This Request for Qualifications (RFQ) #21-2627 is issued by Chesapeake Public Schools (CPS) in Virginia to solicit Statements of Qualifications from Construction Managers interested in providing pre-construction and construction services for the Chesapeake Career Center Replacement project under the Construction Manager at Risk (CMAR) delivery method. The project involves designing and constructing a new 145,000–150,000 square foot career and technical education facility on approximately 20 acres at 727 Clearfield Avenue in Chesapeake, Virginia, designed to accommodate approximately 700 students. RRMM Architects, PC has been selected as the project architect. SOQs must be submitted electronically via CPS's OpenGov Procurement Portal by 2:00 p.m. Eastern Standard Time on Wednesday, December 9, 2026. CPS will evaluate submissions and form a short list of three to five Construction Managers to receive the subsequent RFP by December 17, 2026, with proposals due by January 18, 2027 and contract award anticipated in February 2027. Pre-construction services are anticipated during the second, third, and fourth quarters of 2027, with early site package work beginning October 1, 2027, main site and building work beginning March 1, 2028, and final completion targeted for March 30, 2030 or sooner.
The construction budget is set at approximately $86,000,000, though the total project budget will not exceed the anticipated appropriation and must include all services needed for project completion. CPS requires Construction Managers to provide a valid Virginia Class A Contractor's License and a signed statement from their surety confirming willingness to provide performance and payment bonds exceeding $86 million. All SOQs must pass Pass/Fail requirements including responsiveness to the RFQ, non-debarment status, valid licensing, bonding capacity, and absence of contract completion failures. Point-rating evaluation criteria include project performance (40 percent weight), personnel qualifications and experience (35 percent), organizational structure and financial data (15 percent), and historic safety performance (10 percent). CPS will not be responsible for any costs incurred by Construction Managers during the selection process. Although no specific project set-asides are mandated, CPS encourages participation by small, women-owned, and minority-owned (SWaM) businesses. By Virginia statute and CPS policy, not more than 10 percent of construction work, as measured by cost, may be performed by the Construction Manager with its own forces.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
RFQ #21-2627
REQUEST FOR QUALIFICATIONS
Construction Manager / Construction Services for the Chesapeake Career Center Replacement
Chesapeake Public Schools Date: November 9, 2026
Chesapeake Public Schools has transitioned to a new eProcurement solution (OpenGov) for publishing solicitations, and receiving vendor responses. Bid responses are to be submitted electronically exclusively via the Chesapeake Public Schools’ OpenGov Procurement Portal:
https://procurement.opengov.com/portal/cpschools
Bid responses must be submitted no later than the due date / time specified.
Hard copies and responses submitted by e-mail, facsimile, and telephone will not be accepted.
Instructions for Vendor Registration with OpenGov Procurement are available online in the OpenGov Help Center, or e-mail Support at procurement-support@opengov.com.
Vendors can subscribe to get notifications for upcoming Chesapeake Public Schools’ projects by visiting the Chesapeake Public Schools’ Procurement Portal and clicking the "Subscribe" button.
To receive updates regarding specific solicitations, visit the Chesapeake Public Schools’ OpenGov Procurement Portal, Open the Project link, and click “Follow “.
CHESAPEAKE PUBLIC SCHOOLS
RFQ #21-2627
Request for Qualifications Construction Manager / Construction Services for the
Chesapeake Career Center Replacement
Chesapeake Public Schools (CPS) is soliciting Statements of Qualifications (SOQ) from Construction Managers (CM) interested in providing pre-construction and construction services, under the Construction Manager (CM) method of project delivery, for a CPS Capital Project consisting of a new career and technical education facility (the building will be referenced as “Career Center” and the process of design and construction of the Career Center will be referenced as the “Project). RRMM Architects, PC has been selected as the architect for the Project.
CPS will evaluate responses to this Request for Qualifications (RFQ) to identify CMs with the experience, qualifications, and resources necessary to successfully complete the Project in accordance with the project requirements. Those requirements will be detailed in a Request for Proposal (RFP) that CPS will issue to a short list of CM candidates. CPS will evaluate each CM’s SOQ to determine whether the information provided demonstrates the CM is capable of performing the required work.
