852861solarMdNatl.pdf

PDF 810 KB Posted

Attached to
Design/Build Services: Pauline Betz Addie Tennis Center Rooftop Solar
Solicitation number
P47-124
Issued by
Montgomery County, Maryland

About this file

This is a Design/Build Services solicitation document from the Maryland-National Park and Planning Commission (M-NCPPC) for a rooftop solar photovoltaic (PV) installation project at the Pauline Betz Addie Tennis Center located at 7801 Democracy Blvd, Bethesda, Maryland. The Commission is seeking qualified solar providers to deliver a turnkey installation for an anticipated 318 kilowatt-direct current (kW-DC) solar system. The project represents a comprehensive design and build engagement requiring a single qualified contractor to manage all aspects of the solar installation from design through completion and commissioning.

The solicitation does not specify explicit pricing structures, set-asides, incumbent contractor information, or detailed funding sources within the available documentation. Interested bidders should review the complete solicitation materials for specific submission requirements, evaluation criteria, timeline details including proposal due dates, site visit procedures, and any pre-bid conferences scheduled by M-NCPPC. Additional information regarding contract terms, renewal options, and financial requirements should be obtained directly from the Commission's procurement office.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The Maryland-National Capital Park & Planning Commission

Corporate Procurement Services 6611 Kenilworth Ave, Suite 300, Riverdale, Maryland 20705

RFP No. P47-124 Design/Build Services: Pauline Betz Addie Tennis Center Rooftop Solar

PROJECT DESCRIPTION

The Maryland-National Park and Planning Commission (M-NCPPC or Commission) is soliciting proposals from qualified solar providers to build a turn-key installation for a rooftop solar PV project at the Pauline Betz Addie Tennis Center (7801 Democracy Blvd, Bethesda, MD). The project is for an anticipated 318 kW-DC solar installation.

NOTE: A Pre-Proposal is scheduled for Tuesday, November 17, 2026, at 11 a.m. at Cabin John Ice Rink located 10610 Westlake Dr. Rockville, Maryland. Following a Site Visit at Pauline Betz Tennis Center located at 7801 Democracy Blvd., Bethesda, Maryland.

Solicitation Release Date: Wednesday, November 04, 2026

PROPOSAL DUE DATE/TIME: December 11, 2026 before 3:00 p.m.

COMMISSION TEAM:

Cindy Martinez, Corporate Procurement Specialist

Alice Enz, Project Manager, Park Development Division

THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION

REQUEST FOR PROPOSALS SUMMARY

RFP Number: P47-124

Proposal Name:

Design / Build Services for Pauline Betz Tennis Center Rooftop Solar

Pre-Proposal Meeting:

A Pre-Proposal Meeting will be held on Tuesday, November 17, 2026, at 11 a.m. Interested parties must RSVP: no later November 13, 2026, via OpenGov Procurement RSVP.

Site Visit: A Site Visit will follow the Pre-Proposal Meeting. All interested parties must register on OpenGov Procurement RSVP Tab.

Deadline for Technical Questions:

Technical Questions must be submitted on OpenGov Procurement under the Question and Answer (Q&A) tab no later than November 20, 2026 by 3 p.m.

Deadline for Proposals: December 11, 2026, BEFORE 3:00 P.M.

Proposal Submittal Instructions:

Proposals must be submitted via the Commission’s electronic bid service provider, OpenGov Procurement. The Commission will not be accepting paper copies of proposals.

Follow the link below to submit an electronic Proposal for this Solicitation:

https://procurement.opengov.com/portal/mncppc

Oral, telephonic, email, telegraphic and facsimile Proposals will not be accepted. Offerors are cautioned to allow sufficient time to ensure that all proposal documents are successfully uploaded to OpenGov Procurement before the Deadline for Proposals. The OpenGov Procurement solicitation page will close promptly at the date and time of the Deadline for Proposals, and late proposals will not be accepted. Offerors are to conform to the procurement conditions herein.

