This Statement of Work (SOW) details the repair of six motorized coiling doors at the Bureau of Land Management (BLM) Red Rock Fire Station Engine Barn in Las Vegas, Nevada, scheduled for September 2025. The project involves removing outdated electric edges, cable reels, and associated wiring, and installing new monitored electric edges with Miller seals, coil cords, sensing interface modules, aluminum edge retainers, and junction boxes. Specific tasks include replacing side seals on the southeast door and correcting the deformation of bottom slats and bar on the northwest door.
The work will be completed within 30 working days, with all tasks performed between 7:00 am and 5:00 pm on weekdays. The six Cornell-type rollup doors are approximately 12 ft. wide by 14 ft. high, each equipped with a LiftMaster GF ¾ horsepower, 115-volt operator. The upgrade is necessary to ensure code-compliant door operations, bringing the 20-year-old doors up to the current ANSI/UL 325 monitored electric edge standard. The contractor must coordinate site access with the government, comply with safety regulations, and provide all required submittals, including electric edge and seal specifications, cable details, maintenance manuals, and a final installation report.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Sol_140L3925Q0089.pdf | ||
| A_06_Bid_Sched_-_Sept_2025_-_rev.pdf | ||
| B_03_Wage_Rate_Clark_County_2015-5593_Rev_29.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SCOPE OF WORK
Service
Bureau of Land Management
Red Rock Fire Station Engine Barn
Repair of Coil Doors
Southern Nevada District Office
Las Vegas, Nevada
September 2025
TABLE OF CONTENTS
1.0 PROJECT INTRODUCTION
1.1 Background
1.2 Scope of Work
2.0 SUBMITTALS
3.0 MATERIALS AND QUALITY ASSURANCE
3.1 Acceptable Manufacturers
3.2 Electric Sensing Edge
3.3 Door Seals
3.4 Accessories
3.5 Quality Assurance
4.0 EXECUTION
4.1 Examination
4.2 Installation
4.3 Post Installation Inspection and Testing
5.0 SITE OPERATIONS AND RESTRICTIONS
5.1 Site Access
5.2 Work Times
5.3 Site Operations
5.4 Waste Disposal
5.5 Smoking
6.0 PERIOD OF PERFORMANCE
7.0 BLM POINTS OF CONTACT
8.0 EXHIBITS
E1 - Site Vicinity
E2 - Red Rock Canyon Fire Station
E3 - Fire Station Engine Barn
9.0 PHOTOGRAPHS
P1 - Electric Edge and Seal
P2 - Cable Reel and Wire Cord
P3 - Cable Cord
P4 - Door Bottom Components
P5 - Door Seal
P6 - Bent Bottom Bar and Slats
Red Rock Canyon Fire Station – Engine Barn Coil Doors Repair Page 1 of 5
1.0 PROJECT INTRODUCTION
This Statement of Work (SOW) describes the requirements for the repair of six motorized coiling doors at the Bureau of Land Management (BLM) Red Rock Fire Station Engine Barn.
The Bureau of Land Management Red Rock Fire Station (RRFS) is located at Latitude 36.134438° /
Longitude -115.392396, and is accessed via Moenkopi Road. Moenkopi Road intersects Highway 159 approximately two (2) miles west of Sky Vista Avenue in the community of Summerlin, on the far west side of the Las Vegas Valley. A paved access road leading to the fire station entrance intersects Moenkopi
Road approximately 0.6 miles south of the Highway 159/Moenkopi Road intersection. Refer to Exhibits
1 and 2 for additional location details.
The fire station occupies approximately five (5) acres and shares the premises with law enforcement functions. Site access is controlled by a motorized entry gate. Seasonal increases in operational activity are expected, with the highest levels occurring between March and May.
The engine barn serves as a multifunctional facility, providing storage for fire apparatus, minor equipment repair capabilities, dedicated fire equipment storage, and a designated exercise area for personnel.
1.1 Background
On May 5, 2025 a contractor specializing in coiling and side folding doors inspected and serviced all six
Engine Barn coiling doors. The servicing included checking chain tensions, screws, bolts and bearings, lubing friction points and checking overall operations of each door.
The six rollup doors are Cornell type and nominally 12 ft. wide by 14 ft. high. Each door has a
LiftMaster GF type, ¾ horsepower, 115 volt, single phase operator (Exhibit 3).
The contractor noted that three doors required the electric edge/Miller Seal be removed and on one door remove and replace both side seals.
