Project Manual Summary
This is a Project Manual for an Interior Remodel Project of a building common area at 936 W. Robb Avenue, Lima, Ohio 45801, prepared for the Allen Metropolitan Housing Authority (AMHA) by MA Design, with Project Manager Rolando Matias overseeing the work. The project involves selective removal of existing common area finishes and installation of new finishes, including work in Division 06 (Interior Architectural Woodwork), Division 07 (Joint Sealants), Division 08 (Hollow Metal Frames, Door Hardware, and Glazing), Division 09 (Acoustical Tile Ceilings, Resilient Tile Flooring, and Painting), and Division 10 (Fire-Protection Specialties). The work sequence requires completion of selective removal prior to installation of new finishes, with the contractor having partial use of the premises during construction, subject to owner approval of storage and access locations. The project manual establishes comprehensive procedural requirements for submittal procedures, quality requirements, product requirements, execution, cutting and patching, closeout procedures, and operation and maintenance data, with specific attention to coordination, scheduling, and compliance with CSI MasterFormat 2020 standards.
The manual specifies submittal requirements including action submittals (product data, shop drawings, and samples) and informational submittals (certificates, test reports, and manufacturer's instructions), with initial review allowing fourteen days for the architect's response and resubmittals requiring the same timeframe. Quality assurance and quality control requirements mandate that the contractor engage qualified testing agencies where services are the contractor's responsibility, with all testing performed at the contractor's cost for work that fails to comply with contract documents. The specifications require experienced installers, manufacturers, and fabricators meeting minimum qualification standards, and mockups must be constructed and approved by the architect prior to starting production work. Final completion procedures include preparation of punch lists, submission of warranties organized by division, final cleaning to commercial building standards, and instruction of owner personnel on operation and maintenance of all products and systems, with the contractor responsible for all costs associated with compliance, repair of defective work, and restoration of the site.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 1.0 - IFB B26005 (Lakeview Plaza Air Handler Replacement).pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
775 Yard Street, Suite 325 phone 614 764 0407 www.designwithma.com Columbus, Ohio 43212 USA fax 614 764 0237
Allen Metropolitan Housing
Authority
Interior Remodel Project for
936 W. Robb Avenue
936 W. Robb Avenue
LIMA, OHIO 45801
Project Manual
13 March 2026
Bid Set
Job Number: 2025.061.04
PROJECT MANUAL
New Renovation of Common Area Project for AMHA – 936 W. Robb Avenue, Lima, Ohio 45801
MA DESIGN
775 YARD STREET, SUITE 325
COLUMBUS, OHIO 43212
(614) 764-0407
(614) 764-0237 - FAX
OWNER
ALLEN METROPOLITAN HOUSING AUTHORITY (AMHA)
600 SOUTH MAIN STREET
LIMA, OHIO 45804
(419) 228-6065
(419) 228-1018 - FAX
INTERIOR REMODEL PROJECT FOR AMHA 03/13/26
936 W. ROBB AVENUE
TABLE OF CONTENTS 000110 - 1
DIVISION 00 – PROCUREMENT AND CONTRACTING REQUIREMENTS
BIDDING FORMS AND ALLEN COUNTY FRONT END BIDDING DOCUMENTS
WAGE RATES
DIVISION 01 - GENERAL REQUIREMENTS
011000 SUMMARY
013300 SUBMITTAL PROCEDURES
014000 QUALITY REQUIREMENTS
016000 PRODUCT REQUIREMENTS
017300 EXECUTION
017329 CUTTING AND PATCHING
017700 CLOSEOUT PROCEDURES
017823 OPERATION AND MAINTENANCE DATA
017839 PROJECT RECORD DOCUMENTS
017900 DEMONSTRATION AND TRAINING
DIVISION 02 - EXISTING CONDITIONS
024119 SELECTIVE REMOVAL
DIVISION 03 - CONCRETE
Not Used
DIVISION 04 - MASONRY
DIVISION 05 - METALS
DIVISION 06 – WOOD PLASTICS AND COMPOSITES
064023 INTERIOR ARCHITECTURAL WOODWORK
DIVISION 07 – THERMAL AND MOISTURE PROTECTION
079200 JOINT SEALANTS
DIVISION 08 - OPENINGS
081113 HOLLOW METAL FRAMES
087100 DOOR HARDWARE
088000 GLAZING
DIVISION 09 - FINISHES
095123 ACOUSTICAL TILE CEILINGS
TABLE OF CONTENTS 000110 - 2
096519 RESILIENT TILE FLOORING
099100 PAINTING
DIVISION 10 – SPECIALTIES
104400 FIRE-PROTECTION SPECIALTIES
DIVISION 11 - 33 Not Used
SUMMARY 011000 - 1
SECTION 011000 - SUMMARY
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes the following:
