About this file
This is a Request for Proposals (RFP) issued by Russell County, Virginia, seeking architectural and engineering services for the Three Rivers Destination Center, a regional tourism and education facility planned near St. Paul in Russell County along the Clinch River. The project will serve eight jurisdictions—Buchanan, Dickenson, Lee, Russell, Scott, Tazewell, and Wise counties and the City of Norton—and will function as headquarters for the Heart of Appalachia Tourism Authority, a visitor information center supporting regional recreation amenities including Clinch River State Park, and an ecology discovery center interpreting three regional watersheds. The proposed facility comprises approximately 6,372 square feet with single-story design and limited loft space, including a lobby, regional visitor information areas, hands-on interpretive exhibits, gift shop, classroom, conference room, offices, and outdoor terrace. The RFP was issued November 14, 2026, with proposals due December 14, 2026, at 12:00 p.m. Eastern Time, submitted to Lonzo Lester, County Administrator, at Russell County Board of Supervisors, 137 Highland Drive, Suite A, Lebanon, VA 24266, or electronically to lonzo.lester@russellcountyva.us. The procurement schedule indicates committee review from December 16, 2026, through January 5, 2027, with interviews on January 11, 2027, anticipated selection on January 12, 2027, and an anticipated notice to proceed of February 1, 2027. The selected firm will be responsible for coordinated architectural, engineering, landscape architecture, surveying, and other professional services including prior work review, site investigation, programming, design development, construction documents, permitting assistance, bidding support, and construction administration through closeout.
The RFP specifies selection based on qualifications using a numerical scoring system with evaluation factors including comparable project experience (20 points), project understanding and response to regional mission (20 points), team qualifications (20 points), design and coordination approach (15 points), staff availability and schedule (10 points), grant experience (10 points), and client references (5 points), with a total of 100 points. Price is not a selection factor; instead, the Owner will negotiate fair and reasonable compensation with the highest-ranked firm following the qualifications-based selection method under federal procurement standards. The project is partially funded by the Appalachian Regional Commission (ARC) Area Development grant for design and site preparation and an ARC POWER grant for construction, making it subject to 2 CFR Part 200 (Uniform Guidance) requirements, including documented procurement procedures, debarment certifications, labor standards where applicable, and audit compliance. The selected firm must comply with federal, state, and local requirements and maintain Virginia professional licenses and registrations. Minority-owned and women-owned firms are encouraged to respond. The agreement will feature a guaranteed maximum price structure and will address professional standard of care, insurance, indemnification, suspension, termination, and dispute resolution. The Owner will make prior project materials available, including ARC applications, POWER application PW-1933, and existing studies, surveys, and reports, accessible by written request following selection.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Three Rivers Destination Center | 1
Three Rivers Destination Center
Russell County, Virginia
Request for Proposals for
Architectural & Engineering Services
Issued by: Russell County, Virginia
RFP Release Date: November 14, 2026
Deadline for Proposals: December 14,2026
Three Rivers Destination Center
Three Rivers Destination Center | 2
Request for Proposals for Architectural & Engineering Services
St. Paul area of Russell County Virginia
Solicitation information Details
Issued by County of Russell Virginia
RFP number and issue date RFP #VA20362 | November 14, 2026
Proposals due December 14, 2026 at 12:00 p.m. Eastern Time
Procurement contact
Lonzo Lester, County Administrator
Delivery address Attn: Lonzo Lester
Russell County Board of Supervisors
137 Highland Drive, Suite A
Lebanon, VA 24266
Electronic submission lonzo.lester@russellcountyva.us
RFP and addenda location https://www.russellcountyva.us/
I. Project Introduction
County of Russell Virginia, referred to as the Owner, requests qualifications and technical proposals from architectural and engineering firms to provide coordinated professional services for the Three
Rivers Destination Center. Services include review of previous work, program confirmation, building and site design, permitting assistance, bidding assistance, construction administration, periodic construction observation, and closeout.