The Cornell doors and LiftMaster operators are approximately 20 years old and predate the monitored electric edge standard in ANSI/UL 325. To ensure a future of safe, reliable, and code-compliant door operations BLM has elected to upgrade all doors with new monitored electric edges and Miller seals including installation of monitoring adapters.
1.2 Scope of Work
This scope of work the tasks to be completed for six existing coiling doors. The work includes the removal of outdated electric edges, cable reels, and associated wiring, followed by the installation of new monitored electric edges with Miller seals (or approved equivalent), coil cords, sensing interface modules, aluminum edge retainers, and junction boxes. Additionally, the work involves replacement of side seals on the southeast door and correction of the deformation of the bottom slats and bar on the northwest door, as detailed in the referenced exhibits and supporting photos.
Red Rock Canyon Fire Station – Engine Barn Coil Doors Repair Page 2 of 5
1) Remove six existing coiling door electric edges and seals (Photo 1).
2) Install six new electric edges with Miller seal or equivalent.
3) Remove and replace five cable cords – from junction box to wire reel (Photo 2).
4) Remove and replace one coil cord from junction box to door motor/operator (Photo 3).
5) Install new aluminum mounting channels (Photo 4).
6) Remove and replace six junction boxes (Photo 4).
7) Install two new door side seals – SE door – refer to Exhibit 3 and (Photo5).
8) Straighten bottom three curtain slats and bottom bar – NW door – refer to Exhibit 3 and
(Photo 6).
2.0 SUBMITTALS
The Contractor shall provide the following submittals for Government review and approval to verify compliance with project requirements prior to, during, and after installation.
a. Electric Edge and Seal
b. Coil Cable.
c. Side seal.
d. Operations and maintenance manuals.
e. Final installation report.
f. Material warranties
3.0 MATERIALS AND QUALITY ASSURANCE
The Contractor shall furnish all labor, materials, equipment, tools, transportation and supervision necessary to perform the work described in this Statement of Work.
All work shall be performed in accordance with manufacturer recommendations, industry best practices, applicable safety standards, and ANSI/UL325.
3.1 Acceptable Manufacturers
a. Preferred: Miller Edge, Inc. – Model ME120 Standard Non-Monitored Sensing Edge
b. Acceptable Alternatives: Cookson, DoorKing, Linear, LiftMaster.
1.2 Electric Sensing Edge
a. Type: Pressure sensitive electric sensing edge.
b. Operation: Electrically actuated, stops or reverses door upon contact with an obstruction.
c. Length: 12 ft. - matches door width.
d. Housing: Flexible black thermoplastic or EPDM rubber.
e. Wiring: 2-wire, non-monitored, UL325-recognized. 18 AWG jacketed conductors, pre-wired.
f. Cover: UV and weather resistant.
g. Color: Black
h. Mounting Channel: Extruded aluminum compatible with door. Minimum length of the channel shall be 4-feet with no more than three sections used. If multiple lengths are used to traverse the 12-feet, sections shall be butted tightly together with no visible gap.
Red Rock Canyon Fire Station – Engine Barn Coil Doors Repair Page 3 of 5
3.3 Door Seals
a. Function: Seals against air, dust, light and water infiltration.
b. Material: Match existing seals.
c. Thickness: Match existing.
d. Shape: Flat.
e. Width: 2-inches.
f. Color: Black
3.4 Accessories
a. Mounting Adapter/Channel: 12-foot aluminum extrusion compatible with door bottom bar.
b. Junction Box: NEMA 4 rated, surface mount or flush as required for wiring termination.
c. Wiring Harness: 15 foot minimum length, UV and moisture resistant.
3.5 Quality Assurance
a. Installer qualifications: Installer shall be trained and authorized by the manufacturer for sensing edge products.
b. Regulatory requirements: Comply will all applicable safety standards including UL 325 and local code requirements.
4.0 EXECUTION
This section outlines the activities, coordination responsibilities, workmanship requirements, and specific procedures the Contractor shall follow during execution of the work.
The Contractor shall perform all work in accordance with the requirements outlined in this Statement of
Work, applicable codes and standards, and manufacturer specifications.
4.1 Examination
a. Verify existing door assemblies and surrounding conditions are suitable for electric edge installation.
b. Confirm that door bottom is straight, level and free of deformation. Replace or shim as necessary to provide a proper mounting surface.
c. Inspect all new equipment and materials prior to installation for damage or defects.
d. Immediately remove any damaged or defective equipment from the work area, tag it clearly as
“Do Not Use”, and notify government.
e. Contractor shall relace or repair, at no additional cost to the Government, any new equipment or materials found to be defective, or any equipment damaged during project execution by the
Contractor. Installation shall not proceed until the Government has verified that all equipment is in proper working order.
