853976padot67460.pdf
PDF 573 KB Posted
- Solicitation number
- 67460
- Issued by
- Luzerne County, Pennsylvania
About this file
This Proposal Report is issued by the Pennsylvania Department of Transportation (PennDOT) for a bridge reconstruction project in Luzerne County, District 04. The project involves the construction of approximately 450 feet of improvements on T-427, including replacement of the bridge carrying SR 3040-D50 over an unnamed tributary to Nescopeck Creek. The project is classified as a Standard, Federally-funded, non-NHS bridge reconstruction with a scheduled letting date of December 10, 2026 at 11:00 AM and an anticipated Notice to Proceed of January 25, 2027. The required project completion date is October 18, 2027, with structure work comprising 33 percent of the total project scope. The bid package includes extensive line items for clearing and grubbing, excavation, asphalt paving materials and work, guide rail installation, traffic control, erosion and sediment control, bridge culvert replacement, detour route improvements, and miscellaneous construction items. Prequalification is required for bidders. No pre-bid meeting is scheduled, and the public bid opening will occur at the Commonwealth Keystone Building in Harrisburg. The project cost range is between $1,000,000.00 and $2,499,999.99.
This federally-funded project includes a 0 percent Disadvantaged Business Enterprise (DBE) set-aside and requires compliance with prevailing wage rates. Significant restrictions and requirements govern the project, including holiday and winter shutdown periods, continuous construction operations requirements, and specific milestone dates such as not initiating the detour before September 10, 2027 and removing it by September 30, 2027 to avoid Road User Liquidated Damages (RULD) assessments of $1,528 per day for car detours and $1,500 per day for truck detours. Environmental compliance is critical, with requirements for Erosion and Sediment Pollution Control Plans, infiltration testing for post-construction stormwater management facilities, and adherence to tree removal restrictions related to Northern Long-Eared Bat habitat (no removal April 1 through November 15). The contractor must comply with Buy America provisions, FHWA federal requirements, Pennsylvania's Right-to-Know Law, and various specification changes detailed in the special provisions. All addenda will be electronically posted through the ECMS system, and the project is subject to inspection and quality assurance testing by PennDOT representatives.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROPOSAL REPORT
Project: 67460 Bid Package: 1
Current Let: 12/10/2026 11:00:00 AM Version: Current
Addendum Count: 0
District: 04 County: Luzerne
SR/SEC/Group ID: 3040/D50/---
Description SR 3040 over Tributary Nescopeck Creek
PROPOSAL Report - Project 67460
Page 1 of 59November 5, 2026 13:34:42 PM
TABLE OF CONTENTS
BID PACKAGE SUMMARY 4
PROJECT ITEMS AND QUANTITIES 5
SPECIAL PROVISIONS 9
00 - a00001 CONSTRUCTION RESTRICTIONS & REQUIREMENTS 9 G4011B - a00002 CONSTRUCTION/HOLIDAY RESTRICTIONS 14 G4010C - a00003 REQUIRED NOTIFICATIONS 15 G50B - a00050 APPLICABLE DESIGNATED SPECIAL PROVISIONS (FEDERAL) 15 G113B - a00113 CONTRACT PROVISIONS - RIGHT-TO-KNOW LAW 16 C171A - a00171 CHANGES TO SPECIFICATIONS: SECTIONS 313, 314, 360, 410, 412, and 413 17 C172A - a00172 CHANGES TO SPECIFICATIONS: SECTIONS 107, 871, 872, 875, and 876 24 C173B - a00173 CHANGES TO SPECIFICATIONS: SECTION 106 29 G311A - a00311 ROAD USER LIQUIDATED DAMAGES (RULD) 33 G401A - a00401 ADVANCE NOTICE OF TRAFFIC RESTRICTIONS 34 G901B - a00901 ALTERNATE EROSION AND SEDIMENT POLLUTION CONTROL PLAN 34 G1101B - a01101 CONSTRUCTION PROCEDURES - EROSION AND SEDIMENT POLLUTION
CONTROL 35
G1601A - a01601 E.E.O. COVERED AREA 36 G2302A - a02302 Worker Protection and Investment 36 N10501B - a10501 BRIDGE SHOP DRAWINGS 37 N10550B - a10550 HEAVY CONSTRUCTION WAGE RATES 37 N10601A - a10601 DRIVE ADJUSTMENTS 38 00 - a10851 CIS - 11'-0" x 10'-0" PRECAST REINFORCED CONCRETE
BOX CULVERT AND END SECTIONS 38
S41331A - b04133 SECTION 413.3(h)1.a Placing 39 S41332A - b04134 SECTION 413.3(k)1.a General 39 S6012B - b06012 - SECTION 601.3(f) BACKFILLING TRENCH 40 S6092B - b06092-SECTION 609.2(f) MISCELLANEOUS MATERIALS 41 S9013A - b09013 SECTION 901.3(k) Work Area Pavement Markings 41 00 - c02011 ITEM 4201-0001 CLEARING AND GRUBBING TREE REMOVAL RESTRICTION 42 00 - c02041 ITEM 4204-0100 CLASS 3 EXCAVATION FOR DISTRIBUTION OF STOCKPILED
MATERIAL 42
I50268B - c02058 ITEM 4205-0268 SELECTED BORROW EXC. ROCK, CLASS R-8 CHOKED W/
ROCK, CLASS R-4 & STREAMBED 43
I6091L - c06091 ITEM 0609-0009 EQUIPMENT PACKAGE 44 I4677A - c06771 ITEM 4677-0001 SELECTED MATERIAL SURFACING FOR SIDEROAD AND
DRIVEWAY ADJUSTMENTS 46
00 - c0901 ITEM 0901-0001 MAINTENANCE AND PROTECTION OF TRAFFIC DURING
CONSTRUCTION 46
I80141A - c80141 ITEM 8510-0001/0002 - ALTERNATE CULVERT 47 N1A - c80142 PART B, SPECIAL DRAWINGS AND SPECIAL DESIGN REQUIREMENTS 50 00 - c90001 ITEM 9000-0001 COFFERDAM ALTERNATE 51
Page 2 of 59November 5, 2026 13:34:42 PM
00 - c90002 ITEM 9000-0002 TEMPORARY PUMP BYPASS SYSTEM 53 00 - c90003 ITEM 9000-0003 SEGMENT MARKER 54 00 - c90004 ITEM 9000-0004 OVER-EXCAVATION AND REPLACEMENT WITH COARSE
AGGREGATE 54
00 - c90005 ITEM 9000-0005 PRE AND POST INSPECTION OF DETOUR ROUTE 55 00 - c90006 ITEM 9000-0006 REPAIR OF DETOUR ROUTE 56 I95000A - c95000 ITEM 9000-5000 - SNOWPOLE (ORANGE), 7' 0" 57 I68C - c95101 ITEM 9000-5101 ELECTRONIC TICKETING (E-TICKETING) FOR CONSTRUCTION
AGGREGATE 57
I70C - c95103 ITEM 9000-5103 ELECTRONIC TICKETING (E-TICKETING) FOR CONSTRUCTION
CONCRETE 58
Page 3 of 59November 5, 2026 13:34:42 PM
BID PACKAGE SUMMARY
Project: 67460 Bid Package: 1
Project Type: Standard Posted:
Federal Project Status: PENNDOT Oversight Non-NHS State Type of Work: BRIDGE RECONSTRUCTION
Prequalification Required: Yes Pre-Bid Meeting: None
408 Version: 2026-1
Scheduled Let: 12/10/2026 11:00:00 AM Project Cost Range: $1,000,000.00 - $2,499,999.99 Anticipated NTP: 01/25/2027 Structure Work: 33.00%
Required Completion: 10/18/2027 DBE: 0% Wage Rates: Yes
Description:
This project is the construction of approximately 450 feet on T-427 and from Segment 0030 Offset 0000 to Segment 0030 Offset 0013, including replacement of the bridge carrying SR 3040-D50 over unnamed tributary to Nescopeck Creek, as indicated on the approved drawings included in the Bid Package.
