The document is a Schedule of Items for the Eleven Mile Canyon Entrance project, issued by the Pike-San Isabel National Forests & Cimarron and Comanche National Grasslands (PSICC), specifically for the South Park Ranger District in Colorado. The project involves an entrance road improvement and entrance station replacement, with a comprehensive list of 11 base items including mobilization, construction survey, soil erosion control, asphalt removal, roadway excavation, aggregate base installation, asphalt concrete placement, bollard post installation, pavement markings, temporary traffic control, and a precast concrete fee booth installation. The estimated quantities range from 1 lump sum (LS) for several items to specific quantities like 196 square yards of asphalt removal, 100 cubic yards of roadway excavation, 90 tons of aggregate base, and 193 tons of asphalt concrete.

The Schedule of Items presents a template for bidders to fill in unit prices and total prices, with all current entries showing zero dollars, indicating this is a preliminary bidding document. The project appears to be a infrastructure improvement initiative for a national forest entrance, focusing on road reconstruction and facility upgrades. While specific pricing, funding sources, and bid dates are not detailed in this document, the comprehensive item breakdown suggests a structured approach to road and entrance station renovation. The use of CDOT (Colorado Department of Transportation) specifications for materials like aggregate base and asphalt concrete indicates adherence to state transportation standards, which is typical for federal-state collaborative infrastructure projects.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Pay Item Description Pay Unit Estimated

Quantity Unit Price Total Price

15101 Mobilization and Bonding LS 1 -$ -$

15201 Construction survey and staking, method 1, tolerance

A

LS 1 -$ -$

15701 Soil Erosion & Pollution Control LS 1 -$ -$

20301 Remove Asphalt, Dispose asphalt onsite at comercial landfill

SY 196 -$ -$

20401A Roadway Excavation and Embankment Consrtruction, Placement Method 1

CY 100 -$ -$

30101D Aggregate base, CDOT Class 6, compaction method D TON 90 -$ -$

40301 Asphalt concrete, CDOT Design Mix, 3/4" Nominal

Maximum Aggregate Size

TON 193 -$ -$

61904 Bollard Posts EA 6 -$ -$

63400 Pavement Markings, see pavement marking plan LS 1 -$ -$

63501 Temporary traffic control LS 1 -$ -$

80201 Furnish and Install Precast Concrete Fee Booth, Aggregate Foundation Pad and Cold Patch

LS 1 -$ -$

PROJECT TOTAL -$

BASE ITEMS

Pike-San Isabel National Forests & Cimarron and Comanche National Grasslands (PSICC)

South Park Ranger District

SCHEDULE OF ITEMS

Project Name: Eleven Mile Canyon Entrance