SOQs for the Project will be received only through CPS’s OpenGov Procurement Portal. SOQs must be received in portable document format (PDF) at https://procurement.opengov.com/portal/cpschools/projects/324638. SOQs must be received by 2:00 p.m., eastern standard time, on Wednesday, December 9, 2026. CPS will not consider late submissions. Only electronic responses submitted via the CPS Procurement Portal will be accepted. Please submit any questions regarding this RFQ in writing, using the Procurement Portal. Be sure to click the “Follow” button in the project to receive updates.
BACKGROUND TO THE RFQ
On October 29, 2026, the CPS Division Superintendent of Schools formally requested authority from the School Board of the City of Chesapeake (the “Board”) to use the CM project delivery method for the Project. The Superintendent made certain findings required by statute and CPS Board Procurement Policy in connection with this request. The Board adopted the Superintendent’s findings and passed a motion authorizing the use of CMAR for the Project. A copy of the Superintendent’s findings is attached as Exhibit A. Minutes of the Board meeting at which the Board approved the use of CMAR for the Project will be placed in the procurement file once such minutes are in final, approved form.
PROJECT DESCRIPTION
This Project includes pre-Construction and construction services for the construction of a new 145,000-150,000 square foot career and technical education facility. The site of the new facility is 727 Clearfield Avenue, City of Chesapeake, is approximately 20 +/- acres, and is owned by CPS. It is anticipated that this building will hold approximately 700 students. This Project is part of a series of CPS facilities designed and built to support next-generation, active and differentiated learning. A full package of Owner Project Requirements (OPR), all site information, and project concept will be issued with the upcoming RFP.
The pre-construction scope of services includes collaborating with the design professionals during the design phase, attending design coordination meetings, performing constructability reviews, providing value engineering guidance, developing the construction schedule, and developing and negotiating a guaranteed maximum price (GMP) proposal for construction services. If the GMP negotiations are successful, the contract will be amended to incorporate the
GMP.
The construction budget for the Project has been set at approximately $86,000,000, but in any event, the total Project budget will include all services needed for the construction of the project and will not exceed the anticipated appropriation. CPS anticipates that pre-construction services will be required from the CM in the 2nd, 3rd and 4th quarter of 2027. CPS anticipates construction activities to begin as soon as possible for a Final Completion of the Project by March 30, 2030 or sooner.
Major milestones for the Project are as follows:
November 9, 2026 Issue RFQ for CM at Risk process December 9, 2026 Receive responses to RFQ December 17, 2026 Issue RFP to short-list January 18, 2027 Proposals due February 2027 Award Contract to Construction Manager October 1, 2027 Begin Early Site Package Work March 1, 2028 Begin Main Site and Building Work March 30, 2030 Final Completion of All Building and Site Work
CPS expects the Project Schedule to be collaboratively fine-tuned by the successful CM, CPS, and Design Team.
GENERAL
The successful CM will furnish all labor, materials, equipment, tools, services, and incidentals to complete the Project in accordance with the specifications and drawings.
CPS shall not be responsible for any cost incurred by the CMs because of participation in this selection process. Each CM shall bear its own expenses in connection with the preparation and submission of materials and the provision of any supplemental information requested. CPS shall have no liability for cost incurred by the CMs in connection with the review and evaluation of qualification materials and any findings or determinations made therefrom.
This is not a solicitation for a proposal.
CPS’s decisions concerning the CMs chosen to receive an RFP are final and shall not constitute a determination that the CM is responsible. Accordingly, a short-listed CM may be rejected on the basis of subsequently discovered information. CPS’s action in rejecting a CM as non-responsible shall be final.
Pursuant to law and CPS policy, the contract will include a provision that not more than 10% of the construction work, as measured by the cost of the work, may be performed by the CM with its own forces.
STATEMENT OF QUALIFICATIONS (SOQ) REQUIREMENTS
The CM must complete and submit, via CPS’s Procurement Portal, a portable document format (PDF) of their submittal with all associated forms and attachments, which together comprise the CM’s SOQ. The SOQ shall be signed where indicated and submitted to CPS via CPS’s electronic submittal process. The CM’s name and the Project name “Chesapeake Career Center Replacement” should be clearly displayed on the project documentation.
Time and date of receipt of the SOQ will be logged by CPS’s electronic submittal process.
Timely submission is the sole responsibility of the CM. Hard copies, fax copies, or any submission via any other format other than described above will not be considered. Responses received after the specified time will not be considered.
