Summary of CVPA & CSMB North Vestibule Entrance Project Scope of Work
This Scope of Work document is prepared by St. Louis Public Schools in partnership with Navigate Building Solutions, LLC (Owner Representative), with architectural services provided by Cordogan Clark Architects, for the renovation and addition of secure entries at the Central VPA and Collegiate High Schools North Vestibule Entrance Project. The project scope encompasses all work outlined in the project documents including structural steel framing, masonry, cast-in-place concrete, metal fabrications, thermal insulation, waterproofing, and interior finishes for a new North Vestibule entrance system. The pre-bid meeting is scheduled for March 26, 2026, at 2 PM at 3416 Cook Ave, with substantial completion targeted for August 31, 2027, and final completion by September 30, 2027. The General Works Contractor is responsible for all labor, materials, equipment, supervision, coordination, and site logistics including temporary facilities, utilities, safety compliance, waste management, and erosion control. The contractor must maintain a full-time on-site superintendent, participate in bi-weekly coordination meetings, provide detailed schedules and submittals, and comply with all OSHA standards and local building codes.
The project includes provisions for liquidated damages should the contractor fall behind schedule by more than five work days, with recovery schedules required within five days of notification. Payment and performance bonds equal to 100 percent of the bid amount are due within ten days of contract execution. The contractor must include a $500,000 allowance for unforeseen conditions within the base bid, maintain prevailing wage rates per Missouri Division of Labor Standards, and provide background checks for all on-site personnel including FBI fingerprint clearance. All exposed steel in exterior wall assemblies and elements must be galvanized or receive an equivalent protective finish. The project specifications incorporate comprehensive standards from the American Institute of Architects (AIA), American Concrete Institute (ACI), Steel Joist Institute (SJI), and other industry standards organizations to ensure quality construction and structural performance throughout all building systems and assemblies.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
St. Louis Public Schools CVPA & CSMB North Vestibule Entrance Project
Scope of Work
The Owner Representative (OR) referred to below is Navigate Building Solutions, LLC. The Owner referred to below is the St. Louis Public Schools. The Contractor referred to below is the General Works Contractor. This bid package includes, but is not limited to, the following:
All work outlined by the project documents (plans and specifications) issued by Cordogan Clark Architects.
1. Contractor is to provide bid package scope of CVPA & CSMB North Vestibule Entrance as identified in the project documents.
2. Contractor is aware of the potential for Liquidated Damages. Contractor shall be responsible for maintaining scheduled items for the Contractor’s work as included in the project master schedule below. Contractor shall reference AIA 101 and AIA 201 contract drafts provided in the bid documents, Contractor agrees to pay the Owner, or to deduct from the Contract Sum, not as a penalty, but as liquidated damages, the amounts listed in the contract drafts provided.
3. The draft AIA 101 and AIA 201 have been modified from their original versions. Contractor shall read and understands these are draft documents to the final contract.
4. Contractor shall provide a payment bond and performance bond in the amount of one hundred (100%) percent of the bid amount within (10) days of executed contract agreement.
5. Upon execution of this contract, this contractor must submit to the OR a detailed critical path baseline construction schedule outlining each construction activity and phase. This schedule must fall within the master project schedule outlined below and be submitted no later than twenty-one
(21) days following execution of the contract. Contractor is required to provide updated work schedules on a weekly basis. Contractor’s detailed activity schedule/critical path schedule shall adhere to the master project schedule. Should the Contractor fall behind schedule by more than 5 work days due to the fault of this Contractor, the Contractor shall provide a recovery schedule to the Owner Representative within 5 days of request by the Owner Representative.
Project Master Schedule/Milestone Dates:
a. Pre-Bid Meeting (3416 Cook Ave) March 26, 2026 @ 2PM
North Vestibule Substantial Completion / Punchlist Populated August 31, 2027
b. North Vest. Completion of Punchlist/Final Completion September 30, 2027
Provide all supervision, labor, tools, equipment and materials to complete the work.
6. Perform all freight, unloading, loading, distribution and hoisting of materials.
7. Furnish, install, maintain and remove temporary on-site trailers and storage containers as required to perform the work.
8. Perform all work in accordance with OSHA standards and the Additional Project Safety Requirements issued in the specifications (including OSHA 10-hour requirement).
9. Coordinate all work with the Owner Representative.
10. Review all drawings and specifications and accept responsibility for requirements, general notes, notes, specifications, and details as they relate to this scope of work.
11. This contractor shall provide all layout required to complete the work included in this Contractor’s scope of work.
12. Contractor responsible for temporary road/lane closures and associated permits.
13. Provide street cleaning to remove dirt, mud, and debris generated by the project site as needed to maintain a clean surface along all roads. This includes the school parking lot as well.
