This is Addendum No. 2 to the bidding documents for the Mount Joy Borough Authority's Rapho Tank Rehab Project, Contract 2027-01, issued by RETTEW on November 9, 2026. The project involves general construction work on a water storage tank, including rehabilitation, painting with two logos, metal fabrication, and concrete repairs. The mandatory pre-bid meeting was held on October 28, 2026, at the Mount Joy Borough Authority offices in Mount Joy, Pennsylvania. Sealed bids were to be submitted online through PennBID by 10:00 AM on November 11, 2026, with a required bid bond of 10% of the total bid amount. The successful bidder must substantially complete the project within 180 calendar days of receiving the Notice to Proceed and furnish performance and payment bonds equal to 100% of the contract price.

Addendum No. 2 addresses bidder questions and clarifies project specifications, including confirmation that painted tank logos are included in the contractor's bid scope, clarification that handrails and roof material shall be carbon steel while the platform shall be aluminum, and detailed specifications for exterior tank surface preparation using potable water, surfactant/detergent, and stiff bristle brush scrubbing followed by SSPC-SP-3 methods for rusted or peeling paint areas. The addendum also confirms that Induron products will be accepted as "or equal" alternatives provided they meet Project Manual requirements and NSF certifications. The project is subject to Pennsylvania Prevailing Wage Act conditions, OSHA requirements, and various Pennsylvania state compliance regulations regarding non-discrimination and underground utility protection.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

We answer to you.

3020 Columbia Avenue, Lancaster, PA 17603● Phone: (800) 738-8395 E-mail: rettew@rettew.com ● Website: rettew.com

ADDENDUM NO. 02

November 9, 2026

To: All Prospective Bidders

RE: Mount Joy Borough Authority Rapho Tank Rehab Project Contract 2027-01: General Construction RETTEW Project No. 0136606833

Dear Bidders:

The following Addendum No. 02 is hereby made to the contract documents for the above-referenced project. Any additions, clarifications or deletions described in this Addendum take precedence over any instructions at conflict herein. All items in this Addendum shall be considered in preparation of your proposal for the referenced project.

Receipt of this Addendum shall be acknowledged by inserting this number and date in the space provided on the Bid Form. Failure to do so may result in disqualification of the Bidder. The addendum consists of eight pages.

BIDDING QUESTIONS RECEIVED THROUGH PENNBID

QUESTION: On the drawings, it looks like you are expecting a logo to be on either side of the tank. Is this included in this project bid, or do you have another contractor performing this work?

RESPONSE: Yes, the tank will receive two painted logos on it. This is to be included in the selected contractor's bid.

QUESTION: Section 055000 Metal Fabrication states that the new handrails and platform to be fabricated out of aluminum, but the drawing have the handrail and platform being fabricated from steel. Can you please clarify the material that the roof handrail and platform should be fabricated of?

RESPONSE: The handrail and roof material should be carbon steel. The platform shall be aluminum. We plan to address this at the mandatory prebid meeting and by addendum.

QUESTION: Section 033310 concrete work seems to cover a lot of descriptions on how to repair the Concrete and what to repair it with, but it doesn't provide you with the extent of the work to be performed. Please clarify the work scope for the foundation?

RESPONSE: We will provide photos at the mandatory prebid meeting, we will do a site visit after the prebid meeting and address this by addendum.

Engineers

Environmental Consultants

Surveyors

Landscape Architects

Safety Consultants

Addendum No. 02 Mount Joy Borough Authority/Construction Department Shop Renovations RETTEW Project No. 0136603369

QUESTION: Will products manufactured by Induron be acceptable? These materials will all be at the same material thicknesses listed in the specification?

Seam Sealer/Pit Filler: Aquatapoxy A-6 Interior Wet Primer: Indurazinc MC-67 or Ceramaprime Interior Wet Intermediate: PE-70 Interior Wet Finish: Permaclean 100 or Permaclean 100SL Exterior Primer: E-Bond 100 Exterior Intermediate: PE-70 Exterior 1st Finish: Indurethane 6600+ Exterior Final Finish: Permagloss Valve Vault Primer: Indurazinc MC-67 or Ceramaprime Valve Vault Intermediate: PE-70 Valve Vault 1st Finish: PE-70 Valve Vault Final Finish: PE-70

RESPONSE: The Induron products listed will be considered "Or Equal" during the submittal process as long as they meet the requirements in the Project Manual and NSF certifications.

QUESTION: The exterior tank prep is not clear. Can you please clarify?

RESPONSE: Exterior Surface Preparation

All surfaces shall be wetted with clean potable water, followed by an application of paint manufacturer recommended surfactant/detergent, followed by scrubbing the surface with stiff bristle brushes or brooms, followed by complete rinsing with clean potable water.

All rusted or peeling paint locations shall be addressed using SSPC-SP-3 methods with all fractured paint film edges sanded smooth.

PROJECT MANUAL MODIFICATIONS

The Project Manual shall be modified as follows:

SECTION 05000 – METAL FABRICATION

All the platform framing, handrails and Guard rials, Ladder extension components, brackets, supports, roof material and miscellaneous metal components shall be carbon steel. These items shall be shop blasted and primer coated prior to installation. The platform shall be grated aluminum.

SECTION 098500 – STEEL TANK PAINTING

3.2 – SURFACE PREPRATION

All surfaces shall be wetted with clean potable water, followed by an application of paint manufacturer recommended surfactant/detergent, followed by scrubbing the surface with stiff bristle brushes or brooms, followed by complete rinsing with clean potable water. All rusted or peeling paint locations shall be addressed using SSPC-SP-3 methods with all fractured paint film edges sanded smooth.

END OF ADDENDUM

Addendum No. 02 Mount Joy Borough Authority/Construction Department Shop Renovations RETTEW Project No. 0136603369

Z:\Shared\Projects\01366\0136606833 - Rapho Tank Rehab Project\MUN\Bidding\Addendums\No. 01\00 Addendum No.

01_MJBA_Rapho Tank Rehab_2026-11-02.docx

File details come from the government source that posted it. Updated .