A-01 Arapahoe Wall Paper Removal Specifications.pdf
PDF 190 KB Posted
- Attached to
- Arapahoe Wall Paper Removal Federal contract opportunity
- Solicitation number
- 75H709-OEHE23Q-002
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| 75H709-OEHE23Q-002.pdf | ||
| A-03 Bid Sheet.pdf | ||
| A-02 2021 Arapahoe Wall Paper Removal DWGS.pdf |
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATIONS ARAPAHOE HEALTH CENTER WALL PAPER REMOVAL
BI20WR203C6 ARAPAHOE, WYOMING
SUMMARY 011000 - 1
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes:
1. Project information.
2. Work covered by Contract Documents.
3. Phased construction.
4. Access to site.
5. Coordination with occupants.
6. Work restrictions.
1.2 PROJECT INFORMATION
A. Project Identification: Arapahoe Health Center Flooring Replacement
1. Project Location: Arapahoe Health Center Arapahoe, Wyoming
B. Owner: Billings Area Indian Health Service 2900 4th Ave. North Billings, MT 59107
1. Project Officer: Bridger Hanway Facility Maintenance 307-332-5505
2. COTR: Greg Ault Facilities Engineer 406-247-7140
1.3 WORK COVERED BY CONTRACT DOCUMENTS
A. The Work of the Project is defined by the Contract Documents and consists of the following:
1. The project is to remove the existing wall paper in various locations, prepare the wall surface for texture, machine texture, prime, and paint. The contractor will be responsible for removing items hanging on the wall and replacing them upon finishing painting per the owners recommended locations. The removed cove base will be replaced with new 6” cove base and preformed corners. The work will be scheduled for nights and weekends to minimize disruptions of the service provided at the facility, and the schedule must be approved by the Project Officer. The work includes but is not limited to, demolition, moving of furnishings, wall base, tape and texturing, and painting. See plans and specifications for details. The project is located at the Arapahoe Health Center, in Arapahoe, Wyoming.
B. Type of Contract.
1. Project will be constructed under a single prime contract.
SUMMARY 011000 - 2
1.4 ACCESS TO SITE
A. General: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform operations and normal business.
B. Use of Site: Limit use of Project site to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated.
1. Limits: Confine construction operations to area of work.
2. Driveways, Walkways and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials.
a. Schedule deliveries to minimize use of driveways and entrances by construction operations.
b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site.
1.5 COORDINATION WITH OCCUPANTS
A. Partial Owner Occupancy: Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perform the Work so as not to interfere with Owner's operations. Maintain existing exits unless otherwise indicated.
1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisdiction.
2. Provide not less than 72 hours' notice to Owner of activities that will affect Owner's operations.
B. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not interfere with completion of the Work. Such placement of equipment and limited occupancy shall not constitute acceptance of the total Work.
1. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate and maintain mechanical and electrical systems serving occupied portions of Work.
2. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work.
1.6 WORK RESTRICTIONS
A. Work Restrictions, General: Comply with restrictions on construction operations.
1. Comply with limitations on use of public streets and other requirements of authorities having jurisdiction.
B. On-Site Work Hours: Limit work in the existing building to outside normal business working hours of 8:00 a.m. to 5:00 p.m., Monday through Friday, except as otherwise indicated. All areas under construction must be ready for use during business hours following construction activities unless approved by project officer..
SUMMARY 011000 - 3
1. Alternate work hours of evenings and weekends will be utilized to minimize disruption to Owner operations and must be approved by Project Officer.
C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated:
1. Notify Owner not less than two days in advance of proposed utility interruptions.
2. Obtain Owner’s written permission before proceeding with utility interruptions.
D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner.
1. Owner not less than two days in advance of proposed disruptive operations.
2. Owner’s written permission before proceeding with disruptive operations.
E. Nonsmoking Campus: Smoking is not permitted within the building or on the campus grounds.
F. Employee Identification: Owner will provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times.
G. Employee Screening: Comply with Owner's requirements for screening of Contractor personnel working on Project site.
1. Maintain list of approved screened personnel with Owner's representative.
H. Controlled Substances: Use of tobacco products and other controlled substances within the existing building and on the Project site is not permitted.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
SELECTIVE DEMOLITION 024119 - 1
SECTION 024119 - SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Demolition and removal of selected portions of building or structure.
2. Demolition and removal of selected site elements.
3. Salvage of existing items to be reused or recycled.
B. Related Requirements:
1. Section 011000 "Summary" for restrictions on the use of the premises, Owner-occupancy requirements, and phasing requirements.
1.3 DEFINITIONS
A. Remove: Detach items from existing construction and legally dispose of them off-site unless indicated to be removed and salvaged or removed and reinstalled.
