This document contains Agency-Specific Requirements (ASR) for a federal lease solicitation. The ASR provides detailed space and facility requirements for the U.S. Geological Survey's Utah Water Science Center office and Moab Field Office. Key requirements include approximately 1,596 usable square feet of office and laboratory space, 1,401 square feet of industrial/warehouse space, and 5,000-7,500 square feet of secured outdoor parking. Specific details are provided for individual rooms such as private offices, open office areas, sample preparation rooms, and warehouse/shop space. The ASR also outlines building-wide parameters including site and parking specifications, security, janitorial services, and laboratory equipment needs. This level of requirement specificity is intended to assist potential offerors in preparing competitive proposals that can adequately accommodate the tenant agency's facility and operational needs.

View the file

Other files

File Type Posted
9UT2187_PreSolicitation Ad (Updated 12_27_23).pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Agency-Specific Requirements

ASR

UTAH WATER SCIENCE CENTER

Moab Field Office

Moab, UT

November 8, 2023

IN ADDITION TO THE REQUIREMENTS SET FORTH IN THE REQUEST FOR LEASE PROPOSAL (RLP) AND

LEASE (GSA FORM L202), THE FOLLOWING AGENCY-SPECIFIC REQUIREMENTS (ASR) DEFINES ALL ITEMS

THAT ARE TO BE FURNISHED, INSTALLED, AND MAINTAINED BY THE LESSOR UNLESS INDICATED

OTHERWISE. THE RLP AND LEASE ESTABLISHES THE MINIMUM REQUIREMENTS. THIS DOCUMENT IS A

SUPPLEMENT TO THE RLP AND LEASE AND MAY ESTABLISH MORE STRINGENT REQUIREMENTS.

THE SPECIFIC REQUIREMENTS CONTAINED HEREIN SUPERSEDE ANY CONTRADICTORY ITEMS WHICH

MAY BE CONTAINED IN OTHER PARTS OF THE REQUEST FOR LEASE PROSAL AND LEASE. ALL ITEMS

FOUND IN THESE REQUIREMENTS SHALL BE AMORTIZED IN THE OVERALL RENTAL CONSIDERATION, UNLESS SPECIFIED OTHERWISE.

AGENCY SPECIFIC REQIREMENTS – RLP Initials: _____________ & ______________

Page 2 of 12 Lessor Government

Contents

1.0 PURPOSE OF PROJECT

1.1 INTRODUCTION

1.2 MISSION AND FUNCTION

1.3 GREEN BUILDING

2.0 GENERAL SPACE REQUIREMENTS

2.1 AMOUNT OF SPACE

2.1.1 Square Footage Requirement

2.1.2 Space Break Down

2.2 DELINEATED AREA

2.2.1 Boundaries

2.2.2 Map

2.3 TERM OF LEASE

2.4 BUILDING WIDE PARAMETERS

2.4.1 Site

2.4.2 Operating Hours:

2.4.3 Security

2.4.4 Janitorial

2.4.5 Parking

2.4.6 Laboratory Case Work

2.4.7 Laboratory Equipment (plumbing, fume hoods, sinks, showers)

2.4.8 Antennas

2.4.9 Mail Box

2.4.10 Egress Lighting

3.0 DETAILED REQUIREMENTS

3.1 GENERAL PURPOSE SPACE

3.1.1 Office and Support Spaces

3.1.2 Special Purpose Space-(Non-Utilized)

3.1.3 Warehouse/Light Industrial

3.1.4 Exterior Space

AGENCY SPECIFIC REQIREMENTS – RLP Initials: _____________ & ______________

Page 3 of 12 Lessor Government

1.0 Purpose of Project

1.1 Introduction

The following Agency-Specific Requirements (ASR) is intended to further describe the lease requirements for the U.S. Geological Survey, Utah Water Science Center Office and Moab Field Office. This ASR defines the USGS tenant improvement requirements (Modifications) for offices, support spaces, parking, special spaces, and laboratories. Furthermore, it is intended to provide design and test-fit guidance to the owner in the submittal of leased space offered.

The information is here to assist the owner in preparing their offers, square footages of individual rooms listed are approximate and are provided as a guideline for space layout and to ensure that the space and site offered will provide for an efficient layout and accommodate the needs of the U.S. Geological Survey in an efficient and effective manner. It should be noted that this ASR has been developed prior to the award of a lease. When the offered space becomes available, it may be required to refine this program and make adjustments to accommodate the space offered.

1.2 Mission and Function

The USGS serves the Nation by providing reliable scientific information to describe and understand the

Earth; minimize loss of life and property from natural disasters; manage water, biological, energy, and mineral resources; and enhance and protect our quality of life. USGS has become a world leader in the natural sciences thanks to our scientific excellence and responsiveness to society's needs.

