852948rehabOcp.pdf
PDF 1 MB Posted
- Attached to
- FY26-SBGP Rehab-5201 Central Avenue SE
- Solicitation number
- Doc843967
- Issued by
- District of Columbia
About this file
File Summary
This is a Sealed Bid Invitation for Bid (IFB) document issued by the District of Columbia Office of Contracting and Procurement on behalf of the Department of Housing and Community Development (DHCD) for moderate property rehabilitation services at 5201 Central Avenue SE. The project is funded under DHCD's Small Buildings Housing Provider Grant (SBGP) Program and seeks a general construction contractor pre-qualified under RFQ solicitation Doc782665 to perform general construction, repair, replacement of major systems, and moderate rehabilitation work at the privately owned multifamily property. The contract will be awarded as a single lump-sum firm fixed price agreement with a base period of one year from the award date. The solicitation was issued on November 3, 2026, with offers to be submitted electronically by 2:00 p.m. local time on the submission due date posted in e-Sourcing. The Notice to Proceed will trigger the commencement of work, with the Substantial Completion Date and Final Completion Date to be determined and identified in the individual awarded contract. Key preconstruction deliverables include submission of a detailed project schedule within seven days of Notice to Proceed, a safety plan, required permits within ten days of award, and compliance with OSHA regulations.
The contract pricing structure includes a lump-sum price for the base rehabilitation work (CLIN 0001) and a separate ten percent contingency allocation (CLIN 0002), with bidders required to provide all labor, materials, equipment, bonds, insurance, permits, and project administration costs within the fixed price. For contracts exceeding $250,000, at least thirty-five percent of the dollar volume must be subcontracted to Small Business Enterprises (SBEs) or Certified Business Enterprises (CBEs) in accordance with District law, with a subcontracting plan required at bid submission. The contract is subject to Davis-Bacon Wage Determinations (DC20260003), the Living Wage Act of 2006 for services contracts valued at $100,000 or more, First Source Employment Agreement requirements for contracts of $300,000 or more (with a requirement that at least fifty-one percent of new hires be District residents), and performance and payment bonds equal to one hundred percent of the contract award amount. Contractor responsibilities include site security, daily debris removal, quality assurance planning, warranty provisions for one year following substantial completion, and compliance with all applicable federal and District regulations including lead-based paint abatement, OSHA construction standards, and environmental protection requirements.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
HeSOLICITATION, OFFER, AND AWARD
1. Caption SBGP Moderate Property Rehabilitation Services – 5201 Central Avenue SE
Page of Pages
1 70
2. Contract Number 3. Solicitation Number
Doc843967
4. Type of Solicitation Sealed Bid (IFB) Sealed Proposals (RFP) Sole Source Emergency
5. Date Issued
11/3/2026
6. Type of Market Open Set Aside Set Aside-DHCD/SBGP Approved Supplier
7. Issued By Office of Contracting and Procurement 441 - 4th Street, N.W., Suite 700 South Washington, D.C. 20001
8. Address Offer to:
Office of Contracting and Procurement 441 - 4th Street, N.W., Suite 700 South Washington, D.C. 20001
NOTE: In sealed bid solicitations “offer” or “Offeror” means “bid or “bidder”
SOLICITATION
9. The sealed offers shall be submitted only in electronic format via the on-line solicitation software. Telephonic, hand-delivered, posted, e-mail, telegraphic and facsimile bids will not be accepted. All items accepted by the District, all pages of the Invitation for Bid (IFB), all attachments and all documents containing the offeror’s offer shall constitute the formal contract.
The sealed offers can be submitted electronically until 2:00 p.m. local time on submission due date posted in e-Sourcing.
(Hour)
CAUTION: Late submission, Modifications and Withdrawals: See 27 DCMR chapters 15 & 16 and Section L.3.1 as applicable. All offers are subject to all terms & conditions contained in solicitation
10. For Information Contact A. Name B. Telephone C. E-mail Address
Rebecca Young (Area Code)
(Number) 442-6914
(Ext) rebecca.young@dc.gov
11. Table of Contents
(X) Section Description Page No. (X) Section Description Page No.
PART I – THE SCHEDULE PART II – CONTRACT CLAUSES
X A Solicitation/Contract Form 1 X I Contract Clauses 42 X B Supplies or Services and Price/Cost 2 PART III – LIST OF DOCUMENTS, EXHIBITS AND OTHER ATTACHMENTS X C Specifications/Work Statement 4 X J List of Attachments 60 X D Packaging and Marking 22 PART IV – REPRESENTATIONS AND INSTRUCTIONS X E Inspection and Acceptance 23
X K Representations, certification and other statements of Offeror’s 61
X F Deliveries or Performance 24 X G Contract Administration Data 25 X L Instructions, conditions & notices to Offeror’s 63 X H Special Contract Requirements 31 X M Evaluation factors for award 69
12. In conjunction with the above, the undersigned agrees, if this offer is accepted within _______120_______ calendar days from the receipt of offers specified above, to furnish any or all items upon which prices are offered at the price set opposite each item, delivered at the designated point(s), within the time specified herein.
Prompt Payment 10 Calendar days % 20 Calendar days % 30 Calendar days % ____ Calendar days %
14. Acknowledgement of Amendments (The Offeror acknowledges receipt of amendments to the
SOLICITATION):
Amendment Number
Date Amendment Number Date
15A.