B. Remove and Salvage: Carefully detach from existing construction, in a manner to prevent damage, and deliver to Owner ready for reuse.
C. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall where indicated.
D. Existing to Remain: Existing items of construction that are not to be permanently removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled.
1.4 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition waste becomes property of Contractor.
1.5 INFORMATIONAL SUBMITTALS
A. Proposed Protection Measures: Submit report, including drawings, that indicates the measures proposed for protecting individuals and property for dust control. Indicate proposed locations and construction of barriers.
B. Schedule of Selective Demolition Activities: Indicate the following:
SELECTIVE DEMOLITION 024119 - 2
1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Ensure Owner's on-site operations are uninterrupted.
2. Interruption of utility services. Indicate how long utility services will be interrupted.
3. Coordination for shutoff, capping, and continuation of utility services.
4. Coordination of Owner's continuing occupancy of portions of existing building and of
Owner's partial occupancy of completed Work.
1.6 FIELD CONDITIONS
A. Owner will occupy portions of building immediately adjacent to selective demolition area.
Conduct selective demolition so Owner's operations will not be disrupted.
B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.
C. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.
1. If suspected hazardous materials are encountered, do not disturb; immediately notify
Project Officer and Owner.
D. Storage or sale of removed items or materials on-site is not permitted..
E. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.
1. Maintain fire-protection facilities in service during selective demolition operations.
PART 2 - PRODUCTS
2.1 PEFORMANCE REQUIREMENTS
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Strategically plan demolition to minimize disruption to facility operations and downtime.
B. Verify that utilities have been disconnected and capped before starting selective demolition operations.
C. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict.
Promptly submit a written report to Project Officer.
SELECTIVE DEMOLITION 024119 - 3
3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS
A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.
1. Comply with requirements for existing services/systems interruptions specified in Section 011000 "Summary."
B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished.
1. If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.
2. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated to be removed.
a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.
b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material.
c. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Owner.
3.3 PREPARATION
A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.
B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building.
2. Protect walls, ceilings, floors, and other existing finish work that are to remain or that are exposed during selective demolition operations.
3. Provide dust barriers and ventilation to protect adjacent areas.
4. Cover and protect furniture, furnishings, and equipment that have not been removed.
3.4 SELECTIVE DEMOLITION, GENERAL
A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:
1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level.
2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction.
Use hand tools or small power tools designed for sawing or grinding, not hammering and
SELECTIVE DEMOLITION 024119 - 4
chopping, to minimize disturbance of adjacent surfaces. Temporarily cover openings to remain.
3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.
4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain fire watch and portable fire-suppression devices during flame-cutting operations.
5. Maintain adequate ventilation when using cutting torches.
6. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.
7. Restore adjacent surfaces, areas, and/or items to original condition if damaged during demolition or construction activities.
8. Dispose of demolished items and materials promptly.
B. Reuse of Building Elements: Do not demolish building elements beyond what is indicated on Drawings without Project Officer's approval.
C. Removed and Salvaged Items:
1. Clean salvaged items.
2. Store items in a secure area until delivery to Owner.
3. Protect items from damage during transport and storage.
D. Removed and Reinstalled Items:
1. Clean and repair items to functional condition adequate for intended reuse.
2. Protect items from damage during transport and storage.
3. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.
E. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Project Officer, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.
3.5 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS
A. Concrete: Demolish in small sections. Using power-driven saw, cut concrete to a depth of at least 3/4 inch (19 mm) at junctures with construction to remain. Dislodge concrete from reinforcement at perimeter of areas being demolished, cut reinforcement, and then remove remainder of concrete. Neatly trim openings to dimensions indicated.
B. Masonry: Demolish in small sections. Cut masonry at junctures with construction to remain, using power-driven saw, then remove masonry between saw cuts.
3.6 DISPOSAL OF DEMOLISHED MATERIALS
A. General: Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Owner's property, remove demolished materials from Project site and legally dispose of them in an EPA-approved landfill.
SELECTIVE DEMOLITION 024119 - 5
1. Do not allow demolished materials to accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
B. Burning: Do not burn demolished materials.
C. Disposal: Transport demolished materials off Owner's property and legally dispose of them.
3.7 CLEANING
A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began. Daily cleaning may be required to make construction areas ready for normal business operations following after hour construction.
END OF SECTION 024119
GYPSUM BOARD 092900 - 1
SECTION 092900 - GYPSUM BOARD
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Interior gypsum board.