The SOQ must be typed or neatly printed. The information presented should be clear, complete, concise, truthful, and accurate. All attachments submitted shall be identified with the name of the CM. Failure to submit a response on the official submittal forms provided in the RFQ for that purpose may be considered just cause for rejection of the response. CPS reserves the right to decide on a case-by-case basis, at its sole discretion, whether to reject a CM’s submittal. CPS’s decision to reject a submittal is final.
A. PASS / FAIL REQUIREMENTS
A FAIL rating on any item in the category titled “PASS / FAIL Requirements” will be considered sufficient cause to reject the CM’s SOQ.
The following are PASS or FAIL criteria:
1. Responsiveness to RFQ – Only responsive SOQs, submitted by the deadline indicated previously, will be considered, and evaluated. A responsive SOQ must be completed according to the instructions, include all required attachments and requested information, and be comprised of, but not limited to, the following:
• Attachment B: Cover Page
• Attachment B-1: CM Information
• Attachment B-2: Details of Past Projects
• Attachment B-3: CM Affidavit
Additional information must be included in the SOQ as needed to provide a complete response to the RFQ.
2. Debarment Status – By submitting an SOQ, the CM certifies that neither it nor any affiliated entity is currently debarred or has otherwise agreed not to submit bids on contracts with any government or business entity. If the CM experiences a material change in its debarment status after the SOQ is submitted and prior to the award of the contract for the Project, the CM shall notify CPS of the change, in writing, at the time the change occurs or as soon thereafter as is reasonably practicable. Debarment of the CM, whether occurring prior to or during the SOQ phase, will result in rejection of the CM’s submittal.
3. Contractor’s License – The CM must provide a copy of their valid Virginia Class A Contractor’s License.
4. Bonding Capacity / Statement – The CM must provide a signed statement from its Surety stating that, based on present circumstances, the Surety is willing to provide performance and payment bonds exceeding $86 million for the CM in connection with the Project.
5. Failure to Complete – By submitting an SOQ, the CM certifies that neither it nor any affiliated entity has failed to complete a contract. If the CM experiences a material change in this status after the SOQ is submitted and prior to the award of the contract for the Project, the CM shall notify CPS of the change, in writing, at the time the change occurs or as soon thereafter as is reasonably practicable. If at any time during the evaluation process the CM fails to complete a contract as described above, it will be considered grounds to reject the CM’s submittal.
CONFIDENTIAL / PROPRIETARY INFORMATION
Trade secrets or proprietary information submitted by the CM shall not be subject to public disclosure under the Virginia Freedom of Information Act (Virginia Code § 2.2- 3700 et seq.) (VFOIA). However, to prevent disclosure, the offeror must invoke the protections of Virginia Code § 2.2-4342, in writing, either before or at the time the data or other materials are submitted. The CM must clearly indicate each page that is deemed confidential, proprietary, or a trade secret using the Claim of Business Confidentiality form (Attachment “C”) and state the reasons why protection is necessary. The proprietary or trade secret material submitted must be identified by some distinct method such as highlighting or underlining and must indicate only the specific words, figures, or paragraphs that constitute trade secret or proprietary information. The CM should submit physical materials in such a way that pages marked as confidential, proprietary, or trade secrets can be readily separated, physically, from portions of the submission that are not so marked.
The classification of an entire proposal document, line-item prices and / or total proposal prices as proprietary or trade secrets is not acceptable and will result in the rejection and return of the proposal. If CPS determines that a page or portion of a page designated “proprietary”, “confidential” or “trade secret” is not entitled to protection from public disclosure under VFOIA and Virginia Code § 2.2-4342(F), CPS will undertake reasonable effort to notify the CM of such determination prior to producing the documents in response to a FOIA request. It will be the obligation of the CM to initiate judicial proceedings to protect the confidentiality of the document.
By signing the SOQ, the CM certifies that it will indemnify and hold harmless CPS, including the Board and its employees, from and against any third party claim to obtain disclosure of the document, including the cost and expense (including attorneys’ fees) required to defend against the claim.
If CMs intend to protect any Trade Secrets or Proprietary information, they must submit one (1) identical redacted electronic copy of the proposal at the same time as the original online response, along with invoking the protections in writing as directed.
