 Mounting Modules-Eaton 15kV 75kA VCP-WG mini-mod cells.

b. Quantities stated for the above items not marked with an asterisk are all that will be furnished by the Government. Furnish any additional quantities required.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

-- End of Section --

SECTION 01 11 00.00 25 Page 3

C-4

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 22 00.00 25

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 GENERAL INFORMATION

1.2 UNIT PRICE PAYMENT ITEMS

1.3 JOB PAYMENT ITEMS

1.4 MEASUREMENT AND PAYMENT

1.4.1 Supply 10 Main Unit Breaker Switchgear Assemblies, CLIN 0001

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 22 00.00 25 Page 1

C-5

SECTION 01 22 00.00 25

MEASUREMENT AND PAYMENT

PART 1 GENERAL

1.1 GENERAL INFORMATION

In each instance, the Contract price for an item will constitute full compensation as herein specified, as shown, or as otherwise approved. The Contract price and payment will also constitute full compensation for all work incidental to completion of the item, unless such work is otherwise specifically mentioned for separate payment under another line item. In the event any work is required by the specifications Sections or by the Drawings and not specifically mentioned in the Paragraphs MEASUREMENT and PAYMENT, separate or direct payment will not be made and all costs thereof are incidental to the work and included in the Contract prices and payments for all Contract Line Item Numbers (CLIN) listed in the price schedule.

1.2 UNIT PRICE PAYMENT ITEMS

Payment items for the work of this Contract on which the Contract unit price payments will be made are listed in Section 00 10 00, PRICE SCHEDULE, and described below. The unit price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment; performing all associated Contractor quality control, environmental protection, commissioning, preparation of working as-built drawing redlines, Operation and Maintenance (O&M) manuals, tests and reports, meeting safety requirements; and for performing all work required for each of the unit price items.

1.3 JOB PAYMENT ITEMS

Payment items for the work of this Contract for which Contract job payments will be made are listed in Section 00 10 00, PRICE SCHEDULE, and described below. All costs for items of work, which are not specifically mentioned to be included in a particular job item, must be included in the listed job item most closely associated with the work involved. The job price and payment made for each item listed will constitute full compensation for furnishing all plant, labor, materials, and equipment;

performing all associated Contractor quality control, environmental protection, commissioning, preparation of working as-built drawing redlines, O&M manuals, tests and reports, meeting safety requirements; and for performing all work required for which separate payment is not otherwise provided.

MANDATORY ITEMS

1.4 MEASUREMENT AND PAYMENT

1.4.1 Supply 10 Main Unit Breaker Switchgear Assemblies, CLIN 0001

a. Measurement: Measurement will be made on a per EACH basis for the Supply of 10 Main Unit Breaker Switchgear Assemblies. Each Main Unit Switchgear Assembly for includes all necessary Breakers (1XJ1 through

SECTION 01 22 00.00 25 Page 2

C-6

1XJ10), Disconnect Switches (1ZJ1D through 1ZJ10D), and necessary bus transitions.

b. Payment: Payment will be made at the Contract amount under

CLIN 0001.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

SECTION 01 22 00.00 25 Page 3

C-7

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 GENERAL INFORMATION

1.2 SUBMITTALS

1.3 DEFINITIONS

1.3.1 Submittal Descriptions (SD)

1.3.2 Approving Authority

1.3.3 Work

1.4 SUBMITTAL DESIGNATION

1.5 SUBMITTAL REGISTER

1.5.1 Maintain Submittal Register

1.5.2 Use of Submittal Register

1.5.3 Government Approved Submittals

1.5.3.1 Quantity of Submittals

1.5.3.2 Processing of "G" Submittals.

1.5.4 Information Only Submittals

1.5.4.1 General

1.5.4.2 Processing of Information Only Submittals

1.6 SUBMITTAL COORDINATION

1.6.1 Submittal Coordination Meeting

1.6.2 Submittal Register ENG Form 4288-R

1.6.3 Submittal Register Updates

1.7 SCHEDULING

1.8 TRANSMITTAL FORM (ENG FORM 4025-R)

1.9 CROSS-REFERENCE (ENG FORM 4288-R/ENG FORM 4025-R)

1.10 SUBMITTAL PROCEDURES

1.10.1 e-Submittals

1.10.2 Approval of Submittals by the Contractor

1.10.3 Drawings

1.10.3.1 Printed Material

1.11 SAMPLES REQUIRING VISUAL INSPECTION

1.12 CERTIFICATES OF COMPLIANCE

1.13 CERTIFICATES OF COMPLIANCE

1.14 DISAPPROVED SUBMITTALS

1.15 APPROVED SUBMITTALS

1.16 APPROVED SAMPLES

1.17 CONTRACTOR'S FILES

1.18 PAYMENT

1.19 CONTRACTOR APPROVAL STAMP

1.20 CONTRACTOR APPROVAL STAMP

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 33 00 Page 1

C-8

SECTION 01 33 00 Page 2

C-9

SECTION 01 33 00

SUBMITTAL PROCEDURES

PART 1 GENERAL

1.1 GENERAL INFORMATION

a. Make submittals as required by the Specifications. The Contracting Officer (CO) may request submittals in addition to those specified when deemed necessary to adequately describe the work covered in the respective Sections.

