This document is a Performance Work Statement for the Oak Ridge Reservation Cleanup Contract. It outlines the required scope of work, including transitioning from the previous contractor, performing cleanup activities at the Y-12 National Security Complex, Oak Ridge National Laboratory, and East Tennessee Technology Park sites. Key work includes decontamination and demolition of numerous excess facilities, remediation of environmental media, construction and operation of disposal and treatment facilities, and ongoing surveillance, maintenance, and monitoring activities. The contractor will be responsible for integration and execution of all work, including subcontractor management, in accordance with regulatory requirements and DOE directives to optimize completion of scope, cost, and schedule. The period of performance is to be determined.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
OAK RIDGE RESERVATION CLEANUP CONTRACT – FINAL RFP SECTION C
SOLICITATION NO. 89303319REM000047
C-i
Part I – The Schedule
Section C
Performance Work Statement
C-ii
This page intentionally left blank.
C-iii
Contents
ORR CLEANUP CONTRACT OVERVIEW AND OBJECTIVES .................................................. C-1
Background ..................................................................................................................................... C-1
Contract Purpose and Objectives .................................................................................................... C-1
Description of Performance Requirements ..................................................................................... C-2
Scope Summary and Work Authorization ............................................................................. C-2
C.1 Contract Transition ...................................................................................................................... C-4
C.1.1 Incoming Transition ............................................................................................ C-4
C.1.2 Outgoing Transition and Closeout ...................................................................... C-7
C.2 Post-Retirement Medical Benefits, Long-Term Disability, and Pension Contribution ........ C-7
C.3 Cleanup .................................................................................................................................. C-7
C.3.1 ORNL Cleanup ................................................................................................. C-11
C.3.1.1 3026 Hot Cells ................................................................................................. C-11
C.3.1.2 3038 Facility .................................................................................................... C-12
C.3.1.3 Bethel Valley Isotopes Area Facilities ............................................................. C-12
C.3.1.4 Graphite Reactor Historic Preservation ........................................................... C-12
C.3.1.5 Graphite Reactor Support Facilities ................................................................. C-13
C.3.1.6 Bethel Valley Bulk Shielding and Low Intensity Test Reactors Complex ...... C-13
C.3.1.7 Oak Ridge Research Reactor Facilities ............................................................ C-13
C.3.1.8 3028 Facility .................................................................................................... C-14
C.3.1.9 Bethel Valley Chemical Development Lab Facilities ...................................... C-14
C.3.1.10 3515 Facility .................................................................................................... C-14
C.3.1.11 3517 and Support Facilities ............................................................................. C-14
C.3.1.12 7500 Complex .................................................................................................. C-15
C.3.1.13 2026 Complex .................................................................................................. C-15
C.3.1.14 2525 Complex .................................................................................................. C-15
C.3.1.15 2528 Complex .................................................................................................. C-16
C.3.1.16 3019 Complex .................................................................................................. C-16
C.3.1.17 3039 Stack Complex ........................................................................................ C-17
C.3.1.18 Central Stack East Hot Cell Facilities Complex .............................................. C-17
C.3.1.19 Experimental Gas-cooled Reactor Complex .................................................... C-18
C.3.1.20 Integrated Process Demonstration Facility ...................................................... C-18
C.3.1.21 Molten Salt Reactor Experiment Complex ...................................................... C-18
C.3.1.22 Tower Shielding Facilities Complex ............................................................... C-19
C.3.1.23 3544 Complex .................................................................................................. C-19
C.3.1.24 Melton Valley Reactors and Other Facilities Regulatory Decision
Documents .............................................................................................. C-20
C-iv
C.3.1.25 Reserved .......................................................................................................... C-20
C.3.1.26 Bethel Valley Groundwater ROD .................................................................... C-20
C.3.1.27 ORR Non-watershed Sites ROD ...................................................................... C-20
C.3.1.28 Hot Storage Garden ......................................................................................... C-20
C.3.1.29 Melton Valley Waste Management Complex .................................................. C-21
C.3.1.30 Shielded Transfer Tanks Disposition ............................................................... C-21
C.3.1.31 TRU Waste Processing Complex..................................................................... C-21
C.3.1.32 Bethel Valley Process Drain Diversion ........................................................... C-23
C.3.1.33 Bethel Valley Remedial Actions ...................................................................... C-23
C.3.1.34 Bethel Valley Non-hydraulic Fracturing Well Plug and Abandon .................. C-24
C.3.1.35 ORR Non-watershed Sites Remedial Action ................................................... C-24
C.3.1.36 2007/2008 Complex Demolition ..................................................................... C-24
C.3.1.37 3025 Complex Demolition ............................................................................... C-25
C.3.1.38 3525 Complex Demolition ............................................................................... C-25
C.3.1.39 4501/4505 Complex Demolition ..................................................................... C-25
C.3.1.40 5505 Demolition .............................................................................................. C-25