Additional Information:
This is an ECMS project. All Addenda will be electronically posted.The location of the public bid opening is the Commonwealth Keystone Building, 7th Floor, Contract Awards Room, 400 North Street, Harrisburg. Allow sufficient time before the bid opening to contact Contract Awards and be escorted to the 7th Floor Contract Awards Room. Contract Awards can be reached at 717-395-9754.
Due to recent changes in the Keystone Building, there is no longer a reception on the 5th Floor to greet and check-in visitors.
Page 4 of 59November 5, 2026 13:34:42 PM
PROJECT ITEMS AND QUANTITIES
Alt Item Work Class Code Unit Of
Measure Quantity Unit Price PDP Spec
Prov Add Action
4201-0001 A Lump Sum 1.0000 N Proj
CLEARING AND GRUBBING TREE REMOVAL RESTRICTION
0203-0001 C Cubic Yard 979.0000 N
CLASS 1 EXCAVATION
4204-0100 C1, S1, T1 Cubic Yard 86.0000 N Proj
CLASS 3 EXCAVATION FOR DISTRIBUTION OF STOCKPILED MATERIAL
0205-0265 C1 Cubic Yard 82.0000 N
SELECTED BORROW EXCAVATION ROCK, CLASS R-5
4205-0268 C1 Cubic Yard 698.0000 N Std
SELECTED BORROW EXCAVATION ROCK, CLASS R-8 CHOKED WITH ROCK, CLASS R-4
0212-0001 C3, H, M2 Linear Foot 81.0000 N
GEOTEXTILE, CLASS 1
0212-0014 C3, H, M2 Square Yard 2,234.0000 N
GEOTEXTILE, CLASS 4, TYPE A
0313-0320 E Square Yard 798.0000 N SUPERPAVE ASPHALT MIXTURE DESIGN, BASE COURSE, PG 64S-22, < 0.3 MILLION ESALs, 25.0 MM MIX, 3" DEPTH
0350-0106 C, E Square Yard 1,188.0000 N
SUBBASE 6" DEPTH (NO. 2A)
0350-0120 C, E Cubic Yard 49.0000 N
SUBBASE (NO. 2A)
0413-0195 F Square Yard 1,245.0000 N
SUPERPAVE ASPHALT MIXTURE DESIGN, WEARING COURSE, PG 64S-22, < 0.3 MILLION ESALS, 9.5 MM MIX, 1 1/2"
DEPTH, SRL-L
0413-1019 F Ton 16.0000 N
SUPERPAVE ASPHALT MIXTURE DESIGN, WEARING COURSE (SCRATCH), PG 64S-22, < 0.3 MILLION ESALS, 9.5 MM
MIX, SRL-L
0413-2059 F Ton 633.0000 N
SUPERPAVE ASPHALT MIXTURE DESIGN, WEARING COURSE (LEVELING), PG 64S-22, < 0.3 MILLION ESALS, 9.5 MM
MIX, SRL-L
0413-6035 F Square Yard 798.0000 N
SUPERPAVE ASPHALT MIXTURE DESIGN, BINDER COURSE, PG 64S-22, < 0.3 MILLION ESALS, 19.0 MM MIX, 2 1/2"
DEPTH
E 0413-6037 F Ton 160.0000 N SUPERPAVE ASPHALT MIXTURE DESIGN, BINDER COURSE, PG 64S-22, < 0.3 MILLION ESALS, 19.0 MM MIX
O 0313-0337 E Ton 160.0000 N SUPERPAVE ASPHALT MIXTURE DESIGN, BASE COURSE, PG 64S-22, < 0.3 MILLION ESALs, 25.0 MM MIX
Page 5 of 59November 5, 2026 13:34:42 PM
0460-0003 F4 Square Yard 12,603.0000 N
ASPHALT TACK COAT (NTT/CNTT)
0491-0013 F3 Square Yard 447.0000 N MILLING OF ASPHALT PAVEMENT SURFACE, 2" DEPTH, MILLED MATERIAL RETAINED BY CONTRACTOR
0608-0001 X Lump Sum 1.0000 N
MOBILIZATION
0609-0003 X Lump Sum 1.0000 N
INSPECTOR'S FIELD OFFICE AND INSPECTION FACILITIES, TYPE B
0609-0009 X Lump Sum 1.0000 N Std
EQUIPMENT PACKAGE
0610-7002 H2 Linear Foot 81.0000 N
6" PAVEMENT BASE DRAIN
0615-0022 H2 Linear Foot 19.0000 N
6" SUBSURFACE DRAIN OUTLETS
0615-0040 H2 Each 2.0000 N
SUBSURFACE DRAIN OUTLET ENDWALL
0615-0066 C1, H2, R Each 2.0000 N
66" RED SUBSURFACE DRAIN OUTLET MARKER
0619-0458 J3 Each 1.0000 N
PERMANENT IMPACT ATTENUATING DEVICE, TYPE II, TEST LEVEL 2, TANGENT (MASH)
0619-0459 J1, J3 Each 2.0000 N
PERMANENT IMPACT ATTENUATING DEVICE, TYPE II, TEST LEVEL 3, TANGENT (MASH)
0620-0500 J Linear Foot 13.0000 N
RESET GUIDE RAIL
0620-0503 C1, J Linear Foot 421.0000 N
REMOVE EXISTING GUIDE RAIL (CONTRACTOR'S PROPERTY)
0620-1600 J Linear Foot 313.0000 N
TYPE 31-S GUIDE RAIL
0627-3020 J1 Linear Foot 40.0000 N
TEMPORARY BARRIER, TEST LEVEL 3, BARRIER DEFLECTION DISTANCE < /=2'
4677-0001 C1, E Cubic Yard 11.0000 N Std
SELECTED MATERIAL SURFACING FOR SIDEROAD AND DRIVEWAY ADJUSTMENTS
0686-0050 X Lump Sum 1.0000 N
CONSTRUCTION SURVEYING, TYPE D
0689-0005 X Lump Sum 1.0000 N
CPM SCHEDULE, WITH UPDATES
0690-0001 X Dollar 1,000.0000 $1.00 Y
Page 6 of 59November 5, 2026 13:34:42 PM
INTERNAL FACILITATION