2. Texture finishes.
1.2 ACTION SUBMITTALS
A. Product Data: For each type of product.
B. Samples:
1. Textured Finishes: Manufacturer's standard size for each textured finish indicated and on same backing indicated for Work.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Fire-Resistance-Rated Assemblies: For fire-resistance-rated assemblies, provide materials and construction identical to those tested in assembly indicated according to ASTM E 119 by an independent testing agency.
B. STC-Rated Assemblies: For STC-rated assemblies, provide materials and construction identical to those tested in assembly indicated according to ASTM E 90 and classified according to ASTM E 413 by an independent testing agency.
C. Low Emitting Materials: For ceiling and wall assemblies, provide materials and construction identical to those tested in assembly and complying with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."
2.2 INTERIOR GYPSUM BOARD
A. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:
1. American Gypsum.
2. CertainTeed Corp.
3. Georgia-Pacific Gypsum LLC.
4. Lafarge North America Inc.
5. National Gypsum Company.
6. PABCO Gypsum.
GYPSUM BOARD 092900 - 2
7. Temple-Inland.
8. USG Corporation.
B. Gypsum Wallboard: ASTM C 1396/C 1396M.
1. Thickness: 5/8”.
2. Long Edges: Tapered
C. Gypsum Ceiling Board: ASTM C 1396/C 1396M.
1. Thickness: 5/8”.
2. Long Edges: Tapered
D. Moisture- and Mold-Resistant Gypsum Board: ASTM C 1396/C 1396M. With moisture- and mold-resistant core and paper surfaces.
1. Long Edges: Tapered.
2. Mold Resistance: ASTM D 3273, score of 10.
2.3 TRIM ACCESSORIES
A. Interior Trim: ASTM C 1047.
1. Material: Galvanized or aluminum-coated steel sheet, rolled zinc, plastic, or paper-faced galvanized steel sheet.
2.4 JOINT TREATMENT MATERIALS
A. General: Comply with ASTM C 475/C 475M.
B. Joint Tape:
1. Interior Gypsum Board: Paper.
2. Tile Backing Panels: As recommended by panel manufacturer.
C. Joint Compound for Interior Gypsum Board: For each coat use formulation that is compatible with other compounds applied on previous or for successive coats.
2.5 AUXILIARY MATERIALS
A. Laminating Adhesive: Adhesive or joint compound recommended for directly adhering gypsum panels to continuous substrate.
1. Laminating adhesive shall have a VOC content of 50 g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24).
2. Laminating adhesive shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."
B. Steel Drill Screws: ASTM C 1002, unless otherwise indicated.
C. Sound Attenuation Blankets: ASTM C 665, Type I (blankets without membrane facing).
GYPSUM BOARD 092900 - 3
D. Wall Board Conditioner/Sealer: Gardz Problem Surface Sealer
E. Acoustical Joint Sealant: ASTM C 834. Product effectively reduces airborne sound transmission through perimeter joints and openings as demonstrated by testing according to ASTM E 90.
1. Products: Subject to compliance with requirements, available products that may be incorporated into the Work include, but are not limited to, the following:
a. Accumetric LLC; BOSS 824 Acoustical Sound Sealant.
b. Grabber Construction Products; Acoustical Sealant GSC.
c. Pecora Corporation; AC-20 FTR
d. Specified Technologies, Inc.; Smoke N Sound Acoustical Sealant.
e. USG Corporation; SHEETROCK Acoustical Sealant.
2. Acoustical joint sealant shall have a VOC content of 250> g/L or less when calculated according to 40 CFR 59, Subpart D (EPA Method 24).
3. Acoustical joint sealant shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."
F. Thermal Insulation: As specified in Division 07 Section "Thermal Insulation."
2.6 TEXTURE FINISHES
A. Primer: As recommended by textured finish manufacturer.
B. Non-Aggregate Finish: Pre-mixed, vinyl texture finish for spray application.
1. Products: Subject to compliance with requirements, vailable products that may be incorporated into the Work include, but are not limited to, the following:
a. CertainTeed Corp.; ProRoc Easi-Tex Spray Texture.
b. USG Corporation; BEADEX FasTex Wall and Ceiling Spray Texture.
2. Texture: Light Machine Texture to Match existing adjacent walls.
PART 3 - EXECUTION
3.1 APPLYING AND FINISHING PANELS
A. Comply with ASTM C 840.
B. Examine panels before installation. Reject panels that are wet, moisture damaged, and mold damaged.
C. Isolate perimeter of gypsum board applied to non-load-bearing partitions at structural abutments, except floors. Provide 1/4- to 1/2-inch- wide spaces at these locations and trim edges with edge trim where edges of panels are exposed. Seal joints between edges and abutting structural surfaces with acoustical sealant.
D. Install trim with back flanges intended for fasteners, attach to framing with same fasteners used for panels. Otherwise, attach trim according to manufacturer's written instructions.