C.3.1.41 6010/7019 Complex Demolition ..................................................................... C-26
C.3.1.42 Fire Station Complex Demolition .................................................................... C-26
C.3.1.43 Health Physics Research Reactor Complex Demolition .................................. C-26
C.3.1.44 Southeast Contaminated Labs Complex Demolition ....................................... C-27
C.3.1.45 Southeast Services Complex Demolition ......................................................... C-27
C.3.1.46 Bethel Valley Tank Upgrades .......................................................................... C-28
C.3.1.47 Melton Valley Trench 13 Remedial Action ..................................................... C-28
C.3.2 Y-12 Cleanup .................................................................................................... C-28
C.3.2.1 Biology Complex ............................................................................................. C-28
C.3.2.2 Beta 4 (9204-4) Complex ................................................................................ C-28
C.3.2.3 Alpha 5 (9201-5) Complex .............................................................................. C-29
C.3.2.4 Alpha 4 (9201-4) Complex .............................................................................. C-30
C.3.2.5 Alpha 2 (9201-2) Complex .............................................................................. C-30
C.3.2.6 Alpha 3 (9201-3) Complex .............................................................................. C-30
C.3.2.7 Beta 1 (9204-1) Complex ................................................................................ C-30
C.3.2.8 9206 Complex .................................................................................................. C-31
C.3.2.9 9213 Complex .................................................................................................. C-31
C.3.2.10 9401-2 Facility ................................................................................................. C-31
C.3.2.11 Reserved .......................................................................................................... C-32
C.3.2.12 Reserved .......................................................................................................... C-32
C.3.2.13 Steam Plant Complex ....................................................................................... C-32
C.3.2.14 Tank Facilities Complex .................................................................................. C-32
C.3.2.15 Upper East Fork Poplar Creek 81-10 Area Remedial Action .......................... C-32
C.3.2.16 Y-12 Exposure Unit 5 ...................................................................................... C-33
C-v
C.3.2.17 9401-1 Facility ................................................................................................. C-33
C.3.2.18 Nickel Disposition ........................................................................................... C-33
C.3.2.19 Bear Creek Valley Burial Ground ROD .......................................................... C-33
C.3.2.20 Bear Creek Valley Groundwater ROD ............................................................ C-33
C.3.2.21 Bear Creek Valley Burial Grounds Remedial Action ...................................... C-33
C.3.2.22 Bear Creek Valley S-3 Ponds Remedial Action .............................................. C-33
C.3.2.23 Bear Creek Valley White Wing Scrap Yard Remedial Action ........................ C-33
C.3.2.24 Bear Creek Valley White Wing Scrap Yard ROD ........................................... C-33
C.3.2.25 Chestnut Ridge ROD ....................................................................................... C-33
C.3.2.26 Upper East Fork Poplar Creek Soils Remedial Action .................................... C-34
C.3.2.27 Bear Creek Valley NT-8 Action Memo and Removal Action ......................... C-34
C.3.2.28 Chestnut Ridge Remedial Action .................................................................... C-34
C.3.2.29 9212 Complex Demolition ............................................................................... C-34
C.3.2.30 Y-12 Balance of Facilities ............................................................................... C-35
C.3.3 ETTP Cleanup ................................................................................................... C-35
C.3.3.1 Zone 1 Soil ....................................................................................................... C-35
C.3.3.2 Zone 2 Soil ....................................................................................................... C-36
C.3.3.3 Groundwater and Remaining Ecological, Surface Water, and Sediment
Remediation ..................................................................................................... C-36
C.3.3.4 Haul Road and Bridge Removal ...................................................................... C-36
C.4 CERCLA Disposal Facility Construction (Y-12) ................................................................ C-37
C.4.1 CERCLA Disposal Facility Design .................................................................. C-37
C.4.2 CERCLA Disposal Facility Construction ......................................................... C-37
C.4.3 CERCLA Disposal Facility Startup .................................................................. C-37
C.5 Mission Support Activities .................................................................................................. C-37
C.5.1 Liquid and Gaseous Waste Operations and Life Extension (ORNL) ............... C-37
C.5.1.1 Liquid and Gaseous Waste Operations ............................................................ C-37
C.5.1.2 LGWO Infrastructure and Life Extension ....................................................... C-38
C.5.2 Transuranic and Solid Waste Debris Storage and Shipment Support (ORNL). C-38
C.5.2.1 Melton Valley Solid Waste Storage Facility Operations and Maintenance ..... C-38
C.5.2.2 TRU Shipment Support ................................................................................... C-39
C.5.2.3 TRU Sludge Processing Facility Operations ................................................... C-40
C.5.3 ORNL Surveillance and Maintenance of EM Facilities and Sites and
Environmental Monitoring ................................................................................ C-40
C.5.3.1 ORNL Surveillance and Maintenance ............................................................. C-40
C.5.3.2 ORNL Environmental Monitoring ................................................................... C-41
C.5.3.3 Molten Salt Reactor Experiment Enhanced Maintenance ............................... C-41
C.5.4 Y-12 Surveillance and Maintenance of EM Facilities and Sites and
Environmental Monitoring ................................................................................ C-42
C.5.4.1 Y-12 Surveillance and Maintenance ................................................................ C-42