1. Work covered by the Contract Documents.
2. Work sequence.
3. Use of premises.
4. Specification formats and conventions.
1.2 WORK COVERED BY CONTRACT DOCUMENTS
A. Project Identification: Interior Remodel of a Building Common Area
Project Location: 936 W. Robb Avenue, Lima, Ohio 45801
B. Owner: Allen Metropolitan Housing Authority 600 South Main Street Lima, Ohio 45804
(419) 228-6065, (419) 228-1018 Fax
C. Architect: MA Design 775 Yard Street, Suite 325 Columbus, Ohio 43212
(614) 764-0407, (614) 764-0237 Fax
D. Project Manager: Rolando Matias
(614) 764-0407, (614) 764-0237 Fax
E. The Work consists of the following:
1. The Work includes maintenance projects for the following;
a. Selective removal of Common Area finishes.
b. Installation of new Common Area finishes.
1.3 WORK SEQUENCE
A. Work Sequence: In general, the Work shall be completed in accordance with generally accepted construction practices and sequences in order to ensure effective and efficient completion of the Work. No work is to be started until completion of related or supporting work in the area or until work that is to be covered by subsequent work is completed. General sequencing of the Work shall be as follows:
SUMMARY 011000 - 2
1. Selective removal.
2. New finishes installed.
1.4 USE OF PREMISES
A. General: Contractor shall have partial use of premises for construction operations, including use of Project site, during construction period. Contractor's use of premises is limited only by Owner's right to perform work or to retain other contractors on portions of Project.
1. Storage and Access: Minimize the use of the premises within contract limits for all work and storage. All construction traffic, parking, and storage are restricted to locations approved by the Owner prior to the start of the work. Coordinate use of premises under direction of the Architect.
a. Move any stored products, under contractor's control, that interfere with operations of the Owner or separate contractor.
2. Security: General Contractor shall assume full responsibility for the protection and safekeeping of products under this contract stored on the site. The Owner will not provide security during the Project.
3. Roadway Maintenance: General Contractor shall control and minimize the quantity of dirt, mud and debris deposited on adjacent roadways. Such material shall be removed on a regular basis and at the request of local governing authorities
1.5 SPECIFICATION FORMATS AND CONVENTIONS
A. Specification Format: The Specifications are organized into Divisions and Sections using the 49-division format and CSI/CSC's "MasterFormat 2020" numbering system.
1. Division 01: Sections in Division 01 govern the execution of the Work of all Sections in the Specifications.
B. Specification Content: The Specifications use certain conventions for the style of language and the intended meaning of certain terms, words, and phrases when used in particular situations. These conventions are as follows:
1. Abbreviated Language: Language used in the Specifications and other Contract Documents is abbreviated. Words and meanings shall be interpreted as appropriate. Words implied, but not stated, shall be inferred as the sense requires. Singular words shall be interpreted as plural, and plural words shall be interpreted as singular where applicable as the context of the Contract Documents indicates.
2. Imperative mood and streamlined language are generally used in the Specifications. Requirements expressed in the imperative mood are to be performed by Contractor. Occasionally, the indicative or subjunctive mood may be used in the Section Text for clarity to describe responsibilities that must be fulfilled indirectly by Contractor or by others when so noted.
SUMMARY 011000 - 3
a. The words "shall," "shall be," or "shall comply with," depending on the context, are implied where a colon (:) is used within a sentence or phrase.
b. The intent of the Contract Documents is to include all items necessary for the proper execution and completion of the Work by the Contractor. The Contract Documents are complementary and are intended to be interpreted together, and what is required by one shall be as binding as if required by all; performance by the Contractor shall be required only to the extent consistent with the Contract Documents and reasonably inferable from them as being necessary to produce the indicated results. In the event of inconsistencies within or between parts of the Contract Documents, or between the Contract Documents and applicable standards, codes, and ordinances, the Contractor shall (i) provide the better quality or greater quantity of Work, or (ii) comply with the more stringent requirement; either or both in accordance with the Architect’s interpretation.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 011000
SUBMITTAL PROCEDURES 013300 - 1
SECTION 013300 - SUBMITTAL PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples and other submittals.
B. See Division 01 Section "Construction Progress Documentation" for submitting schedules and reports, including Contractor's Construction Schedule.
C. See Division 01 Section "Quality Requirements" for submitting test and inspection reports and for mockup requirements.