4.2 Installation
a. Install sensing edges, junction boxes, coil cables, and interface modules per manufactures written instructions and UL 325 requirements.
Red Rock Canyon Fire Station – Engine Barn Coil Doors Repair Page 4 of 5
4.3 Post Installation Inspection and Testing
a. Confirm proper operation of each door following installation. Notify Government of inspection and testing in advance to allow for their presence during edge testing.
b. Pre-Testing Preparation:
• Ensure the door edge systems are fully installed and connected according to manufacturer instructions.
• Verify power to the operator is on.
• Confirm Government is present.
c. Visual Inspections
• Check all wiring connections for secure and proper installation.
• Inspect the edge sensor surface for damage or defects.
• Verify mounting brackets and hardware are secure.
d. Functional Testing
• Trigger the monitored edge by manually pressing or simulating obstruction on the sensor edge. Observe whether the door operator stops or reverses as designed immediately upon activation.
• Depress and release door control switch to ensure door fully opens and closes.
• Repeat multiple times to confirm consistent response.
e. Documentation
• Record all test results, including dates, times, tester names and observations.
• Note any failures or issues and corrective actions taken.
• Sign test reports.
• Provide test reports to the Government upon project completion.
• Provide Government with the maximum compression the edges will undergo before reversing direction.
5.0 SITE OPERATIONS AND RESTRICTIONS
This section outlines the operational parameters, conduct expectations, and site protection measures the
Contractor shall adhere to while performing work. Requirements include working hour limitations, site access protocols, restrictions on smoking and hazardous activities, and protection of Government facilities, personnel, and property. The period of performance and other project-specific constraints are also defined herein. The Contractor is responsible for ensuring all personnel always comply with these provisions.
5.1 Site Access
a. Contractor to coordinate with Government three days prior to commencing work to ensure site access is unencumbered.
b. The contractor shall provide the Government with a minimum of three (3) calendar days’ notice prior to mobilization, specifying space requirements necessary to execute the work. This will allow the Government sufficient time to relocate fire apparatus and ensure access to all work areas.
5.2 Work Times
a. All work shall be limited to the hours of 7:00 am to 5:00 pm on weekdays unless otherwise approved by the Government.
Red Rock Canyon Fire Station – Engine Barn Coil Doors Repair Page 5 of 5
b. No work shall occur on federal holidays or weekends without prior approval.
5.3 Site Operations
a. All tasks shall be executed in a manner that ensures safety, minimizes disruption to ongoing operations, and meets project quality expectations.
b. Protect any areas adjacent to the project site from any debris. Comply with governing regulations pertaining to environmental protection. Ensure safety of persons in the work area.
Provide temporary barricades as required to protect personnel and public from injury.
c. While on-site Contractor to conform to all Occupational Health and Safety Administration
(OSHA) requirement during all phases of the project including 29 CFR 1910.333(b) - electrical lock-out/tag-out (LOTO).
d. Notify Government (3) days prior to implementing LOTO protocols. Identify the circuit(s) and the duration of LOTO.
5.4 Waste Disposal
a. All waste generated during the project (demolition material, packaging, etc) shall be hauled off site and disposed of in accordance with State and Local regulations.
b. Remove cable reels and turn over to Government – do not dispose.
5.5 Smoking
Smoking within buildings or temporary storage sheds is prohibited and smoking areas are in open areas and will be away from entrances at least fifty feet away.
6.0 PERIOD OF PERFORMANCE
The duration of this contract will be thirty (30) working days to include mobilization and demobilization, material/equipment acquisition and installation from Notice to Proceed issuance date.
7.0 BLM POINTS OF CONTACT
NVSO Contracting Officer
1340 Financial Blvd
Reno NV 89502
775-861-6402 Office
775-861-6634 Fax
Contracting Officer’s Representative (COR)
Paul Lohman
4701 N Torrey Pines Dr
Las Vegas, NV 89130
(702) 515-5035
8.0 EXHIBITS
9.0 PHOTOGRAPHS
| Project SOW - Revised - pdf |
| Ex - Package |
| EXHIBITS |
| Ex 1 |
| Ex 2 |
| E3 |
| P-Package |
| Photos |
| P1 |
| P2 |
| P3 |
| P4 |
| P5 |
| P6 |
File details come from the government source that posted it. Updated .