0703-0020 C1, H Cubic Yard 416.0000 N
NO. 1 COARSE AGGREGATE
0804-0026 M3 Pound 6.0000 N
SEEDING AND SOIL SUPPLEMENTS - FORMULA C CONSERVATION MIX, INCLUDING MULCH
0804-0027 M3 Pound 33.0000 N
SEEDING AND SOIL SUPPLEMENTS - FORMULA L CLEAR ZONE MIX, INCLUDING MULCH
0804-0032 M3 Pound 10.0000 N
SEEDING - FORMULA T TEMPORARY GRASS MIX, INCLUDING MULCH
0804-0033 M3 Pound 5.0000 N SEEDING AND SOIL SUPPLEMENTS - FORMULA W WETLAND CONSERVATION MIX, INCLUDING MULCH
0810-0023 M1 Lump Sum 1.0000 N
TREE TRIMMING TO A MAX HEIGHT OF 20'
0810-0052 A, M1 Each 9.0000 N
SELECTIVE TREE REMOVAL
0811-0003 J2, M Linear Foot 271.0000 N
TEMPORARY PROTECTIVE FENCE
0845-0001 M2 Dollar 4,500.0000 $1.00 Y
UNFORESEEN WATER POLLUTION CONTROL
0855-0003 M2 Each 2.0000 N
PUMPED WATER FILTER BAG
0855-0004 M2 Each 4.0000 N
REPLACEMENT PUMPED WATER FILTER BAG
0867-0012 M2 Linear Foot 206.0000 N
COMPOST FILTER SOCK, 12" DIAMETER
0867-0018 M2 Linear Foot 58.0000 N
COMPOST FILTER SOCK, 18" DIAMETER
0867-0022 M2 Linear Foot 83.0000 N
COMPOST FILTER SOCK, 24" DIAMETER
0901-0001 Q Lump Sum 1.0000 N Proj
MAINTENANCE AND PROTECTION OF TRAFFIC DURING CONSTRUCTION
0901-0240 Q, R Square Foot 100.0000 N
ADDITIONAL TRAFFIC CONTROL SIGNS
0901-0451 Q Each 6.0000 N
3-LINE CHANGEABLE MESSAGE SIGN WITHOUT TELECOMMUNICATIONS
0931-0001 R Square Foot 7.0000 N
POST MOUNTED SIGNS, TYPE B
Page 7 of 59November 5, 2026 13:34:42 PM
0935-0001 R Square Foot 2.0000 N
POST MOUNTED SIGNS, TYPE F
0937-0107 J, R Each 13.0000 N
GUIDE RAIL MOUNTED DELINEATOR TYPE B, (W/W)
0937-0114 J, R Each 13.0000 N
GUIDE RAIL MOUNTED DELINEATOR TYPE D, (W/W)
0937-0330 R Each 3.0000 N FLEXIBLE DELINEATOR POST, GROUND-MOUNT TYPE GM-2, WHITE POST WITH WHITE/BLANK SHEETING
0962-1005 O Linear Foot 1,400.0000 N
4" YELLOW WATERBORNE PAVEMENT MARKINGS
1018-0060 C1, T1 Lump Sum 1.0000 N
REMOVAL OF EXISTING CULVERT
E 8510-0001 S4 Lump Sum 1.0000 N Std
PRECAST REINFORCED CONCRETE BOX CULVERT, AS DESIGNED, S-42707
O 8510-0002 S4 Lump Sum 1.0000 N Std
ALTERNATE PRECAST CULVERT
9000-0001 M2 Linear Foot 237.0000 N Proj
COFFERDAM ALTERNATE
9000-0002 M2 Lump Sum 1.0000 N Proj
TEMPORARY PUMP BYPASS SYSTEM
9000-0003 R Square Foot 2.0000 N Proj
SEGMENT MARKER
9000-0004 C1 Cubic Yard 91.0000 N Proj
OVER-EXCAVATION AND REPLACEMENT WITH COARSE AGGREGATE
9000-0005 X Dollar 4,500.0000 $1.00 Y Proj
PRE AND POST INSPECTION OF DETOUR ROUTE
9000-0006 E, F1 Dollar 20,000.0000 $1.00 Y Proj
REPAIR OF DETOUR ROUTE
9000-5000 R Each 6.0000 N Std
SNOWPOLE (ORANGE), 7' 0"
9000-5101 X Lump Sum 1.0000 N Std
ELECTRONIC TICKETING (E-TICKETING) FOR CONSTRUCTION AGGREGATE
9000-5103 X Lump Sum 1.0000 N Std
ELECTRONIC TICKETING (E-TICKETING) FOR CONSTRUCTION CONCRETE
Page 8 of 59November 5, 2026 13:34:42 PM
SPECIAL PROVISIONS
Special Provision: 00 - a00001 CONSTRUCTION RESTRICTIONS & REQUIREMENTS Addendum:
Action:
Item(s) Associated:
Header:
CONSTRUCTION RESTRICTIONS & REQUIREMENTS
Provision Body:
Milestone Restrictions and Requirements
The start work date for this project is January 25, 2027 unless otherwise approved in writing by the Project Manager, Department Assistant Construction Engineer, and Inspector in Charge.
Do not initiate the detour before September 10, 2027 unless approved by the Project Manager. A single detour is to be implemented for the entire construction duration, and must be removed at or before September 30, 2027 to avoid RULD costs.
Bridge Restrictions and requirements
For any concrete repair work during the project, provide a concrete compressive strength break machine for concrete cylinder sample testing prior to opening lane to traffic. The machine will be placed at a mutually agreeable location between the contractor and the PennDOT IIC.
Do not allow construction activity under any structural member which are not appropriately tightened and secured.