The Owner intends to select one prime firm responsible for coordinating all site preparation/development and vertical build requirements for the authorized scope, including architectural, engineering, landscape architecture, surveying, and other professional disciplines.
Selection will be based on qualifications.
Minority-owned and women-owned firms are encouraged to respond. The Owner is an equal opportunity provider and employer. Award is subject to successful negotiations, available funding, and required approvals.
This project is partially federally funded and subject to applicable requirements.
Three Rivers Destination Center | 3
II. Project background and objectives
The Three Rivers Destination Center is planned as a regional hub for tourism, outdoor recreation, and environmental education near St. Paul in Russell County, along the Clinch River. The project will serve Buchanan, Dickenson, Lee, Russell, Scott, Tazewell, and Wise counties and the City of Norton, while connecting residents and visitors with regional businesses, attractions, and town centers.
The project combines three principal functions: headquarters for the Heart of Appalachia Tourism
Authority; visitor information and services supporting regional recreation amenities, including Clinch
River State Park; and an ecology discovery center interpreting the Clinch, Powell, and Big Sandy watersheds. Russell County is identified as the facility owner. The Owner will coordinate decisions with the Town of St. Paul, and the Project Management Team.
Building Program
The planning program for a 6,372 Square foot space, includes a lobby and reception desk; regional visitor information, reservation and permit service areas; hands-on interpretive exhibits; a gift shop; a classroom and conference room with kitchenette; public restrooms; offices; storage and building support spaces; and an outdoor terrace or deck. The selected firm shall confirm the room program, operational needs, staffing, circulation, and accessibility with the Owner and intended users.
This building will be a predominantly single-story facility with limited loft space and an outdoor terrace. The selected firm shall reconcile enclosed building area, loft area, and exterior deck area before establishing the final program.
Site and design objectives
Provide safe, welcoming public access; durable and maintainable facilities; appropriate visitor and school-group circulation; and educational connections between indoor exhibits and the riverfront landscape. Coordinate parking, sidewalks, accessible routes, utilities, stormwater management, native landscaping, and outdoor learning opportunities. Evaluate energy efficiency and the sustainable features identified in the applications within the approved budget.
Funding and project controls
This project is partially funded by Appalachian Regional Commission Area Development grant support for design and site preparation and Appalachian Regional Commission POWER grant support for construction. Current grant agreements, amendments, eligible costs, funding balances, and deadlines will govern the work. Upon award, the Agreement for Architectural and Engineering
Services, featuring a guaranteed maximum price, will be submitted for approval by Russell County.
III. Scope of services
a. Project Initiation and prior work review
The awarded firm will meet with the Owner and Project Management Team to establish responsibilities, communications, review procedures, schedule, and decision milestones. Review available grant documents, previously designed conceptual plans, surveys, geotechnical reports, engineering work, utility coordination, permits, and cost estimates. Identify work that can be used, work requiring verification or revision, and missing investigations. Submit a written findings memorandum and a coordinated work plan before proceeding with design.
Three Rivers Destination Center | 4
Prior design and environmental review work was performed by Virginia Tech Community Design
Assistance Center, Dialogue + Design Associates, Cardno, Wallace and Company, and Lighthouse
Engineering Consultants. These references do not establish the present completion status or confer an award under this solicitation. The Owner will identify available documents, existing agreements, and rights to use prior work. No duplication of previously completed services is authorized without written approval.
b. Site investigation and due diligence
The selected firm will confirm property boundaries, topography, easements, rights-of-way, utility locations, access, and survey needs. Review the former runaway truck ramp and filled-site conditions. Evaluate existing subsurface information and recommend supplemental borings, testing, and foundation studies where needed. Coordinate field work and utility locating with the
Owner and affected providers.
Evaluate floodplain and drainage constraints, riverbank conditions, potential wetlands and regulated waters, and environmental or cultural-resource review needs. Identify permitting agencies, required approvals, consultant responsibilities, and information needed from the Owner.