GYPSUM BOARD 092900 - 4
1. Control Joints: Install control joints according to ASTM C 840 and in specific locations approved by Owner for visual effect.
E. Pre-fill open joints and damaged surface areas.
F. Apply joint tape over gypsum board joints, except for trim products specifically indicated as not intended to receive tape.
G. Gypsum Board Finish Levels: Finish panels to levels indicated below and according to ASTM C 840:
1. Level 1: Ceiling plenum areas, concealed areas, and where indicated.
2. Level 2: Panels that are substrate for tile.
3. Level 4: At panel surfaces that will be exposed to view unless otherwise indicated.
a. Primer and its application to surfaces are specified in other Division 09 Sections.
H. Texture Finish Application: Prepare and apply primer to gypsum panels and other surfaces receiving texture finishes. Mix and apply finish using powered spray equipment, to produce a uniform texture free of starved spots or other evidence of thin application or of application patterns.
I. Protect adjacent surfaces from drywall compound and texture finishes and promptly remove from floors and other non-drywall surfaces. Repair surfaces stained, marred, or otherwise damaged during drywall application.
J. Remove and replace panels that are wet, moisture damaged, and mold damaged.
END OF SECTION 092900
INTERIOR PAINTING 099123 - 1
SECTION 099123 - INTERIOR PAINTING
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes surface preparation and the application of paint systems on interior substrates. .
1.2 ACTION SUBMITTALS
A. Product Data: For each type of product. Include preparation requirements and application instructions.
B. Samples: For each type of paint system and in each color and gloss of topcoat.
C. Product List: For each product indicated. Include printout of current "MPI Approved Products List" for each product category specified in Part 2, with the proposed product highlighted.
1.3 MAINTENANCE MATERIAL SUBMITTALS
A. Furnish extra materials that match products installed and that are packaged with protective covering for storage and identified with labels describing contents.
1. Paint: 5 percent, but not less than 1 gal. (3.8 L) of each material and color applied.
1.4 QUALITY ASSURANCE
A. Mockups: Apply mockups of each paint system indicated and each color and finish selected to verify preliminary selections made under Sample submittals and to demonstrate aesthetic effects and set quality standards for materials and execution.
1. Architect will select one surface to represent surfaces and conditions for application of each paint system specified in Part 3.
a. Vertical and Horizontal Surfaces: Provide samples of at least 100 sq. ft. (9 sq. m).
b. Other Items: Architect will designate items or areas required.
2. Final approval of color selections will be based on mockups.
a. If preliminary color selections are not approved, apply additional mockups of additional colors selected by Architect at no added cost to Owner.
PART 2 - PRODUCTS
2.1 MANUFACTURERS
A. Products: Subject to compliance with requirements listed in other Part 2 articles for the paint category indicated. (Sherwin Williams Promar 200 as basis of design)
INTERIOR PAINTING 099123 - 2
2.2 PAINT, GENERAL
A. MPI Standards: Provide products that comply with MPI standards indicated and that are listed in its "MPI Approved Products List."
B. Material Compatibility:
1. Provide materials for use within each paint system that are compatible with one another and substrates indicated, under conditions of service and application as demonstrated by manufacturer, based on testing and field experience.
2. For each coat in a paint system, provide products recommended in writing by manufacturers of topcoat for use in paint system and on substrate indicated.
C. VOC Content: Products shall comply with VOC limits of authorities having jurisdiction :
1. Flat Paints and Coatings: 50 g/L.
2. Nonflat Paints and Coatings: 150 g/L.
3. Dry-Fog Coatings: 400 g/L.
4. Primers, Sealers, and Undercoaters: 200 g/L.
5. Anticorrosive and Antirust Paints Applied to Ferrous Metals: 250 g/L.
6. Zinc-Rich Industrial Maintenance Primers: 340 g/L.
7. Pretreatment Wash Primers: 420 g/L.
8. Floor Coatings: 100 g/L.
9. Shellacs, Clear: 730 g/L.
10. Shellacs, Pigmented: 550 g/L.
D. Low-Emitting Materials: Interior paints and coatings shall comply with the testing and product requirements of the California Department of Health Services' "Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers."
E. Colors: As selected by Owner from manufacturer's full range.
2.3 PRIMERS/SEALERS
A. Primer Sealer, Latex, Interior (RECOMMEND SHERWIN WILLIAMS AS BASIS OF DESIGN).
2.4 WATER-BASED PAINTS
A. Latex, Interior, Flat, (Gloss Level 1 as selected by owner.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine substrates and conditions, with Applicator present, for compliance with requirements for maximum moisture content and other conditions affecting performance of the Work.