1.2 DEFINITIONS
A. Action Submittals: Written and graphic information that requires Architect's responsive action.
B. Informational Submittals: Written information that does not require Architect's responsive action. Submittals may be rejected for not complying with requirements.
1.3 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination. Begin no work requiring submittal until such time as the submittal has been returned reviewed and/or approved by the Architect.
a. Submit materials in groups containing all associated items (i.e. carpet, tile, base, paint, etc.) to allow installation coordination, and color and finish selections. Partial submittals will not be reviewed until all required items have been received.
b. Architect reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.
3. Maintain an accurate submittal log for the duration of the Work showing current status of all submittals at all times. Submittal log shall be available to the Architect and Owner for their review upon request.
SUBMITTAL PROCEDURES 013300 - 2
B. Submittals Schedule: Comply with requirements in Division 01 Section "Construction Progress Documentation" for list of submittals and time requirements for scheduled performance of related construction activities.
C. Processing Time: Allow enough time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Architect's receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.
1. Initial Review: Allow fourteen (14) days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Architect will advise Contractor when a submittal being processed must be delayed for coordination.
2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.
3. Resubmittal Review: Allow fourteen (14) days for review of each resubmittal.
D. Identification: Place a permanent label or title block on each submittal for identification.
1. Indicate name of firm or entity that prepared each submittal on label or title block.
2. Provide a space approximately 6" x 8" on label or beside title block to record
Contractor's review and approval markings and action taken by Architect.
3. Include the following information on label for processing and recording action taken:
a. Project name.
b. Date.
c. Name and address of Architect.
d. Name and address of Contractor.
e. Name and address of subcontractor.
f. Name and address of supplier.
g. Name of manufacturer.
h. Submittal number or other unique identifier, including revision identifier.
1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 061000.01).
Resubmittals shall include an alphabetic suffix after another decimal point (e.g., 061000.01.A).
i. Number and title of appropriate Specification Section.
j. Drawing number and detail references, as appropriate.
k. Location(s) where product is to be installed, as appropriate.
l. Other necessary identification.
E. Deviations: Highlight, encircle, or otherwise specifically identify deviations from the Contract Documents on submittals.
1. Modify submittals to delete information which is not applicable to the Project.
SUBMITTAL PROCEDURES 013300 - 3
F. Additional Copies: Unless additional copies are required for final submittal, and unless Architect observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.
1. Additional copies submitted for maintenance manuals will not be marked with action taken and will be returned.
G. Transmittals: Package each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. Architect will return submittals, without review, received from sources other than Contractor.
1. Transmittal Form: Use AIA Document G810. A copy of this form is contained within the Project Manual under "Standard Forms".
H. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.
1. Note date and content of previous submittal.
2. Note date and content of revision in label or title block and clearly indicate extent of revision.
3. Resubmit submittals until they are marked "Reviewed" or "Reviewed as Noted" with approval notation from Architect's action stamp.
I. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators and installers, authorities having jurisdiction and others as necessary for performance of construction activities. Show distribution on transmittal forms.
J. Use for Construction: Use only final submittals with mark indicating "Reviewed" or "Reviewed as Noted" with approval notation from Architect's action stamp.
K. Delivery: Deliver submittals to Architect's office, prepaid.
1. Upon review by the Architect, any submittal, sample or mock-up that is not being delivered to the Owner for their use shall be retrieved by the Contractor or supplier within two (2) weeks of Contractor being informed of its availability.
2. If the sample is not picked up within that time period or other arrangements made with the Architect, the sample shall be deemed abandoned and become the property of the Architect for disposal as they see fit.
L. Electronic Submittal: Provide electronic file copy of the original shop drawings (in lieu of paper copies - provided only when necessary) transmitted by email to the following address.
a. File Format: Adobe PDF electronic file, notify the Architect of the intent to send email submissions ahead of sending them.
b. Send Files to: rolandom@designwithma.com
c. Return Files: Will be returned via same email to the address sent by the
Contractor.
SUBMITTAL PROCEDURES 013300 - 4
1.4 CONTRACTOR'S USE OF ARCHITECT'S CAD FILES
A. General: At Contractor's written request, copies of Architect's CAD files will be provided to Contractor for Contractor's use in connection with Project, subject to the following conditions:
1. The contractor shall complete an indemnification form provided by the Architect which will hold the Architect harmless for use of drawings other than to which the architect has direct supervision or control over.
2. A fee is charged for the files provided.
PART 2 - PRODUCTS
2.1 ACTION SUBMITTALS
A. General: Prepare and submit Action Submittals required by individual Specification Sections.
B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.