Provide survey and geotechnical services through qualified team members when included in the negotiated scope; distinguish these from independent construction materials testing and special inspections.
c. Programming and schematic design
The selected firm will confirm space requirements, adjacencies, exhibit goals, building systems, security, information technology, service access, and operating and maintenance needs. Conduct coordinated workshops with the Project Management Team and appropriate education, tourism, and conservation partners. Develop and evaluate schematic building and site options, then prepare the selected concept, outline specifications, preliminary code analysis, and an opinion of probable construction cost.
d. Design development and construction documents
The selected firm will provide integrated architectural, interior, structural, mechanical, electrical, plumbing, civil, and landscape design. Address applicable building, fire, energy, and accessibility requirements; emergency egress; accessible public and staff facilities; and maintainable building systems. Advance the approved design through design development and coordinated construction documents suitable for permitting and competitive bidding. Provide sealed documents by professionals authorized to practice in Virginia, as required.
e. Site and landscape design
The selected firm will design site layout, grading, drainage, stormwater management, erosion and sediment controls, water and sewer connections, electrical and communications service, parking, sidewalks, accessible routes, exterior lighting, signage locations, and related improvements.
Coordinate access and utility work with the Town of St. Paul, Russell County, VDOT, and affected utility providers. Establish clear design and construction interfaces for any work performed by the
County or others.
Evaluate the application concepts for permeable pavement, conservation landscaping, a rain garden, riverbank or living shoreline treatments, and seasonal native plantings supporting birds and pollinators. Confirm feasibility, permitting, maintenance, cost, and environmental suitability before
Three Rivers Destination Center | 5 including these features in the approved design. Any off-site work requires specific written authorization.
f. Interpretive planning and exhibit design
The selected firm will develop an interpretive framework and exhibit layout addressing regional biodiversity, watershed ecology, conservation, natural history, and recreation. Coordinate accessible hands-on learning for students and other visitors with indoor and outdoor educational spaces. Consult the Owner and subject matter partners on content, interpretive objectives, and operational requirements.
Integrate exhibit loads, power, lighting, data, plumbing, ventilation, humidity control, structural support, and maintenance access into the building design. If live aquatic displays are approved, identify life support requirements, animal care responsibilities, and operating costs before design authorization. Provide exhibit design documents and cost estimates within the negotiated scope.
Exhibit fabrication, installation, live specimens, and specialist operations are separate procurements unless expressly included in the executed agreement.
g. Sustainability and cost management
The selected firm will evaluate solar readiness or photovoltaic installation, green walls, energy and water efficiency, and sustainable materials identified in the applications. Recommend practical measures based on lifecycle cost, maintainability, funding eligibility, and the approved budget.
Proprietary products identified in prior materials are conceptual references; develop competitive specifications consistent with applicable procurement requirements.
Provide updated opinions of probable construction cost at schematic design, design development, and pre-bid completion. Identify assumptions, escalation, contingencies, site costs, exhibit costs, and exclusions. Reconcile each estimate with the authorized budget, identify funding gaps promptly, and recommend scope adjustments or bid alternates for Owner approval before advancing.
h. Permitting and agency coordination
The selected firm will prepare and submit design related permit applications as assigned in the agreement, respond to review comments, and track approvals. Assist the Owner with documentation required by ARC, DHCD, and other funding agencies. Do not authorize construction or other activities requiring environmental clearance before the Owner confirms the necessary approvals.
i. Bidding and contracting assistance
The selected firm will prepare the technical bidding package, bid forms and alternates in coordination with Owner-provided procurement and grant requirements. Assist with the pre-bid meeting and site visit, respond to technical questions through written addenda, evaluate bids for technical responsiveness, check qualifications as requested, and recommend award. Assist with redesign or rebidding if needed under the negotiated agreement.
j. Construction administration and observation
The selected firm will attend the preconstruction conference and scheduled progress meetings.