Name and Address of
Offeror
16. Name and Title of Person Authorized to Sign Offer/Contract
15B. Telephone 15 C. Check if remittance address is different from above – Refer to Section G
17. Signature 18. Award Date (Area Code) (Number) (Ext)
AWARD (TO BE COMPLETED BY GOVERNMENT)
19. Accepted as to Items Numbered 20. Amount 21. Accounting and Appropriation
2. Name of contracting Officer (Type or Print) 23. Signature of Contracting Officer (district of Columbia) 24. Award Date
Government of the District of Columbia Office of Contracting & Procurement mailto:rebecca
Solicitation Docx843967 SBGP Moderate Property Rehabilitation Services – 5201 Central Avenue SE
SECTION B: CONTRACT TYPE, SUPPLIES OR SERVICES AND
PRICE/COST
B.1 The District of Columbia Office of Contracting and Procurement, on behalf of the Department of Housing and Community Development (DHCD) is seeking a general construction contractor deemed qualified under RFQ solicitation Doc782665 to perform general construction, repair and replacement of major systems and moderate rehabilitation services for the privately owned multifamily property, 5201 Central Avenue SE, within the Department of Housing and Community Development Small Buildings Housing Provider Grant Program, and other related funded programs at
DHCD.
B.2 The District contemplates award of a single lump-sum firm fixed price contract.
B.2.1 This will be Lump Sum Firm Fixed Price type contract. Bidders will be required to provide a Lump Sum Price which shall include sufficient funds to cover all the expenses necessary to complete the Project, including, but not limited to, profit, home and field office overhead, supervision, labor, materials, equipment, bonds, insurance and other services that may be required to obtain the necessary permits, and construct the work. The Lump Sum Price shall also include sufficient funding to fund items that are not specifically identified in the drawings and specifications, but which are reasonably inferable therefrom.
B.3 PRICE SCHEDULE – LUMP-SUM FIRM FIXED PRICE
B.3.1 BASE PERIOD (Award Date to One-Year Thereafter)
B.3.2 The awarded contractor shall be paid a lump sum price, as detailed in the Attachment J.12-Itemized Scope of Work document per property and specified in Section C.5 Requirements, to complete the work. Contractors will be provided with an opportunity to walk the project site with DHCD’s representatives to better understand and clarify the work.
B.3.3 The bidder acknowledges and understands that the lump sum price is based on the Scope of Work (Section C), which is incorporated into the Contract
Contract Line Item Number
(CLIN)
Item Description (as described in Section C.5 and
Attachment J.12)
Unit of Measure
Quantity Total Price
0001 Rehab Property – 5201 Central Avenue SE
Lot 1
0002 Ten percent (10%) for Contingency Lot 1 Grand Total for Base Period:
awarded pursuant this IFB. It is understood and agreed that the Lump Sum Price represents the Bidder’s offer to complete the Project. The Parties acknowledge and agree that it is their intent to have the awarded Contractor provide all labor, materials, and equipment to complete the project as contemplated in the Contract Documents, for the Lump Sum Price and consistent with the Project Schedule. In furtherance of such intent, the awarded Contractor assumes the risks associated with and shall be responsible for (i) any changes in market conditions that affect the cost of labor or materials; (ii) coordination issues between the drawings; (iii) elements of work not shown on the Contract Documents, but which are reasonably inferable from the Contract Documents; (iv) cost associated with acceleration of the work and expediting of materials necessary to meet the Project Schedule which are the result of anything other than an Excusable Delay; and (v) the risk of subcontractor default or non-performance. It is understood and agreed by the Parties that items (i) through (v) listed in the preceding sentence are not intended to be an exclusive list of the risks assumed by the awarded Contractor and that such items represent a partial list of the risks assumed by the awarded Contractor.
B.4 A bidder responding to this solicitation that is required to subcontract shall be required to submit with its bid, any subcontracting plan required by law.
Bids responding to this IFB shall be deemed nonresponsive and shall be rejected if the bidder fails to submit a subcontracting plan that is required by law.
B.5 For contracts in excess of $250,000, at least 35% of the dollar volume of the contract shall be subcontracted in accordance with section H.9.1. A Subcontracting Plan form is available at https://dslbd.dc.gov/node/442332 https://dslbd.dc.gov/node/442332
SECTION C: SPECIFICATIONS/WORK STATEMENT
C.1 SCOPE:
C.1.1 The Department of Housing and Community Development (DHCD) is seeking an approved qualified general contractor to perform general construction, repair and replacement of major systems and moderate rehabilitation services for privately owned multifamily property under the Department of Housing and Community Development Small Buildings Housing Provider Grant Program.
The property is located at 5201 Central Avenue SE.
C.2 APPLICABLE DOCUMENTS
The following documents are applicable to this procurement and are hereby incorporated by this reference:
Item No.