1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.
2. Mark each copy of each submittal to show which products and options are applicable.
3. Include the following information, as applicable:
a. Manufacturer's written recommendations.
b. Manufacturer's product specifications.
c. Manufacturer's installation instructions.
d. Manufacturer's catalog cuts.
e. Wiring diagrams showing factory-installed wiring.
f. Printed performance curves.
g. Operational range diagrams.
h. Compliance with specified referenced standards.
i. Testing by recognized testing agency.
4. Number of Copies: Submit two (2) copies for Architect's use, plus additional copies required by Contractor for Project Record Documents, material suppliers, installers or other parties. Architect will mark up and retain two (2) copies, and mark up and return additional copies.
C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data, unless submittal of Architect's CAD Drawings is otherwise permitted.
1. Preparation: Fully illustrate requirements in the Contract Documents. Include the following information, as applicable:
SUBMITTAL PROCEDURES 013300 - 5
a. Dimensions.
b. Identification of products.
c. Fabrication and installation drawings.
d. Roughing-in and setting diagrams.
e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.
f. Shopwork manufacturing instructions.
g. Templates and patterns.
h. Schedules.
i. Notation of coordination requirements.
j. Notation of dimensions established by field measurement.
k. Relationship to adjoining construction clearly indicated.
l. Seal and signature of professional engineer if specified.
m. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.
n. Additional information indicated in specific materials Sections.
2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submit Shop Drawings on sheets at least 8½" x 11" but no larger than 30" x 40".
3. Number of Copies: Submit two (2) copies for Architect's use, plus additional copies required by Contractor for Project Record Documents, material suppliers, installers or other parties. Architect will mark up and retain two (2) copies, and mark up and return additional copies.
D. Samples: Submit Samples for review of kind, color, pattern and texture for a check of these characteristics with other elements and for a comparison of these characteristics between submittal and actual component as delivered and installed.
1. Transmit Samples that contain multiple, related components such as accessories together in one submittal package.
2. Identification: Attach label on unexposed side of Samples that includes the following:
a. Generic description of Sample.
b. Product name and name of manufacturer.
c. Sample source.
d. Number and title of appropriate Specification Section.
3. Disposition: Maintain sets of approved Samples at Project site, available for quality-control comparisons throughout the course of construction activity.
Sample sets may be used to determine final acceptance of construction associated with each set.
4. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.
a. Number of Samples: Submit two (2) full sets of available choices where color, pattern, texture or similar characteristics are required to be selected from manufacturer's product line. Architect will return one (1) set of submittals with options selected.
SUBMITTAL PROCEDURES 013300 - 6
5. Samples for Verification: Submit full-size units or Samples of size indicated, prepared from same material to be used for the Work, cured and finished in manner specified, and physically identical with material or product proposed for use, and that show full range of color and texture variations expected. Samples include, but are not limited to, the following: Partial sections of manufactured or fabricated components; small cuts or containers of materials; complete units of repetitively used materials; swatches showing color, texture, and pattern; color range sets; and components used for independent testing and inspection.
a. Number of Samples: Submit two (2) sets of Samples. Architect will retain one (1) Sample set; remainder will be returned.
E. Product Schedule or List: As required in individual Specification Sections, prepare a written summary indicating types of products required for the Work and their intended location.
1. Number of Copies: Submit two (2) copies for Architect's use, plus additional copies required by Contractor for Project Record Documents, material suppliers, installers or other parties. Architect will mark up and retain two (2) copies, and mark up and return additional copies.
F. Submittals Schedule: Comply with requirements specified in Division 01 Section "Construction Progress Documentation."
G. Application for Payment: Comply with requirements specified in Division 01 Section "Payment Procedures."
H. Schedule of Values: Comply with requirements specified in Division 01 Section "Payment Procedures."
I. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design.
1. Number of Copies: Submit three (3) copies of subcontractor list, unless otherwise indicated. Architect will return two (2) copies.
2.2 INFORMATIONAL SUBMITTALS
A. General: Prepare and submit Informational Submittals required by other Specification Sections.
1. Number of Copies: Submit two (2) copies of each submittal, unless otherwise indicated. Architect will not return copies.
2. Certificates and Certifications: Provide a notarized statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.
3. Test and Inspection Reports: Comply with requirements specified in Division 01 Section "Quality Requirements."
SUBMITTAL PROCEDURES 013300 - 7
B. Coordination Drawings: Comply with requirements specified in Division 01 Section "Project Management and Coordination."