Review submittals and shop drawings, respond to requests for information, prepare clarifications, Three Rivers Destination Center | 6 review proposed substitutions and change orders, evaluate payment applications, and monitor the construction schedule. Maintain records of design decisions, field observations, and outstanding issues. Obtain Owner approval before authorizing scope or cost changes.
Provide periodic site visits by the architect and relevant engineering disciplines at intervals appropriate to the work, with written reports of observed progress, deviations, and recommended action. The agreement shall establish visit frequency and discipline coverage. Periodic observation is not continuous inspection and does not transfer responsibility for construction means, methods, or site safety from the contractor.
Identify required special inspections, materials testing, system startup, and commissioning activities. Coordinate with independent testing and inspection providers retained as specified in the agreement; do not assume those services are included in periodic observation. Assist with resolution of nonconforming work and provide technical information supporting applicable grant compliance reviews.
k. Completion and closeout
The selected firm will perform substantial completion and final completion reviews, prepare and verify punch lists, review closeout submittals, and assist with final payment recommendations.
Compile warranties, operation and maintenance manuals, equipment training records, permit signoffs, and record drawings based on contractor provided information. Coordinate required testing and systems demonstrations. Provide a warranty review before the end of the agreed correction period if included in the contract.
IV. Deliverables and schedule
Deliverables shall include the findings memorandum and work plan; confirmed program and area schedule; schematic and design development packages; cost estimates; coordinated permit and bid documents; review responses and addenda; construction administration records; field reports; and closeout materials. Provide searchable PDFs and editable source files in formats agreed with the
Owner, including drawings, specifications, and schedules. Identify any third-party licensing limits before execution of the agreement.
The proposal shall include a task sequence and durations measured from notice to proceed, with Owner review periods, agency review assumptions, bidding, construction administration, and closeout.
Following award, the selected firm will establish the baseline schedule and provide monthly progress updates during monthly Project Management Team Meetings. Proceed beyond each design phase only after written Owner approval. Later phases may be authorized separately based on funding and approvals.
Three Rivers Destination Center | 7
V. Proposal requirements and submission
Submit a concise, clearly organized proposal addressing the evaluation factors in Section VI. Use the following order.
● Letter of interest signed by an authorized representative, identifying the prime firm, principal contact, and commitment to the project.
● Firm and team qualifications, including legal business name, office locations, team organization, Virginia professional licenses and registrations as applicable, and proposed subconsultants and their responsibilities.
● Relevant project experience with visitor centers, discovery or education facilities, public buildings, riverfront sites, exhibits, sustainable design, and federally funded work. Describe each project’s scope, your team’s role, completion date, construction budget and final cost, and lessons relevant to this project.
● Resumes of the proposed project manager, lead architect, engineering discipline leads, landscape architect, exhibit or interpretive specialist, and other key personnel. State who will perform each task and how continuity will be maintained.
● Project understanding and approach, addressing the regional purpose, prior work review, site constraints, exhibit integration, accessibility, budget management, permitting, and coordination with the Owner and partners.
● Capacity and schedule, including current and anticipated workload, staff availability, task durations, review milestones, and ability to attend meetings and provide timely site observation.
● Grant experience, including Appalachian Regional Commission (ARC), Department of Housing and Community Development (DHCD), and comparable public funding programs. Explain familiarity with documentation and construction procurement requirements relevant to the work.
● At least three client references for comparable work, with project description, contact name, telephone number, and email address.
● Disclosure of actual or potential conflicts of interest, prior involvement in the project, and relationships that could affect impartial performance. Acknowledge receipt of each addendum.
● Proposed timeline for completion of design documents, ready for construction.
Submission instructions
Submit [6] printed copies by mail or hand delivery to Lonzo Lester at Russell County Board of
Supervisors, 137 Highland Drive, Suite A, Lebanon, VA 24266, and an electronic proposal in PDF format to lonzo.lester@russellcountyva.us. Electronic submission is an alternative to physical delivery;
both are not required. Label the submission “Three Rivers Destination Center Architectural and
Engineering Services” and include the RFP number VA20362. Deliver to the address and authorized electronic destination on page 1 by the stated deadline, 12:00 p.m., December 14, 2026. Receipt, rather than postmark or transmission initiation, determines timeliness. Late proposals will not be considered.