EVALUATION
All SOQs will be evaluated by CPS’s Evaluation Committee (EC). The EC reserves the right to waive any and all irregularities or informalities in the submittal, reject any and all submittals, and to accept the submittals most favorable to CPS. CPS may summarily reject any submittal that is nonconforming to the requirements of this RFQ.
Written notification of each CM’s status regarding an invitation to respond to the RFP will be provided at the conclusion of the SOQ evaluation process. In evaluating each SOQ, CPS will consider, by way of illustration and not limitation, the criteria included in Section B below.
B. POINT-RATING ITEMS
All SOQs that pass the PASS / FAIL Requirements and comply with the other requirements of this RFQ will be evaluated by the EC in accordance with the Point- Rating System identified in Attachment “A”. Based on the Point Rating System, the Evaluation Committee will form a short-list of three (3) to five (5) offerors to receive the RFP. The short list may have less than three (3) offerors to receive the RFP if there are less than three (3) passing responses to the RFQ.
If any of the short-listed CMs subsequently withdraw or are removed for cause, CPS reserves the right to add the next highest ranked CM who passed the PASS / FAIL Requirements to the short-list to ensure there are no fewer than three (3) proposals in response to the RFP. In considering a CM’s points rating, the EC shall be the sole judge of the CM’s financial capacity, as demonstrated by its bonding capacity and the financial information submitted with its SOQ, history of satisfactory performance, and whether or not the contractor possesses a sufficient number of experienced qualified personnel at its management and supervisory levels and has demonstrated a commitment on its projects to accommodating changes and disruptions in the Work, all of which indicate the ability to successfully complete the Project at a reasonable cost to CPS, in accordance with the Project’s schedule.
1. Project Performance – During evaluation of project performance, emphasis will be placed on past performance on projects of a similar size, nature, and scope to this CPS Project (regardless of the delivery method), including CM’s ability to meet scheduled completion dates and project budgets. Preference will be given to CMs with management, manpower, and expertise located in the Mid-Atlantic region. Preference will also be given to CMs who have demonstrated significant experience, ingenuity, transparency, and collaborative approaches in performing projects of similar size, nature, and scope to the Project.
2. Personnel Qualifications / Experience – The potential project manager(s) and superintendent(s) must have experience on projects of similar size, nature, and scope. The qualifications of other key personnel the contractor would like to provide will also be considered in this evaluation.
3. Organizational Structure and Financial Data – Both the CM’s organizational structure and the financial capacity will be evaluated.
4. Historic Safety Performance – Safety data will be reviewed and compared to current OSHA and insurance industry standards.
MINORITY / SMALL BUSINESS PARTICIPANTS
Although there are no specific project requirements for the Project, CPS encourages CMs to seek participation by small, women-owned, and minority-owned (SWaM) businesses.
ADDENDA AND INTERPRETATIONS
All inquiries related to this RFQ must be addressed to Ms. Michele Zimbro, CPPB, Buyer, via the CPS Procurement Portal and must be submitted no later than ten (10) calendar days prior to the date fixed for the submittal of the SOQ. The response to any inquiries and any revisions to or clarification of this RFQ will be made only by addendum and posted in the CPS Procurement Portal, no later than five (5) calendar days prior to the date fixed for submittal of the SOQ.
Failure to receive any such addenda shall not relieve CM from any obligation under the RFQ. All addenda shall become part of the RFQ. In their SOQ submittal, the CMs must acknowledge receipt of the addendum / addenda.
NOTICE OF SUBSTANTIAL CHANGES
If the CM experiences a material change in its debarment status, financial condition, corporate structure, or personnel after the SOQ is submitted, and prior to award of the contract for the Project, the CM shall notify CPS of the change, in writing, at the time the change occurs or as soon thereafter as is reasonably practicable. Failure to notify CPS of any material change in the contractor’s debarment status, financial condition, corporate structure, or personnel may constitute grounds for rescinding an “invitation to propose” or for rejection of the responsive proposal.
MISREPRESENTATION
If any CM knowingly makes a misrepresentation in submitting information to CPS, fails to provide all required information, or provides information that is misleading, such misrepresentation, omission, or misleading information will be sufficient grounds to reject the CM’s submittal, to rescind a previously issued invitation to propose, or for rejection of a proposal submitted as a result of this selection process.