C. Contractor's Construction Schedule: Comply with requirements specified in Division 01 Section "Construction Progress Documentation."
D. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, names and addresses of architects and owners, and other information specified.
E. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification (WPS) and Procedure Qualification Record (PQR) on AWS forms. Include names of firms and personnel certified.
F. Installer Certificates: Prepare written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.
G. Manufacturer Certificates: Prepare written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents.
Include evidence of manufacturing experience where required.
H. Product Certificates: Prepare written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.
I. Material Certificates: Prepare written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.
J. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.
K. Product Test Reports: Prepare written reports indicating current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.
L. Research/Evaluation Reports: Prepare written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project.
M. Preconstruction Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.
N. Compatibility Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests
SUBMITTAL PROCEDURES 013300 - 8
performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.
O. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.
P. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment. Comply with requirements specified in Division 01 Section "Operation and Maintenance Data."
Q. Design Data: Prepare written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions and other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.
R. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address and telephone number of manufacturer.
S. Manufacturer's Field Reports: Prepare written information documenting factory-authorized service representative's tests and inspections. Include the following, as applicable:
1. Statement on condition of substrates and their acceptability for installation of product.
2. Summary of installation procedures being followed, whether they comply with requirements and, if not, what corrective action was taken.
3. Results of operational and other tests and a statement of whether observed performance complies with requirements.
T. Insurance Certificates and Bonds: Prepare written information indicating current status of insurance or bonding coverage. Include name of entity covered by insurance or bond, limits of coverage, amounts of deductibles, if any, and term of the coverage.
U. Material Safety Data Sheets (MSDSs): Submit information directly to Owner; do not submit to Architect. Architect will not review submittals that include MSDSs and will return them for resubmittal.
2.3 DELEGATED DESIGN
A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.
SUBMITTAL PROCEDURES 013300 - 9
1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Architect.
B. Delegated-Design Submittal: In addition to Shop Drawings, Product Data, and other required submittals, submit three (3) copies of a statement, signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.
1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services.
PART 3 - EXECUTION
3.1 CONTRACTOR'S REVIEW
A. Contractor's Review: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Architect.
B. Notify Architect, in writing, at the time of submission, of deviations in submittals from the requirements of the Contract Documents.
C. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval and statement certifying that submittal has been reviewed, checked and approved for compliance with the Contract Documents.
1. By affixing the Contractor’s stamp of approval and signature to each submittal, the Contractor certifies that the submission is in compliance with the requirements of the Contract Documents and the General Conditions Subparagraph 3.12.6. Submittals without the Contractors stamp and signature will not be considered and will be returned immediately for resubmittal.
D. Contractor's responsibility for errors or omissions in the submittal is not relieved by the Architects review of the submittals.
3.2 ARCHITECT'S ACTION
A. General: Architect will not review submittals without the Contractor's stamp and signature, and will return them immediately for resubmittal without action.
B. Action Submittals: Architect will review each submittal, make marks to indicate corrections or modifications required, and return it. Architect will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken, as follows:
SUBMITTAL PROCEDURES 013300 - 10
1. Action Submittals: Architect will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken, as follows:
a. Reviewed.
b. Resubmit.
c. Reviewed as Noted.
2. Informational Submittals: Architect will review each submittal and will not return it, or will reject and return it if it does not comply with requirements. Architect will forward each submittal to appropriate party.
3. Submittals not required by the Contract Documents will not be reviewed and may be discarded.
C. Informational Submittals: Architect will review each submittal and will not return it, or will return it if it does not comply with requirements. Architect will forward each submittal to appropriate party.
D. Partial submittals are not acceptable, will be considered nonresponsive, and will be returned without review.
E. Submittals not required by the Contract Documents may not be reviewed and may be discarded.
END OF SECTION 013300
QUALITY REQUIREMENTS 014000 - 1
SECTION 014000 - QUALITY REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for quality assurance and quality control, and the following:
1. Contractor provided testing.
2. Manufacturer's field services.
3. Mockups
B. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with the Contract Document requirements.
1. Specified tests, inspections, and related actions do not limit Contractor's other quality-assurance and -control procedures that facilitate compliance with the Contract Document requirements.
2. Requirements for Contractor to provide quality-assurance and -control services required by Architect, Owner, or authorities having jurisdiction are not limited by provisions of this Section.
3. See remainder of specification Sections for specific test and inspection requirements.
C. See Division 01 Section "Code-Required Special Inspections and Procedures" for third party testing and inspection services provided by the Owner.