Document Type
Title Date
DC DOEE
Regulation
Guidance Document for Lead-Based Paint Abatement Permit Scope of Work, and Visual and Clearance Inspections https://doee.dc.gov/service/lead-activity-abatement-renovation-permit-application
Current
US HUD
Regulations
HUD Guidelines, Chapter 15 Clearance https://apps.hud.gov/offices/lead/lbp/hudguidelines/Ch15 .pdf
Code of Federal Regulations
29 CFR 1926, OSHA Construction Industry Regulations https://www.ecfr.gov/current/title-29/subtitle-B/chapter- XVII/part-1926?toc=1
EPA
Standards Renovation, Repair and Painting Program: Contractors https://www.epa.gov/lead/renovation-repair-and-painting-program-contractors
Current
DC
Regulation District of Columbia Construction Codes https://dob.dc.gov/page/dc-construction-codes Current
C.3 DEFINITIONS
These terms when used in this IFB have the following meanings:
C.3.1 Project Schedule: The schedule for the project agreed to by the Department and the Contractor herein. Such schedule shall not be changed except by a Change Order or Change Directive issued by the Department. The schedule shall be in a form and contain such detail as may be agreed upon by the Parties.
https://doee.dc.gov/service/lead-activity-abatement-https://doee.dc.gov/service/lead-activity-abatement-https://apps.hud.gov/offices/lead/lbp/hudguidelines/Ch15.pdf https://apps.hud.gov/offices/lead/lbp/hudguidelines/Ch15.pdf http://www.ecfr.gov/current/title-29/subtitle-B/chapter-http://www.ecfr.gov/current/title-29/subtitle-B/chapter-http://www.epa.gov/lead/renovation-repair-and-painting-http://www.epa.gov/lead/renovation-repair-and-painting-https://dob.dc.gov/page/dc-construction-codes
C.3.2 Drawing: Graphic and pictorial portions of the Contract
Documents, wherever located and wherever issued, showing the design, locations and dimensions of the work, generally including plans, elevations, sections, details, schedules and diagrams.
C.3.3 Work Write-Up (WWU):(also referred to as SOW): formal written document providing a detailed itemized list approved by the District with instructions to the Contractor for service work.
This document may include any specifications, plans and drawings and the itemized list of all Work approved by the District, together with any change orders approved by the contractor, homeowner, and the program manager. In addition, it describes and shows the labor, materials, equipment, fixtures and furnishings necessary for the completion of the project work, including the construction budget.
C.3.4 Scope of Work (SOW): a detailed, binding document outlining specific tasks, deliverables, timelines, and responsibilities for a project. The core components of the project SOW listed in this IFB consist of trade, specifications, quantity, unit of measure, unit price, and extended total price. The property location work to be performed and completed at a lump sum price offered by the contractor.
C.4 BACKGROUND
The mission of the Department of Housing and Community Development (DHCD) is to create and preserve opportunities for affordable housing and economic development and to revitalize underserved communities in the District of Columbia. DHCD focuses on three strategic objectives: 1) preserving and increasing the supply of quality affordable housing; 2) increasing homeownership opportunities; and 3) revitalizing neighborhoods, promoting community development, and providing economic opportunities.
This work will be performed under DHCD Small Housing Provider Grant (SHPG) Program within the Affordable Housing Preservation Unit. The program was established resulting from recommendations put forth by the DC Housing Preservation Strike Force, which was published in November 2016. SHPG provides grants to eligible property owners of multifamily buildings for moderate renovations, repairs, and the elimination of hazardous and unsafe living conditions.
C.5 REQUIREMENTS
The Contractor shall adhere to the general requirements of the scope(s) of work for all work performed and being performed at the property, 5201 Central Avenue SE, that is pursuant to the project activities referenced in the RFQ for pre-qualified general contractors of the same project work. The general requirements for the required general construction activities and project work scope of the project are as follows:
C.5.1 Preconstruction Activities
Prior to mobilizing the Project site and commencing work, the Contractor shall be required to complete those activities set forth in this Section C.5.1. Unless a delay in completing the preconstruction, activities are the result of a delay by DHCD or the Contract Administrator beyond the timeframes set forth herein or an event of force majeure, delays in completing the preconstruction activities shall not be considered excusable and shall not justify an extension of the substantial completion date or for further compensation.
Detailed Schedule. Within seven (7) days of the issuance of a Notice to Proceed, the Contractor shall submit to the Department for its approval a schedule for the Project. Such a schedule shall include a schedule for submittals and key milestones that is reasonably acceptable to the Contract Administrator. The Contract Administrator shall have five (5) business days to review such submittals.
C.5.2 Safety Plan. Prior to the start of any maintenance and construction activities, the Contractor shall prepare a safety plan for the construction phase conforming to OSHA, 29 CFR 1926 (such plan, the “Safety Plan”). The Safety Plan shall be submitted to the Department, and the Contractor shall incorporate such comments as the Department may reasonably request.
C.5.2.1 Safety Barriers/Fences As part of its responsibility for project safety, the Contractor shall install such fences and barriers as may be necessary. The Contractor shall develop a plan that describes the proposed separation and the specific nature of the fences and barriers that will be used. The cost of revising and complying with DHCD requirement shall not entitle the Contractor to an increase in the contract price.
C.5.2.2 Site Security. The Contractor shall be responsible for site security and shall be required to provide such watchman as are necessary to protect the site from unwanted intrusion, if applicable.
C.5.2.3 Exculpation. The right of DHCD to comment on the Safety
Plan and the nature and location of the required fences and barriers shall in no way absolve the Contractor from the obligation to maintain a safe site.
C.5.3 Permits. Unless otherwise specified, it is understood that the
Contractor shall be required to secure and pay for any and all permits, governmental fees, licenses and inspections necessary for the execution and completion of the work. DHCD shall cooperate with the Contractor in securing such permits, licenses and inspections; provided however, DHCD shall not be required to pay the fees for such permits, licenses, and inspections unless otherwise noted in this contract. The costs of any such fees or inspections shall be included in the contract price. The Contractor is also responsible for neighbor notifications, if applicable.