14. Provide adequate dust control during construction work, including misting as needed.
15. This Contractor shall furnish all dumpsters for the project and shall include the cost to haul offsite and legally dispose of all construction rubbish and debris. Cleanup all rubbish and debris from the site and building daily.
16. Bi-weekly meetings at the jobsite will be held with the Owner Representative, this contractor’s Project Manager, and Superintendent to coordinate the installation of all systems. The work of this contractor must be performed in accordance with the decisions and schedules formulated at these meetings so as not to delay the work. The Contractor’s Project Manager and Foreman/Supervision must be present at these meetings.
17. The contractor will provide ice, cups, and distribute drinking water for the jobsite.
18. Provide temporary protection, labor, and material.
19. Contractor to furnish first aid and safety supplies as needed. Contractor is solely responsible for site/project safety.
20. Contractor to maintain proper SDS sheets for all materials utilized by this Contractor (and its subcontractors) in a central location on site per OSHA standards. Site Specific Safety Plan shall be completed and kept on site at all times.
21. Contractor will provide temporary construction toilets for the project.
22. Immediately upon award this contractor shall submit a proposed site logistics plan for review. The Owner, OR, Contractor, and/or Architect will meet to review and discuss site logistics and finalize an agreed upon plan of action for construction parking, office/storage containers, temporary toilets, temporary site fence, etc.
23. Contractor responsible for any coordination of staging or relocation for materials after initial unloading.
24. Contractor to coordinate all deliveries of materials with Owner Representative’s personnel.
25. Include ALL caulking and sealants for all systems and materials furnished and installed.
26. No tobacco use is allowed on the project including chewing tobacco, e-cigarettes or smokeless cigarettes.
27. Full-time onsite superintendent is required when any of this Contractor’s labor or this Contractor’s subcontractors labor is onsite.
28. This contractor shall produce a submittal log at the beginning of the project that is populated with all of the required submittals for the project and assign due dates for submission to the OR and/or the Architect and due dates for return from the OR and/or Architect. This log must be submitted to the OR and/or Architect for review on a weekly basis.
29. This contractor shall maintain a RFI log for the project indicating the following. This log must be submitted to the OR and/or Architect for review on a weekly basis.
a. Topic of RFI
b. Date submitted
c. Date requested response by
d. Date returned
e. Status- Open or Closed
30. The contractor is responsible for taking before-and-after photos for all locations. Photos are to be labeled and shared with the Owners representative for district use.
31. This contractor will be responsible for submitting daily logs containing the number of workers, equipment, work accomplished, daily weather, deliveries, at least 5 photos, visitors to the site, any inspections passed or failed, problems encountered, and other relevant data as may be required.
32. This contractor must populate a closeout log and submit it to the OR and/or Architect for review to verify that all required items have been populated. Once approved, this log will be used to track required closeout items prior to final payment. This contractor is highly encouraged to submit O&M requirements as soon as possible in advance of final acceptance to help eliminate delay in payment.
33. This Contractor shall be responsible for the cost of temporary utilities during the course of construction i.e. but not limited to: gas, electric, sewer, and water. If there is only single-phase electric available from the local electric utility for temporary electric, any other needs will require the use of a temporary generator at the contractor’s cost.
34. This contractor will compile for the Owner a ‘record set’ of all documents and drawings for the project at substantial completion. This shall be ‘red-lined’ copies of all project changes throughout the course of the project to identify all systems as they were actually installed on the project for the Owner’s records. These must be electronically recorded and submitted to the Owner in pdf format on a ‘thumb drive’.
35. Contractor is required to hold their alternate pricing that was included in the bid form for 3 months after the bid date. Contractor will notify Owner Representative when decisions need to be made regarding the acceptance of bid alternates in order to maintain deliveries, installation, and the master project schedule.
36. No change orders will be issued for material cost increases or impacts of tariffs that occur during the project.
37. Construction work during the school year will be allowed from 6am – 6pm (Monday – Friday), as long as it does not disrupt scholar learning and/or activities. Work that causes these disruptions must be done on 2nd shift and/or off shift hours that have been coordinated with the District.
38. During the warranty period of the project, this Contractor shall document, maintain and update a Warranty Log of all warranty items, weekly, to be shared with the Client and Owner Representative.
39. Contractor is required to maintain access to the work as needed to maintain schedule. Schedule delays will not be accepted for wet/poor site conditions after weather events.
40. Contractor shall not park on the school parking lots unless previously approved by St. Louis Public Schools.
41. Contractor shall have personnel watching and/or working within a 10ft visual of any exterior door that needs to be open during construction.