The Utah Water Science Center’s mission is to provide reliable, impartial, and timely data, analyses, and reports that are needed to understand the Nation’s water resources. The Center actively promotes the use of this information by decision makers to:

• Minimize the loss of life and property as a result of water-related natural hazards, such as floods, droughts, and land movement.

• Effectively manage groundwater and surface-water resources for domestic, agricultural, commercial, industrial, recreational, and ecological uses.

• Protect and enhance water resources for human health, aquatic health, and environmental quality.

• Contribute to wise physical and economic development of the State’s resources for the benefit of present and future generations.

• Integrate the Center’s basic data and interpretive studies into broader interdisciplinary activities with other DOI bureaus, other Federal agencies, and State cooperative partners.

1.3 Green Building

A commitment to sustainable design is a priority for this project. Federal law and Executive Orders require the Government to apply good sound Green Building Principles for construction, environmental management, operation, and maintenance of federally funded buildings. Government agencies are called upon to promote energy efficiency, water conservation, and the use of renewable energy sources. The

Supplemental Lease Requirements incorporates all the required Green Building requirements for this procurement.

It should be the building owner’s intent to optimize the use of emerging energy management technologies through the implementation of a building design that employs all of the following:

• Optimize Site Potential: Creating sustainable buildings starts with proper site selection, including consideration of the reuse or rehabilitation of existing buildings. The location, orientation, and landscaping of a building affects the local ecosystem, transportation methods, and energy use.

• Minimize Energy Consumption: A building should rely on optimizing system efficiencies and employing conservation measures. Renewable energy technologies should be used in facility projects whenever feasible and cost effective.

AGENCY SPECIFIC REQIREMENTS – RLP Initials: _____________ & ______________

Page 4 of 12 Lessor Government

• Protect and Conserve Water: Fresh water in an increasingly scarce resource. A sustainable building should reduce, control or treat site runoff, use water efficiently, and implement as many

Federal Energy Management Program Water Efficiency Improvement Best Management Practices as practicable.

• Use Environmentally Preferable Products: Buildings should be constructed of materials that minimize lifecycle environmental impacts such as global warming, resource depletion, and toxicity.

• Enhance Indoor Environmental Quality (IEQ): The IEQ of a building has a significant impact on occupant health, comfort, and productivity. Among other attributes, a building should optimize day lighting, be well ventilated, control moisture/humidity, and avoid the use of materials with high-VOC emissions.

• Optimize Operational and Maintenance Practices: Buildings should be designed to take into account the energy and environmental impacts of operating and maintaining the building. Designers are encouraged to specify materials and systems that reduced maintenance requirements, and/or require less water, energy and toxic chemicals to maintain.

2.0 General Space Requirements

2.1 Amount of Space

2.1.1 Square Footage Requirement

The US Geological Survey is interested in leasing approximately 1,596 usable square feet of

Office, and Laboratory space in addition to 1,401 square feet of industrial space/warehouse.

2.1.2 Space Break Down

General Purpose Space

Space Type Square

Feet Quantity

Total Usable Square Feet

Private Office #1 132 1 132

Workstation #1 180 5 900

Copy Room / conference 220 1 220

Computer Room 25 1 25

10% interior circulation 146

Subtotal 1423

Special-Use Space (Non-Utilized) Sample Prep Lab 146

Total Special Use SF 146

Industrial Space

Shop/welding/assembly/warehouse/storage

Total Special Use Square Feet 1401

Site Secured/Fenced Open Parking

(SF) *

5,000- 7,500

General Open Employee/Visitor Parking

8 +

ADA

* Circulation space is not incorporated in the Ware Yard SF which depends on site design parameters or a drive through design concept.

AGENCY SPECIFIC REQIREMENTS – RLP Initials: _____________ & ______________

Page 5 of 12 Lessor Government

TOTAL MIN USABLE SQUARE FEET 3,000

Rentable Square Foot Range 3000 3,500

2.2 Delineated Area

2.2.1 Boundaries

The delineated area from which space will be considered will be within the city limits of Moab and

Spanish Valley within Grand and San Juan Counties, UT within the following boundaries:

N: Highway 191, Colorado river passing

E: S Spanish Valley Dr

S: Old Airport Rd and Highway 191

W 500 W and Rimrock Lane

2.2.2 Map

AGENCY SPECIFIC REQIREMENTS – RLP Initials: _____________ & ______________

Page 6 of 12 Lessor Government

2.3 Term of Lease

The lease term shall be for 5 years, 3 years Firm

2.4 Building Wide Parameters

2.4.1 Site

The building site must accommodate good, safe, vehicular access and circulation throughout for large vehicles and vehicles pulling trailers that can reach in excess of 16’ long with a central pivot point unlike standard semi-trailers. Drive through designs is encouraged otherwise significantly more circulation space will be required adjacent to the building space.