COLLUSION AMONG CMs
More than one (1) response from an individual, firm, partnership, corporation, or association under the same or different name will be rejected. Some or all responses may be rejected if there is any reason for believing that collusion exists among the potential CMs. Participants in such collusion will not be considered in future RFQs / RFPs for the same work. Each CM, by submitting a response, certifies that they are not a party to any collusive action or to any action that is otherwise unlawful.
OTHER MATTERS
This RFQ is subject to (i) all the terms, conditions, and procedures contained in the applicable CPS procurement policies and guidelines, as amended from time to time, and which are incorporated herein by reference and (ii) all applicable provisions of the Virginia Public Procurement Act and other state law. CPS reserves the right to discontinue the procurement process initiated under this RFQ at any time, for any reason or for no reason, and, subsequently, to begin the procurement process for the Project under a new RFQ or under any other procurement method permissible under Virginia law.
ATTACHMENT A
CPS EVALUATION FORM
(This form is for CPS’s Evaluation Committee use only – not for completion by CM)
CM Name:
PASS / FAIL EVALUATION TABLE
CATEGORY PASS FAIL
Responsiveness to RFQ
Debarment Status
Contractor’s License
Bonding Capacity / Statement
Failure to Complete Contract
POINT RATING EVALUATION TABLE
ITEM
POINT RATING
ITEMS
WEIGHT
GRADE
SCALE
(0 thru 5)
TOTAL
1. Project Performance 40%
2.
Personnel Qualifications / Experience
35%
3.
Organizational Structure / Financial Data
15%
4.
Historic Safety Performance
10%
TOTAL
GRADING SCALE
0 = Poor 1 = Questionable 2 = Below Average 3 = Average 4 = Above Average 5 = Most Favorable
ATTACHMENT B
COVER PAGE
A copy of this page shall be the cover page for the SOQ. A set of attachments and any additional information should be included with each copy of the SOQ submittal.
1. CM Name:
Provide all names under which the CM does business:
Is the CM related to another firm as a parent, subsidiary, or affiliate? Yes No If yes, attach names and addresses for all affiliated, parent and / or subsidiary companies, and state the nature of each affiliation.
2. Address:
3. Tax Identification Number (EIN / SSN):
4. Is CM a corporation or limited liability company? Yes No
If yes, what is the State of Incorporation or Organization?
5. If not incorporated as a corporation or organized as an LLC, specify method and date of organization:
If a partnership, attach partnership details (such as partner’s names and individual contact information for each partner). If a Joint Venture (JV), attach the JV agreement and provide details of the intended role of each JV member, including appropriate additional attachments (at a minimum submit an Attachment B for each JV member).
6. Specify the portions of the work that the CM expects to subcontract:
7. Provide contact information including name, title, phone number and email address of the person who can respond authoritatively to any questions regarding this response:
Acknowledgment of Addenda:
No. 1: Date _______________________________Signature___________________________
No. 2: Date _______________________________Signature___________________________
No. 3: Date _______________________________Signature___________________________
Signed by:
Printed name:
Title:
ATTACHMENT B-1
CM INFORMATION
A. PASS / FAIL EVALUATION
1. Responsiveness to RFQ – Responsiveness is defined in the RFQ section titled PASS / FAIL Requirements.
2. Debarment Status: Has the CM or any affiliate experienced:
a. Debarment
b. Deletion from a Prequalified Bidders List
c. Other action which resembles debarment
3. Contractor’s License – Submit a copy of the CM’s valid Virginia Contractors Class A License.
4. Bonding Capacity / Statement – Submit a signed statement from CM’s Surety stating that, based on present circumstances, the Surety will be willing to provide performance and payment bonds exceeding $86 million for the CM in connection with the Project.
Total bonding capacity $
Available bonding capacity $
5. Failure to Complete – Has your organization ever failed to complete any work awarded to it? This includes termination for the convenience of the Owner or any other reason for failing to complete a project. Yes No
B. POINT RATING ITEMS
1. Project Performance
Using a separate copy of Attachment B-2 for each project, provide details of at least three (3) construction projects by any method of project delivery that have reached Substantial Completion over the preceding ten (10) years and that are of similar size, scope, and nature to the Project. Include any other information with Attachment B-2 you believe may be helpful to CPS for an evaluation of your project performance. If your response includes discussion of any CM projects, or if you have comparable experience in any of the following areas, the following information may be helpful to the Evaluation Committee: the CM’s level of participation in design development, preparation of progressive construction estimates, and value engineering reviews / recommendations; the CM’s prior development of GMP proposals using open-book pricing; if subcontractor pre-
(Continued) qualification and work package bidding was administered by the CM; and if the CM was required to submit competitive bids for work packages the CM intended to self-perform.