1.2 DEFINITIONS
A. Experienced: When used with an entity, "experienced" means having successfully completed a minimum of five (5) previous projects similar in size and scope to this Project; being familiar with special requirements indicated; and having complied with requirements of authorities having jurisdiction.
B. Field Quality-Control Testing: Tests and inspections that are performed on-site for installation of the Work and for completed Work.
C. Installer/Applicator/Erector: Contractor or another entity engaged by Contractor as an employee, Subcontractor, or Sub-subcontractor, to perform a particular construction operation, including installation, erection, application and similar operations.
1. Using a term such as "carpentry" does not imply that certain construction activities must be performed by accredited or unionized individuals of a corresponding generic name, such as "carpenter." It also does not imply that requirements specified apply exclusively to tradespeople of the corresponding generic name.
QUALITY REQUIREMENTS 014000 - 2
D. Laboratory Mockups: Full-size, physical assemblies that are constructed at testing facility to verify performance characteristics.
E. Mockups: Full-size, physical assemblies that are constructed on-site. Mockups are used to verify selections made under sample submittals, to demonstrate aesthetic effects and, where indicated, qualities of materials and execution, and to review construction, coordination, testing, or operation; they are not Samples. Approved mockups establish the standard by which the Work will be judged.
F. Preconstruction Testing: Tests and inspections that are performed specifically for the Project before products and materials are incorporated into the Work to verify performance or compliance with specified criteria.
G. Product Testing: Tests and inspections that are performed by an NRTL, an NVLAP, or a testing agency qualified to conduct product testing and acceptable to authorities having jurisdiction, to establish product performance and compliance with industry standards.
H. Quality-Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and substantiate that proposed construction will comply with requirements.
I. Quality-Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that actual products incorporated into the Work and completed construction comply with requirements. Services do not include contract enforcement activities performed by Architect.
J. Source Quality-Control Testing: Tests and inspections that are performed at the source, i.e., plant, mill, factory or shop.
K. Testing Agency: An entity engaged to perform specific tests, inspections, or both.
Testing laboratory shall mean the same as testing agency.
L. Third Party Testing and Inspection Agency: An established and recognized agency regularly engaged in conducting tests and/or furnishing inspection services, when such agency has been approved in accordance with the rules of the Ohio Board of Housing, Buildings and Construction, and hired by the Owner.
1.3 CONFLICTING REQUIREMENTS
A. General: If compliance with two or more standards is specified and the standards establish different or conflicting requirements for minimum quantities or quality levels, comply with the most stringent requirement. Refer uncertainties and requirements that are different, but apparently equal, to Architect for a decision before proceeding.
B. Minimum Quantity or Quality Levels: The quantity or quality level shown or specified shall be the minimum provided or performed. The actual installation may comply exactly with the minimum quantity or quality specified, or it may exceed the minimum within reasonable limits. To comply with these requirements, indicated numeric values
QUALITY REQUIREMENTS 014000 - 3
are minimum or maximum, as appropriate, for the context of requirements. Refer uncertainties to Architect for a decision before proceeding.
1.4 SUBMITTALS
A. Qualification Data: For testing agencies specified in "Quality Assurance" Article to demonstrate their capabilities and experience. Include proof of qualifications in the form of a recent report on the inspection of the testing agency by a recognized authority.
B. Reports: Prepare and submit certified written reports that include the following:
1. Date of issue.
2. Project title and number.
3. Name, address, and telephone number of testing agency.
4. Dates and locations of samples and tests or inspections.
5. Names of individuals making tests and inspections.
6. Description of the Work and test and inspection method.
7. Identification of product and Specification Section.
8. Complete test or inspection data.
9. Test and inspection results and an interpretation of test results.
10. Record of temperature and weather conditions at time of sample taking and testing and inspecting.
11. Comments or professional opinion on whether tested or inspected Work complies with the Contract Document requirements.
12. Name and signature of laboratory inspector.
13. Recommendations on retesting and reinspecting.
C. Permits, Licenses, and Certificates: For Owner's records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations bearing on performance of the Work.
1.5 QUALITY ASSURANCE
A. General: Qualifications paragraphs in this Article establish the minimum qualification levels required; individual Specification Sections specify additional requirements.
B. Installer Qualifications: A firm or individual experienced in installing, erecting, or assembling work similar in material, design, and extent to that indicated for this Project, whose work has resulted in construction with a record of successful in-service performance.
C. Manufacturer Qualifications: A firm experienced in manufacturing products or systems similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
QUALITY REQUIREMENTS 014000 - 4
D. Fabricator Qualifications: A firm experienced in producing products similar to those indicated for this Project and with a record of successful in-service performance, as well as sufficient production capacity to produce required units.