C.5.3.1 The Contractor shall procure permits per property as needed in an electronic or hard printed copy format. The permit applications must be submitted within ten days of award and delivered to the CA upon receipt. Permits must be posted on-site as required by the Department of Buildings (DOB).
C.5.4 Notice to Proceed. The Contractor shall attend and participate in the pre-construction conference meeting with homeowner and DHCD government representative one the agreed upon scheduled date and time. After the meeting ends, DHCD government representative will issue the Notice to Proceed document stating the commencement date to start the project work at the property location.
C.5.5 Work Hours. The Contractor shall coordinate work activities with the Contract Administrator.
C.5.6 Materials. The Contractor shall match replacement materials, sizes, finishes, and colors with existing materials. Patches shall be smooth with no visual seams.
C.5.7 Specifications. The Contractor shall submit all Permits, Drawings and Plans to the contract administrator for review and approval.
C.5.8 Finishes. The Contractor shall repair/replace all architectural finishes directly affected by the Scope of Work in kind. All finished selections are to be submitted to DHCD for review and approval.
Contractor shall notify the contract administrator if any additional architectural finishes are damaged or missing components. All paint shall be zero volatile organic compounds (VOC) and applied with
(1) coat prime and (2) coat finish.
C.5.9 Damaged Property. The Contractor shall repair or replace all damaged property by the construction of repairs. All workers shall protect all surfaces to eliminate potential damage.
C.5.10 The Contractor warrants that all manufacturers or other warranties on all labor, materials, and equipment furnished by the contractor, subcontractor, or supplier shall run directly to; or will be specifically assigned to Department on demand or upon project completion without demand. In the event any issue or defect which would be covered by any warranty arises but is not addressed by the grantor of the warranty, the Contractor shall be required to act as the guarantor of the obligations under the warranty and to perform under the terms of the warranty.
C.5.11 The Contractor warrants that the installation of all materials and equipment shall be in strict accordance with the manufacturers’ requirements or specifications.
C.5.12 General Project Work Scope Requirements. The Contractor must acknowledge, accept, and complete all requested work per property location specified in Attachment J.12: Itemized Scope of Work (SOW) document of the contract. The general project work scope requirements are:
a. Contractor Accepts Scope of Work. The undersigned contractor certifies that he/she has carefully reviewed and agrees to perform the work described in this Work Write Up (WWU) with the specified inspected date and referred to an exhibit. The contractor shall initial & date each page of the
WWU.
b. Verify Quantities – Measurements. All Quantities stated in the attached specifications for this address using Units of Measure other than Each (EA), Room (RM) or Dwelling Unit (DU) are estimates of the finished product for the contractor's convenience and must be verified by the contractor at a mandatory site inspection prior to bid submission. All quantities stated in the Units of Measure Each (EA), Room (RM) or Dwelling Unit (DU) are as stated. Discrepancies in Quantities found by the contractor must be communicated to the Housing Rehabilitation Specialist prior to the submission of a bid. Claims for additional funds due to discrepancies in Quantities shall not be honored if submitted after the bid submission.
c. All Permits Required. The contractor shall apply for, pay for, obtain and forward copies of the following permits indicated to the agency (as applicable): Electric; Heating, Ventilation, Air Conditioning (HVAC); Building; Zoning; Lead Abatement; and Asbestos Abatement.
d. Work Times. Contractors and their Subcontractors shall schedule regular working hours between 8:00am and 6:00pm Monday through Friday. Requests to work at weekends and before or after these hours must be approved by the homeowner.
e. New Material Required. All materials used in connection with this work write-up are to be new, of first quality and without defects - unless stated otherwise or pre-approved by Owner and Construction Specialist.
f. Close-in Inspections Required. Call the agency for inspection of all work that will be concealed from view before it is closed. This type of inspection frequently includes, but is not limited to footings, roof sheathing & flashing prior to installation of new felt & shingles, and repaired framing & decking prior to installation of underlayment & floor coverings, prior to insulation and prior to drywall.
g. One (1) Year General Warranty. Contractor shall remedy any defect due to faulty material or workmanship and pay for all damage to other work resulting there from, which appear within one year from final payment. Further, contractor shall furnish owner with all manufacturers' and suppliers' written warranties covering items furnished under this contract prior to release of the final payment.
h. Painting. All paint is lead-free. All surfaces clean/dry.
Remove loose, blistered, scaling, deteriorated paint. Secure loose materials, set nails, fill holes, dents & cracks. Remove all deteriorated glazing compound & reglaze. Paint can be applied when the temperature is between 40 and 100 degrees Fahrenheit (40℉-100℉). No show-through, runs, sags, or brush marks. All unpainted hardware to be paint free. No windows shall be painted shut. Remove ALL paint from glass, inside and out
i. HVAC. Equipment should operate safely without leakage, noise, or vibration. All penetration of building components shall be neat, sleeved and fire stopped and shall not compromise structural integrity. Contractor shall submit a diagram showing equipment selection and proposed layout of distribution system within ten (10) days of bid award.
j. Plumbing. Unless otherwise specified, all materials shall be copper or polyvinyl chloride (PVC) piping. All items shall operate without leakage, noise, vibration or hammering. All penetration of building components shall be neat, sleeved, & fire stopped. No solder containing lead shall be used in any pipe or fixture. Damage to structural members from drilling or notching shall be repaired to the acceptance of the owner and the Agency.
k. Metal. All wrought metal shall be shop-built with welded joints and dip primed with black shop primer. Field installation shall be in quick setting cement, beveled to shed water, and in lead, leather, or plastic sheathed anchor bolts.
l. Roofing. Unless otherwise specified, all material shall match existing as closely as possible for material, style, color and method of installation.