CPS will contact references listed in the CM’s SOQ. CPS may also contact other potential references if referred to them in the course of this evaluation. CPS reserves the right to contact any party it deems appropriate. By submitting an SOQ, the CM releases CPS and any references from all liability concerning this exchange of information. CMs should ensure that the reference information provided is current. Letters of reference should NOT be included in the CM’s SOQ, since such letters do not follow a standard objective format.
Have any of the following actions occurred on, or in conjunction with, any project performed by the CM, any affiliate, or their officers, partners or directors in the last five (5) years?
a. Legal Action Implemented by CM against Owner: Yes ; No
b. Legal Action Implemented by CM against Subcontractor: Yes ; No
c. Legal Action Implemented by Owner against CM: Yes ; No
d. Legal Action Implemented by Subcontractor against CM: Yes ; No
e. Settlement or Close Out Agreement in effect with Owner: Yes ; No
f. Judgments: Yes ; No
g. Arbitration: Yes ; No
If the answer to any of the items a. through g. above is yes, provide details on a separate sheet for each instance.
Have actions from a third party occurred on, or in conjunction with, any project performed by the CM, any affiliate, or their officers, partners or directors in the last five (5) years related to the following:
a. Erosion and Sediment Control Permit Violations: Yes ; No
b. Violation of Owner’s Discharge or Non-Discharge Permits: Yes ; No
c. 401 / 404 Permit Violation: Yes ; No
If the answer to any of items a. through c. above is yes, provide details on a separate sheet for each instance.
2. Personnel Qualifications / Experience
Provide proposed project organization chart and attach resumes of key personnel.
Include years of construction experience, last employer, last position, and experience on similar projects.
3. Organizational Structure / Financial Data
a. Submit a copy of the CM’s corporate organizational chart. Provide the total quantity of company employees as well as the quantity of employees identified by discipline and project, with names and titles down through field superintendents.
b. Submit your most recent audited financial statements for a 3-year period, including complete balance sheets and income statements.. The statements should be submitted in a separate distinctly titled file and included in the SOQ package. Data provided for parent or child entities related to the CM firm in lieu of the CM’s data shall not be reviewed and shall be considered non-responsive.
c. Has the CM, or any affiliate, ever been denied bonding or had bonding revoked? Yes No
4. Safety Performance
On a separate sheet, provide the following:
a. Experience Modification Factor (EMF) with 3-year and 5-year trends
b. Loss Ratio with 3-year and 5-year trends
c. Accident Frequency Rate with 3-year and 5-year trends
d. A list of OSHA citations levied during the past five (5) years. Describe infractions and indicate whether there was a warning or fine imposed and the dollar amount of each.
e. Details from your organization’s OSHA 300A log for the past five (5) years indicating:
• Number of lost workday cases,
• Number of restricted workday cases,
• Number of cases with medical attention only,
• Number of fatalities.
ATTACHMENT B-2
DETAILS OF PAST PROJECTS
(Use a separate copy of this form for each project)
1. CM Name:
If CM’s name is not the same as the entity performing the past project, state relationship (i.e. parent company, subsidiary, JV, etc.)
Project Manager:
Superintendent:
Nature of Services Performed (e.g. General Contractor, Construction Manager, Design- Builder, etc.):
2. Project Name:
Facility Name:
Project Location:
Contract # Project #
Owner:
Address:
Contact Person:
Contact Title, Phone, E-mail:
3. Architect / Engineer:
4. Construction Manager (if any):
5. Contract Dates (completion dates should reflect Substantial Completion)
Notice to Proceed:
Contractual Completion:
Actual Completion:
6. Description of Project:
(Include Project Delivery Method Used – Design-Bid-Build [DBB]; Design-Build [DB], Construction Manager At-Risk [CMAR], or other [describe]). Use additional attachment, if necessary.