42. Contractor shall ensure the buildings are secured at the end of each day.
43. Contractor shall coordinate the removal and turnover of all St. Louis Public Schools equipment including but not limited to security door contacts, doors, door hardware, cameras, etc.
44. Materials to be salvaged to be coordinated with St. Louis Public Schools before removal.
45. Background checks for workers including office staff that visit site regularly will be required. Vendor delivery drivers will not be required to have background checks. List of employees who have passed the background check for prime Contractors and their subcontractors to be provided to OR before starting work. Background checks to consist of Name Search available from Missouri State Highway Patrol. Search can be requested and paid for by using the following website:
www.machs.mo.gov. Results provided to OR of background checks will only consist of a list of workers that passed. In addition, FBI background checks with finger printing are required and consist of Name Search available from MACHS website. Search can be requested and paid for by using the following website: https://www.fbi.gov/how-we-can-help-you/more-fbi-services-and-information/identity-history-summary-checks. Workers with felony convictions for violent crimes or who are on the sex offender list will be deemed to have not passed the background check and are not allowed on the construction site.
46. Contractor shall include allowance for demo / haul-off / repair back to existing conditions in their proposal for each bid package. The value shall be included within the Base Bid of each bid package as outlined on the Bid Form.
47. Contractor shall furnish and install all supplementary materials required to perform and complete installation of the CVPA & CSMB North Vestibule Entrance Project.
48. Contractor shall include any and all work associated with CVPA & CSMB North Vestibule Entrance Project. Quantities shall be field verified during pre-bid meeting prior to submission of bid.
49. Contractor must include prevailing wage rates as required by law. All wages paid for work performed on site must comply with the Missouri Division of Labor Standards Annual Wage Order Number 32 for City of Saint Louis, Missouri.
50. Contractor shall include allowance for unforeseen conditions in the amount of $500,000.00 in their proposal. The value shall be included within the Base Bid of each bid package as outlined on the Bid Form.
CVPA + CSMB HIGH SCHOOL ADDITIONS / RENOVATIONS #264001
ALLOWANCES 012100 � 1
SECTION 012100 � ALLOWANCES
PART 1 - GENERAL
1.1 SUMMARY
A. This Section includes administrative and procedural requirements governing the following:
1. Contingency allowances
2. Allowances have been established in lieu of additional requirements and to defer selection of actual materials and equipment to a later date when direction will be provided to Contractor.
If necessary, additional requirements will be issued by Change Order.
1.2 SELECTION AND PURCHASE
A. At the earliest practical date after award of the Contract, coordinate with Owner the date when final selection and purchase of each product or system described by an allowance will be completed to avoid delaying the Work.
B. At Architect's request, obtain proposals for each allowance for use in making final selections.
Include recommendations that are relevant to performing the Work.
C. Purchase products and systems required to install Owner provided items from the designated supplier.
1.3 SUBMITTALS
A. Submit proposals for purchase of products or systems included in allowances, in the form specified for Change Orders.
B. Submit invoices or delivery slips to show actual quantities of materials delivered to the site for use in fulfillment of each allowance.
C. Submit time sheets and other documentation to show labor time and cost for installation of allowance items that include installation as part of the allowance.
D. Coordinate and process submittals for allowance items in same manner as for other portions of the Work.
1.4 COORDINATION
A. Coordinate allowance items with other portions of the Work. Furnish templates as required to coordinate installation.
ALLOWANCES 012100 � 2
1.5 CONTINGENCY ALLOWANCES
A. Use the allowance only as directed by Architect for Owner�s purposes IN WRITING.
B. Contractor's overhead, profit, and related costs for products and equipment ordered by Owner under the contingency allowance are included in the allowance and are not part of the Contract Sum. These costs include delivery, installation, taxes, insurance, equipment rental, and similar costs.
C. At Project closeout, credit unused amounts remaining in the contingency allowance to Owner by Change Order.
1.6 ADJUSTMENT OF ALLOWANCES
A. Allowance Adjustment: To adjust allowance amounts, prepare a Change Order proposal based on the difference between purchase amount and the allowance, multiplied by final measurement of work-in-place where applicable.
1. Include installation costs in purchase amount only where indicated as part of the allowance.
2. If requested, prepare explanation and documentation to substantiate distribution of overhead costs and other margins claimed.
B. Submit claims for increased costs because of a change in scope or nature of the allowance described in the Contract Documents, whether for the purchase order amount or Contractor's handling, labor, installation, overhead, and profit.
1. Do not include Contractor's or subcontractor's indirect expense in the Change Order cost amount unless it is clearly shown that the nature or extent of work has changed from what could have been foreseen from information in the Contract Documents.