Seal all edges. Flash & caulk all adjoining surfaces & make weathertight.
Replace all flashing, roofing accessories & nails using rust-resistant material. Install all roofs in one continuous operation. Always protect the house contents from exposure to the elements
m. Drywall. Unless otherwise specified, match surrounding as to materials, thickness, style and method of installation. All materials shall be applied dry with the temperature between 55- 100 degrees F. Provide casing beads and install with non-drying mastic at all exposed edges, corners and abutments. Set all nail and screw heads. Apply tape and filler. Feather all edges. Wet sand, ready for paint.
C.6 Substantial Completion Date.
The Contractor shall substantially complete the Project no later than the date identified in Section F.1 of the contract. For purposes of this requirement, the term “Substantially Complete” shall mean that all the following have occurred:
(1) the work has been completed with only minor punch list items remaining to be completed;
(2) any and all required permits or approvals related to the work have been obtained;
(3) all operating and maintenance manuals, training videotapes and warranties required by the Contract have been delivered to DHCD;
(4) any supplemental training session required by the Contract for operating or maintenance personnel have been completed;
(5) all clean-up required by the Contract has been completed; and
(6) the Project is ready for the homeowner to use for its intended purpose.
“Minor punch list items” are defined for this purpose as items that, in the aggregate, can be completed within thirty (30) days without interfering with DHCD’s normal use of the Project
C.6.1 The Contractor shall promptly correct work rejected by Department for failing to conform to the requirements of the Construction Documents or any approved design document or applicable law or regulations whether observed before or after the Project’s completion and whether or not fabricated, installed or completed, and shall correct any work found to be not in accordance with the requirements within the period of performance from the date of Final Completion or by terms of an applicable special warranty required by the contract.
C.6.2 Final Completion Date. The Final Completion Date of the work to be performed in each awarded contract shall be within the identified day specified in Section F.1 and after the substantial completion date for the property. Final Completion shall mean the point at which Substantial Completion has been achieved, all punch list items noted at Substantial Completion have been completed, and all documents the Contractor is required to deliver to the Department as a condition for receiving final payment have been received. Work is defined as the construction and services required by the Contract whether completed or partially completed, and includes all other labor, materials, equipment, and services provided or to be provided by the Contractor to fulfill the Contractor’s obligations.
C.6.3 Performance and Payment Bonds. The Contractor shall provide to the Department payment and performance bonds to be incorporated into each awarded contract, each with a penal sum equal to one hundred percent (100%) of the contract award amount, as accordance with Section H.11 of the contract.
6.3.1 For each contract valued at One Hundred Thousand Dollars ($100,000) or more, as applicable, the Contractor shall, at the time the contract, as applicable, provide to DHCD a payment bond and performance bond, each with a penal sum equal to the Contract Lump Sum, as applicable. Such bond shall remain in full force and effect until Final Completion is achieved and DHCD shall be able to draw upon such bond regardless of the amount paid by DHCD to the Contractor, even if such amount exceeds the penal value of such bond.
C.6.4 Liquidated Damages. If the Contractor does not complete the work by the Substantial Completion timeframe, the Parties acknowledge and agree that the actual damage to DHCD for the delay will be impossible to determine, and in lieu thereof, the Contractor shall pay to DHCD, as fixed, and liquidated delay damages in the amount specified in the contract for failure to meet the Substantial Completion Date. The Contractor and DHCD agree that the liquidated damages do not constitute, and shall not be deemed, a penalty but represents a reasonable approximation of the damages to DHCD associated with a delay in the Project. In the event the Contractor fails to meet the Substantial Completion Date as defined in each individual contract, the Contractor consents to a termination for default.
C.6.5 Key Personnel. The following individuals shall be considered key personnel: (i) the Field Superintendent, and (ii) the Project Manager/Contract Administrator. The Contractor shall not be permitted to reassign any of the key personnel unless the Department approves the proposed reassignment and the proposed replacement, in writing and by an authorized Contracting Officer ("CO"). The key personnel specified in the contract are essential to the work being performed hereunder. Prior to diverting any of the specified key personnel, the Contractor shall notify the CO at least thirty (30) calendar days in advance and shall submit justification, including proposed substitutions, in sufficient detail to permit evaluation of the impact upon the contract.
C.6.5.1 The Offeror’s personnel should have the necessary experience and licenses to perform the required work. To carry out the work associated with the contract, the Contractor shall provide at least the key personnel identified in its technical proposal which shall be included as an exhibit to the contract and always indicate the function(s) each will carry out for the proposed project and indicate what percentage of each such person’s time will be devoted to the work project.
C.6.6 Access to Site. The Contractor shall ensure the building access and entrances are clear of work activities, materials, and always scaffolding. The contractor must always maintain safe access to the building occupants during work. Take precautions to protect the building, its occupants and the public during construction. The building should be properly maintained in a safe and weather tight condition throughout the construction period. Repair damage caused by construction operations.
C.6.7 Consideration of Tenant's. The building’s tenants may occupy the building during the entire period of construction. Cooperate with the building's representatives during construction operations to minimize conflicts and facilitate the building's tenant usage. Perform the work in a manner that does not interfere with the building’s operations.
C.6.8 Trash. The Contractor shall remove all debris from the site daily.