Inquiries: All other inquiries than technical questions regarding this are to be made to:

Cindy Martinez, Corporate Procurement Specialist Email: Cindy.Martinez@mncppc.org Office: (301) 454-1603 https://procurement.opengov.com/portal/mncppc mailto:Cindy.Martinez@mncppc.org%20

Table of Contents

Part 1. GENERAL INFORMATION

Part 2. SCOPE OF SERVICES

Part 3. GENERAL CONDITIONS – DESIGN BUILD

Part 4. SPECIAL CONDITIONS

Part 5. PROPOSAL FORMAT AND CONTENT

Part 6. PROPOSAL EVALUATION

Part 7. FORMS

Part 8. ATTACHMENTS

Part 1. GENERAL INFORMATION

A. PRESUBMISSION INFORMATION

1. Examination of RFP Documents

Offerors must examine all of the solicitation documents very carefully and must make their proposal after examination of the location and/or nature of the proposed work. The submission of a proposal indicates that the Offeror thoroughly understands all of the terms and conditions, instructions, and specifications of the proposal. Offerors may make proposals for one or multiple projects included in the RFP.

2. Commission Assistance in Proposal Preparation

Commission staff will not assist any Offeror or Offeror's agent in the actual preparation of the proposal. Offerors or their agents will not be permitted to use Commission telephones or other facilities in the preparation of the proposal(s).

3. Interpretation and Correction of RFP Documents, and RFP Addenda

Should an Offeror require an interpretation or clarification of any provisions of the RFP documents or related information provided by the Commission, or believe that there is an ambiguity, error, inconsistency or discrepancy in these documents or information, the Offeror must notify the Commission in writing at least five (5) working days prior to the date set for receipt of proposals.

An Offeror who fails to request any such interpretation or clarification waives any claim for additional cost or time spent addressing any ambiguity, error, inconsistency or discrepancy in any such documents or information which is found to have been apparent at the time of receipt of proposals.

All interpretations, clarifications, corrections, changes or other directions related to these requests of Offerors will be provided in writing via an Addendum issued by the Commission and posted to the solicitation page on the OpenGov Procurement website.

Offerors are solely responsible for checking the solicitation page frequently for Addenda.

Responses to Offeror notifications and inquiries made in any other manner, and especially any oral explanations, instructions or comments provided by any representative of the Commission, will not be binding on the Commission.

If an Offeror omits acknowledgment of Addenda, M-NCPPC may request that the successful Offeror state in writing that the Offeror will be bound by any substantive changes made to the terms of the RFP by the Addenda without any effect on the cost of the project.

4. Extension of Proposal Opening

The Commission may extend the proposal opening date at its option. If the date is extended, the Commission will notify all prospective Offerors by posting them on the

Commission’s website and the OpenGov Procurement website.

B. PREPARATION AND SUBMISSION OF PROPOSALS

All proposals must be submitted as indicated in the RFP announcement, and must be:

a. Initialed by the Offeror where there are erasures or other changes in the proposal.

b. Signed in ink or electronic signature by authorized principals with the Offeror's legal name fully stated. Corporations must give the state in which incorporated, using the phrase "A Corporation organized under the laws of the State of ".

Partnerships must give names of partners, using the phrase "Co-partners, doing business under the firm name of ". Individuals using a trade name must give the individual name, using the phrase "An individual doing business under the trade name of " (see Form A – Proposal Declaration in Part 7).

c. Submitted in accordance with the format as specified in Part 5. Proposals may be submitted as the Offeror may determine, but the proposals must follow the prescribed format as to the requirements of content and order of content.

d. Fully completed by the Offeror, including all information requested and any attachments that may be required.

e. Received on or before the time, date and at the location specified in the RFP

Announcement herein.

Only Proposals submitted through the OpenGov Procurement portal will be accepted. Facsimile or e-mailed Proposals will not be accepted.

M-NCPPC is not liable for any costs incurred by any Offeror in connection with this RFP.

The expenses incurred by the proposer in the preparation, submission, and presentation of the proposal are the sole responsibility of the proposer.

C. BID GUARANTIES, PAYMENT AND PERFORMANCE BONDS AND

CERTIFICATES OF INSURANCE

All bids, where total bid is in excess of $100,000, must be accompanied by a Bid Bond in an amount equal to not less than five percent (5%) of the total amount of the Base Bid, properly executed in favor of the M-NCPPC. A performance bond and a labor and material payment bond, each in the amount of 100 percent of the contract amount, are required for any design/build or construction contract in excess of $100,000.