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 EXAMINATION
A. Examine products covered by an allowance promptly on delivery for damage or defects. Return damaged or defective products to manufacturer for replacement.
3.2 PREPARATION
A. Coordinate materials and their installation for each allowance with related materials and installations to ensure that each allowance item is completely integrated and interfaced with related work.
3.3 SCHEDULE OF ALLOWANCES
A. Allowance 1 � Contingency Allowance:
ALLOWANCES 012100 � 3
1. Allowance includes material cost, installation cost, delivery, insurance, overhead and profit.
END OF SECTION 012100
012200 UNIT PRICES 012200 - 1
SECTION 012200 UNIT PRICES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for unit prices.
B. Related Requirements:
1. Division 01 Section "Contract Modification Procedures" for procedures for submitting and handling Change Orders.
2. Division 01 Section "Quality Requirements" for general testing and inspecting requirements.
1.3 DEFINITIONS
A. Unit price is an amount incorporated in the Agreement, applicable during the duration of the Work as a price per unit of measurement for materials, equipment, or services, or a portion of the Work, added to or deducted from the Contract Sum by appropriate modification, if the scope of Work or estimated quantities of Work required by the Contract Documents are increased or decreased.
1.4 PROCEDURES
A. Unit prices include all necessary material, plus cost for delivery, installation, insurance, applicable taxes, overhead, and profit.
B. Measurement and Payment: See individual Specification Sections for work that requires establishment of unit prices. Methods of measurement and payment for unit prices are specified in those Sections.
C. Owner reserves the right to reject Contractor's measurement of work-in-place that involves use of established unit prices and to have this work measured, at Owner's expense, by an independent surveyor acceptable to Contractor.
D. List of Unit Prices: A schedule of unit prices is included in Part 3. Specification Sections referenced in the schedule contain requirements for materials described under each unit price.
012200 UNIT PRICES 012200 - 2
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION
3.1 SCHEDULE OF UNIT PRICES
A. Unit Price 1: Add/Remove Electrical Receptical
1. Description: Add or remove an electrical Receptical
2. Unit of Measurement: One Receptical
END OF SECTION 012200
SUBSTITUTION PROCEDURES 012500 - 1
SECTION 012500 - SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for substitutions.
B. Related Requirements:
1. Document 002600 "Procurement Substitution Procedures" for requirements for substitution requests prior to award of Contract.
2. Section 016000 "Product Requirements" for requirements for submitting comparable product submittals for products by listed manufacturers.
1.3 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.
2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required to meet other Project requirements but may offer advantage to Contractor or Owner.
1.4 ACTION SUBMITTALS
A. Substitution Requests: Submit documentation identifying product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Substitution Request Form: Use form acceptable to Architect.
2. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
a. Statement indicating why specified product or fabrication or installation method cannot be provided, if applicable.
b. Coordination of information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution.
c. Detailed comparison of significant qualities of proposed substitutions with those of the Work specified. Include annotated copy of applicable Specification Section.
SUBSTITUTION PROCEDURES 012500 - 2
Significant qualities may include attributes, such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.
d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested.
g. List of similar installations for completed projects, with project names and addresses as well as names and addresses of architects and owners.
h. Material test reports from a qualified testing agency, indicating and interpreting test results for compliance with requirements indicated.
i. Research reports evidencing compliance with building code in effect for Project, from ICC-ES.
j. Detailed comparison of Contractor's construction schedule using proposed substitutions with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
k. Cost information, including a proposal of change, if any, in the Contract Sum.
l. Contractor's certification that proposed substitution complies with requirements in the Contract Documents, except as indicated in substitution request, is compatible with related materials and is appropriate for applications indicated.
m. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
3. Architect's Action: If necessary, Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution.
Architect will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later.
a. Forms of Acceptance: Change Order, Construction Change Directive, or Architect's Supplemental Instructions for minor changes in the Work.
b. Use product specified if Architect does not issue a decision on use of a proposed substitution within time allocated.
1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
1.6 PROCEDURES
A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.
SUBSTITUTION PROCEDURES 012500 - 3
1.7 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Contract Documents and will produce indicated results.
b. Substitution request is fully documented and properly submitted.
c. Requested substitution will not adversely affect Contractor's construction schedule.
d. Requested substitution has received necessary approvals of authorities having jurisdiction.
e. Requested substitution is compatible with other portions of the Work.
f. Requested substitution has been coordinated with other portions of the Work.
g. Requested substitution provides specified warranty.
h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
B. Substitutions for Convenience: Architect will consider requests for substitution if received within 60 days after the Notice to Proceed / Notice of Award. Requests received after that time may be considered or rejected at discretion of Architect.
