9035X 9050X 9053X Carpet SOW.pdf
PDF 140 KB Posted
- Attached to
- New Carpet and Flooring (Amendment 0002)
- Solicitation number
- FA441722QC234
View the file
Other files
| File | Type | Posted |
|---|---|---|
| FA441722QC234 -- Carpet and Flooring.pdf | ||
| 9035X 9050X 9053X Carpet SOW.pdf | ||
| 9035X 9050X 9053X Carpet SOW.pdf | ||
| FA441722QC234 -- Carpet and Flooring.pdf | ||
| 9050X 9053X 9035X CARPET.xlsx | XLSX spreadsheet |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK FOR
CARPET/TILE INSTALLATION
1.0 JOB DESCRIPTION:
1.1. The contractor shall furnish all labor, equipment and materials, and perform all operations in connection with “Remove Old Carpet and Replace with New Carpet/Tile.”
2.0 WORK INCLUDED: The work to be performed includes but is not limited to the following:
2.1. Multiple Facilities, Contractor shall remove existing carpet/base in facility.
2.2. Contractor shall replace all material removed with carpet and/or tile to include replacing base.
2.2.1. Transition strips shall be installed as necessary to complete work.
2.2.2. Floor shall be level and clear of all debris prior to installation of new tile.
2.2.3. Contractor is responsible for moving/replacement of standard/system furniture.
2.3 Specific work and quantities are provided below per facility:
90357
REMOVE EXISTING CARPET 290 SY
REMOVE EXISTING COVE BASE 200 LF
REMOVE EXISTING VINYL TILE 686 SF
MOVE STANDARD FURNITURE 290 SY
4 INCH RUBBER BASE 220 LF
TRANSITION STRIP 250 LF
CARPET-IMPULSE MODULAR J & J 319 SY
LUXURY VINYL TILE J & J 686 SF
SHAW CARPET PAD 510 SY
90503
REMOVE EXISTING CARPET 79 SY
MOVE STANDARD FURNITURE 79 SY
TRANSITION STRIP 48 LF
CARPET-SHAW HOME ROOM SCHOLARSHIP 86.9 SY
90531
REMOVE EXISTING COVE BASE 424 LF
MOVE STANDARD FURNITURE 401 SY
4 INCH RUBBER BASE 480 LF
LUXURY VINYL TILE J & J 4575 SF
3.0 HOURS OF WORK:
3.1. Normal hours of work shall be from 7:00 AM to 4:00 PM, Monday through Friday, except Federal
Holidays. Work outside normal hours may be approved on a case by case basis, with prior approval by the Contracting Officer.
4.0 ESTIMATED JOB COMPLETION:
4.1. Period of performance shall be 90 Days after NTP, receipt of order and coordination with the
Government.
5.0 COORDINATION OF WORK:
5.1. The contractor shall coordinate all work through the using agencies Point of Contact (POC), and the Contracting Officer or his/her representative.
5.2. Contractor shall protect Government property from any possible damage at all times during the accomplishment of the work described for this project.
6.0 CLEANUP AND DISPOSAL:
6.1. All equipment, and tools, shall be secured and stored in a predetermined location so that there is no interference with the movement or operation of military equipment. All debris shall be picked up and removed daily from job site.
7.0 REGULATORY WORK REQUIREMENTS:
7.1. Preparatory floor work is required on all jobs to include scraping, grinding, sanding, proper grading, and leveling of floor to bring the finished product to satisfactory and desired end result as determined by the Contracting Officer Representative. If and when floor leveling compound is needed in excess, the contractor will consult the COR before providing the Government an estimate, to determine the requirement and funding of the line item for floor leveling.
8.0 UTILITIES:
8.1. The Government will provide all necessary utilities needed to complete this project.
9.0 MATERIALS:
9.1. All required materials will be provided by the contractor.
10.0 WORK PERFORMANCE:
10.1. Job site shall be cleaned on a daily basis.
10.2. Contractor shall ensure areas outside and adjacent to work area are free of all debris on a daily basis.
10.3. Contractor shall perform all work as described in paragraph 2.0.
11.0 FINAL ACCEPTANCE:
11.1. The contractor shall request a final inspection from the Contracting Officer Representative after all work has been completed, work site and lay-down areas have been cleaned and restored to original condition and all contractor equipment has been removed from the installation. The Contracting Officer Representative will submit a 100% work acceptance letter to the Contracting Officer.
END OF STATEMENT OF WORK