B. Maximum Moisture Content of Substrates: When measured with an electronic moisture meter as follows:
1. Wood: 15 percent.
INTERIOR PAINTING 099123 - 3
2. Gypsum Board: 12 percent.
C. Verify suitability of substrates, including surface conditions and compatibility with existing finishes and primers.
D. Proceed with coating application only after unsatisfactory conditions have been corrected.
1. Application of coating indicates acceptance of surfaces and conditions.
3.2 PREPARATION
A. Comply with manufacturer's written instructions and recommendations in "MPI Manual" applicable to substrates indicated.
B. Remove hardware, covers, plates, and similar items already in place that are removable and are not to be painted. If removal is impractical or impossible because of size or weight of item, provide surface-applied protection before surface preparation and painting.
1. After completing painting operations, use workers skilled in the trades involved to reinstall items that were removed. Remove surface-applied protection if any.
C. Clean substrates of substances that could impair bond of paints, including dust, dirt, oil, grease, and incompatible paints and encapsulants.
1. Remove incompatible primers and reprime substrate with compatible primers or apply tie coat as required to produce paint systems indicated.
3.3 APPLICATION
A. Apply paints according to manufacturer's written instructions and to recommendations in "MPI Manual."
B. Apply paints to produce surface films without cloudiness, spotting, holidays, laps, brush marks, roller tracking, runs, sags, ropiness, or other surface imperfections. Cut in sharp lines and color breaks.
3.4 CLEANING AND PROTECTION
A. Protect work of other trades against damage from paint application. Correct damage to work of other trades by cleaning, repairing, replacing, and refinishing, as approved by Project Officer, and leave in an undamaged condition.
B. At completion of construction activities of other trades, touch up and restore damaged or defaced painted surfaces.
3.5 INTERIOR PAINTING SCHEDULE
A. Steel Substrates:
1. Latex over Alkyd Primer System:
a. Intermediate Coat: Latex, interior, matching topcoat.
INTERIOR PAINTING 099123 - 4
b. Topcoat: Latex, interior.
B. Gypsum Board Substrates:
1. Latex System:
a. Prime Coat: Latex, interior, matching topcoat.
b. Intermediate Coat: Latex, interior, matching topcoat.
c. Topcoat: Latex, interior, END OF SECTION 099123
RESILIENT BASE AND ACCESSORIES 096513 - 1
SECTION 096513 - RESILIENT BASE AND ACCESSORIES
PART 1 - GENERAL
1.1 SUMMARY
A. Section Includes:
1. Resilient base.
1.2 SUBMITTALS
A. Product Data: For each type of product indicated.
B. Samples: For each type of product indicated, in manufacturer's standard-size Samples but not less than 12 inches (300 mm) long, of each resilient product color, texture, and pattern required.
1.3 QUALITY ASSURANCE
A. Fire-Test-Response Characteristics: As determined by testing identical products according to ASTM E 648 or NFPA 253 by a qualified testing agency.
1. Critical Radiant Flux Classification: Class I, not less than 0.45 W/sq. cm.
1.4 PROJECT CONDITIONS
A. Maintain ambient temperatures within range recommended by manufacturer in spaces to receive resilient products.
B. Until Substantial Completion, maintain ambient temperatures within range recommended by manufacturer.
C. Install resilient products after other finishing operations, including painting, have been completed.
PART 2 - PRODUCTS
2.1 RESILIENT BASE : B-1
A. Resilient Base:
1. Manufacturers: Basis of Design: Armstrong Vinyl. Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to, the following:
a. Allstate Rubber Corp.; Stoler Industries.
b. Armstrong World Industries, Inc.
c. Burke Mercer Flooring Products; Division of Burke Industries, Inc.
RESILIENT BASE AND ACCESSORIES 096513 - 2
d. Endura Rubber Flooring; Division of Burke Industries, Inc.
e. Estrie Products International; American Biltrite (Canada) Ltd.
f. Flexco, Inc.
g. Johnsonite.
h. Mondo Rubber International, Inc.
i. Musson, R. C. Rubber Co.
j. Nora Rubber Flooring; Freudenberg Building Systems, Inc.
k. PRF USA, Inc.
l. Roppe Corporation, USA.
m. VPI, LLC; Floor Products Division.
B. Resilient Base Standard: ASTM F 1861.
1. Material Requirement: Type TV (vinyl, thermoplastic).
2. Manufacturing Method: Group I (solid, homogeneous).
3. Style: Cove (base with toe).
C. Minimum Thickness: 0.125 inch (3.2 mm).
D. Height: 6 inch.
E. Lengths: Coils in manufacturer's standard length.
F. Outside Corners: Preformed.
G. Inside Corners: Preformed.
H. Finish: As selected by Owner from manufacturer's full range.
I. Colors and Patterns: Basis of Design: Armstrong standard color #92 “Cadet Blue” or as selected by Owner from full range of industry colors.