After completion of all rehabilitation, perform a final cleaning and remove from site all construction materials, tools, debris, and containment materials; sweeps clean all exterior work areas. HEPA vacuums all interior surfaces, removing all visible dust, stains, labels, and tags. Clean all windows referenced in specifications.
C.6.9 Risks Assumed by Contractor
The Contractor shall be deemed to have thoroughly examined the terms of the IFB, the Drawings (if applicable) and Specifications that may be included with the IFB and shall constitute its acknowledgement that it has been provided with an opportunity to visit the Project site had the opportunity to become familiar with local conditions under which the work is to be performed. Further, the Contractor shall be deemed to represent that it has satisfied itself that it can undertake the work for the stated cost. Among other things, the Contractor assumes the following risks:
(1) the nature of the land and subsoil unless such conditions constitute a Differing Site Condition under Article 4.A of the Standard Contract Provisions for Construction Contracts (J.9);
(2) the form and nature of the site and surrounding areas;
(3) details and levels of existing pipelines, conduits, sewers, drains, cables or other existing services;
(4) the quantities, nature and availability of the materials, tools, equipment and labor necessary for the completion of the work;
(5) the means of access to the site and any accommodation that may be required; and
(6) uncertainties of weather and physical conditions at the site; and in general, to have obtained all necessary information as to risk contingencies, climatic, hydrological, and natural conditions and other circumstances which may influence or affect his performance of the work.
C.6.10 Quality Plan. Prior to the start of construction activities, the
Contractor shall prepare a Quality Plan. The Quality Plan shall address: (i) the processes employed by the Contractor to ensure quality assurance; (ii) to determine how items are checked for quality and which items need to be checked; (iii) list the specific quality materials used during the project including standards, guidelines, checklist, templates, procedures, user guides and processes; and how the Contractor will handle defective items.
C.6.11 Coordination with DHCD. The Contractor shall be required to coordinate with the assigned Program Manager for each individual project. Unless specified otherwise in the Contract, the work shall generally be performed during normal business hours; however, the Contractor may be required to work after hours or on weekend and holidays as to not adversely impact the work of DHCD of Columbia employees/and or Contractors. The Contractor shall be required to develop work plans that are coordinated with, and acceptable to, the Program Manager assigned to the contract.
C.7 Construction Phase
The Construction Phase shall commence when DHCD issues a written Notice to Proceed for Construction. The Contractor shall construct the work described on the Construction Documents including any work that is not specifically shown thereon but is reasonably inferable therefrom or necessary for a fully functioning Project. The work shall be carried out in a workmanlike and timely fashion. All materials and equipment to be incorporated into the Project shall be new and previously unused, unless otherwise specified, and shall be free of manufacturing or other defects. The Contractor hereby assumes the risks associated with and shall be responsible for (i) any changes in market conditions that affect the cost of labor or materials; (ii) cost associated with acceleration of the work and expediting of materials necessary to meet the Project Schedule which are the result of anything other than an Excusable Delay; and (iii) the risk of subcontractor default.
C.7.1 Coordination with DHCD
C.7.1.1 Supervision & Coordination. The Contractor shall be required to properly supervise and coordinate its work. At a minimum, it is envisioned that the Contractor shall be required to undertake the following tasks:
a) Participate and assist in Project/Planning meetings;
b) Maintain full-time on-site construction supervision and provide daily inspections, quality control, monitoring, coordination of various trades, record drawings, and daily work log;
c) Coordinate work with homeowners or DHCD personnel to ensure that their activities are not adversely affected;
d) Conduct periodic progress meetings following a Contractor generated agenda with the Contract Administrator;
e) Provide general safety and signage and posting for the project and see that each subcontractor prepares and submits adequate safety program and monitoring throughout the project;
f) Obtain all job permits and approvals from the Department of Buildings that are required to perform and complete the work, unless otherwise noted herein;
g) Prepare payment requests, verify accuracy and forward to DHCD for approval and payment;
h) Assemble close-out documents required;
i) Provide assistance to DHCD through all applicable warranty periods.
j) Coordinate its work with all third parties so as not to delay the critical path of the Project; and
k) Prepare and submit to DHCD construction meeting minutes, progress meeting minutes, daily logs, inspection reports, preliminary and baseline schedules, and schedule updates demonstrating the critical path of the Project.
C.7.2 CBE Subcontractors. The Contractor shall not substitute or replace any subcontractor or supplier certified by the Department of Small Business Development (DSLBD) without DHCD’s prior written consent.
C.7.3 Site Observations. The Contractor shall be required to visit the site, in the presence of DHCD construction analyst become familiar with local conditions under which the work is to be performed and correlate personal observations with requirements of the Construction Documents as provided for projects solicited under the IFBs. The Contractor shall carefully study and compare the Construction Documents with each other and with information furnished by DHCD. Before commencing activities, the Contractor shall (1) take field measurements and verify field conditions; (2) carefully compare this and other information known to the Contractor with the Construction Documents; and (3) promptly report errors, inconsistencies or omissions discovered to DHCD.
Once work is started, the Contractor assumes the responsibility and costs for the work and the cost of correcting work previously installed.