The proposer is responsible for confirming delivery.
Questions and addenda
Send written questions only to the procurement contact, Lonzo Lester, by December 1, 2026. Answers affecting the solicitation will be issued by addendum at the posting location on page 1. Oral statements do not amend the RFP. Proposers shall monitor and acknowledge all addenda.
Three Rivers Destination Center | 8
VI. Evaluation and selection
A Selection Committee will review responsive proposals using the following numerical scoring system. Each evaluator will score proposals independently; scores will then be compiled for committee review. The same published factors will guide discussions and final ranking. Price will not be a selection factor.
Evaluation factor Points
Comparable building and site project experience 20
Project understanding and response to the regional mission and site constraints
Qualifications of the project manager and assigned multidisciplinary team
Proposed approach to design, coordination, cost control, and construction administration
Staff availability, current and projected workload, and proposed schedule
Experience with ARC, DHCD, and comparable grant requirements
Client references and demonstrated performance 5
Total 100
The capacity review will consider the team’s ability to provide timely meetings, site visits, and responses. Office proximity alone will not receive separate points.
Discussions and final ranking
The Selection Committee will invite two or more firms deemed fully qualified, responsible, and suitable to participate in individual discussions or interviews, unless a documented exception under applicable procurement requirements is justified. Firms may be asked to elaborate on qualifications, staffing, methods, and project concepts. After discussions and reference review, the Committee will rank the most qualified firms in order of preference.
Negotiation and award
The Owner will begin negotiations with the highest-ranked firm to establish detailed scope, deliverables, schedule, responsibilities, and fair and reasonable compensation. If agreement cannot be reached, the Owner will formally terminate those negotiations and proceed to the next ranked firm.
The Owner may cancel or readvertise the solicitation if negotiations do not result in an acceptable agreement. No work is authorized until the agreement is executed and a written notice to proceed is issued.
Three Rivers Destination Center | 9
Procurement schedule
● Issue date: November 14, 2026
● Questions due: December 1, 2026
● Final addendum target: December 8, 2026
● Proposals due: December 14 and 12:00 p.m. Eastern Time
● Committee review: December 16, 2026 – January 5, 2027
● Interviews: January 11, 2027
● Anticipated selection: January 12, 2027
● Contract Negotiation to begin: January 12, 2027
● Anticipated notice to proceed: February 1, 2027
The Owner may revise the schedule by written notice or addendum as appropriate.
VII. Federal grant requirements and Uniform Guidance
Title 2 of the Code of Federal Regulations Part 200, known as the Uniform Guidance, is the government-wide framework established by the Office of Management and Budget for federal grants and financial assistance. Its full title is Uniform Administrative Requirements, Cost Principles, and
Audit Requirements for Federal Awards. Appalachian Regional Commission grants are federal grants.
Appalachian Regional Commission (ARC) grantees and subrecipients must comply with the applicable requirements of 2 CFR Part 200, together with ARC award conditions and applicable pass-through requirements.
The version and provisions applicable to this project shall be determined from the controlling awards and amendments and agency implementation requirements. The selected firm shall comply with requirements applicable to its work and with required provisions incorporated into its contract and subcontracts. Retaining an A/E firm does not transfer the grantee’s responsibility for federal award administration or audit compliance to that firm.
Procurement and negotiation
The Owner shall apply the applicable procurement standards in 2 CFR 200.317 through 200.327, including documented procedures, oversight, conflicts-of-interest controls, competition, procurement records, and required cost or price analysis. The A/E qualifications-based method described in 2 CFR
200.320(b)(2)(iv) permits selection of the most qualified firm followed by negotiation of fair and reasonable compensation. It does not extend to unrelated services merely because they are offered by an A/E firm. Separately procured fabrication, equipment, or construction shall use the appropriate procurement method.