C-vi
C.5.4.2 Y-12 Environmental Monitoring ..................................................................... C-42
C.5.5 CERCLA Disposal Facilities and ORR Landfills Management and Operations
(Y-12) ................................................................................................................ C-43
C.5.5.1 EMWMF and EMDF Management, Waste Acceptance Criteria Attainment, and
Operations ........................................................................................................ C-43
C.5.5.2 ORR Sanitary, Industrial, and Construction and Demolition Landfills ........... C-44
C.5.6 Outfall 200 Mercury Treatment Facility (Y-12) ............................................... C-44
C.5.6.1 MTF Construction Support .............................................................................. C-44
C.5.6.2 MTF Checkout, Testing, and Commissioning ................................................. C-45
C.5.6.3 MTF Operations ............................................................................................... C-46
C.5.7 ETTP Site Closure, Historic Preservation, Surveillance and Maintenance, and
Environmental Monitoring ................................................................................ C-46
C.5.7.1 ETTP Site Closure ........................................................................................... C-46
C.5.7.2 ETTP Historic Preservation ............................................................................. C-47
C.5.7.3 ETTP Surveillance and Maintenance, and Environmental Monitoring ........... C-47
C.5.8 Legacy Waste Disposition ................................................................................. C-48
C.5.9 Infrastructure Enhancements ............................................................................. C-48
C.5.9.1 Infrastructure for ORNL and Y-12 Cleanup .................................................... C-48
C.5.9.2 Design Basis Threat Mitigation ....................................................................... C-48
C.6. Core Functions .................................................................................................................... C-48
C.6.1 Central Services ................................................................................................ C-49
C.6.1.1 Project Support Performance Requirements .................................................... C-49
C.6.1.2 Project Performance Reporting ........................................................................ C-52
C.6.1.3 Health and Safety ............................................................................................. C-54
C.6.1.4 Radiation Protection ........................................................................................ C-55
C.6.1.5 Nuclear Safety ................................................................................................. C-55
C.6.1.6 Nuclear Criticality Safety ................................................................................ C-55
C.6.1.7 Safety Culture .................................................................................................. C-56
C.6.1.8 Quality Assurance ............................................................................................ C-57
C.6.1.9 Engineering ...................................................................................................... C-57
C.6.1.10 Environmental Protection ................................................................................ C-57
C.6.1.11 Environmental Sustainability ........................................................................... C-57
C.6.1.12 Federal Facility Agreement and Related Support ............................................ C-57
C.6.1.13 Records Management ...................................................................................... C-58
C.6.1.14 Public Relations and Media Support................................................................ C-59
C.6.1.15 Legal Management .......................................................................................... C-60
C.6.1.16 Safeguards and Security ................................................................................... C-60
C.6.1.17 Information Technology .................................................................................. C-63
C.6.1.18 Audit Support Services .................................................................................... C-64
C-vii
C.6.1.19 Administration of Pension and Benefits Services at ORR, Portsmouth, and
Paducah Sites ................................................................................................... C-64
C.6.1.20 Other Program Activities ................................................................................. C-64
C.6.2 Project Services ................................................................................................. C-65
C.6.2.1 Reservation Management ................................................................................ C-65
C.6.2.2 Reindustrialization ........................................................................................... C-65
C.6.2.3 Emergency Management and Fire Protection .................................................. C-65
C.6.2.4 Technology Development ................................................................................ C-65
C.6.2.5 Historic Preservation and Cultural Resource Management ............................. C-66
C.6.2.6 Analytical Services (Sample Management Office Integration) ....................... C-66
C.6.2.7 Transportation Services ................................................................................... C-66
C.6.2.8 Waste Management .......................................................................................... C-66
C.6.2.9 Land Use Controls ........................................................................................... C-67
C.6.2.10 Support DOE Natural Resource Damage Assessment ..................................... C-67
C.7 List of Section C Attachments ............................................................................................. C-68
C-1
ORR CLEANUP CONTRACT OVERVIEW AND OBJECTIVES
Background
Since its inception in 1943, the U.S. Department of Energy (DOE) Oak Ridge Reservation (ORR)’s Y-12
National Security Complex (Y-12), Oak Ridge National Laboratory (ORNL), and East Tennessee
Technology Park (ETTP) sites have supported a variety of DOE missions including weapons development and production, science and energy research, and isotope and nuclear fuel production. Today
Y-12 and ORNL are enduring sites performing key DOE missions. Y-12, managed and operated by
DOE’s National Nuclear Security Administration (NNSA), processes and stores uranium to maintain the nation’s nuclear stockpile and provide fuel for the U.S. Nuclear Navy. ORNL, managed and operated by
DOE’s Office of Science, is the nation’s largest multi-program science and energy laboratory. As cleanup is completed, portions of ETTP are being transitioned to a commercial industrial park to support the regional economy.