C.7.4 Warranty of Construction Work. The selected contractor shall warrant to DHCD that materials and equipment furnished under the awarded contract will be of good quality and new unless otherwise expressly permitted in writing, that for the period specified in each contract’s scope of work following the substantial completion date the construction work will be free from defects not inherent in the quality required or permitted, and that the work will conform to the construction documents and/or any approved design documents. The Contractor’s warranty excludes remedy for damage or defect caused by abuse, modifications not executed by the contractor, improper or insufficient maintenance, improper operation, or normal wear and tear and normal usage. The Contractor and construction analyst of DHCD shall walk the Project together to identify any necessary warranty work. In the event the Contractor fails to schedule such a walk, the Warranty period shall be extended until such time as the Contractor schedules such a walk.
C.7.4.1 If during the guarantee or warranty period, any material, equipment or system requires corrective work because of defects in materials or workmanship, the Contractor shall commence corrective work within forty-eight (48) hours after receiving the notice and work diligently until corrective work is completed; provided, however, if such notice is received on the day before a weekend or a holiday, the Contractor will commence corrective work on the next business day. If the Contractor does not, in accordance with the terms and provisions of the contract documents, commence all corrective work within forty-eight (48) hours or if the Contractor commences such work but does not pursue it in an expeditious manner, DHCD may either notify the bonding company (if any) to have such work and/or obligations performed at no additional cost to DHCD or may perform such work and/or obligations and charge the costs thereof to contractor. If more than forty-eight (48) hours is needed, a request must be submitted in writing for approval from the project manager.
C.7.4.2 The selected contractor warrants DHCD all manufacturers or other warranties on all labor, materials and equipment furnished by the contractor or a Subcontractor or supplier shall run directly to or will be specifically assigned to DHCD on demand or upon project completion without demand. In the event any issue or defect which would be covered by any warranty arises but is not addressed by the grantor of the warranty, the selected contractor shall be required to act as the guarantor of the obligations under the warranty and to perform under the terms of the warranty.
The Contractor shall provide all warranties in electronic format and hard printed copy format. The warranties must be submitted within ten days upon completion of construction.
C.7.5 Extent of Responsibility and Site Conditions. The Contractor shall be entitled to submit a change request for differing site conditions only to the extent that such conditions could not have been discovered by a competent visual inspection of the site and are of unusual nature and differ materially from those ordinarily encountered and generally recognized as inhering to work of the character provided for in the Contract (such circumstances, “Differing Site Conditions”). The term Differing Site Conditions shall mean subsurface conditions on or adjacent to the Project site which differ materially from those indicated in the geotechnical reports prepared by the Contractor. The term Differing Site Conditions shall also include unknown physical conditions at the site of an unusual nature which differ materially from those ordinarily encountered and generally recognized as inhering to work of the character provided for in this Contract. Prior to commencing construction, the Contractor shall be required to conduct a thorough review of the Project site and the surrounding area and shall document its findings. In the event the Contractor fails to undertake and document such a thorough review, the Contractor shall be deemed to have known of those conditions which a thorough review would have detected. Any Change Request related to Differing Site Conditions shall be made pursuant to the Standard Contract Provisions.
C.7.6 Unsafe Materials and Hazardous Materials
C.7.6.1 The Contractor shall not bring, spill or release onto the site asbestos, polychlorinated biphenyls (PCBs) chemicals, or any other Hazardous Material that is not customarily used in a project location of the type and similar to the Project, and shall bring to DHCD’s attention any specification of such
Hazardous Materials in the design documents. If the Contractor believes that anything in the Contract would require that it use or bring onto the site asbestos, PCBs, or any Hazardous Material that is not customarily used in a facility of the type and similar to the Project, it shall immediately inform DHCD and seek directions before proceeding.
C.7.6.2 If Hazardous Materials are discovered on the site, the
Contractor shall immediately inform the Program Manager and DHCD of such discovery. The Contractor shall be entitled to submit a Change Request for any hazardous materials abatement and disposal work as in accordance with Article 3 - CHANGES clause of the Department of General Services Standard Contract Provisions. The Contractor shall comply with all laws, including, without limitation, the requirements of the US Environmental Protection Agency (EPA) and all jurisdictional agencies as well as all laws relating to safety, health welfare, and protection of the environment, in removing, treating, encapsulating, passivating, and/or disposing of Hazardous Materials, including, but not limited to, removal, treatment, encapsulation, passivation, and/or disposal of the Hazardous Materials. If any notices to governmental authorities are required, the Contractor shall also give those notices at the appropriate times. The Contractor shall ensure abatement subcontractors and disposal sites are appropriately licensed and qualified.
C.7.6.3 The Contractor shall keep detailed records documenting
Work done so that DHCD may independently verify compliance with all laws, the number of units actually removed, treated, and/or disposed of, and the appropriate unit price(s) applicable to the work.
C.7.7 Work by Separate Contractors. DHCD reserves the right to perform construction or operations related to the Project with DHCD’s own forces, and to award separate contracts in connection with other portions of the Project or other construction or operations on the site.
C.7.8 Close-Out and Training. Contractor shall also provide DHCD with a complete set of its Project files, including, but not limited to, shop drawings, product manuals, warranties, etc., prepared by the Contractor or its subcontractors along with any other documentation that may reasonably be requested by DHCD or its Program Manager and/or Project Manager, at close out so as to assist DHCD. In addition, if the Project includes work on heating or cooling systems, at the beginning of the first heating and cooling season following turnover of the Project, the Contractor shall be available to assist with, and train the homeowner in the start-up of the systems for the new weather cycle, if needed.
C.7.9 Salvaged and Stored Items. The Contractor shall be responsible for salvaging and storing all items as identified by DHCD in accordance with all applicable DHCD laws and regulations, after notifying DHCD and receiving DHCD’s permission to proceed.