Required contract provisions
Under 2 CFR 200.327 and Appendix II to Part 200, the contract shall contain the provisions applicable to its type, value, and funding. These may address remedies and termination; debarment and suspension; lobbying; environmental requirements; and other required certifications and flow-down clauses. Construction labor provisions shall be included when applicable. The Owner shall identify and attach the applicable clauses and any ARC or pass-through supplements before execution; a general reference to Part 200 does not replace required contract language.
Three Rivers Destination Center | 10
Costs and supporting records
Provide itemized invoices identifying authorized services, deliverables, reimbursable expenses, and approved changes. Supply supporting documentation needed for the grantee’s determination of cost allowability, reasonableness, and allocability under Subpart E, including 2 CFR 200.403 through
200.405. Do not incur or direct unapproved additional services on the assumption that grant funds will reimburse them.
Records access and closeout
Maintain and provide access to project and financial records supporting the contract, as specified in the agreement to support compliance with 2 CFR 200.334 through 200.337 and applicable audit requirements. Retention shall account for the federal award reporting date and any applicable extensions for litigation, claims, or audits, rather than being measured solely from the A/E final invoice. Assist the grantee with technical reporting and closeout documentation; Subpart F audit obligations remain with the entities to which they apply.
Regulatory references: 2 CFR Part 200 and Appendix II, available at www.ecfr.gov/current/title-
2/subtitle-A/chapter-II/part-200. A/E selection also shall follow applicable Virginia procurement requirements, including Code of Virginia Section 2.2-4302.2.
VIII. Contract and administrative requirements
Professional responsibility
The selected firm and its subconsultants shall maintain authorizations and professional credentials required for their services in Virginia. The agreement will address professional standard of care, responsibilities, compensation, reimbursable expenses, changes, insurance, indemnification as permitted by law, suspension, termination, and dispute resolution.
Grant and regulatory requirements
Performance shall comply with applicable federal, state, and local requirements and the controlling grant agreements and amendments. The Owner will identify required ARC, DHCD, and other funding provisions in the contract attachments. The firm shall assist with design and technical documentation for applicable accessibility, environmental review, nondiscrimination, procurement, and construction requirements. Applicable labor standards, domestic-content requirements, debarment certifications, and other award conditions shall be incorporated where required by the funding agreements and governing requirements.
Competition and conflicts of interest
The Owner will conduct the procurement using its applicable written procedures and funding requirements, including the qualifications-based approach for architectural and engineering services.
The Owner will make relevant project information available on an equitable basis. Prior project involvement will be reviewed for conflicts and unfair competitive advantage under applicable requirements. Participation does not by itself establish entitlement to award.
Three Rivers Destination Center | 11
Ownership and use of documents
The executed agreement shall provide the Owner with rights to use the project documents for construction, operation, maintenance, and future alteration of this facility, subject to agreed professional responsibility and reuse provisions. Identify the status of prior design document rights during initiation. The selected firm shall deliver the agreed digital and record-document formats at closeout.
Owner rights and proposal records
The Owner may reject any or all proposals, cancel the solicitation, or waive minor informalities when permitted by applicable requirements. Proposal preparation costs are the proposer’s responsibility.
Submission does not create a contract. Proposal records will be handled under applicable public-records requirements; identify proprietary material specifically and explain the basis for protection.
Blanket confidentiality designations are not sufficient. Contractual exceptions for A/E services will be addressed after ranking, except where earlier disclosure is required by governing requirements.
IX. Reference materials
Project reference materials include the 2019 ARC Area Development application; the resubmitted
ARC application VA-20362; the April 16, 2021 POWER application PW-1933; and the Three Rivers entry in the 2021 POWER award summaries. Access to these materials and available prior studies, surveys, plans, and reports, will be made available to the selected contractor by written request to the
Owner. Current grant agreements, amendments, and Owner issued addenda control where they supersede historical application information.