2.2 INSTALLATION MATERIALS
A. Trowelable Leveling and Patching Compounds: Latex-modified, portland cement based or blended hydraulic-cement-based formulation provided or approved by manufacturer for applications indicated.
B. Adhesives: Water-resistant type recommended by manufacturer to suit resilient products and substrate conditions indicated.
1. Use adhesives that comply with the following limits for VOC content when calculated according to 40 CFR 59, Subpart D (EPA Method 24):
a. Cove Base Adhesives: Not more than 50 g/L.
PART 3 - EXECUTION
3.1 PREPARATION
A. Prepare substrates according to manufacturer's written instructions to ensure adhesion of resilient products.
RESILIENT BASE AND ACCESSORIES 096513 - 3
B. Concrete Substrates for Resilient Stair Treads and Accessories: Prepare according to ASTM F 710.
1. Verify that substrates are dry and free of curing compounds, sealers, and hardeners.
2. Remove substrate coatings and other substances that are incompatible with adhesives and that contain soap, wax, oil, or silicone, using mechanical methods recommended by manufacturer.
Do not use solvents.
3. Alkalinity and Adhesion Testing: Perform tests recommended by manufacturer.
4. Moisture Testing: Perform tests recommended by manufacturer. Proceed with installation only after substrates pass testing.
a. Perform anhydrous calcium chloride test, ASTM F 1869. Proceed with installation only after substrates have maximum moisture-vapor-emission rate of 3 lb of water/1000 sq. ft.
(1.36 kg of water/92.9 sq. m) in 24 hours.
b. Perform relative humidity test using in situ probes, ASTM F 2170. Proceed with installation only after substrates have maximum 75 percent relative humidity level measurement.
C. Fill cracks, holes, and depressions in substrates with trowelable leveling and patching compound and remove bumps and ridges to produce a uniform and smooth substrate.
D. Do not install resilient products until they are same temperature as the space where they are to be installed.
1. Move resilient products and installation materials into spaces where they will be installed at least 48 hours in advance of installation.
E. Sweep and vacuum clean substrates to be covered by resilient products immediately before installation.
3.2 RESILIENT BASE INSTALLATION
A. Comply with manufacturer's written instructions for installing resilient base.
B. Apply resilient base to walls, columns, pilasters, casework and cabinets in toe spaces, and other permanent fixtures in rooms and areas where base is required.
C. Install resilient base in lengths as long as practicable without gaps at seams and with tops of adjacent pieces aligned.
D. Tightly adhere resilient base to substrate throughout length of each piece, with base in continuous contact with horizontal and vertical substrates.
E. Do not stretch resilient base during installation.
3.3 CLEANING AND PROTECTION
A. Comply with manufacturer's written instructions for cleaning and protection of resilient products.
B. Cover resilient products until Substantial Completion.
END OF SECTION 096513
| 011000 - Summary |
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Section includes: |
| 1. Project information. |
| 2. Work covered by Contract Documents. |
| 3. Phased construction. |
| 4. Access to site. |
| 5. Coordination with occupants. |
| 6. Work restrictions. |
| 1.2 PROJECT INFORMATION |
| A. Project Identification: Arapahoe Health Center Flooring Replacement |
| 1. Project Location: Arapahoe Health Center |
| Arapahoe, Wyoming |
| B. Owner: Billings Area Indian Health Service |
| 2900 4th Ave. North |
| Billings, MT 59107 |
| 1. Project Officer: Bridger Hanway |
| Facility Maintenance |
| 307-332-5505 |
| 2. COTR: Greg Ault |
| 1.3 WORK COVERED BY CONTRACT DOCUMENTS |
| A. The Work of the Project is defined by the Contract Documents and consists of the following: |
| 1. The project is to remove the existing wall paper in various locations, prepare the wall surface for texture, machine texture, prime, and paint. The contractor will be responsible for removing items hanging on the wall and replacing them upon finis... |
| B. Type of Contract. |
| 1. Project will be constructed under a single prime contract. |
| 1.4 ACCESS TO SITE |
| A. General: Contractor shall have full use of Project site for construction operations during construction period. Contractor's use of Project site is limited only by Owner's right to perform operations and normal business. |
| B. Use of Site: Limit use of Project site to work in areas indicated. Do not disturb portions of Project site beyond areas in which the Work is indicated. |
| 1. Limits: Confine construction operations to area of work. |
| 2. Driveways, Walkways and Entrances: Keep driveways, loading areas, and entrances serving premises clear and available to Owner, Owner's employees, and emergency vehicles at all times. Do not use these areas for parking or storage of materials. |
| a. Schedule deliveries to minimize use of driveways and entrances by construction operations. |
| b. Schedule deliveries to minimize space and time requirements for storage of materials and equipment on-site. |
| 1.5 COORDINATION WITH OCCUPANTS |
| A. Partial Owner Occupancy: Owner will occupy the premises during entire construction period, with the exception of areas under construction. Cooperate with Owner during construction operations to minimize conflicts and facilitate Owner usage. Perf... |