All concrete mix designs are to be submitted at the pre-construction conference.•
The contractor is to provide PennDOT confirmation of fabrication and scheduled delivery of the Box Culvert.•
Utility Restrictions and Requirements
An initial PA One Call must be placed, and a Complex Ticket Meeting with all necessary parties scheduled within ten (10) days of when contract work is to begin.
Be responsible for any damages to existing utilities caused by contractor operations. Contact the applicable authority immediately in the event of any damage.
Paving / Shoulder Restrictions and Requirements
Submit all asphalt mixture designs for Department approval a minimum of two weeks prior to the first placement. If more than one asphalt supplier is used, each source is required to have a Department approved mix designs.
All milled surfaces must be paved prior to the removal of the traffic control pattern. Traffic must not run-on milled surfaces.
All pavement joints, including longitudinal joints, are to be sealed.•
Page 9 of 59November 5, 2026 13:34:42 PM
Trackless tack coat is required.•
Repair any damage to existing pavement areas adjacent to construction operations as directed and at no additional cost to the Department.
Complete the final wearing course within 14 consecutive calendar days of placing the scratch/leveling course.
Make driveway adjustments, when required, using material from the resurfacing operation unless otherwise indicated or directed.
Contractor is responsible for completing improvements to the County portion of Old Airport Route that is being used as the detour for this project. Approximate quantities have been provided in the Bid Plans and improvements are to be completed at the discretion of the Project Manager, Department Assistant Construction Engineer, and Inspection in Charge.
Pavement Marking Restrictions and Requirements
Complete all permanent pavement markings within 30 calendar days of placing the final wearing course.
After October 31st, place permanent pavement markings with 7 calendar days after the completion of paving.
Prior to beginning milling or resurfacing operations, field view the locations of the existing pavement markings and prepare sketches and/or reference in the field so that they can be reproduced.
Contact / Notification Restrictions and Requirements
Notify the Project Manager and Contact Jessica Ruddy, District 4-0 Community relations Coordinator, at
(570) 963-4044 for a media release of work two weeks prior to start of work. Include project specific details.
Notify the Department a minimum of fourteen (14) calendar days prior to beginning milling operations.•
Contact the contractors for the ECMS #67460 SR 3040, Section D50 Structure Replacement project and Department Manager to coordinate the work schedule.
Notify all municipalities and emergency services, to keep them informed of work that will close off their highway access and/or crossover access.
Notify the Department Representative at least 4 calendar days prior to the start of any operation which will affect the flow of vehicular traffic and provide the Department representative with details of the work to be done. The Department will advise the public of these restrictions and possible delays.
Provide all property owners and/or residents affected by construction written notification of impending work. Provide information in accordance with the special provision titled PUBLIC NOTIFICIATION.
Contact emergency services and appropriate municipal officials including police, fire, ambulance, schools, and postal services two (2) weeks prior to start of work to inform them of proposed work schedule. Provide copies of notification to the Project Manager.
Notify property owners ten (10) calendar days in advance of driveway restrictions affecting their properties.•
Right-of-Way Restrictions and Requirements
Right-Of-Way must be staked out withing 10 days of the Notice to Proceed.•
All work is to be completed within the Right of Way.•
Page 10 of 59November 5, 2026 13:34:42 PM
General Restrictions and Requirements
Once the project is initiated, make every effort to perform continuous construction operations and minimize the length of the project. Continuous construction operations are defined as providing active construction staffing, equipment, and sufficient material each workday.
Comply with all local municipal zoning ordinances regarding construction related noise.•
Coordinate work with projects in or near the limits of work. No time extensions will be given in this contract, due to delays on work to be performed by others.
Protect any material being hauled to or away from the construction site. Cover any loads which create dust or other undesirable conditions. Loads of waste material emitting any liquid drippings are not allowed on any public roadway. Clean or sweep debris left from construction activities on any public roadway with a street sweeper or broom to the satisfaction of the Representative at no additional cost to the Department.
The Department has not provided additional time in the contract for acquiring waste areas and/or permits for these waste areas, if required. The contractor is fully responsible for complying with all non-Department permits as well as the construction schedule as required in this contract.
No blasting is allowed on this project.•
No burning is allowed.•
Ensure Inspection Field Offices are within 1 miles of project site.•
The work area is to be maintained in a neat and orderly condition. Remove all debris from the work area at the close of each day operations.
Do not store flammable material and chemicals underneath any bridge within the project limits.•
Maintain access of existing driveway for property owners. Existing driveway will only be used to deliver material and equipment. Do not store any material or equipment on existing driveway.
Sufficient time has been allowed in the project to procure materials. A time extension will not be given for materials not ordered on time.
Do not operate off-road equipment on any State-owned bridge or roadway.•
Supply sufficient crew, equipment, and materials to complete the necessary work during the allotted 14 -calendar day bypass pumping period.
Be responsible for and provide security as required to prevent vandalism or cracking on unhardened concrete surfaces.
Contractor must inspect and record using photos and video the condition of property owner’s foundation in the presence of the property owner before and after construction is started and completed.
There are no on-site waste areas. The contractor will be responsible for hauling all excess spoils to an offsite location(s). The contractor will be responsible for ensuring all offsite waste areas have approved E&S plans and associated permits.
Do not store any equipment or stockpile any material within 30 feet of any roadway open to traffic unless protected by temporary barrier.
Road user liquidated damages will be assessed on this project in accordance with the specifications established in the Special Provision entitled “Road User Liquidated Damages”.
Page 11 of 59November 5, 2026 13:34:42 PM
The contractor is to utilize and allocate crews equipment and materials as necessary for the completion of work activities within the specified work periods, to deliver the project on the specified completion date, uphold project milestones, and meet all contractual requirements.
Structural Class R-8 rock and streambed material are to be placed by mechanical means and not end dumped.
Saint Johns Road is weight posted for 5 tons through the limits of Butler and Sugarloaf Townships. The Contractor will be responsible for procuring any required Township permits and any necessary bonding of Saint Johns Road from the Townships.
Traffic / Traffic Control Restriction and Requirements
5 days before the completion of work of each phase of construction and before the M&PT is reset or removed, the contractor is to contact the Assistant Bridge Engineer (Gary Borgacci at 570.963.3513) to schedule an (NBI) inspection for each bridge, and to include a letter stating the inspection was completed before closing out the job.
Monitor traffic control devices as specified in the Special Provision “Item 0901-0001 – Maintenance and Protection of Traffic During Construction” and the Traffic Control Plan. Be prepared to correct any deficiencies immediately. Failure to correct deficiencies in a timely fashion may result in a project shutdown.
No additional contract time will be allowed to compensate for time lost resulting from a failure to meet requirements of this provision
Submit any alternate work plan along with proposed methods of traffic control a minimum of two (2) weeks prior to the pre-construction conference for Department review and approval. Submit alternate plans only when a time savings or significant benefit to the Department is approved.