Acceptable security for bonds includes:

1. A bond in a form satisfactory to the Commission underwritten by an acceptable bonding company. Acceptable bonding companies are those having active claims offices in the District of Columbia; Arlington or Fairfax Counties or the City of Alexandria in Virginia; or Montgomery, Prince George’s or Baltimore Counties in Maryland; and which are licensed by the Maryland Commissioner of Insurance and currently have an ‘A’ or better rating from A.M. Best Company, or a minimum Standard & Poor’s rating of BBBq. The bonding company must have a resident agent named in Maryland.

2. A bank certified check, bank cashier’s check, bank treasurer’s check, or bank trust account.

3. Pledge of securities backed by the full faith and credit of the United States

Government or bonds issued by the State of Maryland or Montgomery or Prince George’s Counties in Maryland.

4. Irrevocable Letter of Credit acceptable to the Commission.

5. Alternative security approved by the Secretary-Treasurer.

The length of all contract securities must be consistent with the performance period of the contract.

Bid guaranties will be returned upon request by unsuccessful Offerors.

The successful Offeror must deliver the executed performance and payment bonds, together with all certificates of insurance required by the contract documents and the executed contract, to the Commission within 10 calendar days after the successful Offeror receives notice of award of the contract. If the successful Offeror fails to deliver these items within that period, the Commission may reject the bid and bidder will forfeit the bid guaranty. The Commission may then award the contract to the next lowest responsive and responsible bidder.

D. MODIFICATION AND WITHDRAWAL OF PROPOSALS

An Offeror can modify or withdraw a Proposal submitted in response to this RFP by sending a written notice to the Commission representative identified in the Request for Proposals Summary on page 2. Such notice must be received before the time and date specified as the Deadline for Proposals.

Timely modifications or withdrawals must be in writing over the signature of the Offeror.

Modifications or withdrawals must include written confirmation over the signature of the Offeror and must have been received on or before the date and time established as the Deadline for Proposals.

Withdrawn Proposals may be resubmitted up to the Deadline for Proposals, provided that they are then fully in conformance with the RFP.

Proposals cannot be modified or supplemented after the Deadline for Proposals.

E. IRREVOCABILITY OF PROPOSALS

Unless otherwise provided in the RFP, proposals submitted shall be irrevocable for a period of one hundred fifty (150) calendar days following the date of proposal receipt.

F. CONSIDERATION OF PROPOSALS

Proposals will be opened privately. Unless stated otherwise in the RFP or in any Addenda to the RFP, the properly identified Proposals received on time will be reviewed and evaluated by the evaluation committee.

M-NCPPC has the right to reject any or all Proposals and, in particular, to reject a Proposal not accompanied by any data required by the RFP documents or a Proposal deemed incomplete or irregular in any way by M-NCPPC.

G. M-NCPPC’S RIGHTS AND LIABILITIES

M-NCPPC reserves all rights available to it by law in administering this RFP including, without limitation, the right in its sole discretion to:

1. Reject any and all proposals at any time;

2. Terminate consideration or evaluation of any and all proposals at any time;

3. Suspend, discontinue and/or terminate discussions regarding confidentiality agreements, interim agreements and comprehensive agreements at any time prior to the authorized execution of such agreements by all parties;

4. Request and/or receive additional information regarding any proposal;

5. Issue addenda to and/or cancel any RFP;

6. Revise, supplement or withdraw all or any part of this RFP;

7. Request revisions to RFP proposals.

An Offeror who submits a proposal agrees to hold M-NCPPC, their officers, employees, agents and volunteers harmless and free from all liability, loss, injury, and/or cost and expense which might be incurred by such Offeror in responding to, or as a consequence of, the RFP, and agrees to waive any and all claims for damages arising in connection with the procurement process contemplated by the RFP.

An Offeror shall not employ any subcontractor, supplier, or other individual or entity against which M-NCPPC may have reasonable objection. An Offeror shall not be required to employ any subcontractor, supplier or other individual or entity to furnish or perform any of the Work against which Offeror has reasonable objection.