Street access to and from the site shall be safe and allow safe and easy access in both directions of travel. A site that provides access via two different streets is preferred.

Outdoor lighting will need to be sufficient for safety and to ensure preventive lighting for GOV vehicles parked overnight in the parking lot.

2.4.2 Operating Hours:

Services, maintenance, and utilities shall be provided daily, extending 6:00 am to 6:00 pm except

Saturdays, Sundays, and federal Holidays.

LABORATORY AREA – Services, maintenance, and utilities shall be provided 24 hours per day, 7 days per week for the entire Laboratory area of the building.

2.4.3 Security

Primary security specification and level identification are incorporated into the RLP. The

Government may choose its own perimeter security system and monitoring.

All outside doors should be keyed the same.

2.4.4 Janitorial

A. Janitorial shall be full service 3- 5 times per week and provided in the daytime hours with prior notice or schedule (vacuuming before 5 pm ) and per the Lease Section 5.07

B. Daily janitorial to include trash, restroom cleaning, and vacuuming (once per week).

Carpet shampooing to be provided twice per year.

C. Janitorial Service is not required in the laboratory space.

2.4.5 Parking

A minimum of 5 parking spaces shall be available for employees, visitors, and GOV vehicles must be provided on-site. Disabled spaces shall be included in the 5 requested spaces and must meet all the requirements addressed in the RLP.

2.4.6 Laboratory Case Work

All laboratory case work, work surfaces, and furniture shall be provided by the government and maintained by the lessor as part of the finished tenant improvements.

2.4.7 Laboratory Equipment (plumbing, sinks, eyewash station)

The Lessor will be responsible for maintaining plumbing, sink, emergency eyewash station. The

Laboratory HVAC and ventilation system shall be on the same air-handling systems as the office space in the building.

2.4.8 Antennas

The Lessor shall allow the Government and/or its designated telecommunications providers to affix telecommunications antennae (high frequency, mobile, microwave, satellite, or other emerging

AGENCY SPECIFIC REQIREMENTS – RLP Initials: _____________ & ______________

Page 7 of 12 Lessor Government technologies), subject to weight and wind load conditions, to roof, parapet, or building envelope as required. Access/penetrations for the antenna(s) to the leased space shall be provided by the lessor.

2.4.9 Mail Box

The Lessor is required to provide a large lockable/securable mail box for Government only access.

2.4.10 Egress Lighting

24 Hour Egress/Night lighting is required throughout the leased interior space.

3.0 Detailed Requirements

3.1 General Purpose Space

This section of the ASR is intended to provide the characteristics of principal areas in more detail. Individual room details and requirements are provided on the following pages to allow for detailed cost estimating.

The offeror is required to provide scaled drawings and a test fit layout as part of their offer based on the requirements and specifications contained in the RLP and this ASR. Any questions regarding these requirements shall be submitted in writing. The government will make all reasonable efforts to provide input on draft space layouts during the solicitation process. Efficient space layout and vehicle circulation is critical in addition to layout by office functions and divisions. All columns and obstructions that will impact an efficient layout of the space shall be clearly noted on the drawings.

AGENCY SPECIFIC REQIREMENTS – RLP Initials: _____________ & ______________

Page 8 of 12 Lessor Government

3.1.1 Office and Support Spaces

ROOM NAME: Open Office and computer area

SECTION:

SQUARE FEET:

SPACE TYPE: Workstations/Printer/c omputer

OCCUPANTS:

QUANTITY:

DESCRIPTION

This Open Office houses most of the office staff and will contain workstations provided by the Government

WALL CONSTRUCTION

Perimeter partitioning to be drywall, deck to deck (Demising Wall) with sound proofing

DOORS & FRAMES NA

DOORS HARDWARE NA

FINISHES:

FLOORS

Commercial grade carpet to include carpet or vinyl perimeter cove base per

SFO.

WALL FINISH

One coat of best quality interior primer and two coats paint. Paint per SFO.

No texture unless prior approval by government.

CEILING

SFO/Building standard: Suspended acoustical ceiling system: 2’-0” x 2’-0” or 2’-0” x 4’-0” standard “T” grid with standard edge lay-in acoustical tile.

WINDOWS (Fenestration) Mini-Blinds as applicable per SFO.