Environmental liabilities from past DOE Oak Ridge activities remain to be addressed. To reduce risk, hundreds of excess contaminated facilities at Y-12 and ORNL must be demolished and sites with contaminated environmental media require remediation. Mercury is the prevalent legacy contaminant at
Y-12, but beryllium, uranium, and other chemicals are also present. ORNL excess facilities are contaminated with a variety of radioactive isotopes, including transuranics, as well as other chemicals.
Y-12 and ORNL also include DOE’s Office of Environmental Management (EM) operating facilities that support waste treatment and disposal and environmental compliance. Upon completion of decontamination and demolition activities at ETTP, most of the site will be privately owned. However, DOE will retain responsibility for the remaining environmental media cleanup, post-closure monitoring and care, and historic preservation.
The mission of DOE’s Oak Ridge Office of Environmental Management (OREM) is to complete cleanup of the ORR to protect the region’s health and environment, make clean land available for future use, and enable vital DOE missions in science, energy, and national security. OREM’s mission supports DOE strategic goals to advance America’s sciences, energy security, and economic growth while minimizing the nation’s environmental and national security threats.
Contract Purpose and Objectives
One of DOE’s strategic goals is to clean up the nation’s Manhattan Project and Cold War legacies in compliance with laws and regulations. To accomplish this goal, DOE must reduce its environmental liabilities through accelerated cleanup of high-risk areas, thereby reducing risk and financial liability and returning land for its projected future use. This will be accomplished in a manner that is protective of human health and the environment.
The purpose of the ORR Cleanup Contract is to achieve maximum measurable results in advancing environmental cleanup requirements on the ORR at the best value to the U.S. taxpayer. This Performance
Work Statement (PWS) includes DOE’s desired outcomes and related end states to progress towards
ORR cleanup completion during the period of performance.
The Contractor is responsible for the performance of the scope under the Contract, including defining the specific methods, innovations, and graded approaches for accomplishing all work to be performed and managing, integrating, and executing work described in this PWS. DOE’s goal is to optimize scope completion, cost, and schedule associated with performance of all work in compliance with all applicable requirements. The work involves accessing classified information, up to and including Secret Restricted
Data level and category and/or special nuclear material, both of which require access authorizations
C-2
(clearances). Therefore, the Contractor must possess a facility clearance before access authorizations may be granted.
The Contractor shall comply with the Federal Facility Agreement (FFA); the Oak Ridge Reservation Site
Treatment Plan; approved Records of Decision (RODs) and other Comprehensive Environmental
Response, Compensation, and Liability Act of 1980, (CERCLA) as amended decision documents; and other applicable regulatory requirements. Hazardous Waste Operations and Emergency Response
(HAZWOPER) requirements apply to certain facilities/areas as specified in 29 Code of Federal
Regulations (CFR) 1910.120.
Accelerated cleanup (i.e., accomplishing cleanup faster and more efficiently than planned) is a cooperative undertaking that requires the Contractor and the Government to seek innovative approaches to achieve the end states. Streamlining processes, eliminating non-value-added requirements, and identifying efficiencies and performance improvements are critical to accomplishing accelerated cleanup.
The Contractor shall, throughout the Contract period of performance, seek to reduce non-value-added requirements and processes that impede progress and identify efficiencies and performance improvements that reduce the actual cost and/or improve the schedule for the work.
Description of Performance Requirements
Scope Summary and Work Authorization
The overall scope of this Contract includes the following:
(a) Transition: Transition includes activities for the incoming transition from the ETTP Cleanup
Contract to the ORR Cleanup Contract and the outgoing transition to the follow-on contractor.
(b) Cleanup: Cleanup of the ORR encompasses preparation for demolition and/or demolition of numerous facilities and remediation of environmental media at ETTP, ORNL, and Y-12. Cleanup includes disposal of all associated wastes. Cleanup includes improvements (e.g., repairs, stabilization, upgrades) for facilities planned for future use or historic preservation.
(c) Construction and/or Startup of Mission Support Facilities: Complete Phase 1 construction and initiate operation of the Environmental Management Disposal Facility (EMDF), and complete commissioning of the Outfall 200 Mercury Treatment Facility (MTF) at Y-12.
(d) Operations:
(1) Liquid and Gaseous Waste Operations (LGWO): Operate and maintain LGWO facilities to dispose of ORNL and OREM liquid and gaseous wastes and ensure reliability of these essential systems and services.