7. Contract Value:
Original: $
Final Contract Value $
Final Subcontract Value $
Total % of GC and OH&P $
Value of Change Orders $
Outstanding Claims (if any) $
Owner Budget (if known) $
9. Bonding Company:
10. Work Packages (Trade) Self-Performed (Use additional attachments, if necessary):
a. Work Performed:
Work Package Contract Value: $
b. Work Performed:
Work Package Contract Value: $
c. Work Performed:
Work Package Contract Value: $
d. Work Performed:
Work Package Contract Value: $
e. Work Performed:
Work Package Contract Value: $
f. Work Performed:
Work Package Contract Value: $
g. Work Performed:
Work Package Contract Value: $
h. Work Performed:
i. Work Performed:
11. List the five (5) largest subcontracts on this project.
a. Subcontractor Name
Trade: Subcontract Value:
Work Performed:
Address:
b. Subcontractor Name
Trade: Subcontract Value:
Work Performed:
Address:
c. Subcontractor Name
Work Performed:
Address:
d. Subcontractor Name
Work Performed:
Address:
e. Subcontractor Name
Work Performed:
Address:
ATTACHMENT B-3
CM AFFIDAVIT
The undersigned hereby attests under penalty of perjury and by personal knowledge to the following:
1. The contents of the SOQs (including all submitted attachments and other documentation) are true, correct, and not misleading.
2. To the best of my knowledge neither the CM, nor its agents, affiliates, partners, employees, officers, directors or other associates of any kind, have colluded with any individual or entity on behalf of the CM, or themselves, to produce an unfair advantage over others or to gain favoritism in the award of any contract resulting from this RFQ.
3. By responding to this RFQ and submitting the SOQs, the CM agrees to indemnify and hold harmless CPS and any architect, engineer or other professional CPS employs or retains in connection with the Project or this RFQ, or any associated RFP, from any and all claims, damages, losses, and expenses arising out of or relating to the CM’s response, participation in this RFQ, or any associated RFP; and affirms that no compensation is expected as a result of the preparation of said response.
CM Name:
Officer’s Signature:
Printed Name and Title:
Telephone Number:
COMMONWEALTH OF VIRGINIA
CITY / COUNTY OF ________________________
BEFORE ME, a Notary Public of the Commonwealth of Virginia and the jurisdiction aforesaid, appeared this day of , 2026, one , known to me to be of , and swore to me under penalties of perjury on behalf of the CM that the statements contained in the attached affidavit are true and correct to his or her knowledge and belief.
[NOTARY SEAL] Notary Public
ATTACHMENT C
CLAIM OF BUSINESS CONFIDENTIALITY
Virginia Public Procurement Act – Virginia Code § 2.2-4342
Public inspection of certain records: Except as provided in this section, all proceedings, records, contracts and other public records relating to procurement transactions shall be open to the inspection of any citizen, or any interested person, firm or corporation, in accordance with the Virginia Freedom of Information Act (§ 2.2-3700 et seq.).
Trade secrets or proprietary information submitted by a bidder, offeror, or contractor in connection with a procurement transaction or prequalification application submitted pursuant to subsection B of § 2.2-4317 shall not be subject to the Virginia Freedom of Information Act (§ 2.2-3700 et seq.); however, the bidder, offeror, or contractor shall (i) invoke the protections of this section prior to or upon submission of the data or other materials; (ii) identify the data or other materials to be protected; and (iii) state the reasons why protection is necessary.
A bidder, offeror, or contractor shall not designate as trade secrets or proprietary information (a) an entire bid, proposal, or prequalification application; (b) any portion of a bid, proposal, or prequalification application that does not contain trade secrets or proprietary information; or (c) line item prices or total bid, proposal, or prequalification application prices.
References may be made within the body of the proposal to proprietary information; however, all information contained within the body of the proposal, not under separate cover and labeled proprietary, shall be Public Information in accordance with state statutes.
The statement of reasons supporting the claim of business confidentiality applies to the following information in this proposal:
Page Paragraph Reason
Please use additional sheets, if needed.
Signed: _____________________________________________________
Printed Name: ________________________________________________
Title: __________________________________Date: ________________ RFQ #21-2627
MEMORANDUM
TO: Members of the School Board
FROM: Doug Brubaker, Ph.D, Superintendent J. Paige Stutz, Chief Operations Officer
DATE: October 22, 2026
SUBJECT: Request for Authorization to Procure Construction Management at Risk Services for the Chesapeake Career Center Replacement
The school administration requests authorization from the Board to utilize Construction Management at Risk (“CMAR”) services for the Chesapeake Career Center Replacement (“Career Center”). A local public body is permitted to contract for construction on a fixed-price or not-to-exceed price basis by procuring construction management services. See Virginia Code § 2.2-4382. Prior to entering into a contract, the local public body must adopt procedures for construction management. The Board adopted, via resolution, construction management procedures that include the requirements found at § 2.2-4382 and are consistent with the procedures adopted by the Commonwealth of Virginia Secretary of Administration for utilizing construction management contracts. The “Construction Management (CM) Construction Contract Procedures Adopted by the School Board of the City of Chesapeake” are attached as Exhibit A.
[HL2]
The Board hired RRMM Architects, PC (“RRMM”) to design the Career Center and to advise the Division on the suitability of CMAR services for the Career Center. RRMM has many years of significant experience with alternative project delivery methods. The firm is currently involved in multiple CMAR projects throughout Virginia, including our elementary school project located in the Culpepper Landing subdivision.
For the Career Center project, RRMM recommends the use of the CMAR model. The construction industry continues to experience significant subcontractor and supply chain challenges. The CMAR model gives the Construction Manager the ability to engage earlier in the design process and to manage the critical project timeline, complex phasing, site constraints, continual need to value-engineer, and navigation of the current construction market.
Exhibit A
Outlined below are additional points consistent with the procedures approved for CMAR specifically related to the Career Center.
● Project Phasing and Project Schedule: The Project has a unique complexity due to the low elevation of the site, the unsuitable soil bearing capacity, and a tight schedule. The first phase of site preparation is expected to last approximately five months prior to the start of main site and building construction. Unlike the Design-Bid-Build process, in the CMAR process, the contract will be awarded and executed prior to the completion of the main site and building design. Importantly, this allows the Construction Manager to integrate responsibility, liability, and coordination for the early phases of work with the main site and building construction contract. Similarly, the Construction Manager may recommend and incorporate other early packages to the benefit of Chesapeake Public Schools.
● Competitive Pricing: Current construction pricing is volatile, and general contractors and subcontractors are in high demand. In the Crestwood Elementary School project which used the Design-Bid-Build method of procurement, market conditions and the lack of subcontractor participation prevented the District from obtaining competitive pricing. Here, the CMAR process will allow the Construction Manager to develop subcontractor teams and solicit bids over an extended time period, which will be more fiscally advantageous to Chesapeake Public Schools. The Construction Manager will determine a Guaranteed Maximum Price (“GMP”) early in the process and prior to the final completion of detailed construction documents. Early delivery of the GMP avoids much of the delay and negotiation required to award a contract through the traditional Design-Bid-Build delivery method.
● Economy, Efficiency, and Integrated Design: CMAR integrates the construction contractor into the design process. The early involvement of the Construction Manager benefits the District by allowing the Construction Manager to advise on cost savings, constructability review, and preliminary GMP opinions. It brings critical construction trade subcontractors and suppliers to the design process in an advisory capacity and manages possible early construction and procurement packages. The design team will benefit from the input of the Construction Manager in the design of the project’s complex mechanical systems. This synergy during the design process will increase project team efficiency and avoid constructability issues.
● Delays in Construction Material Procurement: Market lead times for purchase and delivery of major building components, if procured through a traditional Design-Bid-Build timeline, would push project completion well past the required completion date. The Construction Manager will be positioned to begin procuring construction materials during the design phase, specifically with respect to components requiring a longer lead time. The Construction Manager may also assist the Division with early direct purchase items as deemed appropriate due to excessive lead times.
● Legal Advice: The Board’s attorney reviewed records relevant to the Career Center project and advises that this project follows the Board’s CM procedures, is consistent with the Secretary of Administration’s procedures, and complies with the requirements of the Virginia Code.
Based on the justifications provided above, I recommend the School Board authorize the administration to proceed with the procurement of CMAR services for the construction of the Career Center.
Attached: Exhibit A
| ^Career Center Draft FINAL |
| Request for Authorization to Procure CMAR Services for CCC Replacement |
| MEMORANDUM |
File details come from the government source that posted it. Updated .