ELECTRICAL LIGHTING

2’-0” x 2’-0” or 2’-0” x 4’-0” recessed modern, fluorescent fixtures with deep cell parabolic louvers per SFO. A uniform lighting level of 50 foot candles required at 36” AFF at all work surfaces. Motion equipped light sensor per SFO. NOTE: Be sure to include/consider 62" high system furniture partitions throughout the space when calculating lighting foot candles.

ELECTRICAL POWER TBD

COMMUNICATIONS TBD

HVAC SFO/Building Standard

SECURITY NA

SPECIAL CONSTRUCTION

EQUIPMENT Government Provided

FURNITURE Government Provided and Installed

NOTES AND OTHER Government to provide computer cage

ROOM NAME: Private Office SECTION: SQUARE FEET: 132

SPACE TYPE: Workstations/Printer/c omputer

OCCUPANTS:

QUANTITY:

DESCRIPTION

This Open Office houses a supervisor and will contain a workstation provided by the Government

WALL CONSTRUCTION

Perimeter partitioning to be drywall, deck to deck (Demising Wall) with sound proofing

AGENCY SPECIFIC REQIREMENTS – RLP Initials: _____________ & ______________

Page 9 of 12 Lessor Government

DOORS & FRAMES

Stained, natural wood veneer face, solid-core wood interior door per SFO and Metal Door Frame per SFO.

DOORS HARDWARE

Door hardware shall be building standard heavy-weight hinges and standard lever latch set per SFO, commercial grade, ABAAS/ADA Approved.

FINISHES:

FLOORS

Commercial grade carpet to include carpet or vinyl perimeter cove base per

SFO.

WALL FINISH

One coat of best quality interior primer and two coats paint. Paint per SFO.

No texture unless prior approval by government.

CEILING

SFO/Building standard: Suspended acoustical ceiling system: 2’-0” x 2’-0” or 2’-0” x 4’-0” standard “T” grid with standard edge lay-in acoustical tile.

WINDOWS (Fenestration) Mini-Blinds as applicable per SFO.

ELECTRICAL LIGHTING

2’-0” x 2’-0” or 2’-0” x 4’-0” recessed modern, fluorescent fixtures with deep cell parabolic louvers per SFO. A uniform lighting level of 50 foot candles required at 36” AFF at all work surfaces. Motion equipped light sensor per SFO. NOTE: Be sure to include/consider 62" high system furniture partitions throughout the space when calculating lighting foot candles.

ELECTRICAL POWER TBD

COMMUNICATIONS TBD

HVAC SFO/Building Standard

SECURITY NA

SPECIAL CONSTRUCTION

EQUIPMENT Government Provided

FURNITURE Government Provided and Installed

NOTES AND OTHER Government to provide computer cage

3.1.2 Special Purpose Space-(Non-Utilized)

ROOM NAME: Sample prep room/lab storage

SECTION:

NA

SQUARE FEET:

SPACE TYPE: Sample Prep OCCUPANTS: 0 QUANTITY: 1

DESCRIPTION

This room serves as the general sampler preparation and field prep shared by all scientists and clean lab storage. This room serves as the clean storage area for laboratory supplies and sampling equipment.

WALL CONSTRUCTION

Partitioning to be drywall, installed from finish floor to 6" above suspended ceiling, insulated to provide an STC rating of 43-45 or above.

Walls shall be properly construction and reinforced to accommodate wall hanging cabinets through the work area.

AGENCY SPECIFIC REQIREMENTS – RLP Initials: _____________ & ______________

Page 10 of 12 Lessor Government

DOORS & FRAMES

Stained, natural wood veneer face, solid-core wood interior door per SFO and Metal Door Frame per SFO.

All interior laboratory doors shall incorporate a minimum of 1 square foot of window/glass space for safety concerns.

DOORS HARDWARE

Door hardware shall be building standard heavy-weight hinges and standard lever latch set per SFO, commercial grade, ABAAS/ADA Approved.

FINISHES:

FLOORS

ACID RESISTANT - Vinyl composite tile, 12” x 12” x 1/8”. Vinyl resilient base, top set, 1/8” x 4”, with factory formed external and internal corners.

WALL FINISH

One coat of best quality interior primer and two coats paint. Paint per SFO.

No texture unless prior approval by government.

CEILING

SFO/Building standard: Suspended acoustical ceiling system: 2’-0” x 2’-0” or 2’-0” x 4’-0” standard “T” grid with standard edge lay-in washable and humidity resistant acoustical tile.

WINDOWS (Fenestration) Mini-Blinds as applicable per SFO.

