Machine Rigging for MR002, at the Watervliet Arsenal, Watervliet NY
Solicitation number
W911PT25R0011
Issued by

About this file

This Statement of Work (SOW) details machine rigging services for the Watervliet Arsenal's manufacturing buildings. The contractor will be responsible for moving, scrapping, and relocating machinery, which includes preparing and securing equipment, verifying energy source disconnection, managing foundation preparation, and handling waste disposal. Specific tasks include floor preparation, machine leveling, electrical work for machines over 200 FLA, and securing work sites using snow fencing.

The related federal contract opportunity is a pre-solicitation for machine rigging services, set aside exclusively for HUBZone small business concerns with an estimated project value between $250,000 and $500,000. The procurement will be completed 180 days after notice to proceed, with an anticipated solicitation issue date of May 1, 2025. The contract will be awarded by the Department of the Army Materiel Command Contracting Command Detroit Arsenal, with the solicitation to be published electronically on beta.sam.gov. Offerors must have an active SAM registration and meet sustainable acquisition principles outlined in FAR Part 23.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOW for Machine Rigging MR002

Prepared by: Tim Fontaine Email: timothy.j.fontaine.civ@army.mil Phone: Office: 518-266-3909 Cell: 518-376-7965

Contractor Responsibilities

· Contractor will supply all necessary material, tools and equipment needed to scrap out and/or move a piece of equipment within WVA’s manufacturing buildings. This will include building to building moves as well.

· Contractor will verify all energy sources (electrical, pneumatics, etc.) have been disconnected and deenergized prior to work commencing. Contractor will also check for any fluids left (cutting oils, water-based coolants, hydraulics, etc.) prior to commencing.

· Contractor may have the assistance of the WVA overhead crane with an Arsenal employee operating the crane. This must be coordinated with the COR 1 day prior to the need.

· If the contractor’s method of removal generates any spark or the use of any open flame the contractor must obtain a “Burn Permit” from the WVA’s Fire Department. The COR will instruct the contractor on how to obtain if needed.

· Contractor will prep the floor to accept the machine prior/during machine move.

· Cut out wood block floor to accept new machine spacer, electrical conduit, etc.

· Verify all measurements where machine feet are located on said machine. Also, any electrical trenching that is required.

· Contractor will secure the machine to the floor. For example: core hole, thunder stud, threaded rod with epoxy, etc. The method of securing the machine to the floor will be discussed with the COR prior to work commencing.

· Contractor will rough level the machine once said machine is secured to the floor in the new location.

· For any machine over 200 FLA the contractor will be responsible for all electrical work.

· Contractor will have all machine foundations cleaned once machine has been removed from the foundation.

· The foundation will be free from all:

· Debris

· Oil

· Metal that is not secured to the concrete

· For all non-hazardous waste the contractor will be responsible for proper disposal.

· For all hazardous waste that wasn’t identified/removed prior to work commencing the WVA will be responsible for removing and disposal.

· Contractor will be responsible for securing all worksites before and after the machine has been removed. Snow fencing is the preferred method here at the WVA.

WVA Responsibilities

· The WVA will have all energy sources (electrical, pneumatics, etc.) disconnected prior to work commencing. The WVA will drain and dispose of any fluids in said machine (cutting oils, water-based coolants, hydraulics, etc.) prior to commencing.

· The WVA will identify the new move location to the contractor in the instance of a machine move. The WVA will clear the space and prepare the area to accept the machine for install from contractor.

· The WVA will supply the buss switch necessary unless otherwise stated by the COR prior to work commencing. In the case of WVA not supplying a buss switch the COR will discuss with the Contracting Specialist for the contractor to purchase said buss switch.

· The WVA will be responsible for all machines under 200 FLA and will supply all electrical needs to get the machine reenergized.

· The WVA will organize all transportation of said machine from the WVA to the holder of WVA’s Scrap Contract at the time of work commencing.

· If contractor organizes with WVA’s Scrap Contractor for transportation of said machine this will need to be coordinated with the COR 5 days prior to work commencing.