Milestone Restrictions and Requirements
No work is to be performed within the project limits prior to April 1st of any calendar year unless prior approval is granted by the District Executive.
No work is to be performed within the project limits during the Winter Shutdown period(s) (Tuesday before Thanksgiving to April 1st) of any calendar year unless prior approval is granted by the District Executive.
(Tie RULDS to Tuesday before Thanksgiving)
Environmental / E & S Restrictions and Requirements
Construct sedimentation control devices in affected work area prior to performing clearing and grubbing operations, as approved by the Project Manager. Satisfactorily remove all sedimentation control devices when adequate stabilization has occurred, as directed by the Project Manager, and in accordance with the Erosion and Sediment Pollution Control Plan.
The contractor is fully responsible for complying with all non-Department permits as well as the construction schedule as required in this contract.
Material excavation from the stream during construction of the box culvert must be stockpiled and maintained at the site. Upon completion of in-stream and channel work, return the material as indicated.
This material will not otherwise be disposed of within any floodplain or wetland areas.
All stockpiled material and wetland soils must be tarped from initial stockpiling to final stockpiling when it will be used for restoration.
Temporary fill placed within wetlands during project construction must be removed at the completion of the project, and all temporary wetland disturbances must be stabilized and restored. This project will have 4075
Page 12 of 59November 5, 2026 13:34:42 PM
SF of temporary wetland impacts and 359 SF of permanent wetland impacts. This project will have 443 SF of temporary watercourse impacts and 2255 SF of permanent watercourse impacts.
Install Temporary Protective Fence prior to start of work to identify wetland areas.•
When removing selected trees and shrubs, contractor must cut all stumps at the ground line.•
No additional contract time will be permitted for alternate temporary stream diversion concept submissions, review or permitting. The contractor is responsible for acquiring Department acceptance for all alternate temporary stream diversion submissions prior to submitting for a DEP permit modification. A minimum of 5 calendar days of review time is required by the Department for each contractor submission. The contractor is required to provide the Department with all waterway permit modification documents for submission to DEP. All permit modification submissions will be made by the Department through the KEES system. The Department is not responsible for permit review times required by DEP.
Immediately remove any stone or debris that adversely enters or impacts the stream during construction activities. Removal of stone or debris that enters the stream during construction activities is considered incidental.
Temporary fill placed within wetlands during project construction must be removed at the completion of the project, and all temporary wetland disturbances must be stabilized and restored.
Do not store equipment or stockpile material in any wetland or waterway. Do not park equipment or vehicles overnight near any waterway that would allow oil, gas, hydraulic fluid , or other contaminants to enter the waterway.
Inspect all erosion and sediment pollution control devices daily and after each rainstorm that results in runoff. The Department will monitor these inspections. Repair or replace any defective devices prior to resuming construction activities.
All off-site waste and borrow areas must have an E&S plan approved by the local conservation district and the department fully implemented prior to being activated.
The contractor is responsible for ensuring that any material brought on site is clean fill. Form FP-001 must be retained by the property owner for any fill material affected by a spill or release of a regulated substance but qualifying as clean fill due to analytical testing.
The project is located in the vicinity of the Northern Long-Eared Bat spring staging/fall swarming habitat. To ensure take is not reasonably certain to occur, do not conduct tree removal from April 1st to November 15th of any calendar year.
Ensure all operators, employees, and contractors working in areas of Indiana bat, NLEB, or TCB suitable habitat are aware of all Transportation Agency environmental commitments, including all applicable AMMs.
Modify all phases/aspects of the project (e.g., temporary work areas, alignments) to the extent practicable to avoid tree removal/trimming in excess of what is required to implement the project safely.
Ensure tree removal/trimming is limited to that specified in project plans and ensure that contractors understand clearing limits and how they are marked in the field (e.g., install bright colored flagging/fencing prior to any tree
Environmental Due Diligence must be deformed to determine if the fill materials associated with the project qualify as clean fill. See Department’s policy “Management of Clean Fill” for more information on Environmental due Diligence.
Permitting
Page 13 of 59November 5, 2026 13:34:42 PM
Any coordination with the Department of Environmental Protection (DEP) should be done through the District Permit Coordinator.
Refer to Publication 783 – The Environmental Permitting Handbook for preparation of permits.•
Project Specific Details:
Special Provision: G4011B - a00002 CONSTRUCTION/HOLIDAY RESTRICTIONS Addendum:
CONSTRUCTION/HOLIDAY RESTRICTIONS
Provision Body:
Implement the following holiday restriction for the time frames listed below. Do not perform any work, including permit work, which will affect traffic on any State Route unless approved by the Department. Such work and/or activities include, but are not limited to the following:
Slow Moving Construction vehicles entering or leaving the roadways, Crane swings over or near the highway, Any lane closures
Easter - Restriction starts from Friday, 12:01 A.M. preceding the holiday to Monday, 12:59 P.M. following the holiday.
Memorial Day and Labor Day - Restriction starts from Friday, 12:01 A.M. preceding the holiday to Tuesday, 12:59 P.M. following the holiday.
Thanksgiving - Restriction starts from Wednesday, 12:01 A.M. preceding the holiday to Sunday, 12:59 P.M. following the holiday.
Independence Day (July 4th), Christmas (December 25th) and New Year's (January 1st)
If the holiday is Monday, then the restriction starts from Friday, 12:01 A.M. preceding the holiday to Tuesday, 12:59 P.M. following the holiday.
If the holiday is Wednesday, then the restriction starts from Tuesday, 12:01 A.M. preceding the holiday to Thursday, 12:59 P.M.
following the holiday.
If the holiday is Thursday, then the restriction starts from Wednesday, 12:01 A.M. preceding the holiday to Sunday, 12:59 P.M.
following the holiday.
If the holiday is Friday, then the restriction starts from Thursday, 12:01 A.M. preceding the holiday to Monday, 12:59 P.M. following the holiday.
If the holiday is Saturday or Sunday, then the restriction starts from Friday, 12:01 A.M. preceding the holiday to Monday, 12:59 P.M.
following the holiday.
Independence Day (July 4th)
If the holiday is Tuesday, then the restriction starts from Monday, 12:01 A.M. preceding the holiday to Wednesday, 12:59 P.M.
Page 14 of 59November 5, 2026 13:34:42 PM following the holiday.
Christmas (December 25th) and New Year's (January 1st)
If the holiday is Tuesday, then the restriction starts from Friday, 12:01 A.M. preceding the holiday to Wednesday, 12:59 P.M. following the holiday.