ELECTRICAL LIGHTING

2’-0” x 2’-0” or 2’-0” x 4’-0” recessed modern, fluorescent fixtures with deep cell parabolic louvers per SFO. Energy Efficient T8 Bulbs and a uniform lighting level of 50 foot candles required at 36” AFF over all work surfaces.

Motion equipped light sensor in lab.

ELECTRICAL POWER

12 (Minimum) 120v Duplex Receptacles – Alternating Circuits with no more than 4 outlets per circuit.

Outlets shall be installed between 36” – 42” AFF (Bench Level) and 18” AFF if not above cabinet space.

COMMUNICATIONS One (1) – Phone Outlet and two (2) Data Outlets installed by the lessor.

HVAC Normal Building HVAC per SFO

SECURITY NA

PLUMBING Two sinks, eye wash, hook up for deionized water system

SPECIAL CONSTRUCTION

All walls shall be constructed to support shelving and cabinets. The government shall install cabinets/shelving as needed in this room after occupancy.

EQUIPMENT Government Provided

FURNITURE Government Provided

NOTES AND OTHER Room must be minimum of 14.5 Feet long

AGENCY SPECIFIC REQIREMENTS – RLP Initials: _____________ & ______________

Page 11 of 12 Lessor Government

3.1.3 Warehouse/Light Industrial

ROOM NAME: Warehouse/shop SECTION: NA SQUARE FEET: 1401

SPACE TYPE: Light Industrial OCCUPANTS: 0 QUANTITY: 1

DESCRIPTION Light industrial warehouse area for storage of field equipment and vehicles

WALL CONSTRUCTION

Standard Light Industrial Construction. Insulated walls throughout exterior and office area separation. Deck to Deck.

DOORS & FRAMES

Pre-finished, insulated personnel metal door, painted. Welded, thermally broken, painted hollow metal frame. (36” wide) Door shall be adjacent to all over head doors and be ADA compliant.

DOORS HARDWARE

Door hardware shall be building standard heavy-weight hinges and standard lever latch set per SFO, commercial grade, ABAAS/ADA Approved.

FINISHES:

FLOORS Level, sealed concrete.

WALL FINISH

Level 2 Drywall Finish where appropriate and One coat of best quality interior primer as applicable.

CEILING

Unfinished – 12’ working height. Overhead door opener and other penetrations may not protrude into this working height. Hanging heat units may be accepted upon approval of the Contracting Officer.

WINDOWS (Fenestration) Mini-Blinds as applicable per SFO.

ELECTRICAL LIGHTING

All light fixtures shall maintain a uniform light level at 36” AFF of 20 foot candles. Three way light switch required at every door.

ELECTRICAL POWER

120v Duplex Receptacle: Every 12’ along all walls – alternating circuits at

42” AFF.

COMMUNICATIONS One (1) – Phone Outlets (installed by the lessor).

HVAC

Heat only with individual thermostat control.

24” side wall exhaust fan and make up air unit as necessary and per code – see below for additional information.

SECURITY

Deadbolt locks (keyed the same as all locks on facility) for doors on outside of building.

PLUMBING -

SPECIAL CONSTRUCTION

EQUIPMENT Government Provided

FURNITURE Government Provided

NOTES AND OTHER

AGENCY SPECIFIC REQIREMENTS – RLP Initials: _____________ & ______________

Page 12 of 12 Lessor Government

3.1.4 Exterior Space

ROOM NAME: Ware Yard SECTION: NA SQUARE FEET: 5000-7500

SPACE TYPE: Outdoor OCCUPANTS: 0 QUANTITY: 1

DESCRIPTION Secured-Fenced area for storing vehicles, boats, and trailers.

FENCE Fencing: Min. Six (6) ft tall Industrial grade chain link fence

GATE

FINISHES:

FLOORS Level, graded and asphalt or concrete paved.

WALL FINISH NA

CEILING NA

WINDOWS (Fenestration) NA

ELECTRICAL LIGHTING Exterior Lighting per SFO

ELECTRICAL POWER One 120v Duplex Receptacles – exterior and GFCI Protected.

COMMUNICATIONS NA

HVAC NA

SECURITY NA

PLUMBING NA

SPECIAL CONSTRUCTION NA

EQUIPMENT Government Provided

FURNITURE Government Provided

NOTES AND OTHER

Secured parking area must be located within reasonable walking distance from the light industrial portion of space. Preferred adjacent.

The requested square footage does not included circulation space in regards to accessing the industrial area if it is incorporated and adjacent to the light industrial space/overhead doors.

A drive through design is desired otherwise circulation space may be required within the ware yard area depending on layout and access.

A) Trash/Dumpster service is required on site.