| 1. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities. Do not close or obstruct walkways, corridors, or other occupied or used facilities without written permission from Owner and authorities having jurisd... |
| 2. Provide not less than 72 hours' notice to Owner of activities that will affect Owner's operations. |
| B. Owner Limited Occupancy of Completed Areas of Construction: Owner reserves the right to occupy and to place and install equipment in completed portions of the Work, prior to Substantial Completion of the Work, provided such occupancy does not inte... |
| 1. Before limited Owner occupancy, mechanical and electrical systems shall be fully operational, and required tests and inspections shall be successfully completed. On occupancy, Owner will operate and maintain mechanical and electrical systems servi... |
| 2. On occupancy, Owner will assume responsibility for maintenance and custodial service for occupied portions of Work. |
| 1.6 WORK RESTRICTIONS |
| A. Work Restrictions, General: Comply with restrictions on construction operations. |
| 1. Comply with limitations on use of public streets and other requirements of authorities having jurisdiction. |
| B. On-Site Work Hours: Limit work in the existing building to outside normal business working hours of 8:00 a.m. to 5:00 p.m., Monday through Friday, except as otherwise indicated. All areas under construction must be ready for use during business h... |
| 1. Alternate work hours of evenings and weekends will be utilized to minimize disruption to Owner operations and must be approved by Project Officer. |
| C. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owner or others unless permitted under the following conditions and then only after providing temporary utility services according to requirements indicated: |
| 1. Notify Owner not less than two days in advance of proposed utility interruptions. |
| 2. Obtain Owner’s written permission before proceeding with utility interruptions. |
| D. Noise, Vibration, and Odors: Coordinate operations that may result in high levels of noise and vibration, odors, or other disruption to Owner occupancy with Owner. |
| 1. Owner not less than two days in advance of proposed disruptive operations. |
| 2. Owner’s written permission before proceeding with disruptive operations. |
| E. Nonsmoking Campus: Smoking is not permitted within the building or on the campus grounds. |
| F. Employee Identification: Owner will provide identification tags for Contractor personnel working on Project site. Require personnel to use identification tags at all times. |
| G. Employee Screening: Comply with Owner's requirements for screening of Contractor personnel working on Project site. |
| 1. Maintain list of approved screened personnel with Owner's representative. |
H. Controlled Substances: Use of tobacco products and other controlled substances within the existing building and on the Project site is not permitted.
| PART 2 - PRODUCTS (Not Used) |
| PART 3 - EXECUTION (Not Used) |
| 024119 - Selective Demolition |
| PART 1 - GENERAL |
| 1.1 RELATED DOCUMENTS |
| A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section. |
| 1.2 SUMMARY |
| A. Section Includes: |
| 1. Demolition and removal of selected portions of building or structure. |
| 2. Demolition and removal of selected site elements. |
| 3. Salvage of existing items to be reused or recycled. |
| B. Related Requirements: |
| 1. Section 011000 "Summary" for restrictions on the use of the premises, Owner-occupancy requirements, and phasing requirements. |
| 1.3 DEFINITIONS |
| A. Remove: Detach items from existing construction and legally dispose of them off-site unless indicated to be removed and salvaged or removed and reinstalled. |
| B. Remove and Salvage: Carefully detach from existing construction, in a manner to prevent damage, and deliver to Owner ready for reuse. |
| C. Remove and Reinstall: Detach items from existing construction, prepare for reuse, and reinstall where indicated. |
| D. Existing to Remain: Existing items of construction that are not to be permanently removed and that are not otherwise indicated to be removed, removed and salvaged, or removed and reinstalled. |
| 1.4 MATERIALS OWNERSHIP |
| A. Unless otherwise indicated, demolition waste becomes property of Contractor. |
| 1.5 INFORMATIONAL SUBMITTALS |
| A. Proposed Protection Measures: Submit report, including drawings, that indicates the measures proposed for protecting individuals and property for dust control. Indicate proposed locations and construction of barriers. |
| B. Schedule of Selective Demolition Activities: Indicate the following: |
| 1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Ensure Owner's on-site operations are uninterrupted. |
| 2. Interruption of utility services. Indicate how long utility services will be interrupted. |
| 3. Coordination for shutoff, capping, and continuation of utility services. |
| 4. Coordination of Owner's continuing occupancy of portions of existing building and of Owner's partial occupancy of completed Work. |
| 1.6 FIELD CONDITIONS |
| A. Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted. |
| B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical. |
| C. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work. |