b. Use the same units of weights and measures on all submittals as those used in the Contract Drawings.

c. Each submittal must be complete and in sufficient detail to allow ready determination of compliance with Contract requirements.

d. The Contractor's Quality Control (CQC) System Manager must check and approve all items prior to submittal and stamp, sign, and date indicating action taken. Proposed deviations from the Contract requirements must be clearly identified. Submittals must include items such as: Contractor's, manufacturer's, or fabricator's drawings; descriptive literature including (but not limited to) catalog cuts, diagrams, operating charts or curves; test reports; test cylinders; samples; O&M manuals (including parts list);

certifications; warranties; and other such required submittals.

e. Submittals requiring Government approval must be scheduled and approved prior to the acquisition of the material or equipment covered thereby.

f. Pick up and dispose of samples not incorporated into the work in accordance with manufacturer's Safety Data Sheets (SDS) and in compliance with existing laws and regulations.

g. Submittals requiring professional licensure, signature, and stamp must comply with all State professional licensing and registration requirements.

1.2 SUBMITTALS

Government approval is required for submittals with a "G" designation;

submittals not having a "G" designation are for information only. Submit the following in accordance with this Section:

SD-01 Submittals

Submittal Register; G

SD-07 Certificates

Authorized Shop Drawing Approvers

SECTION 01 33 00 Page 3

C-10

1.3 DEFINITIONS

1.3.1 Submittal Descriptions (SD)

Submittal requirements are specified in the technical Sections and in the preliminary submittal register (ENG Form 4288-R, Attachment A1).

Submittals are identified by Submittal Description (SD) numbers and titles as follows:

SD-01 Submittals

a. Submittals required prior to start of onsite activities.

SD-02 Shop Drawings

a. Drawings, diagrams, and schedules specifically prepared to illustrate some portion of the work.

b. Diagrams and instructions from a manufacturer or fabricator for use in producing the product and as aids to the Contractor for integrating the product or system into the project.

c. Drawings prepared by or for the Contractor to show how multiple systems and interdisciplinary work will be coordinated.

SD-03 Product Data

a. Catalog cuts, illustrations, schedules, diagrams, performance charts, instructions and brochures illustrating size, physical appearance, and other characteristics of materials, systems, or equipment for some portion of the work.

b. Warranty language when the Contract requires extended product warranties.

SD-06 Test Reports

a. Report signed by authorized official of testing laboratory that a material, product, or system identical to the material, product, or system to be provided has been tested in accordance with specified requirements. (Testing must have been within three years of date of Contract award for the project.)

b. Report which includes findings of a test required to be performed by the Contractor on an actual portion of the work or prototype prepared for the project before shipment to job site.

c. Report which includes finding of a test made at the job site or on sample taken from the job site, on portion of work during or after installation.

d. Investigation reports.

e. Daily logs and checklists.

f. Final acceptance test and operational test procedure.

g. Any reports required by the CO or designated representative to assure successful completion of tasks during the life of the Contract.

SECTION 01 33 00 Page 4

C-11

SD-07 Certificates

a. Statements printed on the manufacturer's letterhead and signed by responsible officials of manufacturer of product, system, or material attesting that product, system, or material meets specification requirements. Must be dated after award of project Contract and clearly name the project.

b. Document required of Contractor, or of a manufacturer, supplier, installer, or subcontractor through Contractor, the purpose of which is to further quality of orderly progression of a portion of the work by documenting procedures, acceptability of methods or personnel qualifications.

c. Confined space entry permits.

d. Text of posted operating instructions.

SD-10 Operation and Maintenance Data

a. Data that is furnished by the manufacturer, or the system provider, to the equipment operating and maintenance personnel, including manufacturer's help and product line documentation necessary to maintain and install equipment. This data is needed by operating and maintenance personnel for the safe and efficient operation, maintenance, and repair of the item.

b. This Data is intended to be incorporated in an operations and maintenance manual or control system.

SD-11 Closeout Submittals

a. Documentation to record compliance with technical or administrative requirements or to establish an administrative mechanism.

b. Special requirements necessary to properly close out the Contract.

For example, Record Drawings and as-built drawings.