(2) Transuranic and Solid Waste Debris Storage and Shipment Support: Manage OREM’s remaining transuranic (TRU) and legacy waste inventory and support shipments to the Waste Isolation Pilot
Plant (WIPP) or other offsite disposal facilities.
(3) Surveillance and Maintenance of Facilities and Sites at ORNL and Y-12 under EM responsibility:
Maintain OREM’s excess contaminated facilities and sites to ensure a safe and stable condition that minimizes risks pending facility demolition, site remediation, and/or transfer.
(4) CERCLA Disposal Facilities and ORR Landfills: Operate and maintain disposal facilities to ensure efficient disposal of cleanup debris and other wastes.
C-3
(5) Outfall 200 MTF Operations: Operate and maintain the newly constructed MTF to reduce mercury contamination in Y-12 surface waters. Additional use of the facility to treat other waters may be considered by DOE in the future.
(6) ETTP Site Closure, Historic Preservation, Surveillance and Maintenenance, and Environmental
Monitoring: Complete closure of ETTP as a DOE site and implement surveillance and maintenenance, and environmental monitoring responsibilities. Complete historic preservation commitments.
The scope in the PWS will be authorized by Task Orders that will be defined and individually negotiated before and/or during the Contract period of performance.
The Contractor is responsible for managing, integrating, and executing the work described in this PWS as authorized through Task Orders. The Contractor shall provide all personnel, facilities (office space, change houses, etc.), equipment, materials, services, and supplies required to complete the Contract work scope, except for the items identified as government-furnished services and information as described in
Section J, Attachment J-8, Government-Furnished Services and Information. The permanent duty station for employees and subcontractors who are permanently assigned to this Contract is located on the Oak
Ridge Reservation or in Oak Ridge, TN.
The ORR Cleanup Contract scope contains both capital and non-capital asset acquisition projects and activities. The Contractor shall be responsible for the integration and management of all projects and subprojects. The Contractor shall maximize efficient and cost-effective methods for completing the work scope. The Contractor shall be the single point of accountability for the ORR Cleanup Contract activities, safety and quality assurance programs, interface with ORNL and Y-12 site contractors, and project management in the performance of this Contract, including any subcontracts. The Contractor shall develop a regulatory approach for all work under this Contract and ensure regulatory approval is obtained for any related changes to regulatory requirements prior to their execution.
Some of the facilities included in this ORR Cleanup Contract scope may currently be the responsibility of
DOE program offices other than EM and/or other contractors, including but not limited to the facilities identified in Attachment C-1, Facility and Site List. The Contractor shall support transfer and/or accept operational responsibility for these facilities to support execution of the work. Likewise, certain facilities currently included in the Contract scope may be transferred to other DOE program offices. The
Contractor will be performing Contract scope in environments where other DOE contractors are engaged in activities that are not controlled by the Contractor’s programs and procedures (e.g., work planning and control, safety and health). The Contractor shall develop interface documents with other DOE contractors, as needed, to support transition, stipulate respective roles and responsibilities, and define services to be provided by other DOE contractors. Interfaces and roles and responsibilities are summarized in Section J, Attachment J-3, Site Services and Interface Requirements. The Contractor shall interact in such a way as to avoid or minimize impacts to the successful performance of the scope under the Contract and to programmatic site mission operations and activities.
In the performance of this Contract, the Contractor shall comply with all applicable laws, regulations, permits, and DOE Directives (including invoked Technical Standards), including but not limited to those identified in Section J, Attachment J-2, Requirements Sources and Implementing Documents. The
Contractor shall also comply with all CERCLA decision documents in effect for the ORR while conducting the authorized scope of work.
The Contractor shall support OREM in achieving its goals, as described in the DOE Office of
Environmental Management Annual Performance Agreement in effect during the period of performance.
C-4
C.1 Contract Transition
C.1.1 Incoming Transition
The contract transition period is estimated to be 90 days. The first day of the Transition Period will be the effective date of the transition task order. DOE will issue a Notice to Proceed, identifying the effective date of the transition task order. During the transition period, the Contractor shall perform those activities that are necessary to transition work from the previous ETTP contractor in a manner that: (1) ensures that all work for which the Contractor is responsible under the contract is continued without disruption; (2) provides for an orderly transfer of resources, responsibilities, and accountability from the previous contractor; and (3) provides for the ability of the Contractor to perform the work in an efficient, effective, and safe manner. Workforce transition shall be managed in accordance with the requirements of applicable Section H Contractor Human Resource Management clauses.
The Contractor shall establish the necessary logistical support (office space, computers, telephone, etc.) to execute the 90-day transition period (estimated) and shall ensure all necessary personnel, including key personnel for the Contractor, are available during the transition period, unless specifically directed otherwise by the Contracting Officer (CO). All key personnel shall be assigned full-time to their respective positions and shall meet the requirements detailed in Section H.44, Key Personnel.
The desired outcome is the readiness to assume full responsibility for OREM facilities and activities for execution of subsequent Task Orders upon direction by the CO.
As authorized by Task Order 1, the Contractor shall perform the activities necessary to declare readiness to assume responsibility for the following:
Facilities, activities and in-process work documented in Task Order 2
Incumbent contractor’s subcontracted work as deemed necessary
Workforce in accordance with the requirements of Section H of this Contract
Within 15 days after a Notice to Proceed, the Contractor shall submit a Transition Plan for DOE approval that provides sufficient detail for all transition activities, including but not limited to: a description of all necessary transition activities; a list of the organizations involved; a transition spend plan and a transition schedule, including key milestones; earned value reporting during transition; Memoranda of
Understanding (MOUs) with outside organizations; required utilities; and other transition activities such as acquisition of necessary equipment, hiring and training of personnel, and development or revisions of required plans and procedures. The Contractor is responsible for performing due diligence to ensure that all transition activities are identified and completed during the transition period (see Task
Order 1, Section J, Attachment J-7, Contract Deliverables).
The list below includes the major elements necessary for transition of the Contract, but does not include all transition requirements. The following items shall be addressed in the Transition Plan:
(a) Public Release Statement: Within 72 hours following the effective date of the Contract Transition
Task Order, the Contractor shall release on its own website a brief Executive Summary of its offer including the following elements:
(1) Name of Contractor including the identification of teaming partners and subcontractors, and a description of the experience that each party brings to the project
(2) Summary/description of Contractor’s management approach
(3) Organizational structure and identification of key personnel
C-5
(4) Contractor performance commitments
(5) Brief overview of Contractor’s work on similar projects
(6) Commitments to the community
(7) Commitments to small business subcontracting (if applicable)
(b) Implementation of Human Resources Management Requirements: The Contractor’s Transition
Plan required above shall include a description of the Contractor’s implementation of human resource management consistent with requirements as described in Section H, clauses H.4 through H.7, including:
(1) Expected workforce composition and any immediate or anticipated workforce restructuring
(2) Identification of any existing issues under the National Labor Relations Act and the Contractor’s plan for engaging with labor representatives
(3) A schedule for preparation and submission of any bargaining parameters requests
(4) Identification of any prevailing wage requirements, including requirements under Section 4(c) of the Service Contract Labor Standards statute as well as National Labor Relations Act requirements regarding determination of wages and benefits
(5) Descriptions of processes for handling labor standards determinations for work packages
(6) Definition of obligations regarding pension and post-retirement benefit plans
(7) A plan for identification and resolution of any legal issues regarding the above, including the
Contractor’s plan for engaging outside counsel as needed
(8) A plan for communicating and engaging with DOE on these matters
(c) Inter-contractor Ordering and Financial Agreements: The Contractor shall develop the inter-contractor ordering and financial agreements necessary to support transition and Contract performance, and will be responsible for the costs incurred under these agreements.
(d) Programs and Procedures: To ensure continuity of operations, the Contractor may adopt, as applicable, the incumbent contractors’ programs and procedures at the effective date of the transition task order (e.g., Documented Safety Analysis (DSA), Technical Safety Requirements (TSR), operating procedures, etc.), provided the Contractor has formally reviewed the programs and procedures to ensure compliance with contract requirements, current regulatory requirements, DOE
Orders and directives, and the Contractors’ organizational roles and responsibilities. The Contractor shall revise those programs and procedures it deems necessary, provided the programs and procedures remain in compliance with DOE requirements, and shall maintain its plans, procedures, programs, etc. in accordance with this PWS. Any Programs and Procedures that are adopted shall be updated to the new Contractor’s organization within the first year of the effective date of the contract.
(e) Status Reports – Transition Activities: The Contractor shall provide weekly status reports of transition activities to DOE. The Contractor shall establish routine status meetings with DOE and affected contractors to review transition activities and issues (see Task Order 1, Section J, Attachment
J-7, Contract Deliverables).
(f) Government-owned Property: All real and personal property currently accountable to the incumbent contractor for contract performance will be provided to the Contractor. During the transition period, an inventory record of such property in the DOE Facilities Information
C-6
Management System (FIMS) and the incumbent contractor’s personal property databases will be provided to the Contractor. Specifically, the following property acceptance requirements will be implemented:
(1) The Contractor shall perform a joint comprehensive physical inventory with the incumbent contractor of all accountable high-risk and sensitive property, as defined in CFR Title 41, Chapter
109, during the transition period, and shall accept full accountability for the high-risk and sensitive property at the end of transition.
(2) At the end of transition, the Contractor shall accept transfer of accountability for the remaining government-owned real and personal property not covered under paragraph (1), based on existing inventory records on an as-is, where-is basis, or shall perform a wall-to-wall inventory within the transition period of the Contract. At the discretion of the Contractor, a review of existing inventory records may be performed during transition. Any discrepancies with the existing inventory records shall be reported to the CO. If the physical inventory is not accomplished within the allotted time frame, the previous contractor's records will become the inventory baseline.
(3) Once the Standard Form 122, Transfer Order – Excess Personal Property, is completed and approved by the CO/Organizational Property Management Officer, the Contractor shall assume responsibility and liability for subsequent losses and damages.
(g) DOE Safeguards and Security (S&S) Survey: During the transition period and prior to assuming control and responsibility for S&S responsibilities, the Contractor shall be subject to a DOE S&S initial survey conducted in accordance with DOE Order 470.4, Safeguards and Security Program.
The results of the survey shall be documented and shall form the basis for DOE authorization to assume S&S responsibilities, in particular responsibility for special nuclear material. Following a satisfactory survey and upon CO direction, the Contractor shall assume responsibility for all applicable S&S resources, materials, facilities, documents, and equipment.
(h) Legal Management Transition: The Contractor shall ensure all legal management activities are addressed pursuant to the Section H clause Legal Management and 10 CFR Part 719.
(i) Communication of Contractor’s Approach: The Contractor shall communicate its approach and commitments for accomplishing the scope of the Contract to workers, federal staff, stakeholders, and other interested entities during the transition period.
(j) Graded Approach: The Contractor shall submit a Graded Approach for Implementation of Contract
Requirements Plan for DOE approval to streamline processes, apply a graded approach, and identify efficiencies and performance improvements (e.g., DOE directives, regulations, and others) that are critical to accomplishing the site mission. The plan shall include a review and recommendations of changes to the current site standards and implementing procedures for eliminating requirements and/or streamlining processes. The Contractor shall interface with the other site contractors on proposed changes, as necessary.
(k) Task Order Proposals: During transition, DOE will request Task Order proposals that are compliant with Federal Acquisition Regulation Subpart 15.4 (see Task Order 1, Section J, Attachment J-7, Contract Deliverables). The CO will provide direction as applicable regarding these Task Orders.
(l) Design Authority:
C-7
(1) The Contractor shall review the preliminary EMDF design with the incumbent contractor such that the Contractor assumes Design Authority responsibilities at the conclusion of the transition period.
(2) The Contractor shall review the final DOE-approved design for the Outfall 200 MTF, approved design changes, and construction progress with the incumbent contractor such that the Contractor assumes Design Authority responsibilities at the conclusion of the transition period.
(3) The Contractor shall review the design for ETTP Historic Preservation requirements per the approved Memorandum of Understanding with the incumbent contractor such that the Contractor assumes Design Authority responsibilities at the conclusion of the transition period.
(m) Declaration of Readiness: The Contractor shall submit a Declaration of Readiness to Execute the
Contract to the CO, prior to the end of transition, that indicates the Contractor’s readiness to assume responsibility for execution of the Contract upon CO direction. The Contractor shall also identify any post-transition activities that are required to be completed (e.g., notifications to outside agencies of transfer of co-operator responsibilities, completion of procedure updates).
C.1.2 Outgoing Transition and Closeout
The desired outcome is a seamless transition of full responsibility for OREM facilities and activities to a successor contractor.
As authorized by Task Order, the Contractor shall perform those activities necessary to transition the work under this Contract to a successor contractor upon contract expiration:
Cooperate with the incoming contractor to ensure all work for which the Contractor is responsible under the Contract continues without disruption in an efficient, effective, and safe manner.
Provide for an orderly transfer of resources, responsibilities, and accountability from the
Contractor.
The Contractor shall provide a plan for closeout activities at least 60 days prior to Contract expiration or when directed by the CO. The Contractor shall also cooperate with and support the successor contractor’s phase-in plan.
C.2 Post-Retirement Medical Benefits, Long-Term Disability, and Pension
Contribution
As authorized by Task Order, the Contractor shall:
Fund the post-retirement medical benefits for ORR EM workers retiring prior to April 1, 1998 in coordination with the NNSA Management and Operating (M&O) contractor at Y-12.
Manage and fund the post-retirement medical benefits for ORR EM workers retiring on or after
April 1, 1998.
Manage and fund the long-term disability program for all ORR EM workers.
In addition, the Contractor shall manage and fund the pension plan for Grandfathered Employees.
C.3 Cleanup
The desired outcome is maximized completion of end-states for excess contaminated facilities and/or remediation of environmental media at Y-12, ORNL, and ETTP in a safe, efficient, and compliant manner in accordance with approved regulatory documents and DOE Directive requirements. Completion of end-states shall maximize reduction of environmental liabilities and related risks. Desired outcomes for the
C-8 cleanup scope (listed in C.3.1, C.3.2, and C.3.3) are expressed in terms of completion of some or all of the following cleanup end states:
Characterization
The desired outcome of this end state is a characterized facility with approved documentation (e.g., data quality objectives [DQOs], sampling and analysis plans, quality assurance plan, and waste handling plan) pursuant to the FFA. The Contractor shall mobilize personnel and equipment and establish access controls. The Contractor shall ensure worker and environmental safety and health through monitoring and protection.
Characterization work includes, but is not limited to the following activities as necessary or required:
DQO preparation for the specific waste streams in accordance with U.S. Environmental
Protection Agency (EPA) QA/G-4 (EPA/600/R-96/055) guidance or equivalent as required by
DOE Order 435.1
Identifying and evaluating historical documents and conducting interviews, as necessary, to develop documentation in support of process knowledge to support sampling decisions
Presenting the DQO, including proposed sampling methods and locations, to Potential
Responsible Parties or appropriate stakeholders and obtaining agreement
Developing project-specific sampling and analysis plans and quality assurance plans to document agreed-upon sampling methods and locations (via the DQO sessions) for the specific waste streams
Preparing sampling and analysis plans in accordance with approved DQOs, EPA protocols, and approved FFA documentation
Ensuring the sampling and analysis plans describe a phased approach for collecting data to satisfy the waste acceptance criteria (WAC) of the intended disposal facility
Preparing the project-specific waste handling plan for pre-demolition and demolition waste
Collecting random and biased (as needed) physical, structural, debris, soil, and slab samples using standard EPA protocols for sample collection methodologies and analytical test methods as specified in EPA Guidance SW-846, Test Methods for Evaluating Solid Waste: Physical/
Chemical Methods
Performing surface scans and direct measurements to support radiological safety or characterization requirements as applicable
Ensuring all commitments are completed as specified in applicable EPA and FFA protocols and approved documentation
Performing a data quality assessment briefing with DOE to demonstrate that sample analytical results meet WAC for the intended disposal facility
Ensuring that sample analytical results are properly formatted to allow direct transfer into DOE data management systems such as Oak Ridge Environmental Information System (OREIS), Project Environmental Measurements System (PEMS), and others
Performing and coordinating field oversight and field technical support associated with characterization activities
Preparation for Demolition
The desired outcome of this end state is a facility ready for demolition that no longer requires regular personnel access (i.e., condemned with no further entry authorized). Preparation for demolition activities
C-9 should be conducted in accordance with standard industry practices and should include the compliant disposition of all wastes generated.
Preparation for demolition work includes, but is not limited to the following activities as necessary or required:
Mobilization of personnel and equipment and establishment of access controls
Develop and submit to DOE applicable regulatory documents in accordance with the FFA and applicable recordations and/or other mitigating actions in accordance with National Historic
Preservation Act requirements
Ongoing characterization to ensure protection of worker health and safety
Review/revise safety basis documentation as required to support activities
Worker and environment safety and health, monitoring, and protection equipment and plans
Removal of legacy material
Deactivation and isolation of utility systems
Abatement, removal, and disposition of hazardous materials (e.g., fluids, asbestos, universal wastes, and other Resource Conservation and Recovery Act [RCRA] wastes)
Stabilization of pipes, ducts, and equipment including venting, purging, and draining
Decontamination or stabilization of surface contaminants (e.g., mercury in walls may require stabilization or passive extraction prior to demolition, beryllium may be stabilized with a fixative prior to invasive work, and radioactive contamination may be managed with a fixative spray)
Removal and disposal of process equipment
Ensuring proper management and disposal of any classified information, material, equipment, or waste
Preparation of Critical Decision (CD) documentation to obtain DOE approvals as required by
DOE Order 413.3 prior to initiating demolition; the Contractor shall define a sound engineering approach to demolition and waste management in order to develop a defensible baseline and obtain funding approval.
Demolition
The desired outcome of this end state is a facility footprint cleared, stabilized, and prepared for subsequent environmental media remediation or future use. Demolition includes the disposition of all wastes generated during these activities.
The Contractor shall complete facility demolition in a safe and environmentally sound manner and in accordance with DOE and other regulatory requirements. Facility demolition activities include, but are not limited to:
Mobilization of personnel and equipment and establishment of access controls
Implementation of plans and procedures for worker and environmental safety and health, monitoring, and protective equipment
Review/revise safety basis documentation as required to support activities
Waste segregation and packaging
Hazardous and radioactive contaminant control throughout decontamination and demolition, packaging, and disposal activities
Removal and disposition of structural, non-friable asbestos (e.g., transite siding)
C-10
Preparations for decontamination, dust suppression, and stormwater runoff and containment
Preparations and protection of surrounding environmental media during building demolition
(e.g., protection of soils from releases of mercury during building demolition)
Capture, storage, and treatment of contaminated contact water (e.g., decontamination fluids,…