E. Professional Engineer Qualifications: A professional engineer who is legally qualified to practice in jurisdiction where Project is located and who is experienced in providing engineering services of the kind indicated. Engineering services are defined as those performed for installations of the system, assembly, or products that are similar to those indicated for this Project in material, design and extent.
F. Specialists: Certain sections of the Specifications require that specific construction activities shall be performed by entities who are recognized experts in those operations. Specialists shall satisfy qualification requirements indicated and shall be engaged for the activities indicated.
1. Requirement for specialists shall not supersede building codes and regulations governing the Work.
G. Testing Agency Qualifications: An NRTL, an NVLAP, or an independent agency with the experience and capability to conduct testing and inspecting indicated, as documented according to ASTM E 548; and with additional qualifications specified in individual Sections; and where required by authorities having jurisdiction, that is acceptable to authorities.
1. NRTL: A nationally recognized testing laboratory according to 29 CFR 1910.7.
2. NVLAP: A testing agency accredited according to NIST's National Voluntary
Laboratory Accreditation Program.
H. Factory-Authorized Service Representative Qualifications: An authorized representative of manufacturer who is trained and approved by manufacturer to inspect installation of manufacturer's products that are similar in material, design, and extent to those indicated for this Project.
I. Mockups: Before installing portions of the Work requiring mockups, build mockups for each form of construction and finish required to comply with the following requirements, using materials indicated for the completed Work:
1. Build mockups in location and of size indicated or, if not indicated, as directed by Architect.
2. Notify Architect seven (7) days in advance of dates and times when mockups will be constructed.
3. Demonstrate the proposed range of aesthetic effects and workmanship.
4. Obtain Architect's approval of mockups before starting work, fabrication, or construction.
5. Maintain mockups during construction in an undisturbed condition as a standard for judging the completed Work.
6. Demolish and remove mockups when directed, unless otherwise indicated.
J. Laboratory Mockups: Comply with requirements of preconstruction testing and those specified in individual specification Sections.
QUALITY REQUIREMENTS 014000 - 5
1.6 QUALITY CONTROL
A. Owner Responsibilities: Where quality-control services are indicated as Owner's responsibility, Owner will engage a qualified testing agency to perform these services.
1. Owner will furnish Contractor with names, addresses, and telephone numbers of testing agencies engaged and a description of types of testing and inspecting they are engaged to perform.
2. Costs for retesting and reinspecting construction that replaces or is necessitated by work that failed to comply with the Contract Documents will be charged to Contractor, and the Contract Sum will be adjusted by Change Order.
B. Tests and inspections not explicitly assigned to Owner are Contractor's responsibility.
Unless otherwise indicated, provide quality-control services specified and those required by authorities having jurisdiction. Perform quality-control services required of Contractor by authorities having jurisdiction, whether specified or not.
1. Where services are indicated as Contractor's responsibility, engage a qualified testing agency to perform these quality-control services.
a. Contractor shall not employ same entity engaged by Owner, unless agreed to in writing by Owner.
2. Notify testing agencies at least twenty-four (24) hours in advance of time when Work that requires testing or inspecting will be performed.
3. Where quality-control services are indicated as Contractor's responsibility, submit a certified written report, in duplicate, of each quality-control service.
4. Provide protected storage areas for test specimens.
5. Testing and inspecting requested by Contractor and not required by the Contract
Documents are Contractor's responsibility.
6. Submit additional copies of each written report directly to authorities having jurisdiction, when they so direct.
C. Manufacturer's Field Services: Where indicated, engage a factory-authorized service representative to inspect field-assembled components and equipment installation, including service connections. Report results in writing as specified in Division 01 Section "Submittal Procedures."
D. Retesting/Reinspecting: Regardless of whether original tests or inspections were Contractor's responsibility, provide quality-control services, including retesting and reinspecting, for construction that replaced Work that failed to comply with the Contract Documents.
E. Testing Agency Responsibilities: Cooperate with Architect and Contractor in performance of duties. Provide qualified personnel to perform required tests and inspections.
1. Notify Architect and Contractor promptly of irregularities or deficiencies observed in the Work during performance of its services.
2. Determine the location from which test samples will be taken and in which in-situ tests are conducted.
QUALITY REQUIREMENTS 014000 - 6
3. Conduct and interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from requirements.
4. Submit a certified written report, in duplicate, of each test, inspection, and similar quality-control service through Contractor.
5. Do not release, revoke, alter or increase the Contract Document requirements or approve or accept any portion of the Work.