1. Conditions: Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar considerations.
b. Requested substitution does not require extensive revisions to the Contract Documents.
c. Requested substitution is consistent with the Contract Documents and will produce indicated results.
d. Substitution request is fully documented and properly submitted.
e. Requested substitution will not adversely affect Contractor's construction schedule.
f. Requested substitution has received necessary approvals of authorities having jurisdiction.
g. Requested substitution is compatible with other portions of the Work.
h. Requested substitution has been coordinated with other portions of the Work.
i. Requested substitution provides specified warranty.
j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
SUBSTITUTION PROCEDURES 012500 - 4
PART 2 - PRODUCTS (Not Used)
PART 3 - EXECUTION (Not Used)
END OF SECTION 012500
CONTRACT MODIFICATION PROCEDURES 012600 - 1
SECTION 012600 - CONTRACT MODIFICATION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for handling and processing Contract modifications.
B. Related Requirements:
1. Division 01 Section "Substitution Procedures" for administrative procedures for handling requests for substitutions made after the Contract award.
1.3 MINOR CHANGES IN THE WORK
A. Architect will issue supplemental instructions authorizing minor changes in the Work, not involving adjustment to the Contract Sum or the Contract Time, on "Architect's Supplemental Instructions."
1.4 PROPOSAL REQUESTS
A. Owner-Initiated Proposal Requests: Architect will issue a detailed description of proposed changes in the Work that may require adjustment to the Contract Sum or the Contract Time. If necessary, the description will include supplemental or revised Drawings and Specifications.
1. Work Change Proposal Requests issued by Architect are not instructions either to stop work in progress or to execute the proposed change.
2. Within 5 working days after receipt of Proposal Request, submit a quotation estimating cost adjustments to the Contract Sum and the Contract Time necessary to execute the change.
a. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
b. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
c. Include costs of labor and supervision directly attributable to the change.
d. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
e. Quotation Form: Use forms acceptable to Architect.
B. Contractor-Initiated Proposals: If latent or changed conditions require modifications to the Contract, Contractor may initiate a claim by submitting a request for a change to Architect.
1. Include a statement outlining reasons for the change and the effect of the change on the Work. Provide a complete description of the proposed change. Indicate the effect of the proposed change on the Contract Sum and the Contract Time.
2. Include a list of quantities of products required or eliminated and unit costs, with total amount of purchases and credits to be made. If requested, furnish survey data to substantiate quantities.
CONTRACT MODIFICATION PROCEDURES 012600 - 2
3. Indicate applicable taxes, delivery charges, equipment rental, and amounts of trade discounts.
4. Include costs of labor and supervision directly attributable to the change.
5. Include an updated Contractor's construction schedule that indicates the effect of the change, including, but not limited to, changes in activity duration, start and finish times, and activity relationship. Use available total float before requesting an extension of the Contract Time.
6. Comply with requirements in Division 01 Section "Substitution Procedures" if the proposed change requires substitution of one product or system for product or system specified.
7. Proposal Request Form: Use form acceptable to Architect.
1.5 ADMINISTRATIVE CHANGE ORDERS
A. Allowance Adjustment: See Division 01 Section "Allowances" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect actual costs of allowances.
B. Unit-Price Adjustment: See Division 01 Section "Unit Prices" for administrative procedures for preparation of Change Order Proposal for adjusting the Contract Sum to reflect measured scope of unit-price work.
1.6 CHANGE ORDER PROCEDURES
A. On Owner's approval of a Work Changes Proposal Request, Architect will issue a Change Order for signatures of Owner and Contractor on AIA Document G701.
1.7 CONSTRUCTION CHANGE DIRECTIVE
A. Construction Change Directive: Architect may issue a Construction Change Directive on AIA Document G714. Construction Change Directive instructs Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.
1. Construction Change Directive contains a complete description of change in the Work. It also designates method to be followed to determine change in the Contract Sum or the Contract Time.
B. Documentation: Maintain detailed records on a time and material basis of work required by the Construction Change Directive.
1. After completion of change, submit an itemized account and supporting data necessary to substantiate cost and time adjustments to the Contract.
PART 2 - PRODUCTS (Not Used)
END OF SECTION 012600
PAYMENT PROCEDURES 012900 - 1
SECTION 012900 - PAYMENT PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements necessary to prepare and process Applications for Payment.
B. Related Requirements:
1. Division 01 Section "Allowances" for procedural requirements governing the handling and processing of allowances.
2. Division 01 Section "Unit Prices" for administrative requirements governing the use of unit prices.
3. Division 01 Section "Contract Modification Procedures" for administrative procedures for handling changes to the Contract.