C.7.10 Cutting and Patching. The Contractor shall be responsible for cutting, fitting or patching required to complete the Work. All areas requiring cutting, fitting and patching shall be restored to like new condition existing prior to the cutting, fitting and patching. The Contractor shall not damage or endanger a portion of the Work or fully or partially completed construction of DHCD or separate contractors by cutting, patching or otherwise altering such construction, or by excavation.
C.7.11 Correction of Work
C.7.11.1 DHCD will be at liberty to object and to require the
Contractor to remove forthwith from the Project site and the work and to promptly replace the superintendent, any foreman, technical assistant, laborer, agent, representative, or other person used by the Contractor in or about the execution or maintenance of the Work, who in the sole opinion of DHCD is misconducting himself or herself, or is incompetent or negligent in the proper performance of his or her duties, or whose performance in the work is otherwise considered by DHCD to be undesirable or unsatisfactory, and such person shall not be again employed upon the Project without the written permission of DHCD.
C.7.11.2 The Contractor shall promptly correct work rejected by
DHCD for failing to conform to the requirements of the Construction Documents or any approved design document or applicable law or regulations whether observed before or after the Project’s completion and whether or not fabricated, installed or completed, and shall correct any work found to be not in accordance with the requirements within a period of one (1) year from the date of Final Completion or by terms of an applicable special warranty required by the Contract.
C.7.11.3 If during the guarantee or warranty period, any material, equipment or system requires corrective work because of defects in materials or workmanship, the Contractor shall commence corrective work within forty-eight (48) hours after receiving the notice and work diligently until corrective work is completed; provided, however, if such notice is received on the day before a weekend or a holiday, the Contractor will commence corrective work on the next business day. If the Contractor does not, in accordance with the terms and provisions of the Contract Documents, commence all corrective work within forty-eight (48) hours or if the Contractor commences such work but does not pursue it in an expeditious manner, DHCD may either notify the bonding company (if any) to have such work and/or obligations performed at no additional cost to DHCD or may perform such Work and/or obligations and charge the costs thereof to Contractor.
C.7.12 Manufacturers’ Warranties
C.7.12.1 The Contractor shall warrant that all manufacturers or other warranties on all labor, materials and equipment furnished by the Contractor or a Subcontractor or supplier shall run directly to or will be specifically assigned to DHCD on demand or upon Project completion without demand. In the event any issue or defect which would be covered by any warranty arises but is not addressed by the grantor of the warranty, the Contractor shall be required to act as the guarantor of the obligations under the warranty and to perform under the terms of the warranty.
C.7.12.2 The Contractor warrants that the installation of all materials and equipment shall be in strict accordance with the manufacturers’ requirements or specifications.
C.7.13 Acceleration. Subject to the terms of this Section, DHCD shall have the right to direct the Contractor to accelerate the work if, in the reasonable judgment of DHCD, the Contractor fails to: (i) supply a sufficiency of workers or to deliver the materials or equipment with such promptness as to prevent the delay in the progress of the work;
or (ii) the progress of the work materially falls behind the projections contained in the then currently approved Project Schedule. In the event that DHCD or its Program Manager determine that either of the events specified in the preceding sentence have occurred, DHCD shall provide the Contractor with written notice of such event and the Contractor shall be required to provide DHCD with a corrective action plan that is reasonably designed to address the concerns raised in such notice within three (3) days after receipt of such notice. If DHCD and the Contractor are unable to agree on the terms of such corrective action plan within five (5) calendar days after the issuance of the notice (i.e. with forty-eight (48) hours after the receipt of the proposed corrective action plan), DHCD shall have the right to direct such acceleration as DHCD, in its reasonable judgment, deems necessary. Provided the notice provisions of this Section are complied with, the cost of any acceleration directed under this Section shall not justify an adjustment to the Contract Price or the Substantial Completion Date. The Contractor hereby acknowledges that this provision is a material inducement upon which DHCD has relied in entering into the Contract; and represents and warrants that it has included sufficient funding in its Contract Price in order to comply with the requirements of this Section.
C.8 Administrative Matters
C.9 Compensation
C.9.1 The Contractor shall be paid its compensation in partial or full payment requests. A partial payment is considered when work on a property for a specific CLIN is completed and verified by the contract administrator and designated construction analyst. These may also require Department of Buildings inspectors to verify prior to approval by DHCD. Final payment can be made after work is completed on all properties.
C.9.2 Otherwise, the Contractor shall be paid its compensation in a series of progress payments and a final payment. Progress payments shall be based on a Schedule of Values that is agreed upon by the Parties as well as the Contract Administrator’s good faith estimate of the level of completion for each component of the Schedule of Values. The Contractor shall prepare the Schedule of Values which breaks down the contract price for the various parts of the project work. The Schedule of Values shall be maintained in such a manner to provide a breakdown of the contract price in enough detail to facilitate continued evaluation of applications for payment and progress reports. Large subcontracts shall be broken into several line items where, in the opinion of the Contract Administrator, such detail is necessary to properly track the progress of the work. The proposed schedule of values shall include separate line items for each part of the work, when requested by the Contract Administrator. The Contractor and the Contract Administrator shall meet as necessary to maintain the schedule of values for the Project in a manner acceptable to the Contract Administrator. No progress payments shall be made unless the current Schedule of Values is acceptable to the Contract Administrator.