1.3.2 Approving Authority

Office or designated person authorized to approve submittal.

1.3.3 Work

As used in this Section, on-site activities required by Contract documents.

1.4 SUBMITTAL DESIGNATION

Submittals are classified as follows:

a. Government Approved (G). Government approval is required for critical materials, deviations, an "or equal" decision, equipment whose compatibility with the entire system must be checked, and other items as designated by the CO.

b. Information Only. Submittals not requiring Government approval will be for information only.

SECTION 01 33 00 Page 5

C-12

1.5 SUBMITTAL REGISTER

1.5.1 Maintain Submittal Register

a. Prepare and maintain Submittal Register, ENG Form 4288-R, see Section 01 45 00.15 25, RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM), as the work progresses. Do not change data which is output in columns (c), (d), (e), and (f) as delivered by Government; retain data which is output in columns (a), (g), (h), and (i) as approved.

This list may not be all inclusive and additional submittals may be required. Do not preassign transmittal numbers when preparing the submittal register. The preliminary and then the approved submittal register will become the scheduling documents and will be updated monthly and used to control submittals throughout the life of the Contract.

b. The Government will provide the preliminary submittal register in electronic format with the following fields completed, to the extent that will be required by the Government during subsequent usage.

Column (c): Lists Specification Section in which submittal is required.

Column (d): Lists each submittal description (SD No. and type, e.g. SD-02 Shop Drawings) required in each Specification Section.

Column (e): Lists one principal paragraph in Specification Section where a material or product is specified. This listing is only to facilitate locating submitted requirements. Do not consider entries in column (e) as limiting project requirements.

c. Thereafter, track all submittals by maintaining a complete list, including completion of all data columns, including dates on which submittals are received and returned by the Government.

1.5.2 Use of Submittal Register

Submit submittal register with project schedule and QC plan. Verify that all submittals required for work are listed and add missing submittals.

Coordinate, update, and complete the fields on the submitted register in RMS CM with the project schedule and QC plan.

1.5.3 Government Approved Submittals

1.5.3.1 Quantity of Submittals

SD-01, SD-02, SD-03, and SD-05 through SD-11 submittals: Upload submittals with corresponding ENG 4025-R transmittal forms (Attachment A2) as outlined in Paragraph entitled E-SUBMITTALS . SD-04 submittals: Submit two samples of "G" submittals with two corresponding ENG 4025-R transmittal forms, unless otherwise specified. Upon completion of review, "G" submittal copies will be marked with an action code, dated, electronically signed, and electronically returned to the Contractor as specified below:

1.5.3.2 Processing of "G" Submittals.

a. Submittals will be reviewed and processed as follows:

SECTION 01 33 00 Page 6

C-13

(1) Approved as Submitted (Action Code "A"): Submittals which can be approved without correction will be stamped "Approved" and returned electronically to the Contractor.

(2) Approved, Except as Noted on Drawings (Action Code "B"):

Submittals which have only minor discrepancies will be annotated in red to indicate necessary corrections. Marked material will be stamped "Approved Except as Noted" and returned electronically to the Contractor for correction.

(3) Approved, Except as Noted on Drawings, Resubmission Required (Action Code "C"): Submittals which are incomplete or require more than minor corrections will be annotated in red to indicate necessary corrections. Marked material will be stamped "Approved Except as Noted - Resubmission Required" and returned electronically to the Contractor for correction. Resubmittal of only those items needing correction required.

(4) Will be Returned by Separate Correspondence (Action Code "D"): Submittals will be addressed by Serial Letter and the Contractor must respond according to instructions in the letter.

(5) Disapproved (Action Code "E"): Submittals which are fundamentally in error, cover wrong equipment or construction, or require extensive corrections, will be returned to the Contractor stamped "Disapproved." Submittal will be returned electronically to the Contractor and an explanation will be furnished on the submitted material or on ENG Form 4025-R indicating reason for disapproval. Complete resubmittal required.

(6) Receipt Acknowledged (Action Code "F"): Submittals stamped "Receipt Acknowledged" are complete and returned electronically to the Contractor.

(7) Other (Specify) (Action Code "G"): Submittals requiring other specific action will be stamped "Other (Specify)" and returned with a description in the Remarks section. Submittal will be returned electronically to the Contractor. Resubmittal of only those items needing correction required.

(8) Receipt Acknowledged, Does Not Comply (Action Code "X"):

Submittals which have been received but do not comply with Contract requirements. Submittal will be returned electronically to the Contractor stamped "Receipt Acknowledged, Does Not Comply" and an explanation will be furnished. Corrective action and resubmittal required.

b. Resubmittal will not be required for approved submittals unless subsequent changes are made by Contractor or by Contract modification. For submittals required to be resubmitted, make corrections required, note any changes by dating the revisions to correspond with the change request date, and promptly resubmit the corrected material. Resubmittals must be associated with the "parent" by use of sequential numbers (for example, resubmittal of transmittal 8 will be 8.1, 8.2, etc) . Government costs incurred after the first resubmittal may be charged to the Contractor.