4. Division 01 Section "Construction Progress Documentation" for administrative requirements governing the preparation and submittal of the Contractor's construction schedule.
1.3 DEFINITIONS
A. Schedule of Values: A statement furnished by Contractor allocating portions of the Contract Sum to various portions of the Work and used as the basis for reviewing Contractor's Applications for Payment.
1.4 SCHEDULE OF VALUES
A. Coordination: Coordinate preparation of the schedule of values with preparation of Contractor's construction schedule.
1. Coordinate line items in the schedule of values with other required administrative forms and schedules, including the following:
a. Application for Payment forms with continuation sheets.
b. Submittal schedule.
c. Items required to be indicated as separate activities in Contractor's construction schedule.
2. Submit the schedule of values to Architect at earliest possible date, but no later than fourteen (14) days before the date scheduled for submittal of initial Applications for Payment.
PAYMENT PROCEDURES 012900 - 2
3. Subschedules for Separate Elements of Work: Where the Contractor's construction schedule defines separate elements of the Work, provide subschedules showing values coordinated with each element.
B. Format and Content: Use Project Manual table of contents as a guide to establish line items for the schedule of values. Provide at least one line item for each Specification Section.
1. Identification: Include the following Project identification on the schedule of values:
a. Project name and location.
b. Name of Architect.
c. Architect's project number.
d. Contractor's name and address.
e. Date of submittal.
2. Arrange schedule of values consistent with format of AIA Document G703.
3. Arrange the schedule of values in tabular form with separate columns to indicate the following for each item listed:
a. Related Specification Section or Division.
b. Description of the Work.
c. Name of subcontractor.
d. Name of manufacturer or fabricator.
e. Name of supplier.
f. Change Orders (numbers) that affect value.
g. Dollar value of the following, as a percentage of the Contract Sum to nearest one-hundredth percent, adjusted to total 100 percent.
1) Labor.
2) Materials.
3) Equipment.
4. Provide a breakdown of the Contract Sum in enough detail to facilitate continued evaluation of Applications for Payment and progress reports. Coordinate with Project Manual table of contents. Provide multiple line items for principal subcontract amounts in excess of ten (10%) percent of the Contract Sum.
a. Include separate line items under Contractor and principal subcontracts for Project closeout requirements in an amount totaling ten (10%) percent of the Contract Sum and subcontract amount.
5. Round amounts to nearest whole dollar; total shall equal the Contract Sum.
6. Provide a separate line item in the schedule of values for each part of the Work where
Applications for Payment may include materials or equipment purchased or fabricated and stored, but not yet installed.
a. Differentiate between items stored on-site and items stored off-site. Contractor to comply with AIA Document A201-2007 General Conditions of the Contract for Construction, see Article 9 Payments and Completion, Section 9.3 Applications for Payment and Section 9.3.2.
7. Provide separate line items in the schedule of values for initial cost of materials, for each subsequent stage of completion, and for total installed value of that part of the Work.
8. Allowances: Provide a separate line item in the schedule of values for each allowance.
Show line-item value of unit-cost allowances, as a product of the unit cost, multiplied by
PAYMENT PROCEDURES 012900 - 3
measured quantity. Use information indicated in the Contract Documents to determine quantities.
9. Each item in the schedule of values and Applications for Payment shall be complete.
Include total cost and proportionate share of general overhead and profit for each item.
a. Temporary facilities and other major cost items that are not direct cost of actual work-in-place may be shown either as separate line items in the schedule of values or distributed as general overhead expense, at Contractor's option.
10. Schedule Updating: Update and resubmit the schedule of values before the next Applications for Payment when Change Orders or Construction Change Directives result in a change in the Contract Sum.
1.5 APPLICATIONS FOR PAYMENT
A. Each Application for Payment following the initial Application for Payment shall be consistent with previous applications and payments as certified by Architect and paid for by Owner.
1. Initial Application for Payment, Application for Payment at time of Substantial Completion, and final Application for Payment involve additional requirements.
B. Payment Application Times: Submit Application for Payment to Architect by the First of the month. The period covered by each Application for Payment is one month, ending on the last day of the previous month.
1. Submit draft copy of Application for Payment seven days prior to due date for review by Architect.
C. Application for Payment Forms: Use AIA Document G702 and AIA Document G703 as form for Applications for Payment.
D. Application Preparation: Complete every entry on form. Notarize and execute by a person authorized to sign legal documents on behalf of Contractor. Architect will return incomplete applications without action.
1. Entries shall match data on the schedule of values and Contractor's construction schedule. Use updated schedules if revisions were made.