Special Provision: G4010C - a00003 REQUIRED NOTIFICATIONS
REQUIRED NOTIFICATIONS
Provision Body:
Provide the following notification to the Inspector-in-Charge of the following:
Start of physical work – seven calendar days• Width, height, or weight restrictions to any roadway – ten working days (excluding State holidays). This information should be on the form M-937R.
Removal of width, height, or weight restrictions to any roadway – immediately upon removal. This information should be on the form M-937RO.
Start of any operation affecting traffic (lane closures, total closures, etc.) -- seven calendar days with a confirmation the morning of the operation.
You will not be permitted to close or restrict any roadway until ten working days (excluding State holidays) after such notification is received by the District Permits Unit.
No time extensions will be granted for failure to submit the required notices.
Also, directly notify local residents, school districts, local and county emergency management agencies (EMAs) of work that impacts those entities at the start of the project and again no less than four calendar days in advance of such work. Provide documentation of such notifications to the Inspector-in-Charge.
Regardless of these provisions, provide notification to any entities that are affected by your operations sufficiently ahead of the operations to allow those entities to adjust their operations accordingly.
Special Provision: G50B - a00050 APPLICABLE DESIGNATED SPECIAL PROVISIONS (FEDERAL)
Action:
Item(s) Associated:
Page 15 of 59November 5, 2026 13:34:42 PM
APPLICABLE DESIGNATED SPECIAL PROVISIONS (FEDERAL)
Provision Body:
APPLICABLE DESIGNATED SPECIAL PROVISIONS. The following Designated Special Provisions are found in Appendix C and apply to this bid proposal.
DSP7. Disadvantaged Business Enterprise (DBE) Requirements for Federally-funded Construction Projects.
DSP8. F.A.R. - Required Contract Provisions Federal-Aid Construction Contracts FHWA-1273 (Revised October 23, 2023). Also attached to the Proposal/Contract.
DSP9. Special Supplement - Anti-Pollution Measures - August 26, 1999.
DSP12. Executive Order 11246, with Appendix A and B.
DSP13. Buy America.
DSP15. Commonwealth Standard Terms and Conditions.
DSP16. Lobbying Certification Form. (Form is located in ECMS File Cabinet and must be completed and uploaded to the Contractor Checklist in ECMS).
DSP17. Federal Audit Clause.
DSP19. The United States Department of Transportation (USDOT) Standard Title VI/Non-Discrimination Assurances.
DSP20. FAR 52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act- Covered Foreign Entities.
Special Provision: G113B - a00113 CONTRACT PROVISIONS - RIGHT-TO-KNOW LAW
CONTRACT PROVISIONS - RIGHT TO KNOW LAW
Provision Body:
I. Contract Provisions – Right to Know Law 8-K-1532
a. The Pennsylvania Right-to-Know Law (RTKL), 65 P.S. §§ 67.101-3104, applies to this Contract.
b. If the Department needs assistance in any matter arising out of the RTKL related to this Contract, the Department will notify the Contractor using the legal contact information provided in this Contract. The Contractor, at any time, may designate a different contact for such purpose upon reasonable prior written notice to the Department.
Page 16 of 59November 5, 2026 13:34:42 PM
c. Upon written notification from the Department that it requires assistance in responding to a request under the RTKL for information related to this Contract that may be in the Contractor’s possession, constituting, or alleged to constitute, a public record in accordance with the RTKL (“Requested Information”), the Contractor will:
1. Provide the Department, within 10 calendar days after receipt of written notification, access to, and copies of, any document or information in the Contractor’s possession arising out of this Contract that the Department reasonably believes is Requested Information and may be a public record under the RTKL; and
2. Provide such other assistance as the Department may reasonably request, in order to comply with the RTKL with respect to this Contract.
d. If the Contractor considers the Requested Information to include a request for a Trade Secret or Confidential Proprietary Information, as those terms are defined by the RTKL, or other information that the Contractor considers exempt from production under the RTKL, notify the Department and provide, within 7 calendar days of receiving the written notification, a written statement signed by a representative of the Contractor explaining why the requested material is exempt from public disclosure under the RTKL.
e. The Department will rely upon the written statement from the Contractor in denying a RTKL request for the Requested Information unless the Department determines that the Requested Information is clearly not protected from disclosure under the RTKL. Should the Department determine that the Requested Information is clearly not exempt from disclosure, provide the Requested Information within 7 calendar days of receipt of written notification of the Department’s determination.
f. Failing to provide the Requested Information within the time period required by these provisions, indemnify and hold the Department harmless for any damages, penalties, costs, detriment or harm that the Department may incur as a result of this failure, including any statutory damages assessed against the Department.
g. The Department will reimburse the Contractor for any costs associated with complying with these provisions only to the extent allowed under the fee schedule established by the Office of Open Records or as otherwise provided by the RTKL if the fee schedule is inapplicable.
h. The Contractor may file a legal challenge to any Department decision to release a record to the public with the Office of Open Records, or in the Pennsylvania Courts, however, indemnify the Department for any legal expenses incurred by the Department as a result of such a challenge and hold the Department harmless for any damages, penalties, costs, detriment or harm that the Department may incur as a result of the failure, including any statutory damages assessed against the Department, regardless of the outcome of such legal challenge. As between the parties, agree to waive all rights or remedies that may be available as a result of the Department’s disclosure of Requested information pursuant to the RTKL.
i. The Contractor’s duties relating to the RTKL are continuing duties that survive the expiration of this Contract and continue as long as the Requested Information remains in the Contractor's possession.
Special Provision: C171A - a00171 CHANGES TO SPECIFICATIONS: SECTIONS 313, 314, 360, 410, 412, and 413
Addendum:
CHANGES TO SPECIFICATIONS: SECTIONS 313, 314, 360, 410, 412, and 413
Provision Body:
SECTION 313—SUPERPAVE ASPHALT MIXTURE DESIGN, STANDARD CONSTRUCTION, BASE COURSE
Page 17 of 59November 5, 2026 13:34:42 PM
Section 313.3(m) Tests for Depth. Revise to read as follows:•
(m) Tests for Depth.
(m) Tests for Depth. Replace with the following:
Control the loose depth of each layer to construct the base course to the compacted depth indicated and within the specified tolerance. On the top lift and in the presence of the Inspector, drill full-depth cores at one random location selected by the Inspector according to PTM No. 1 in each 3,000 square yards of completed base course and at other locations the Inspector suspects are deficient. After the Inspector completes depth measurements, backfill, compact, and seal core holes with the mixture used to construct the course.
The Inspector will measure the full-depth cores according to PTM No. 737. Pavement deficient in depth by 1/2 inch or more and that cannot be satisfactorily corrected is defective. Immediately delineate the limits of pavement deficient in depth from the core location by proceeding longitudinally, forward and backward, obtaining additional pavement cores every 50 feet until the depth is less than 1/2 inch deficient of the design depth. The defective course will be the full width of the affected lane.