SECTION 01 33 00 Page 7

C-14

1.5.4 Information Only Submittals

1.5.4.1 General

Upload submittal with corresponding ENG 4025 forms as outlined in Paragraph entitled E-SUBMITTALS. Normally information only submittals will not be returned. Government approval is not required on information only submittals. These submittals will be used for information purposes.

The Government reserves the right to require the Contractor to resubmit any item found not to comply with the Contract. This does not relieve the Contractor from the obligation to furnish material conforming to the plans and specifications; will not prevent the CO from requiring removal and replacement of nonconforming material incorporated in the work; and does not relieve the Contractor of the requirement to furnish samples for testing by the Government laboratory or for check testing by the Government in those instances where the technical specifications so prescribe.

1.5.4.2 Processing of Information Only Submittals

Submit information only submittals electronically prior to delivery of the material or equipment to the job site. ENG Form 4025-R must be marked with the words "Contractor approved - information copy only" in the REMARKS block of the form. Submittals will be monitored and spot checks made. When such checks indicate noncompliance, the Contractor will be notified by the same method used for Government Approval submittals.

Resubmittal of nonconforming information only submittals must be reclassified Government Approval ("G") and re-submitted electronically for approval.

1.6 SUBMITTAL COORDINATION

1.6.1 Submittal Coordination Meeting

Meet with the CO, after the preconstruction conference and before any submittals are sent to the CO, to further develop the preliminary submittal register (ENG Form 4288-R). During the meeting identify and group all required items into the categories as shown in Paragraph entitled SUBMITTAL DESIGNATION.

1.6.2 Submittal Register ENG Form 4288-R

Coordinate the submittal register with the progress schedule and submit within 60 days of Notice to Proceed. In preparing the final document, allow a minimum of 30 days for review and approval, and possible resubmittal of each item on the register.

1.6.3 Submittal Register Updates

The CQC System Manager must review the listing at least every 30 days and take appropriate action to maintain an effective system. Submit copies of updated or corrected listings to the CO at least every 30 days in the quantity specified.

1.7 SCHEDULING

Schedule and submit concurrently submittals covering component items forming a system or items that are interrelated. Adequate time (a minimum of 30 calendar days) must be allowed and shown on the register for

SECTION 01 33 00 Page 8

C-15

Government review and approval. No delay damages or time extensions will be allowed for time lost in late submittals.

a. Coordinate scheduling, sequencing, preparing, and processing of submittals with performance of work so that work will not be delayed by submittal processing. Allow for potential resubmittal of requirements.

b. Submittals called for by the Contract documents must be listed on the register. Approval by the CO does not relieve the Contractor of supplying submittals required by the Contract documents but which have been omitted from the register.

c. Re-submit register and annotate monthly with actual submission and approval dates. When all items on the register have been fully approved, no further re-submittal is required.

d. Carefully control procurement operations to ensure that each individual submittal is made on or before the Contractor scheduled submittal date shown on the approved "Submittal Register".

1.8 TRANSMITTAL FORM (ENG FORM 4025-R)

Use the sample transmittal form (ENG Form 4025-R, Attachment A2) for submitting both Government Approval and Information Only submittals in accordance with the instructions on the reverse side of the form. These forms are included in the RMS CM software that the Contractor is required to use for this Contract, per Section 01 45 00.15 25, RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM). Fill forms in completely prior to submittal. Exercise special care to ensure proper listing of the specification paragraph number(s) and Contract Drawing sheet number(s) pertinent to the data submitted for each item. List each submittal item separately on the form, naming subcontractor, supplier, or manufacturer;

applicable specification paragraph number(s); drawing/sheet number; pay item number; and any other information needed to identify the item, define its use, and locate it in the work. One or more ENG 4025-R forms may be used per Specification Section, however, DO NOT include more than one Specification Section per transmittal.

1.9 CROSS-REFERENCE (ENG FORM 4288-R/ENG FORM 4025-R)

To provide a cross-reference between the approved submittal register and transmittal forms, the Contractor must record the "transmittal numbers" assigned when submitting items in column "Transmittal No." of the ENG Form 4288-R. The numbers in column "Transmittal No." of the submittal register must correspond to the column "Item No." on ENG Form 4025-R.