6. Do not perform any duties of Contractor.
F. Associated Services: Cooperate with agencies performing required tests, inspections, and similar quality-control services, and provide reasonable auxiliary services as requested. Notify agency sufficiently in advance of operations to permit assignment of personnel. Provide the following:
1. Access to the Work.
2. Incidental labor and facilities necessary to facilitate tests and inspections.
3. Adequate quantities of representative samples of materials that require testing and inspecting. Assist agency in obtaining samples.
4. Facilities for storage and field curing of test samples.
5. Delivery of samples to testing agencies.
6. Preliminary design mix proposed for use for material mixes that require control by testing agency.
7. Security and protection for samples and for testing and inspecting equipment at
Project site.
G. Coordination: Coordinate sequence of activities to accommodate required quality-assurance and -control services with a minimum of delay and to avoid necessity of removing and replacing construction to accommodate testing and inspecting.
1. Schedule times for tests, inspections, obtaining samples, and similar activities.
1.7 SPECIAL TESTS AND INSPECTIONS
A. Special Tests and Inspections: Owner will engage a qualified testing agency to conduct special tests and inspections required by authorities having jurisdiction as specifically noted in Division 01 Section "Code-Required Special Inspections and Procedures".
B. All other tests and inspections required by authorities having jurisdiction are the responsibility of the Contractor.
C. Contractor to coordinate and schedule the Owner’s testing and inspection agency’s work. Provide minimum three (3) days notice prior to required testing and inspection work.
QUALITY REQUIREMENTS 014000 - 7
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 REPAIR AND PROTECTION
A. General: On completion of testing, inspecting, sample taking, and similar services, repair damaged construction and restore substrates and finishes.
1. Provide materials and comply with installation requirements specified in other Specification Sections. Restore patched areas and extend restoration into adjoining areas with durable seams that are as invisible as possible.
B. Protect construction exposed by or for quality-control service activities.
C. Repair and protection are Contractor's responsibility, regardless of the assignment of responsibility for quality-control services.
END OF SECTION 014000
PRODUCT REQUIREMENTS 016000 - 1
SECTION 016000 - PRODUCT REQUIREMENTS
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements for selection of products for use in Project; product delivery, storage, and handling; manufacturers' standard warranties on products; special warranties; product substitutions; and comparable products.
B. See Division 01 Section "Closeout Procedures" for submitting warranties for Contract closeout.
C. See Division 02 through 49 Sections for specific requirements for warranties on products and installations specified to be warranted.
1.2 DEFINITIONS
A. Products: Items purchased for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system" and terms of similar intent.
1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation shown or listed in manufacturer's published product literature, that is current as of date of the Contract Documents.
2. New Products: Items that have not previously been incorporated into another project or facility. Products salvaged or recycled from other projects are not considered new products.
3. Comparable Product: Product that is demonstrated and approved through submittal process, or where indicated as a product substitution, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.
B. Substitutions: Changes in products, materials, equipment and methods of construction from those required by the Contract Documents and proposed by Contractor.
C. Voluntary Substitutions: Changes in products, materials, equipment and methods of construction from those required or listed in the Contract Documents that use alternative materials and/or methods of construction required by the Contract Documents and proposed by Contractor during the Bidding period. Voluntary substitutions are listed on the Bid Forms. Such substitutions may not be used to prepare bid or alternate amounts and do not require the Architect's review or pre-approval. The Owner reserves the right to accept or reject any such substitute proposed.
PRODUCT REQUIREMENTS 016000 - 2
D. Basis-of-Design Product Specification: Where a specific manufacturer's product is named and accompanied by the words "basis of design," including make or model number or other designation, to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics for purposes of evaluating comparable products of other named manufacturers.
1.3 SUBMITTALS
A. Substitution Requests: Submit three copies of each request for consideration. Identify product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Substitution Request Form: Use form provided by Owner.
2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
a. Statement indicating why specified material or product cannot be provided.
b. Coordination information, including a list of changes or modifications needed to other parts of the Work and to construction performed by Owner and separate contractors, that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities of proposed substitution with those of the Work specified. Significant qualities may include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated.
d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. List of similar installations for completed projects with project names and addresses and names and addresses of architects and owners.
g. Material test reports from a qualified testing agency indicating and interpreting test results for compliance with requirements indicated.
h. Research/evaluation reports evidencing compliance with building code in effect for Project, from a model code organization acceptable to authorities having jurisdiction.
i. Detailed comparison of Contractor's Construction Schedule using proposed substitution with products specified for the Work, including effect on the overall Contract Time.