SECTION 314—SUPERPAVE ASPHALT MIXTURE DESIGN, STANDARD CONSTRUCTION, ASPHALT RICH BASE COURSE
Section 314.3(m) Tests for Depth. Revise to read as follows:•
(m) Tests for Depth.
(m) Tests for Depth. Replace with the following:
Control the loose depth of each layer to construct the ARBC to the compacted depth indicated and within the specified tolerance. In the presence of the Inspector, drill full-depth cores at one random location selected by the Inspector according to PTM No. 1 in each 3,000 square yards of completed ARBC and at other locations the Inspector suspects are deficient. After the Inspector completes depth measurements, backfill, compact, and seal core holes with ARBC.
The Inspector will measure the full-depth cores according to PTM No. 737. Pavement deficient in depth by 1/2 inch or more and that cannot be satisfactorily corrected is defective. Immediately delineate the limits of pavement deficient in depth from the core location by proceeding longitudinally, forward and backward, obtaining additional pavement cores every 50 feet until the depth is less than 1/2 inch deficient of the design depth. The defective course will be the full width of the affected lane.
SECTION 360—ASPHALT TREATED PERMEABLE BASE COURSE
Section 360.2(e)3. Production. Revise to read as follows:•
3. Production. During the first day of production, take at least three asphalt content and gradation tests to verify the mixture conforms to the JMF. After the first day, perform tests for asphalt content and aggregate gradation according to the QC Plan and PTM No. 1. Produce ATPBC conforming to the gradation requirements in Table A and with an asphalt content within 0.8% of the JMF (n=1). Ensure the aggregate is uniformly coated with asphalt and no runoff of excess asphalt is observed.
Section 360.3(m). Tests for Depth. Revise to read as follows:•
(m) Tests for Depth: Binder and Wearing Courses. Replace with the following:
Carefully dig or drill one random 6-inch diameter test hole selected by the Representative according to PTM No. 1 to the full depth of the ATPBC for each 3,000 square yards, or less, of completed base course. The Representative may require additional test holes in areas the Representative suspects are deficient in depth. The Representative will measure the depth of the base course. Using material acceptable to the Representative, backfill the test holes and compact the material to fill the test hole flush with the completed base course.
ATPBC deficient in depth by 1/2 inch or more is defective. Immediately delineate the limits of ATPBC deficient in depth from the location by proceeding longitudinally, forward and backward, obtaining additional test holes every 50 feet until the depth is less than 1/2 inch deficient of the indicated depth. The defective course will be the full width of the affected lane.
SECTION 410—SUPERPAVE MIXTURE DESIGN, STANDARD AND RPS CONSTRUCTION OF PLANT-MIXED ASPHALT FINE-
GRADED COURSES
Section 410.3. CONSTRUCTION. Revise to read as follows:•
Page 18 of 59November 5, 2026 13:34:42 PM
410.3 CONSTRUCTION—Section 413.3 using the test procedures, limits, and tolerances for a 9.5 mm nominal maximum aggregate size mixture except where procedures, limits and tolerances are specifically indicated for a 9.5 mm fine-graded nominal maximum aggregate size mixture and as modified as follows:
Revise Table G to include 9.5 mm Fine Grade Wearing Course as follows:
TABLE G
Mixture Minimum Indicated Compacted Depths
Mixture Minimum Depth
9.5 mm Fine Grade Wearing Course 1 inch
SECTION 412—SUPERPAVE MIXTURE DESIGN, CONSTRUCTION OF PLANT-MIXED 6.3 MM ASPHALT OVERLAY COURSES
Section 412.3(a)2. Preplacement Meeting. Revise to read as follows:•
2. Preplacement Meeting. At least 2 weeks before placing asphalt paving mixtures, schedule an asphalt preplacement meeting with the Representative to review at a minimum the specification, paving operation QC Plan, sequence of paving operations, asphalt mixture temperature checks, mixture acceptance, density acceptance and the care and custody of asphalt acceptance samples.
Section 412.3(h)1.a. Placing. Revise to read as follows:•
1.a Placing. Unless otherwise allowed, deliver, place, and compact 6.3 mm paving mixtures during daylight hours. Ensure the mixture does not contain lumps of cold material. Deliver and place 6.3 mm paving mixtures at the laying temperatures specified in Table B.
Material placed outside the temperature limits as specified in Table B is defective.
Utilize a Material Transfer Vehicle (MTV) as specified in Section 108.05(c)5 for 6.3 mm paving mixtures unless otherwise approved by the Representative.
Section 412.4(a)4.b. Dispute Resolution. Revise TABLE H to read as follows:•
TABLE H
Dispute Resolution Retest Cost Table
Test Method
Mixture Acceptance Retest Cost if Retest Results Indicate
100% Pay Factor(s) for Full Lots (n > 3)* or Single Sample (n=1) Requirements in Table B were met for Partial Lots (n < 3)**
Mixture Acceptance Retest Cost if Retest Results Indicate
< 100% Pay Factor(s) for Full Lots (n > 3)* or Single Sample (n=1) Requirements in Table B were not met for Partial Lots (n < 3)**
PTM No.
702/739 $900 $3,500
PTM No. 757 $500 $2,000
* For full lots (n ≥ 3) where the original test results indicated a defective lot, only the pay factor(s) where original test results indicated a defective lot for asphalt content or percent passing the 75 μm (No. 200) sieve will be utilized to determine the retest cost.
** For partial lots (n < 3) where the original test results indicated a pay parameter (asphalt content, percent passing the 75 µm (No. 200) sieve, or both) did not meet the Single Sample (n = 1) requirements in Table B, only the pay parameter(s) that did not meet the Single Sample (n =1) requirements will be utilized to determine the retest cost.
Page 19 of 59November 5, 2026 13:34:42 PM
SECTION 413—SUPERPAVE MIXTURE DESIGN, STANDARD AND RPS CONSTRUCTION OF PLANT-MIXED ASPHALT
COURSES WITH PERCENT WITHIN LIMITS AND LTS TESTING (PWS-LTS)
Section 413.2(e)1. Recycled Asphalt Material. Revise to read as follows:•
1. Virgin Material Mixtures. Size, uniformly grade, and combine aggregate fractions, asphalt binder, and either WMA Technology additive(s) or modifier(s) in proportions to produce a JMF that conforms to the material, gradation, and volumetric Superpave Asphalt Mixture Design requirements according to Bulletin 27, Chapter 2A. Produce an asphalt mixture for the specified nominal maximum aggregate size and design ESALs except as procedurally modified by the WMA Technology Manufacturer Technical Representative (Technical Representative) to address laboratory procedures when preparing, compacting and testing asphalt mixtures to achieve a uniform blend. Special additive(s) or modifier(s) need not be used if mixture temperature, workability, and compaction can be achieved solely through plant mechanical modification to produce foamed asphalt. Do not incorporate the WMA Technology additive, modifier or process during the volumetric asphalt mixture design process, so that the JMF volumetrics and material percentages are based on a mixture with no WMA Technology. Only use the WMA Technology additive, modifier or process to evaluate results from moisture susceptibility testing during the mix design process. Develop an asphalt mixture JMF, then incorporate the WMA Technology additive, modifier, or process into that JMF during production. Create an asphalt JMF cover sheet (Form TR-448A) for approval containing the WMA Technology used, additive dosage rate or percent water added for foaming, material code, and the TSR data from the moisture susceptibility testing.