1.10 SUBMITTAL PROCEDURES

Upload submittals in accordance with subparagraphs entitled Government Approved Submittals and Information Only Submittals, unless indicated otherwise in the technical specifications. Submit a complete collated "reviewers copy" with one ENG 4025-R form and attachments (not originals). Submit hard copy and electronic copies of Record (as-built) Drawings and O&M Manuals in accordance with the applicable Specification Sections.

SECTION 01 33 00 Page 9

C-16

1.10.1 e-Submittals

The intent of electronic submittals is to expedite the process by reducing paperwork, improving information flow, and decreasing turnaround time.

Transmit all submittals, including either an electronically signed or signed scanned copy of form ENG 4025, to the Government electronic (PDF) format via email or other secure internet accessible service such as ShareFile, ProCore, Submittal Exchange, or a FTP site that utilize 256-bit SSL encryption and hosted as SAS70 Type II compliant data centers.

Submittals must be entered and tracked using RMS CM (see Section 01 45 00.15 25, RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM). At completion of Contract closeout, provide a minimum of two archival discs (DVD-R) that include all documents and tracking logs. Color samples, color charts, or physical material samples shall not be transmitted electronically. E-Submittals will not relieve the Contractor from following all applicable requirements within this and other Specifications Sections and Contract Clauses.

1.10.2 Approval of Submittals by the Contractor

a. Submit names and titles of Contractor Authorized Shop Drawing Approvers to the CO with the ENG Form 4288-R. Supplier or subcontractors certifications are not acceptable as meeting this requirement.

b. Before submittal to the CO, the Contractor's Authorized Shop Drawing Approvers must review and correct shop drawings prepared by subcontractors, suppliers, and itself, for completeness and compliance with Drawings and Specifications. Do not use red markings for correcting material to be submitted. Red markings are reserved for CO's use.

c. Submittals for Government Approval must first be Contractor-approved and stamped, see Paragraph entitled CONTRACTOR

APPROVAL STAMP.

d. Submittals not conforming to the requirements of this Section will be returned to the Contractor for correction and resubmittal.

1.10.3 Drawings

Each drawing must be not larger than D size (22 inches high by 34 inches wide), include a title block in lower right hand corner, and a 3- by 4-inch clear area adjacent. The title block must contain vendor's name, Contract number, description of item(s), Contract line item number, and a revision block. Separate drawings are required for each Contract line item. Where drawings are submitted for assemblies of more than one piece of equipment or systems, of components dependent on each other for compatible characteristics, complete information must be submitted on all such related components at the same time. The information must be complete and the sequence of drawing submittal must be such that all information is available for reviewing each drawing. Drawings for all items and equipment, of special manufacture or fabrication, must consist of complete assembly and detail drawings. All revisions after initial submittal must be shown by number, date, and subject in revision block.

Any drawing submitted, that is not of satisfactory quality, will be returned and must be corrected and re-submitted.

SECTION 01 33 00 Page 10

C-17

1.10.3.1 Printed Material

All requirements for shop drawings apply to catalog cuts, illustrations, printed specifications, or other data submitted, except the 3- by 4-inch clear area adjacent to the title block is not mandatory. Mark out inapplicable portions of the documents. Applicable items such as model numbers, sizes, and accessories must be indicated by arrow or highlighted.

1.11 SAMPLES REQUIRING VISUAL INSPECTION

Coordinate samples requiring only physical inspection for appearance and suitability with the on-site Government Quality Assurance Representative

(GQAR).

1.12 CERTIFICATES OF COMPLIANCE

Submit an electronic copy of certificates required for demonstrating proof of compliance of materials with specification requirements. Each certificate must be signed by an official authorized to certify on behalf of the manufacturing company, contain the name and address of the Contractor, the project name and location, and the quantity and date or dates of shipment or delivery to which the certificates apply. Copies of laboratory test reports submitted with certificates must contain the name and address of the testing laboratory and the date or dates of the tests to which the report applies. Certification shall not be construed as relieving the Contractor from furnishing satisfactory material if, after tests are performed on selected samples, the material is found not to meet the specific requirements.

1.13 DISAPPROVED SUBMITTALS

a. Make all corrections required by the CO and promptly furnish a corrected submittal in the form specified for the initial submittal.

The Contractor must be responsible for the dimensions and design of connection details and construction of work. Failure to point out deviations may result in the Government requiring rejection and removal of such work at the Contractor's expense.

b. If changes are necessary to submittals, make such revisions and re-submit the submittals in accordance with the procedures above. No item of work requiring a submittal change is to be accomplished until the changed submittals are approved.