2. Include amounts for work completed following previous Application for Payment, whether or not payment has been received. Include only amounts for work completed at time of Application for Payment.
3. Include amounts of Change Orders and Construction Change Directives issued before last day of construction period covered by application.
4. Indicate separate amounts for work being carried out under Owner-requested project acceleration.
E. Stored Materials: Include in Application for Payment amounts applied for materials or equipment purchased or fabricated and stored, but not yet installed. Differentiate between items stored on-site and items stored off-site.
1. Provide certificate of insurance, evidence of transfer of title to Owner, and consent of surety to payment, for stored materials.
2. Provide supporting documentation that verifies amount requested, such as paid invoices.
Match amount requested with amounts indicated on documentation; do not include overhead and profit on stored materials.
PAYMENT PROCEDURES 012900 - 4
3. Provide summary documentation for stored materials indicating the following:
a. Value of materials previously stored and remaining stored as of date of previous Applications for Payment.
b. Value of previously stored materials put in place after date of previous Application for Payment and on or before date of current Application for Payment.
c. Value of materials stored since date of previous Application for Payment and remaining stored as of date of current Application for Payment.
F. Transmittal: Submit three signed and notarized original copies of each Application for Payment to Architect by a method ensuring receipt within 24 hours. One copy shall include waivers of lien and similar attachments.
1. Transmit each copy with a transmittal form listing attachments and recording appropriate information about application.
G. Waivers of Mechanic's Lien: With each Application for Payment, submit waivers of mechanic's liens from subcontractors, sub-subcontractors, and suppliers for construction period covered by the previous application.
1. Submit partial waivers on each item for amount requested in previous application, after deduction for retainage, on each item.
2. When an application shows completion of an item, submit conditional final or full waivers.
3. Owner reserves the right to designate which entities involved in the Work must submit waivers.
4. Initial application for payment shall be accompanied by the Contractor�s partial waiver of lien only for the full amount of the payment.
5. Submit final Application for Payment with or preceded by conditional final waivers from every entity involved with performance of the Work covered by the application who is lawfully entitled to a lien.
6. Waiver Forms: Submit executed waivers of lien on forms, acceptable to Owner.
H. Initial Application for Payment: Administrative actions and submittals that must precede or coincide with submittal of first Application for Payment include the following:
1. List of subcontractors.
2. Schedule of values..
3. Contractor's construction schedule (preliminary if not final).
4. Combined Contractor's construction schedule (preliminary if not final) incorporating Work of multiple contracts, with indication of acceptance of schedule by each Contractor.
5. Products list (preliminary if not final).
6. Schedule of unit prices.
7. Submittal schedule (preliminary if not final).
8. List of Contractor's staff assignments.
9. List of Contractor's principal consultants.
10. Certificates of insurance and insurance policies.
11. Performance and payment bonds, if required in the agreement between Owner and
Contractor. Contractor to review Instruction to Bidders, Section 00300.
I. Application for Payment at Substantial Completion: After Architect issues the Certificate of Substantial Completion, submit an Application for Payment showing 100 percent completion for portion of the Work claimed as substantially complete.
1. Include documentation supporting claim that the Work is substantially complete and a statement showing an accounting of changes to the Contract Sum.
PAYMENT PROCEDURES 012900 - 5
2. This application shall reflect Certificate(s) of Substantial Completion issued previously for Owner occupancy of designated portions of the Work.
J. Final Payment Application: After completing Project closeout requirements, submit final Application for Payment with releases and supporting documentation not previously submitted and accepted, including, but not limited, to the following:
1. Evidence of completion of Project closeout requirements.
2. Insurance certificates for products and completed operations where required and proof that taxes, fees, and similar obligations were paid.
3. Updated final statement, accounting for final changes to the Contract Sum.
4. AIA Document G706, "Contractor's Affidavit of Payment of Debts and Claims."
5. AIA Document G706A, "Contractor's Affidavit of Release of Liens."
6. AIA Document G707, "Consent of Surety to Final Payment."
7. Evidence that claims have been settled.
8. Final meter readings for utilities, a measured record of stored fuel, and similar data as of date of Substantial Completion or when Owner took possession of and assumed responsibility for corresponding elements of the Work.
9. Final liquidated damages settlement statement, if required in the agreement between Owner and Contractor. Contractor to review Instruction to Bidders, Section 00300.
PART 2 - PRODUCTS (Not Used)
PAYMENT PROCEDURES 012900 - 6
END OF SECTION 012900
PROJECT MANAGEMENT AND COORDINATION 013100 - 1
SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following:
1. General coordination procedures.
2. Coordination drawings.
3. Requests for Information (RFIs).
4. Project Web site.
5. Project meetings.
B. Each contractor shall participate in coordination requirements. Certain areas of responsibility are assigned to a specific contractor.
C. Related Requirements:
1. Division 01 Section "Construction Progress Documentation" for preparing and submitting
Contractor's construction schedule.
2. Division 01 Section "Execution" for procedures for coordinating general installation and field-engineering services, including establishment of benchmarks and control points.
3. Division 01 Section "Closeout Procedures" for coordinating closeout of the Contract.
1.3 DEFINITIONS
A. RFI: Request from Owner, Architect, or Contractor seeking information required by or clarifications of the Contract Documents.
1.4 INFORMATIONAL SUBMITTALS
A. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design.
Include the following information in tabular form:
1. Name, address, and telephone number of entity performing subcontract or supplying products.
2. Number and title of related Specification Section(s) covered by subcontract.
3. Drawing number and detail references, as appropriate, covered by subcontract.
B. Key Personnel Names: Within 15 days of starting construction operations, submit a list of key personnel assignments, including superintendent and other personnel in attendance at Project
PROJECT MANAGEMENT AND COORDINATION 013100 - 2
site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home, office, and cellular telephone numbers and e-mail addresses. Provide names, addresses, and telephone numbers of individuals assigned as alternates in the absence of individuals assigned to Project.
1. Post copies of list in project meeting room, in temporary field office, on Project Web site, and by each temporary telephone. Keep list current at all times.
1.5 The General Contractors site superintendent shall be required to have had experience in the construction and coordination of at least (3) similar facilities.
1.6 GENERAL COORDINATION PROCEDURES
A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
B. Coordination: Each contractor shall coordinate its construction operations with those of other contractors and entities to ensure efficient and orderly installation of each part of the Work. Each contractor shall coordinate its operations with operations, included in different Sections, that depend on each other for proper installation, connection, and operation.
1. Schedule construction operations in sequence required to obtain the best results where installation of one part of the Work depends on installation of other components, before or after its own installation.
2. Coordinate installation of different components with other contractors to ensure maximum performance and accessibility for required maintenance, service, and repair.
3. Make adequate provisions to accommodate items scheduled for later installation.
C. Prepare memoranda for distribution to each party involved, outlining special procedures required for coordination. Include such items as required notices, reports, and list of attendees at meetings.
1. Prepare similar memoranda for Owner and separate contractors if coordination of their Work is required.
D. Administrative Procedures: Coordinate scheduling and timing of required administrative procedures with other construction activities and activities of other contractors to avoid conflicts and to ensure orderly progress of the Work. Such administrative activities include, but are not limited to, the following:
1. Preparation of Contractor's construction schedule.
2. Preparation of the schedule of values.
3. Installation and removal of temporary facilities and controls.
4. Delivery and processing of submittals.
PROJECT MANAGEMENT AND COORDINATION 013100 - 3
5. Progress meetings.
6. Preinstallation conferences.
7. Project closeout activities.
8. Startup and adjustment of systems.
E. Conservation: Coordinate construction activities to ensure that operations are carried out with consideration given to conservation of energy, water, and materials. Coordinate use of temporary utilities to minimize waste.
1. Salvage materials and equipment involved in performance of, but not actually incorporated into, the Work. See other Sections for disposition of salvaged materials that are designated as Owner's property.
1.7 COORDINATION DRAWINGS
A. Coordination Drawings, General: Prepare coordination drawings according to requirements and additionally where limited space availability necessitates coordination, or if coordination is required to facilitate integration of products and materials fabricated or installed by more than one entity.
Minimum requirements for Coordination Drawings for the following, (but not limited to) Subcontracts:
1) Steel
2) Mechanical (HVAC)
3) Mechanical (Plumbing)
4) Electrical (Including Data)
5) Fire Protection
Note: Coordination Drawings are not to be considered shop drawings for review. Coordination drawings and/or meetings are to take place prior to shop drawing submittals. Coordination meeting is to take place early in the project schedule. Subcontractors are required to prepare questions in the form of RFIs to be reviewed and discussed. Do not submit RFIs to Architect prior to coordination meeting.
2. Content: Project-specific information, drawn accurately to a scale large enough to indicate and resolve conflicts. Do not base coordination drawings on standard printed data. Include the following information, as applicable:
a. Use applicable Drawings as a basis for preparation of coordination drawings. Prepare sections, elevations, and details as needed to describe relationship of various systems and components.
b. Coordinate the addition of trade-specific information to the coordination drawings by multiple contractors in a sequence that best provides for coordination of the information and resolution of conflicts between installed components before submitting for review.
c. Indicate functional and spatial relationships of components of architectural, structural, civil, mechanical, and…