| 1. If suspected hazardous materials are encountered, do not disturb; immediately notify Project Officer and Owner. |
| D. Storage or sale of removed items or materials on-site is not permitted.. |
| E. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations. |
| 1. Maintain fire-protection facilities in service during selective demolition operations. |
| PART 2 - PRODUCTS |
| 2.1 PEFORMANCE REQUIREMENTS |
| A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction. |
| PART 3 - EXECUTION |
| 3.1 EXAMINATION |
| A. Strategically plan demolition to minimize disruption to facility operations and downtime. |
| B. Verify that utilities have been disconnected and capped before starting selective demolition operations. |
| C. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to Project Officer. |
| 3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS |
| A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage. |
| 1. Comply with requirements for existing services/systems interruptions specified in Section 011000 "Summary." |
| B. Existing Services/Systems to Be Removed, Relocated, or Abandoned: Locate, identify, disconnect, and seal or cap off indicated utility services and mechanical/electrical systems serving areas to be selectively demolished. |
| 1. If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building. |
| 2. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated to be removed. |
| a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material. |
| b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material. |
| c. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Owner. |
| 3.3 PREPARATION |
| A. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities. |
| B. Temporary Facilities: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain. |
| 1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building. |
| 2. Protect walls, ceilings, floors, and other existing finish work that are to remain or that are exposed during selective demolition operations. |
| 3. Provide dust barriers and ventilation to protect adjacent areas. |
| 4. Cover and protect furniture, furnishings, and equipment that have not been removed. |
| 3.4 SELECTIVE DEMOLITION, GENERAL |
| A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows: |
| 1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level. |
| 2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not ha... |
| 3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces. |
| 4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain fire watch and po... |
| 5. Maintain adequate ventilation when using cutting torches. |
| 6. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing. |
| 7. Restore adjacent surfaces, areas, and/or items to original condition if damaged during demolition or construction activities. |
| 8. Dispose of demolished items and materials promptly. |
| B. Reuse of Building Elements: Do not demolish building elements beyond what is indicated on Drawings without Project Officer's approval. |
| C. Removed and Salvaged Items: |
| 1. Clean salvaged items. |
| 2. Store items in a secure area until delivery to Owner. |
| 3. Protect items from damage during transport and storage. |
| D. Removed and Reinstalled Items: |
| 1. Clean and repair items to functional condition adequate for intended reuse. |
| 2. Protect items from damage during transport and storage. |
| 3. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated. |
E. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Project Officer, items may be removed to a suitable, protected storage location during selective demoliti...
| 3.5 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS |
| A. Concrete: Demolish in small sections. Using power-driven saw, cut concrete to a depth of at least 3/4 inch (19 mm) at junctures with construction to remain. Dislodge concrete from reinforcement at perimeter of areas being demolished, cut reinfor... |
| B. Masonry: Demolish in small sections. Cut masonry at junctures with construction to remain, using power-driven saw, then remove masonry between saw cuts. |
| 3.6 DISPOSAL OF DEMOLISHED MATERIALS |
| A. General: Except for items or materials indicated to be reused, salvaged, reinstalled, or otherwise indicated to remain Owner's property, remove demolished materials from Project site and legally dispose of them in an EPA-approved landfill. |
| 1. Do not allow demolished materials to accumulate on-site. |
| 2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas. |
| B. Burning: Do not burn demolished materials. |
| C. Disposal: Transport demolished materials off Owner's property and legally dispose of them. |
| 3.7 CLEANING |
| A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began. Daily cleaning may be required to make const... |
| 092900 - Gypsum Board |
| PART 1 - GENERAL |
| 1.1 SUMMARY |
| A. Section Includes: |
| 1. Interior gypsum board. |
| 2. Texture finishes. |
| 1.2 ACTION SUBMITTALS |
| A. Product Data: For each type of product. |
| B. Samples: |
| 1. Textured Finishes: Manufacturer's standard size for each textured finish indicated and on same backing indicated for Work. |
| PART 2 - PRODUCTS |
| 2.1 PERFORMANCE REQUIREMENTS |
| A. Fire-Resistance-Rated Assemblies: For fire-resistance-rated assemblies, provide materials and construction identical to those tested in assembly indicated according to ASTM E 119 by an independent testing agency. |