1.14 APPROVED SUBMITTALS

a. The CO's approval or acceptance of submittals shall not be construed as a complete check, and indicates only that the general method of construction, materials, detailing, and other information are satisfactory .

b. Approval or acceptance will not relieve the Contractor of the responsibility for any error which may exist, as the Contractor under the Contractor Quality Control (CQC) requirements of this Contract must be responsible for dimensions, the design of adequate connections and details, and the satisfactory construction of all work.

c. After submittals have been approved by the CO, no resubmittal for the purpose of substituting materials or equipment will be considered unless accompanied by an explanation of why a substitution is

SECTION 01 33 00 Page 11

C-18 necessary.

1.15 APPROVED SAMPLES

a. Approval of a sample is only for the characteristics or use named in such approval and must not be construed to change or modify any Contract requirements. Before submitting samples, ensure that the materials or equipment will be available in quantities required. No change or substitution will be permitted after a sample has been approved.

b. If requested, approved and/or disapproved samples, including those which may be damaged in testing, will be returned at the expense of the Contractor upon completion of the Contract.

c. Failure of any materials to pass the specified tests will be sufficient cause for refusal to consider, under this Contract, any further samples of the same brand or make of that material.

Government reserves the right to disapprove any material or equipment which previously has proved unsatisfactory in service.

d. Samples of various materials or equipment delivered on the site or in place may be taken by the CO for testing. Samples failing to meet Contract requirements will automatically void previous approvals.

Contractor must replace such materials or equipment to meet Contract requirements.

e. Approval of the Contractor's samples by the CO does not relieve the Contractor of his/her responsibilities under the Contract.

1.16 CONTRACTOR'S FILES

Maintain "Approved as Accepted" and "Approved, Except as Noted on Drawings" (Action Codes "A" and "B") shop drawing files in fabrication shops and at field sites for Government use.

1.17 PAYMENT

Separate payment will not be made for submittals, and all costs associated therein must be included in the applicable unit prices or job prices contained in the Price Schedule. Payment will not be made for any material or equipment which does not comply with Contract requirements.

1.18 CONTRACTOR APPROVAL STAMP

Stamps used by the Contractor on the submittal data to certify that the submittal meets Contract requirements must be similar to the following:

| CONTRACTOR |

| (Firm Name) | | _____ Approved | | _____ Approved with corrections as noted on submittal data and/or | | attached sheets(s). |

SECTION 01 33 00 Page 12

C-19

| SIGNATURE: __________________________________________________________ |

| TITLE: ______________________________________________________________ |

| DATE: _______________________________________________________________ |

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

SECTION 01 33 00 Page 13

C-20

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 42 00

SOURCES FOR REFERENCE PUBLICATIONS

PART 1 GENERAL

1.1 REFERENCES

1.2 ORDERING INFORMATION

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 42 00 Page 1

C-21

SECTION 01 42 00

SOURCES FOR REFERENCE PUBLICATIONS

PART 1 GENERAL

1.1 REFERENCES

Various publications are referenced in other sections of the specifications to establish requirements for the work. These references are identified in each section by document number, date and title. The document number used in the citation is the number assigned by the standards producing organization (e.g. ASTM B564 Standard Specification for Nickel Alloy Forgings). However, when the standards producing organization has not assigned a number to a document, an identifying number has been assigned for reference purposes.

1.2 ORDERING INFORMATION

The addresses of the standards publishing organizations whose documents are referenced in other sections of these specifications are listed below, and if the source of the publications is different from the address of the sponsoring organization, that information is also provided.

AMERICAN CONCRETE INSTITUTE (ACI)

38800 Country Club Drive Farmington Hills, MI 48331-3439 Ph: 248-848-3700 Fax: 248-848-3701 Internet: https://www.concrete.org/

AMERICAN INSTITUTE OF STEEL CONSTRUCTION (AISC)

130 East Randolph, Suite 2000 Chicago, IL 60601 Ph: 312-670-5444 Fax: 312-670-5403 Steel Solutions Center: 866-275-2472 E-mail: solutions@aisc.org Internet: https://www.aisc.org/

AMERICAN SOCIETY OF CIVIL ENGINEERS (ASCE)

1801 Alexander Bell Drive Reston, VA 20191 Ph: 800-548-2723; 703-295-6300 Internet: https://www.asce.org/

AMERICAN SOCIETY OF MECHANICAL ENGINEERS (ASME)

Two Park Avenue New York, NY 10016-5990 Ph: 800-843-2763 Fax: 973-882-1717 E-mail: customercare@asme.org Internet: https://www.asme.org/

SECTION 01 42 00 Page 2

C-22

ASTM INTERNATIONAL (ASTM)

100 Barr Harbor Drive, P.O. Box C700 West Conshohocken, PA 19428-2959 Ph: 610-832-9500 Fax: 610-832-9555 E-mail: service@astm.org Internet: https://www.astm.org/

INSTITUTE OF ELECTRICAL AND ELECTRONICS ENGINEERS (IEEE)

