8a. 23947073_SPECIFICATION.pdf
PDF 8 MB Posted
- Attached to
- MAINTENANCE DREDGING AT THE U. S. COAST GUARD (USCG), STATION CAPE DISAPPOINTMENT, ILWACO, WA - FY 2024
- Solicitation number
- 70Z08824R0000113
About this file
This document outlines a sources sought notice for maintenance dredging services. The United States Coast Guard is seeking a contractor to dredge approximately 15,000 cubic yards of sediment from the mooring basin and boat lift areas at Coast Guard Station Cape Disappointment in Ilwaco, Washington. The dredged material must be disposed of in the Baker Bay Flow Lane Disposal site in Oregon. Services include pre-dredge eelgrass and hydrographic surveys, and production of a dredge operations plan within 30 days of award. Dredging must commence following approval of the plan and be completed by June 1, 2024. The place of performance is Coast Guard Station Cape Disappointment. The soliciting agency is the Department of Homeland Security United States Coast Guard.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SOURCES SOUGHT-70Z08824R0000113-MTC Dredging at USCG Cape Disappointment.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DIVISION 01 - GENERAL REQUIREMENTS
01 10 00-GENERALPARAGRAPHS
PART 1 GENERAL
1. 01
1. 02
SCOPE OF WORK: Provide all labor, materials, and equipment necessary to dredge and dispose of sediment from the mooring basin and boat lift areas at U.S. Coast
Guard (USCG) Station Cape Disappointment, located within
Baker Bay in Ilwaco, Washington. Dredge approximately
15,000 cubic yards (cy) of sediment from the USCG Station
Cape Disappointment boat basin by hydraulic or mechanical means to the indicated design depth of -10.0 feet Mean
Lower Low Water (MLLW) plus 2 feet over depth allowance.
The dredged sediment shall be permanently disposed of using a bottom dump barge, scow, or hopper dredge, in the
Baker Bay Flow Lane Disposal (BB-3) within the Columbia
River in Clatsop County, Oregon. The Coast Guard has been authorized to dredge outside of the permitted in-water work window. All other requirements of the attached permits remain the same. The contractor is expected to mobilize for pre-dredge Eelgrass and hydrographic surveys as soon as possible and to produce a Dredge Operations
Plan (DOP) within 30 days of award (to include the surveys). The contractor shall begin dredging as soon as a notice to proceed is received by the United States Army
Corps of Engineers (USACE) following approval of the DOP, while implementing requirements and best practices identified in the attached permits. Dredging must be complete by June 1, 2024.
BASIS FOR BIDS
Mobilize and demobilize personnel and equipment including the dredge, barge, scow, hydraulic pipeline, trucks, and other equipment necessary to complete the work. Prepare a
Dredge Operations Plan, conduct pre-and post- dredge hydrographic surveys, and conduct pre-dredge and post dredge eelgrass surveys. Include all direct costs not associated with the dredging operation.
1) Mobilization & preparation of dredging and disposal site(s) and demobilization.
File details come from the government source that posted it. Updated .