Submit a copy of each completed JMF, signed by a certified Asphalt Level 2 plant technician, to the DME/DMM at least 3 weeks before the planned start of mixture production. Include a list of all material sources and the asphalt mixture producer in the JMF.
Provide the calibration factors (Cf and 200 Cf) according to PTM No. 757 with the JMF. Do not start mixture production until after the DME/DMM reviews the JMF.
Submit a new JMF with a change in material sources or if a new JMF is necessary to produce a mixture conforming to this specification.
No additional revisions were made to Section 413.2(e)1.•
Section 413.2(e)1.d.5. Volumetric Analysis of Compacted Specimens. Revise TABLE A as follows:•
TABLE A
Job-Mix Formula Composition Tolerance Requirements of the Completed Mix
Single Sample (n=1) Multiple
Samples (n > 3)
Gradation Passing 12.5 mm (1/2 inch) and Larger Sieves +8% +6% Passing 9.5 mm (3/8 inch) to 150 µm (No. 100) Sieves (Inclusive) +6% +4%
Passing 75 µm (No. 200) Sieve +3.0% +2.0% Asphalt Content
19.0 mm Asphalt mixtures and smaller +0.7% +0.4%
25.0 mm Asphalt mixtures and larger +0.8% +0.5%
Temperature of Mixture (F)
Class of Material
Type of Material
Chemical, Organic, Foaming Additives
Minimum*
Mechanical Foaming Equipment/Process
Minimum* Maximum*
PG 58S-28 Asphalt Binder 215 230 310 PG 64S-22 Asphalt Binder 220 240 320 PG 64E-22 Asphalt Binder 240 260 330
The higher of 215 or the minimum temp.
The higher of 230 or the minimum temp.
As specified in Bulletin All other Binders Asphalt Binder
Page 20 of 59November 5, 2026 13:34:42 PM specified in Bulletin 25 minus 45F specified in Bulletin 25 minus 30F
* Outline in the Producer QC Plan and follow more restrictive temperature requirements provided by the WMA technology manufacturer or Technical Representative(s) for production and placement of the mixture. Determine the SGC compaction temperature for the production QC which yields the same target air voids as the designed JMF. Include the SGC compaction temperature in the Producer QC Plan. Compact the completed mixture in the SGC for QC volumetric analysis at the SGC compaction temperature according to the guidelines provided by the Technical Representative.
Section 413.2(i)2. Certification Acceptance. Revise to read as follows:•
2. Certification Acceptance. Acceptance by certification is appropriate for the following mixtures, conditions, or applications:
Scratch courses, leveling courses less than 2-inch depth and driveway adjustments.•
Mixtures used by Department maintenance forces.•
Mixtures purchased by local or municipal governments.•
Mixtures placed in quantities not exceeding 500 tons in a continuous placement operation unless otherwise directed by the Representative.
Mixtures used for parking lots.•
All 4.75 mm NMAS asphalt mixtures.•
Other mixtures, conditions, or applications as approved by the Representative.•
2.a General. Obtain certification from the mixture Producer. Use all QC tests during mixture production as acceptance tests. Certify mixtures using Form CS-4171B. Include, or attach, the QC test results on the form. Provide the form to the Inspector-in-Charge within 1 working day after completing the QC tests. Certify mixtures as specified in Section 106.03(b)3 and the requirements below.
2.b Certification of Mixture. Certify each mixture daily if QC test results conform to the single sample and multiple sample JMF production tolerances of Table A. The acceptance values will be:
Asphalt Content.•
Percent Passing the 2.36 mm (No. 8) sieve (not applicable for 4.75 mm NMAS asphalt mixtures).•
Percent Passing the 75 µm (No. 200) sieve.•
If using printed ticket results in place of laboratory test results for asphalt content, certify that at least 90% of each day’s printed ticket results for asphalt content are within 0.2 percentage points of the JMF.
If the mixture does not conform to the above requirements, do not certify the mixture. Instead, provide all QC test results to the Inspector-in-Charge. If using printed ticket results for asphalt content, provide the percentage of daily printed ticket results within 0.2 percentage points of the JMF to the Inspector-in-Charge. Payment will be determined according to Table H based on the QC test results.
If a day’s production is interrupted by corrective action, material produced after the corrective action may be certified if QC test results conform to production tolerances.
2.c Maintaining Approval to Certify Mixtures. The Department may suspend a plant’s approval to certify mixtures if QC is not performed according to the Producer QC Plan, mixtures are not produced according to Bulletin 27, a mixture cannot be certified on 2 consecutive production days, or as described below.
The Department may take IA samples of the completed mixture at the plant. In the presence of the Department, test the IA samples for asphalt content and gradation according to the test methods indicated in the Producer QC Plan. Take immediate corrective actions if the mixture does not conform to Table A.
The Department may take QA samples of the completed mixture at the plant or on the roadway directly from the uncompacted mixture placed by the paving equipment specified in Section 413.3(e). The Department will test QA samples according to PTM No. 757 or PTM
Page 21 of 59November 5, 2026 13:34:42 PM
No. 702, Modified Method D, if previously identified problematic aggregates are used in the mixture, for conformance to Table A. If the results of the QA samples do not comply with Table A, review the Producer QC Plan and the QC test results that followed the QA samples for conformance to Table A. If QC results do not conform to Table A, perform the corrective actions necessary to provide a mixture conforming to Table A.
After completing corrective actions or the sample review, the Department will perform an on-site evaluation of the Producer’s plant operation and QC and then take a sample of the completed mixture at the plant. In the presence of the Representative, test the sample.
If the sample does not comply with Table A, the Department will suspend certification. Immediately suspend shipping mixtures accepted by certification to the project.
After testing verifies that the produced mixture conforms to Tables A and B and with the Representative present, conduct JMF verification according to the Producer QC Plan. After successfully completing JMF verification, resume both certification and shipping mixtures accepted by certification to the project.