445 and 501 Hoes Lane Piscataway, NJ 08854-4141 Ph: 732-981-0060 or 800-701-4333 Fax: 732-981-9667 E-mail: onlinesupport@ieee.org Internet: https://www.ieee.org/

NATIONAL ELECTRICAL MANUFACTURERS ASSOCIATION (NEMA)

1300 North 17th Street, Suite 900 Arlington, VA 22209 Ph: 703-841-3200 Internet: https://www.nema.org

NATIONAL FIRE PROTECTION ASSOCIATION (NFPA)

1 Batterymarch Park Quincy, MA 02169-7471 Ph: 800-344-3555 Fax: 800-593-6372 Internet: https://www.nfpa.org

U.S. ARMY CORPS OF ENGINEERS (USACE)

CRD-C DOCUMENTS available on Internet:

http://www.wbdg.org/ffc/army-coe/standards Order Other Documents from:

Official Publications of the Headquarters, USACE E-mail: hqpublications@usace.army.mil Internet: http://www.publications.usace.army.mil/ or https://www.hnc.usace.army.mil/Missions/Engineering-Directorate/TECHINFO/

UNDERWRITERS LABORATORIES (UL)

2600 N.W. Lake Road Camas, WA 98607-8542 Ph: 877-854-3577 or 360-817-5500 E-mail: CustomerExperienceCenter@ul.com Internet: https://www.ul.com/ UL Directories available through IHS at https://ihsmarkit.com/

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

SECTION 01 42 00 Page 3

C-23

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 45 00.15 25

RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

PART 1 GENERAL

1.1 CONTRACT ADMINISTRATION

1.1.1 Correspondence and Electronic Communications

1.2 RMS SOFTWARE

1.3 RMS USER GUIDE

1.4 RMS HELPDESK

1.5 CONTRACT DATABASE

1.6 DATABASE MAINTENANCE

1.6.1 Administration

1.6.1.1 Contractor Information

1.6.1.2 Subcontractor Information

1.6.1.3 Correspondence

1.6.1.4 Equipment

1.6.1.5 Management Reporting

1.6.1.6 Request For Information (RFI)

1.6.2 Finances

1.6.2.1 Pay Activity Data

1.6.2.2 Payment Requests

1.6.3 Submittal Management

1.6.4 Import/Export of Data

1.7 IMPLEMENTATION

1.8 MONTHLY COORDINATION MEETING

1.9 NOTIFICATION OF NONCOMPLIANCE

PART 2 PRODUCTS

PART 3 EXECUTION

SECTION 01 45 00.15 25 Page 1

C-24

SECTION 01 45 00.15 25

RESIDENT MANAGEMENT SYSTEM CONTRACTOR MODE (RMS CM)

PART 1 GENERAL

1.1 CONTRACT ADMINISTRATION

The Government will use the Resident Management System (RMS) to assist in its monitoring and administration of this Contract. There is no separate payment for establishing and maintaining the RMS database; costs associated will be included in the Contract pricing for the work. The Contractor uses the Government-furnished Contractor Mode of RMS, referred to as RMS CM, to record, maintain, and submit various information throughout the Contract period. The Contractor mode user manuals, updates, and training information can be downloaded from the RMS web site. The joint Government-Contractor use of RMS facilitates electronic exchange of information and overall management of the Contract. RMS CM provides the means for the Contractor to input, track, and electronically share information with the Government in the following areas:

a. Administration

b. Finances

c. Quality Control

d. Submittal Monitoring

e. Scheduling

f. Import and Export of Data

1.1.1 Correspondence and Electronic Communications

For ease and speed of communications, exchange correspondence and other documents in electronic format to the maximum extent feasible between the Government and Contractor.

1.2 RMS SOFTWARE

The RMS CM software can be downloaded from: https://rms.usace.army.mil .

The Contractor must download, install and use the latest version of the RMS software from the Government's RMS Internet Website immediately after award of Contract. Any program updates of RMS will be made available to the Contractor via the Government RMS Website as the updates become available.

1.3 RMS USER GUIDE

After Contract award, download instructions for the installation and use of RMS from the Government RMS Internet Website.

1.4 RMS HELPDESK

The RMS Helpdesk is available 24 hours a day, seven days a week. The

SECTION 01 45 00.15 25 Page 2

C-25 phone number is (442) 333-1011.

1.5 CONTRACT DATABASE

After Contract Award, the Government will provide the Contractor with basic Contract award data to use for RMS. The Government will provide data updates to the Contractor as needed. These updates will generally consist of submittal reviews, correspondence status, Quality Assurance(QA) comments, and other administrative and QA data.

1.6 DATABASE MAINTENANCE

Establish, maintain, and update data in the RMS database throughout the duration of the Contract at the Contractor's site office. Submit data updates to the Government (e.g., monthly reports, submittals, RFI's, schedule updates, payment requests) using RMS. The RMS database typically includes current data on the following items:

1.6.1 Administration

1.6.1.1 Contractor Information

Contain within the database the Contractor's name, address, telephone numbers, management staff, and other required items. Within seven calendar days of receipt of RMS software from the Government, deliver Contractor administrative data in electronic format in RMS.

1.6.1.2 Subcontractor Information

Contain within the database the name, trade, address, phone numbers, and other required information for all subcontractors. A subcontractor is listed separately for each trade to be performed. Assign each subcontractor and trade a unique Responsibility Code, provided in RMS.

Within seven calendar days of receipt of RMS software from the Government, deliver subcontractor administrative data in electronic format.

1.6.1.3 Correspondence

Identify all Contractor correspondence to the Government with a serial number. Prefix correspondence initiated by the Contractor's site office with "S". Prefix letters initiated by the Contractor's home (main) office with "H". Letters are numbered starting from 0001. (e.g., H-0001 or S-0001). The Government's letters to the Contractor will be prefixed with "C".

1.6.1.4 Equipment

Contain within the Contractor's RMS database a current list of equipment planned for use or being used on the jobsite, including the most recent and planned equipment inspection dates.

1.6.1.5 Management Reporting

RMS includes a number of reports that Contractor management can use to track the status of the project. The value of these reports is reflective of the quality of the data input, and is maintained in the various sections of RMS. Among these reports are: Progress Payment Request worksheet, Quality Assurance/Quality Control (QA/QC) comments, Submittal Register Status, and Three-Phase Control checklists.

SECTION 01 45 00.15 25 Page 3

C-26

1.6.1.6 Request For Information (RFI)

Exchange all Requests For Information (RFI) using the Built-in RFI generator and tracker in RMS.

1.6.2 Finances

1.6.2.1 Pay Activity Data

Include within the RMS database a list of pay activities that the Contractor develops in conjunction with the project schedule. The sum of pay activities equals the total Contract amount, including modifications.

Each pay activity must be assigned to a Contract Line Item Number (CLIN).

The sum of the activities equals the amount of each CLIN. The sum of all CLINs equals the Contract amount.

1.6.2.2 Payment Requests

Prepare all progress payment requests using RMS. Complete the payment request worksheet, prompt payment certification, and payment invoice in RMS. Update the work completed under the Contract, measured as percent or as specific quantities, at least monthly. After the update, generate a payment request report using RMS. Submit the payment request, prompt payment certification, and payment invoice with supporting data using RMS CM. A signed electronic copy of the approved payment request is also required.

1.6.3 Submittal Management

The Government will provide the initial submittal register in electronic format. Thereafter, maintain a complete list of submittals, including completion of data columns. Dates when submittals are received and returned by the Government will be included. Use RMS CM to track and transmit submittals. ENG Form 4025, submittal transmittal form, and the submittal register update is produced using RMS. RMS will be used to update, store and exchange submittal registers and transmittals. In addition to requirements stated in Section 01 33 00, SUBMITTAL PROCEDURES, actual submittals are to be stored in RMS CM, with electronic or hard copies also provided. Exception will be where the Contracting Officer (CO) specifies only hard copies required, where size of document cannot be saved in RMS CM, and where samples, spare parts, color boards, and full size drawings are to be provided.

1.6.4 Import/Export of Data

RMS includes the ability to import schedule data using SDEF.

1.7 IMPLEMENTATION

Use of RMS CM as described in the preceding Paragraphs is mandatory.

Ensure that sufficient resources are available to maintain Contract data within the RMS CM system. RMS CM is an integral part of the Contractor's management of quality control.

1.8 MONTHLY COORDINATION MEETING

a. At least monthly, generate and submit a schedule update. At least one week prior to submittal, meet with the Government representative

SECTION 01 45 00.15 25 Page 4

C-27 to review the planned progress payment data submission for errors and omissions.

b. Make required corrections prior to Government acceptance of the export file and progress payment request. Payment requests accompanied by incomplete or incorrect data submittals will not be accepted. The Government will not process progress payments until all required corrections are processed.

1.9 NOTIFICATION OF NONCOMPLIANCE

The CO will notify the Contractor of any detected noncompliance with the requirements of this Specification. Take immediate corrective action after receipt of such notice. Such notice, when delivered to the Contractor at the work site, will be deemed sufficient for the purpose of notification.

PART 2 PRODUCTS

Not Used.

PART 3 EXECUTION

Not Used.

SECTION 01 45 00.15 25 Page 5

C-28

DIVISION 01 - GENERAL REQUIREMENTS

SECTION 01 78…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .