855378jobNN.pdf

PDF 675 KB Posted

Attached to
Job Order Contracting Services
Solicitation number
27-2170-1108
Issued by
Alexandria City, Nathalie CDP, Virginia

About this file

This Request for Proposals (RFP #27-2170-1108) is issued by the City of Newport News on behalf of a consortium of participating agencies including the City of Hampton, Hampton City Schools, York County, York County Schools, Gloucester County, and Gloucester County Public Schools to solicit Job Order Contracting (JOC) Services. The RFP seeks qualified contractors to provide construction services including minor construction, renovation, repair, replacement, alteration projects, and infrastructure work on an as-needed basis across the participating jurisdictions. Projects are limited to a maximum of $1,000,000 per project, with an aggregate annual contract value not to exceed $10,000,000. The RFP was released on November 19, 2026, with questions due by November 30, 2026, at 2:00 p.m., and proposals due on December 18, 2026, at 5:00 p.m. via the City's e-Procurement Portal. No pre-proposal conference is scheduled. The contract term commences upon execution and continues for one year with two optional one-year renewal periods at the City's discretion. The City anticipates making primary and secondary awards to the most qualified offerors. Contact information for inquiries is provided through Aretha Williams, Contract Specialist, and Japonica Wilkes, Procurement Services Specialist.

Pricing is based on a Unit Price Book (UPB), anticipated to be the current edition of RS Means Facility Construction Cost Data adjusted for the region, with contractors submitting coefficients as decimal multipliers applied to UPB line-item prices for work performed during normal hours, other than normal hours, and for items not found in the UPB. Historical spending by participating agencies over the past three fiscal years totaled approximately $8.9 million, with the City of Newport News accounting for $5.6 million. The contract replaces existing agreements with Matthews Group, Inc. and Centennial Contractors Enterprises, Inc., which expire February 16, 2027. Contractors must maintain appropriate contractor's licenses, be prepared to provide performance and labor and material payment bonds as required, and comply with Davis-Bacon Act prevailing wage requirements for federally funded projects. The contractor must maintain a field office within reasonable proximity of participating agencies, provide software access to the UPB for up to three agency employees at no additional cost, and demonstrate bonding capacity including blanket bond capability. Participation in the cooperative purchasing program is encouraged but optional. No specific set-asides for small, women-owned, or minority-owned businesses are mandated; however, the RFP encourages their participation and requests information regarding planned utilization of such firms as subcontractors.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

REQUEST FOR PROPOSALS

RFP No. 27-2170-1108

Title: JOB ORDER CONTRACTING SERVICES

Issue Date: November 19, 2026

Proposals Due: December 18, 2026 at 5:00 pm

The City of Newport News (the “City”) is seeking proposals from qualified firms (the

“Offeror” or “Contractor”) to furnish the goods and/or services described herein and proposals will be received at https://secure.procurenow.com/portal/nnva/, through the due date and hour shown above (local prevailing time).

Contracting Officer: Aretha Williams, Contract Specialist williamsas@nnva.gov

Assistant: Japonica Wilkes, Procurement Services Specialist wilkesjd@nnva.gov

Office of Purchasing

City of Newport News

2400 Washington Avenue, 4th Floor

Newport News, Virginia 23607

757-926-8721

City of Newport News

REQUEST FOR PROPOSALS

Job Order Contracting Services

I. Introduction II. Scope of Work

III. Technical Proposal Format IV. Price Proposal Format V. Evaluation Criteria

VI. Evaluation of Proposals VII. Contract Specific Terms and Conditions

VIII. Standard Terms and Conditions IX. Federal Terms and Conditions X. Insurance Requirements

XI. Vendor Questionnaire

Attachments:

A - Contract_Provisions_for_Federally_Funded_Projects

B - Draft_Contract_Services_Agreement-JOC

C - Job_Order_Contract_Services_-STANDARD_PRODUCTS_LIST

RFP #27-2170-1108 Job Order Contracting Services

1. Introduction

1.1. Summary

The City of Newport News (the “City”) is seeking proposals from qualified firms (the “Offeror” or “Contractor”) to furnish the goods and/or services described herein and proposals will be received via the City’s e-Procurement Portal, OpenGov Procurement

(https://secure.procurenow.com/portal/nnva), to be received no later than Friday, December 18, 2026 at 5:00 pm (local prevailing time).

The purpose of this Request for Proposals (RFP) is to solicit proposals to from qualified Offerors to provide Job Order Contracting (JOC) Services to the City of Newport News, City of Hampton, Hampton City Schools, York County, York County Schools, Gloucester County and Gloucester

County Public Schools hereafter referred to as Participating Agency or Agencies. References to

"City" in the Terms and Conditions shall be interpreted to include all Participating Agencies.

1.2. Background

The City of Newport News serves as the lead agency to administer a joint procurement with the defined Participating Agencies to establish an agreement for Job Order Contracting (JOC) services. This RFP will be administered and awarded in accordance with §2.2-4302.2 of the

Virginia Code. In accordance with Virginia Code, each individual project shall not exceed

$1,000,000 and the sum of all jobs performed in a one-year contract term shall not exceed the maximum threshold amount of $10,000,000.00. The Participating Agencies currently have existing Job Order Contracts with the Matthews Group, Inc. and Centennial Contractors

Enterprises, Inc. These contracts were established in 2024 and are set to expire by February 16, 2027, via the effluxion of time, hence the need for this solicitation.

Each Participating Agency will establish and administer its own contract in accordance with

§2.2-4303.2 of the Code of Virginia.

The Contract established from this Request for Proposals is an indefinite delivery/indefinite quantity type contract that would enable each Participating Agency to accomplish repair, alteration, and new construction projects with a single competitively solicited contract. JOC is based on a Unit Price Book (“UPB”) of pre-priced items. Contractors may offer a coefficient/adjustment factor or multiplier that is applied to the prices in the UPB. The

Contractor may be asked to perform a series of projects simultaneously or at different times during the course of the contract period for each Participating Agency.

The City of Newport News and other Participating Agencies anticipate that JOC projects may include but not be limited to construction services for minor construction, renovation, repair, replacement and alteration projects and various infrastructure projects located in Newport News, Hampton, York County and Gloucester County, Virginia.

The historical spend of the Participating Agencies through existing JOC Contracts over the past three fiscal years (July through June) is as follows:

Participating Agency FY 2024, 2025 &

City of Newport News $5, 628,063.71 https://secure.procurenow.com/portal/nnva

City of Hampton & Hampton Schools $2,200,000.00

York County and York County

Schools

1,114.000.00

Gloucester County and Gloucester

County Public Schools

No Projects

1.3. Timeline

Release Project Date: November 19, 2026

Question Submission Deadline: November 30, 2026, 2:00pm

Proposal Submission Deadline: December 18, 2026, 5:00pm

1.4. Contact Information

Project Contact:

Aretha Williams

Contract Specialist

2400 Washington Ave

Newport News, VA 23607

Email: williamsas@nnva.gov

Phone: (757) 926-8037

Secondary Contact:

Japonica Wilkes

Procurement Services Specialist

2400 Washington Avenue

Newport News, VA 23607

Email: wilkesjd@nnva.gov

Phone: (757) 926-8043

2. Scope of Work

2.1. Scope of Work

A. GENERAL INFORMATION: The Contractor shall provide a broad range of construction services with a maximum cost of $1,000,000.00 per project which may include minor construction, repair, renovations, alterations, and maintenance projects required by the City of Newport

News and other Participating Agencies on an 'as-needed basis'.

B. SOURCE DATA, DOCUMENTS AND PROJECT PRICING. The following documents shall be used in the execution of work under the Contract:

1. It is anticipated that the Unit Price Book (UPB) be the current edition of the RS Means

Facility Construction Cost Data, which contains pricing information for the description of work to be provided in the unit of measure specified. Other data sources or approaches to create a UPB will be considered.

2. International Building Code, the most current adopted IBC code, for all trades.

3. Any other relevant National, State, and Local laws, codes, and regulations.

4. Hampton Roads Regional Construction Standards, 6th Edition when applicable.

C. CONTRACTORS LICENSE. The Contractor shall have and maintain an appropriate Contractor's

License from the Department of Professional and Occupational Regulation. A Contractor's

License is required for each sub-contractor, as is an individual license for Contractor/sub-contractor employees when applicable.

D. PERFORMANCE AND LABOR AND MATERIAL PAYMENT BONDS. The Contractor may be required to provide Performance and Labor and Material Payment Bonds to each Participating Agency in a form and amount required by the Participating Agency in accordance with State or Local Law.

E. FEDERALLY FUNDED PROJECTS

1. During the course of the contract, projects for each Participating Agency may be federally funded.

2. Davis-Bacon Act wage requirements will apply to construction, alteration, or repair

(including painting and decorating) of public buildings or public works. The Contractor and subcontractors must pay their laborers and mechanics employed under the contract no less than the locally prevailing wages and fringe benefits for corresponding work on similar projects in the area.

3. Additional Terms and Conditions will apply to those projects as detailed in Attachment B.

F. WORK SCHEDULING, ORDERING AND PROJECT PRICING.

1. Any work required under the resulting Contract shall be initiated by issuance of a Purchase

Order from the Participating Agency unless otherwise agreed. The anticipated process shall be:

a. The designated Participating Agency will notify the Contractor of a potential project.

b. The Contractor shall respond to each request promptly and shall:

i. Visit the proposed site and/or meet with the Participating Agency’s Project Manager to define the scope of the project.

ii. The Contractor shall prepare a scope of work for the project and submit to the

Participating Agencies’ Project Manager in a timeframe agreed by the Participating

Agency and Contractor.

iii. Upon approval of the project scope of work, the Contractor shall provide a line-item proposal of the individual tasks, quantities, and costs and a proposed construction schedule.

iv. The UPB shall serve as the basis for establishing the cost of the work to be performed. The Contractor shall not adjust any prices from the UPB without approval of the Participating Agency. Unit Prices for which the market values have significantly risen in price over the UPB may be considered at the request of the

Contractor and prices from the UPB that significantly exceed market values, as determined by the Participating Agency, may be negotiated.

v. Upon receipt of the Contractor's proposal, the Participating Agencies’ Project

Manager will review the project proposal for completeness and a final determination on pricing, schedule, and all other terms, prior to issuance of a

Purchase Order.

vi. The Participating Agency will issue a Purchase Order that establishes the start date, price and schedule.

vii. The Purchase Order will serve as the Contractor’s Notice to Proceed.

viii. The Contractor shall submit the required number of shop drawings to the Project

Manager for review and approval in a manner and quantity agreed upon by the

Participating Agency.

ix. Should the Participating Agency not issue a Purchase Order after receipt of the

Contractor's proposal, the Agency shall have no obligation to reimburse the

Contractor for costs incurred in the preparation of the proposal.

x. In the event of emergency request for service, procedures will be established by each Participating Agency. The Contractor is expected to provide services on an urgent basis to the greatest extent possible.

2. The first day of performance shall be mutually agreed between the Participating Agency and

Contractor. If a date is not agreed in advance, the day after the Purchase Order shall be used.

3. Any preliminary work initiated, materials ordered or purchased before receipt of the

Purchase Order shall be at the risk and expense of the Contractor.

4. The Contractor shall diligently prosecute the Work to completion within the time set forth in the Purchase Order and approved Construction Schedule.

5. The period of performance shall include allowance for mobilization, holidays, weekends, inclement weather, and cleanup, therefore, claims for delay based on these elements will not be considered. When the Contractor determines that the work is substantially complete and ready for its intended use, the Contractor shall request an inspection by the

Participating Agency to determine the status of completion.

6. The Participating Agency will provide a list of punch-list items, when applicable. The

Contractor shall proceed promptly to complete and correct items on the punch-list.

7. The Contractor shall take all precautions to ensure that there is no damage to the project property, buildings or structures. All damage shall be repaired or replaced by the Contractor at no cost to Participating Agency.

8. When necessary, the Contractor shall be responsible for providing all necessary traffic control and traffic control materials as required for each project at no additional cost to

Participating Agencies. Proposed traffic control activities shall be submitted to the

Participating Agency for final approval.

9. The Contractor shall procure all permits and licenses pay all charges, fees and taxes and give all notices necessary and incidental for the project work except those provided by the

Participating Agency.

10. A time extension shall not be deemed a waiver by the Participating Agency to relieve the

Contractor from full responsibility for the performance of their obligations from the contract.

11. Should the Contractor be delayed by the applicable Participating Agency, more time may be added to the completion date equal to the period of such delay caused by the Agency or as otherwise agreed between the Participating Agency and the Contractor. The Contractor shall not be entitled to claim damages or extra compensation for such delay.

G. QUALITY ASSURANCE/QUALITY CONTROL PROGRAM: The Contractor shall maintain a Quality

Assurance/Quality Control Plan for each project. This plan should address all aspects of quality control including the responsibility or surveillance of work, documentation, trend analysis, corrective action and interface with Participating Agencies’ inspectors.

H. JOC PROJECT SUPPORT REQUIREMENTS:

1. It is anticipated that the Contractor will provide software/data access for each Participating

Agency to view current UPB items and prices and (upon request) provide printed versions, if available. A maximum of three (3) accounts or access by three (3) employees of each

Participating Agency shall be provided to the Unit Price Book software. This access shall be provided at no additional cost.

2. The Contractor shall not alter, append, delete or otherwise modify the programming, UPB items or prices contained in software, unless otherwise directed by the Participating

Agencies.

3. Each project proposal submitted by the Contractor shall contain a software generated list of the Unit Price Book items, quantities, extended prices, and a total proposed cost. The unit prices should be grouped such that they correspond to the activities in the Contractor’s schedule.

I. CONTRACTOR FIELD OFFICE: The Contractor shall maintain a Field Office/Office within a reasonable proximity of the Participating Agencies.

J. PARTICIPATING AGENCIES FURNISHED UTILITIES: Participating Agencies shall provide available utilities, including water and electricity and toilet facilities that are available at each site for work performed under this Contract.

K. POWER OF CONTRACTOR TO ACT IN AN EMERGENCY. The Contractor shall take necessary action in an emergency that threatens loss or injury of property and/or safety of life. The

Contractor shall notify the Participating Agency Project Manager immediately of emergency actions.

L. SUPERVISION.

1. The Contractor shall supervise and direct the Work, and shall be solely responsible for the means, methods, techniques, sequences and procedures of construction. The Contractor shall employ and maintain on each project a qualified supervisor who shall have been designated in writing by the Contractor as the Contractor's representative at the site. The supervisor shall have full authority to act on behalf of the Contractor and all communications given to the supervisor shall be the same as if mailed to the business address of the Contractor. The supervisor or a designated representative shall be present on the site at all times as required to perform adequate supervision and coordination of the work. The Contractor shall notify the Participating Agency in writing prior to any change of supervisor and receive the Participating Agencies approval for the replacement.

2. Upon notification to the Contractor, Participating Agencies reserve the right to suspend the

Work until such time as a supervisor satisfactory to the Participating Agency is assigned to the project. Project time shall not be extended for such suspension, nor shall the Contractor be entitled to any additional payment of any kind whatsoever as a result of such suspended work.

3. Any employee of the Contractor or a subcontractor who is deemed unsuitable may be removed from the job site by the Participating Agency, provided that Written Notice and just cause is given to the Contractor. Said employee shall be removed immediately upon receipt of said notice.

M. LAYOUT OF WORK: The Contractor shall lay out their work in accordance with the Project Plans and Specifications and shall be responsible for all measurements in connection with the layout of the work. The Contractor shall furnish, as part of the coefficient, all labor, stakes, templates, platforms, equipment, tools, materials, and labor required to layout any part of the work.

N. PLANS AND SPECIFICATIONS – INTERPRETATIONS:

1. The Contractor shall have a minimum of one (1) copy of the plans and specifications signed and identified by the Participating Agencies’ Project Manager and shall at all times give the

Project Manager and other representatives of the Participating Agency access to the plans and specifications.

2. Anything shown on the plans and not mentioned in the specifications or mentioned in the specifications and not shown in the plans, shall have the same effect as if shown or mentioned respectively in both.

3. In case of any conflict or inconsistency between the plans and specifications, the most stringent of the two will govern.

4. Any discrepancy between the figures and drawings shall be submitted to the Project

Manager by the Contractor. The Participating Agencies' Project Manager decision shall be conclusive.

5. The Contractor shall notify the Participating Agency of any discrepancies or omissions in the plans and specifications as soon as they are discovered.

O. The Contractor shall examine the premises and the site and compare them with any applicable drawings and specifications.

P. To the greatest extent possible, the Contractor shall employ methods or means to not disrupt work by Participating Agencies' employees.

Q. PROTECTION OF WORK AND PROPERTY:

1. The Contractor will be responsible for initiating, maintaining and supervising all safety precautions and programs in connection with each project. The Contractor shall take all necessary precautions for the safety of, and shall provide the necessary protection to prevent damage, injury or loss to all employees on the project and other persons who may be affected thereby, all the work and all materials or equipment to be incorporated therein, whether in storage on or off the site, and other property at the site or adjacent thereto, including trees, shrubs, lawns, walks, pavements, roadways, structures and utilities not designated for removal, relocation or replacement in the course of construction. The

Contractor shall provide and maintain all necessary watchmen, barricades, lights, and warning signs, and take all necessary precautions for the protection and safety of the public.

2. The Contractor shall comply with all applicable laws, ordinances, rules, regulations and orders of any Participating Agency having jurisdiction. The Contractor shall erect and maintain, as required by the conditions and progress of the Work, all necessary safeguards for safety and protection, and shall notify Participating Agencies of adjacent utilities when prosecution of the Work may affect them. The Contractor shall remedy all damage, injury or loss to any property caused, directly or indirectly, in whole or in part, by the Contractor, any subcontractor, or anyone for who acts on the Contractors behalf.

3. In accordance with generally accepted construction practices, and the requirements of

OSHA, the Contractor shall be solely and completely responsible for conditions of each project site. This requirement shall apply continuously and not be limited to normal working hours. The Contractor shall comply with Federal and State safety regulations, at the site of the project and provide such equipment and medical facilities as necessary to supply first aid service to anyone who may be injured. The Contractor shall promptly report in writing to the Participating Agency all accidents whatsoever arising out of, or in connection with, the performance of the project whether on, or adjacent to, the site and which caused death, personal injury or property damage, giving full details and statement of witnesses. In addition, if death or serious injuries or serious damages are caused, the accidents shall be reported immediately to the Participating Agency.

4. The Contractor shall detail all services to be provided for the project including work such as moving furniture and equipment in the immediate work area, replacing items to the original location, etc. If furniture and office equipment cannot be replaced in its original location, the Participating Agency will designate new locations.

R. WORKMANSHIP: The Contractor shall perform quality work and all materials shall be new, good quality and meet industry standards.

S. STANDARD PRODUCTS LIST: A standard products list desired by the City of Newport News is included as Attachment C. Products of manufacturers other than those specified, may be accepted when they are equal in strength, durability and usefulness for the purpose. Standard product lists for other Participating Agencies may differ from those provided and may be provided at the time individual agreements are established between each Participating Agency.

T. UNCOVERING WORK.

1. The Contractor shall be responsible for damage or injury to property during the prosecution of the work resulting from any act, omission, neglect, or misconduct in the method of executing the work or attributable to defective work or materials.

2. If any work has been covered or concealed without the Participating Agencies approval prior to being covered or concealed, the Participating Agency may request to see such work and it shall be exposed by the Contractor. The Contractor shall pay the cost of opening or uncovering and replacement and shall, in addition, at no cost to the Participating Agency, make the necessary corrections to bring the work into accord with the plans, specifications and drawings as applicable to the project.

3. Uncovering work shall be at the Contractor’s expense unless the Contractor has given the

Participating Agency timely notice of the Contractor’s intention to cover the same and the

Participating Agency has not acted with reasonable promptness in response to such notice.

4. If the Participating Agency considers it necessary or advisable that covered work previously approved be reinspected or tested by others, the Contractor, at the Participating Agencies request, shall uncover, expose or otherwise make available for observation, inspection or testing as the Participating Agency may require, that portion of the work in question, furnishing all necessary labor, materials, tools, and equipment. If it is found that such work is defective, the Contractor shall bear all the expenses of such uncovering, exposure, observation inspection and testing and of satisfactory reconstruction. If, however, such work is not found to be defective, the Contractor will be allowed an increase in the project price or an extension of the contract time or both directly attributable to such uncovering, exposure, observation, inspection, testing and reconstruction and an appropriate Change

Order shall be issued.

U. PROJECT SITE CLEAN UP

1. The Contractor shall at all times keep the premises and adjacent areas free from accumulations of waste material. Work in interior areas shall be reasonably clean at the end of the workday. At the completion of the work, the Contractor shall ensure all rubbish, tools and surplus materials are removed and the area shall be “Broom Clean” and ready for use.

The cost for clean-up will be included in the coefficient and will not be included as a line item in the unit price proposal.

V. WORKING HOURS

1. The Contractor shall comply fully with the U.S. Department of Labor Safety and Health

Regulation promulgated under the Occupational Safety and Health Act of 1970, as amended, and under Section 107 of the Contract Work Hours and Safety Standards Act, as amended. The Contractor shall also comply fully with the Overhead High Voltage Act as set forth in Chapter 30, Title 59.1 of the Code of Virginia; Subpart P - “Elevations, Trenching and

Shoring”, of the Virginia Occupational Safety and Health Standards for Construction

Industry; the Virginia Confined Space Standard 1910.146 of the Virginia Occupational Safety and Health Standards for General Industry; and the “Underground Utility Damage

Prevention Act” as set forth in Chapter 10.3, Title 56 of the Code of Virginia, 1950, as amended. The above listing of safety laws and regulations is for informational purposes and in no way alters or limits Contractor’s responsibility to comply with the safety laws of all

Participating Agencies having jurisdiction.

2. Normal working hours shall be 8:00 a.m. to 5:00 p.m., Monday through Friday, except that

Work shall not start any earlier than one-half hour after sunrise or continue beyond one-half hour prior to sunset. If the Contractor desires to perform Work outside the normal working hours, on holidays, or on weekends, the Contractor shall request permission, in writing, three (3) working days in advance to allow arrangements to be made.

3. The Contractor shall make reasonable efforts to avoid undue noise during the night and on weekends, including, but not limited to, fireproof covering necessary to dampen excessive noise from engines or pumps which operate before 7:00 a.m. and after 9:00 p.m., if it is necessary to work at those times. The Contractor shall designate a representative and furnish a telephone number at which the representative may be contacted at any time after working hours. This representative shall be empowered and authorized to provide such personnel and equipment as may be required to remedy emergency situations that may develop after normal working hours, or on weekends and holidays. The Contractor shall receive approval of the Participating Agency, in advance, of any work to be performed on holidays. The Participating Agency reserves the right to deny permission to work on Sundays and/or holidays without cause.

4. Holidays are as listed below for the City of Newport News (holiday schedules for

Participating Agencies may vary from those listed below and the Contractor shall verify the holiday schedule for each Participating Agency):

▪ New Years’ Day-1st day of January

▪ Dr. Martin Luther King’s Birthday-3rd Monday in January

▪ President’s Day-3rd Monday in February

▪ Memorial Day Last Monday in May

▪ Juneteenth Day-June 19

▪ Independence Day-4th day in July

▪ Labor Day-1st Monday in September

▪ Veteran’s Day-11th day of November

▪ Thanksgiving Day- 4th Thursday in November

▪ Friday after Thanksgiving Friday after 4th Thursday in November

▪ Christmas Eve-24th day of December

▪ Christmas Day-25th day of December

▪ Note: Holidays that occur on a Saturday will be observed on the preceding Friday and holidays that occur on a Sunday will be observed on the following Monday with the exception that if Christmas Eve falls on a Sunday, the Tuesday following such day shall be observed as a holiday and in the event Christmas Day falls on a

Saturday, the Thursday preceding such day shall be observed as a holiday.

3. Technical Proposal Format

3.1. Technical Proposal Format

To facilitate the analysis of proposals, Offerors are encouraged to prepare the proposal according to the instructions and in the order presented in this section. Proposals should be prepared as simply as possible with straightforward, concise descriptions to demonstrate an understanding of the project and services required. Proposals that provide innovative alternatives and creative approaches are encouraged. Any other information thought to be relevant, but not applicable to the categories below, may be provided as an appendix to the proposal.

The proposal should be organized with the following information and minimally contain the following information:

• An executive summary that provides a narrative, prepared in non-technical terms, summarizing the proposal.

• A profile that includes company/firm history, ownership, products or services offered, qualifications, financial status, etc.

• A description of the Offeror’s understanding of the requirements contained in the Scope of Work.

• The approach to be used, in detail, to meet the requirements identified in the Scope of

Work including source data to be used for the Unit Price Book (UPB).

• Include information on the Offeror’s plan and capacity to manage multiple simultaneous projects for Participating Agencies.

• Key personnel, including experience history, who will be assigned to work on the project/provide services.

• Provide the number of subcontractor resources, including certified Small Women and

Minority Owned (SWaM) businesses, by construction category and discipline.

• Explain the process to add new subcontractor resources to meet project demands.

• Provide a summary of JOC contracts completed within the last three (3) years, or currently in progress.

• Provide information on quality assurance and quality control actions and plans for JOC projects.

• Prior successes or challenges related to meeting project schedules through a JOC.

• Provide plans, actions and activities related to workplace safety and Occupational Safety and Health Administration requirements and standards.

• Provide the safety record over the past three (3) years.

• Provide a brief narrative regarding the history of change orders related to JOC services.

• Provide a typical response time and timeline when Participating Agencies request a proposal for a project (i.e. number of days from the Participating Agency request to delivery of the project proposal from the Contractor).

• Describe your availability to respond to urgent or emergency requests for service.

• Provide bonding capacity of the Offeror and the Offeror's ability to provide blanket type bonds.

Offerors should attach and submit their Technical Proposal where prompted in the "Vendor

Questionnaire" section of their submittal.

4. Price Proposal Format

4.1. Price Proposal

The Price Proposal should include the rationale the Contractor will use in computing the coefficients:

A. It is anticipated that the Offeror provide a Unit Price Book based on the most current edition of the RS Means Facilities Construction Cost Data for the region but alternate data source information to create a UPB will be considered.

B. A Coefficient should be offered to include general and administrative expenses, profit, overhead, labor, burden and contingencies and any other related expenses.

C. Offerors should explain how project costs that require prevailing wage rates will be determined and if a different Coefficient will be used.

D. Offeror should provide a Coefficient for Work during Normal Work Hours from the line- item

Total unit prices column of the current edition of the R.S. Means Facility Construction Cost Data adjusted for the region or from an alternate data source if offered. (Express as a decimal, e.g.

.82 or 1.12, rounded-off to two decimal places.)

E. Offeror should provide a Coefficient for Work Performed during Other Than Normal Hours.

Contractor will provide construction services, when directed by Participating Agencies, during times other than Normal for the line-item Total unit prices in the current edition of the R.S.

Means Facility Construction Cost Data, adjusted for region or from an alternate data source if offered. (Express as a decimal, e.g. .82 or 1.12, rounded-off to two decimal places. It is assumed that only a small portion of services will be provided during Other Than Normal Hours.)

F. Offeror should provide a Coefficient for any Work that is not found in the Unit Price Book as well as an explanation of how unit prices will be determined.

Offerors should attach and submit their Price Proposal where prompted in the "Vendor

Questionnaire" section of their submittal.

5. Evaluation Criteria

Each proposal will be evaluated according to the following criteria. The criteria are listed in order of importance

No. Evaluation Criteria Scoring Method Weight (Points)

1. The demonstrated understanding and approach to provide Job Order

Contract Services to Participating

Agencies.

N/A N/A

2. Successful experience and capabilities of the firm providing Job Order

Contract services.

N/A N/A

3. Experience and demonstrated knowledge of key personnel.

N/A N/A

4. Price/Coefficient N/A N/A

5. Quality Assurance Action Plan and

Safety History N/A N/A

6. Completeness of Proposal. N/A N/A

6. Evaluation of Proposals

6.1. Evaluation of Proposals

Proposals will be evaluated according to the established evaluation criteria identified herein. The

City will select two (2) or more Offeror proposals that are deemed to be fully qualified and best suited to provide the required services contained in the Scope of Work. The City may initiate discussions/interviews and may conduct negotiations with each of the selected Offerors. During negotiations, proposals may be revised by the Offeror and the City may obtain best and final offers. Once negotiations are completed, the City may again make a determination as to whether the Offeror has the capability, integrity and reliability to provide the required services.

Only proposals from responsible Offerors that are seen as reasonably susceptible of being selected for award, based on information contained in the proposal, will be evaluated by the City.

Should the City determine that only one Offeror is fully qualified or that one Offeror is clearly more highly qualified than others, a contract may be negotiated and subsequently awarded to that

Offeror if the City finds that such a selection is in the best interest of the City.

7. Contract Specific Terms and Conditions

7.1. Questions

Questions regarding this Request for Proposals (RFP) must be submitted in writing through the

OpenGov Procurement Question/Answer Tab via the City's e-Procurement portal, on or before, Monday, November 30, 2026 by 2:00 pm. Please include the section title for each question, if applicable, in order to ensure that questions asked are responded to correctly. All questions submitted and answers provided shall be electronically distributed to bidders following this solicitation on the City's e-Procurement Portal received prior to the date and time as provided for in this solicitation.

7.2. Pre-Proposal Conference

There is not a pre-proposal conference scheduled for this project.

7.3. Contractor Qualifications

Firms shall have the capability in all respects to fully perform the services or provide the goods specified and have the experience necessary to assure good faith performance of the contract.

The firm shall have experience provide JOC services.

7.4. Method of Award

The City will make a Primary and Secondary Award to the responsible Offeror(s) who has made the best proposal and determined to be most advantageous to the City by taking into consideration price and the evaluation criteria identified herein.

7.5. Assignment of Work/Ordering

The Contractor will be issued a Purchase Order for individual task order or project under this contract and shall provide the services requested in the established timeframes.

7.6. Contract/Agreement

Following award, a contract will be executed between the Contractor and the City. A sample contract is included in this Request for Proposals. Do not return the sample contract with the proposal; it is provided for informational purposes only.

7.7. Contract Modifications

Any modifications made to the contract must be approved by the Office of Purchasing in advance. The City and the Contractor must mutually agree to modify the terms, conditions, scope or prices/costs contained in the contract before modifications are implemented.

7.8. Contract Period/Renewal

The contract term shall commence on the date written is executed and shall continue for one year with options to renew at the City's sole discretion, for two (2) additional one-year periods.

7.9. Method of Ordering

Receipt of a Purchase Order constitutes the authorization to provide the goods or services specified on the order.

7.10. Invoicing and Payment

Participating Agencies may make progress payments on a monthly basis or at more frequent intervals as determined by the Participating Agency. The Contractor shall furnish a breakdown of the work completed. Participating Agencies’ may authorize payment for material delivered on the site if the Contractor provides evidence that material title/ownership has been acquired.

For projects of less than 30 days, payment shall be made after completion of and acceptance of the work by the Participating Agency.

Payment will be authorized following receipt of a valid invoice which must minimally include the Purchase Order Number, Purchase Order Line Item Number(s), Contract number (if provided by the City), Description of Goods and Services, Delivery Date(s) of Goods or Services, Unit

Prices and Total Price.

Participating Agencies may, at their discretion, retain five percent (5%) of the estimated amount until final completion and acceptance of the Work to ensure good faith performance of the

Contractor.

The Contractor shall pay subcontractors within seven (7) days or less after receiving payment from the applicable Participating Agency.

The Contractor may be required to use the City of Newport News Project and Contract

Management System (Projectmates) to electronically submit invoices, change orders, and complete subcontractor reporting.

Participating Agencies are exempt from payment of any and all Sales Tax. A certificate of exemption and exemption number will be furnished to the Contractor. Contractor’s proposals should not contain assessment of any of these taxes. Contractor’s proposal shall also not include any mark-up for material or equipment beyond the unit price in the Unit Price Book.

7.11. Equipment

Any equipment delivered must be standard new and unused equipment, latest model, except as otherwise specifically stated in the proposal. Where any part or the normal accessories of equipment is not described, it shall be understood that all the equipment and accessories that are usually provided in the manufacturer’s stock model shall be furnished.

7.12. Product Availability and Substitution

Substitution of a product, brand or manufacturer after the award of contract is expressly prohibited unless approved in writing by the Office of Purchasing. The City may require, at its discretion, the Contractor provide a substitute item of equivalent or better quality subject to the approval for a price no greater than the contract price, if the product for which the contract was awarded becomes unavailable to the Contractor.

7.13. Substitutions/Alternates

A. Unless qualified by the provision "NO SUBSTITUTE", the use of the name of the manufacturer, brand make or catalog designation in specifying an item does not restrict Offerors to the manufacturer, brand, make or catalog designation identification. This is used simply to indicate the character, quality and/or performance equivalence of the goods and/or services desired.

The goods and/or services on which proposals are submitted must be of such character, quality and/or performance equivalence that it will serve as that specified. In submitting proposals on goods and/or services other than as specified, Offeror shall furnish complete data and identification with respect to the alternate goods and/or services they propose to furnish.

B. Consideration will be given to proposals submitted on alternate goods and/or services to the extent that such action is deemed to serve the best interests of the City. If the Offeror does not indicate that the goods and/or services he proposes to furnish are other than specified, it will be construed to mean that the Offeror proposes to furnish the exact goods and/or services described.

7.14. Insurance

The Contractor shall maintain adequate liability insurance, which shall protect and save harmless the City of Newport News, Virginia, and its officials from all suits and actions of every kind and description arising from injury or damage to persons and property in the prosecution of said work or in failure to properly safeguard same, and from all claims arising under the workmen's compensation laws. Following award of the contract, the Contractor shall furnish proof of said insurance prior to commencement of services.

Prior to submitting a proposal, ensure that your firm fully understands the City’s insurance requirements, your carrier is properly rated and that your carrier can provide the required insurance and endorsements.

Contractor shall have seven (7) days from the date of the City’s request to provide insurance certificates and endorsements. Failure to provide the certificates and endorsements within this timeframe may be cause for the City to rescind award of a contract and hold the original

Bidder/Offeror liable for excess costs.

Insurance requirements are specified herein in Section titled Insurance Requirements.

7.15. Warranty

The Contractor shall warrant and guarantee to the Partcipating Agency that all work is in accordance with the project requirements and is not defective. Prompt notice of all defects shall be given to the Contractor. The Contractor shall promptly correct all defective work performed and replace defective materials or items found deficient during the final inspection, in a manner satisfactory and at no additional cost to the Participating Agency for a period of one (1) year following the date of final completion of the specific project; provided, however, if the local ordinances or code regarding warranties and guarantees, or if any provision in the local ordinances or code regarding the timing of performance or defect bonds conflicts with such one

(1) year period, the local ordinance or code shall control. This warranty and guarantee shall not operate as a waiver of any of the rights and remedies of the Participating Agency for default under or breach of the agreement which rights and remedies may be exercised at any time within the period of any applicable statute of limitations.

Where defective work (and damage to other work resulting therefrom) has been corrected, removed or replaced, the correction period hereunder with respect to such work will be extended for an additional period of one (1) year after such corrections or removal and replacement has been satisfactorily completed. Repetitive malfunction of an equipment or product item shall be cause for replacement and an extension of the correction period to a date one (1) year following acceptable replacement. A repetitive malfunction shall be defined as the third failure of an equipment or product item following original acceptance.

If the Contractor does not promptly correct the defective work or replace defective materials, the

Participating Agency may have the defective work corrected or the rejected work removed and replaced, and all costs of such removal and replacement shall be paid by the Contractor.

https://secure.procurenow.com/portal/nnva/projects/326567/document?section=undefined

Certain equipment or items for each project may be required to be warranted for periods longer than one year.

7.16. Examination of Conditions

Each Offeror shall fully investigate site conditions and determine work conditions and take necessary measures to ensure a complete understanding of the specifications and work requirements. Failure to become familiar with the site conditions or work conditions will not relieve the Contractor from furnishing all materials or performing the work in accordance with the Specifications or Scope of Work.

7.17. Scheduling and Delays

The parties to a contract resulting from this RFP acknowledge that all or part of the work to be performed hereunder may be delayed and extended at the option of the City. Such delays may be caused by delays, denials and modifications of the various state or federal permits, or for other reasons. The City shall not be required to pay any of the Contractor’s direct or indirect costs, or claims for compensation, extended overhead, or other damage or consequential damages arising out of or related to any delays or interruptions required or ordered by the City. If the City delays the project for any reason for a continuous period of ninety (90) days or more, the City and

Contractor will negotiate a mutually agreeable adjustment to the Contractor’s award amount.

7.18. Continuity of Services

The services rendered in the contract resulting from this RFP are vital to City and must be continued without interruption. At contract expiration, the Contractor shall provide best efforts and cooperation to facilitate an efficient and effective transition to a successor, whether City or other Contractor at no additional cost to the City.

8. Standard Terms and Conditions

8.1. Pre-Proposal and Proposal Submission Requirements

A. Direct contact with anyone other than the City of Newport News Office of Purchasing, including other City departments or the City’s consultants, regarding this Request for Proposals (also referred to “solicitation” herein) is expressly forbidden. Violation of this directive may result in a determination that the Offeror is ineligible for award.

B. All proposals shall be submitted sealed via the City’s e-Procurement Portal, OpenGov

Procurement. Fax and Email transmittals will not be considered. Proposals cannot be submitted after the due date and time noted above. Failure to return required documents and information specified herein may result in a determination that the proposal will not be considered for award.

C. All costs associated with preparing a proposal, including any mailing costs, are the Offeror’s responsibility.

D. All proposals must be submitted by an officer or employee having the authority to sign on behalf of the firm.

E. Prices shall be stated in units of quantity specified. No additional charges shall be passed on to the City, including sales tax, delivery charges or other surcharges. Prices quoted shall be the final cost to the City. All deliveries shall be F.O.B. Destination.

F. The Terms, Conditions and Specifications in this Request for Proposals shall supersede any terms and conditions offered. Any additional conditions an Offeror intends to be considered should be submitted with the proposal. Exceptions may result in a determination that a proposal will not be considered for award . All Terms, Conditions and Specifications will be incorporated by reference and be part of the contract following award.

G. Failure to provide a proposal from an authorized representative shall be cause for rejection of the proposal.

H. Failure to use the forms provided may be cause for rejection of the proposal.

I. The viability and accessibility of the Offeror’s submitted attachments is entirely the responsibility of the Offeror. Attachments that are not accessible cannot be considered during the review and evaluation of the proposal, which may result in that proposal being determined non-responsive and not being further considered for award.

J. Submission of a proposal is not to be construed as an award or an order to ship.

K. A proposal by the Offeror certifies that they are not currently debarred or suspended by a local, state or federal government entity from doing business with that entity. If a debarment or suspension exists, supporting information shall be provided with the proposal. Suspension or debarment may disqualify the Offeror from award of a contract.

8.2. Addenda

Changes or supplemental instructions to this Request for Proposals will be posted online with this solicitation. It is the Offeror's responsibility to check for addenda prior to the proposal due date and time to ensure that all Addenda are received. Addenda shall be posted on the City's e-

Procurement Portal, OpenGov Procurement and Addenda notifications will be sent via email to all persons on record who are following this RFP on OpenGov Procurement.

All Bidders shall acknowledge receipt of Addenda with the proposal. Acknowledgement of all

Addenda shall be completed in OpenGov Procurement. If all Addenda are not acknowledged, the proposal may be deemed non-responsive.

8.3. Award

A. Award shall be made to the responsible Offeror whose proposal is determined in writing to be the most advantageous and provides the best value to the City, taking into consideration the evaluation factors set forth in this Request for Proposals. When the terms and conditions for multiple awards are provided in the Request for Proposals, awards may be made to more than one (1) Offeror.

B. The City may request additional information and make reasonable investigations as deemed proper and necessary to determine the ability of the Offeror to perform the services/furnish the goods and the Offeror shall provide the City information and data for this purpose. The City may inspect physical facilities if deemed necessary. In addition, the City reserves the right to conduct any test/inspection deemed necessary to assure goods and services conform to the specifications or Scope of Work.

C. An Offeror may protest the award or decision to award by submitting such protest in writing to the Purchasing Agent no later than ten (10) days after the award or the announcement of the decision to award as indicated in the Code of the City of Newport News Section 2-576.3. No protest shall lie for a claim that the selected Offeror is not a responsible Offeror. The written protest shall include the basis for the protest and the relief sought. The Purchasing Agent shall issue a decision in writing within ten (10) business days stating the reasons for the action taken.

This decision shall be final unless the Offeror appeals within ten (10) days of the written decision by invoking the administrative procedures established by the Purchasing Agent.

D. The Administrative Appeals Procedure is posted on the Office of Purchasing website https://www.nnva.gov/707/Vendor-Resources. This procedure shall be used for hearing protests of a decision to award or an award, appeals from refusal to allow withdrawal of bids, appeals from disqualification, appeals for debarment or suspension, or determinations of non-responsibility and appeals from decision or disputes arising during the performance of a contract.

8.4. Public Inspection of Records

All proceedings, records, contracts and other public records relating to procurement transactions shall be open to the inspection of any citizen, or any interested person, firm or corporation, in accordance with the Virginia Freedom of Information Act (§ 2.2-3700 et seq., Code of Virginia, 1950, as amended).

As indicated in the Code of the City of Newport News Section 2-557.2, any Offeror, upon request, shall be afforded the opportunity to inspect proposal records within a reasonable time after the evaluation and negotiations of proposals are completed but prior to award, except in the event that the…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .