Sol_89503224QWA000600_Amd_0001.pdf

PDF 94 KB Posted

Attached to
CODY-LV-NC OPGW Installation Traffic Control
Solicitation number
89503224QWA000600
Issued by

About this file

This document is an amendment to Solicitation No. 89503224QWA000600 for CODY-LV-NC OPGW Installation Traffic Control services. The Western Area Power Administration (WAPA) requires a contractor to perform traffic control services at various road crossings between the Lovell Substation and North Cody Substation along a 69 kV transmission line in Wyoming.

The amendment provides answers to questions from prospective vendors. Key details include: there are no freeways to cross, but there are some busy US Highway crossings; traffic may need to be limited to one lane for up to 30 minutes at a time to accommodate the aerial work, but complete stoppages will only occur in a catastrophic incident; the helicopter will only cross highways if absolutely necessary, for a couple minutes at a time; expected work hours are up to 10 hours per day, not starting before 7:30 am, and the traffic control points are limited to the areas circled on the map. The contractor will need to set up and break down the work zones as they move between the crossing locations.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

(x)

89503224QWA000600

x x copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted ; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGEMENT TO BE

RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR

OFFER. If by virtue of this amendment you desire to change an offer already submitted , such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

x

LOVELAND CO 80539-8986

RMR

5555 E. CROSSROADS BLVD

ROCKY MOUNTAIN REGIONAL OFFICE

US DOE/WESTERN AREA POWER

WAPA (RMR)

05/23/20240001

13. THIS ITEM ONLY APPLIES TO MODIFICATION OF CONTRACTS/ORDERS. IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

12. ACCOUNTING AND APPROPRIATION DATA (If required) is not extended.is extended, Items 8 and 15, and returning

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended , by one of the following methods: (a) By completing

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

FACILITY CODE CODE

10B. DATED (SEE ITEM 13)

10A. MODIFICATION OF CONTRACT/ORDER NO.

9B. DATED (SEE ITEM 11)

9A. AMENDMENT OF SOLICITATION NO.

CODE

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State and ZIP Code)

7. ADMINISTERED BY (If other than Item 6)CODE 6. ISSUED BY

PAGE OF PAGES

4. REQUISITION/PURCHASE REQ. NO.3. EFFECTIVE DATE2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO. (If applicable)

1. CONTRACT ID CODE

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

05/23/2024

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority) appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

E. IMPORTANT: Contractor is not is required to sign this document and return __________________ copies to the issuing office.

ORDER NO. IN ITEM 10A.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

The purpose of this amendment is to provide answers to questions posted by prospective quoters:

1. Are there any freeway/expressways they need to cross?

A1: No, there are no freeway/expressways, There are some busy US Highway crossings, but most are rural state and county roads.

2. How long are they planning to hold traffic for at one time?

A2: Traffic may need to be limited to a one lane closure for up to a half hour at a time to create room for outriggers setting up an aerial reach, but not at all locations. Traffic

Continued ...

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)15A. NAME AND TITLE OF SIGNER (Type or print)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 15B. CONTRACTOR/OFFEROR 16C. DATE SIGNED

(Signature of person authorized to sign) (Signature of Contracting Officer)

John W. Pratt

STANDARD FORM 30 (REV. 11/2016)

Prescribed by GSA FAR (48 CFR) 53.243

Previous edition unusable

Except as provided herein, all terms and conditions of the document referenced in Item 9 A or 10A, as heretofore changed, remains unchanged and in full force and effect .

05/23/2024 Signature on File

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

2 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

89503224QWA000600/0001

will only need to be completely stopped in the event of a catastrophic incident that drops wire on the highway during the wire stringing operation. If a catastrophic event occurs and traffic stoppage is needed, the length of time for the Hwy closure will depend on the amount of time it takes to evaluate the situation and develop a plan to make the situation safe for our workers and the public.

3. How often will the helicopter need to cross over and will there be clear communication on when that will happen?

A3: WAPA is utilizing a helicopter to fly men suspended below it on a long line from power line structure to power line structure. FAA regulations require highway traffic to be stopped if a helicopter is used in this manner while crossing major highways. The plan is not to have men flown over highways for this reason, but if there is an unplanned immediate need to ferry men quickly such as a catastrophic event happening, there a small potential that traffic would need to be halted for the short time it would take to fly men over the highway, no longer than a couple of minutes each passing. As far as communications, a spare radio may need to be supplied to the Foreman.

4. What are the expected work hours? Is there the potential to need light plants?

A4: Traffic control may be needed for up to 10 hours but mostly 4-6 hours per day not starting earlier than 7:30 am

5. Are the areas circled on the map the only areas of crossing in which traffic control will be set up?

A5: Yes that is correct.

6. Are we able to set up & breakdown work zones as we go for each crossing?

A6: The distance between the two points that the fiber optic being installed at any given time is at minimum 15,600’ and the longest distance is

Continued ...

NSN 7540-01-152-8067 OPTIONAL FORM 336 (4-86)

Sponsored by GSA

FAR (48 CFR) 53.110

ITEM NO. SUPPLIES/SERVICES QUANTITY UNIT UNIT PRICE AMOUNT

NAME OF OFFEROR OR CONTRACTOR

3 3

CONTINUATION SHEET

REFERENCE NO. OF DOCUMENT BEING CONTINUED PAGE OF

(A) (B) (C) (D) (E) (F)

89503224QWA000600/0001

28,000’. Traffic control will be required at the same time in each pull over all the listed roads.

ALL OTHER TERMS AND CONDITIONS REMAIN UNCHANGED.