This is notification to prospective Offerors that M-NCPPC has unlimited data rights regarding Proposals submitted in response to its Solicitations. Unlimited data rights mean that the M-NCPPC has the right to use, disclose, reproduce, prepare derivative Works, distribute copies to the public, or perform publicly and display publicly any information submitted by Offerors in response to this or any Solicitation issued by M-NCPPC.

However, information that is deemed to be confidential commercial or financial information as defined by the Maryland Public Information Act (MPIA), MD [State Gov.] Code Ann, §§10-611 through 10-630 will be exempted from disclosure in accordance with MPIA. It is the responsibility of the Offeror to clearly identify each part of its Submission that is confidential commercial or financial information by stamping the bottom right-hand corner of each pertinent page with one-inch bold face letters stating the words "confidential" or “proprietary.” The Offeror agrees that any portion of the Submission that is not stamped as proprietary or confidential will be deemed not to be proprietary or confidential.

H. RECEIPT AND OPENING OF PROPOSALS

Proposals received prior to the date and time specified for the receipt of proposals will be securely kept, unopened. The Commission representative whose duty it is to open the proposals will decide when the specified opening time has arrived.

If the Offeror to whom an award is made should fail to execute a contract or deliver any insurance certificates within the time specified:

1. The award may be annulled and the project awarded to the Offeror ranked second under the evaluation criteria, who shall be required to fulfill all stipulations as if such Offeror were the original Offeror to whom the award was made; or

2. The Commission may reject all remaining proposals.

Unless otherwise stated in the RFP, the Commission reserves the right to award in the aggregate or to make separate awards. The Commission reserves the right, when reviewing proposals for award, to waive minor informalities or irregularities in the proposals and in the proposing procedure. The Offeror to whom the award is made will be notified at the earliest possible date. The Commission reserves the right to reject any or all proposals, and to reject any or all optional items included in the proposal.

I. MISTAKES IN PROPOSALS

After the opening of proposals, Commission staff shall examine all proposals for mistakes. In cases of apparent mistakes, other than those involving extension of unit prices or other arithmetic errors, when Commission staff has reason to believe that a mistake may have been made, staff shall request from the bidder a verification of the proposal. If the offeror alleges a mistake, the matter shall be brought to the attention of the Purchasing Manager. Such actions shall be taken prior to award.

The Purchasing Manager is required to make the administrative determinations necessary in cases of alleged proposal mistakes. The authority permitting correction of proposals is limited to proposals which are responsive as submitted and shall not be used to permit correction of bids to make them responsive.

If the Purchasing Manager knows or has reason to conclude that a mistake in a proposal may have been made, the Purchasing Manager shall require that the bidder confirm the proposal. Confirmation by the offeror of the proposal will be requested when the bid reflects either an obvious, apparent error on its face or the bid’s amount is unreasonably lower than those of either the other bids submitted or the Commission’s estimate.

If the offeror fails to respond to a request for confirmation of an apparent mistake within the time allotted to the Purchasing Manager, the proposal may be considered as originally submitted or may be rejected as non-responsive at the discretion of the Purchasing Manager. If the offeror confirms his proposal, the Purchasing Manager shall consider it as originally submitted.

If the offeror alleges a mistake, the Purchasing Manager shall advise him to support the allegation by statements concerning the alleged mistake and by all pertinent evidence, such as the bidder’s file copy of the bid, original worksheets and other data used in preparing the bid, such as subcontractor’s and supplier’s quotations, if any, published price lists, and any other evidence which will serve to establish the mistake, the manner in which it occurred, and the bid actually intended.

Additionally:

• A determination may be made permitting the bidder to correct his bid if the bidder requests permission to do so and clear and convincing evidence establishes both the existence of a mistake and the bid actually intended. In lieu of bid correction, the Commission may permit a low bidder alleging a material mistake of fact to withdraw his bid if there is reasonable proof that a mistake was made and the intended bid cannot be ascertained.

• A determination may be made permitting the bidder to withdraw his bid if the bidder requests permission to do so and clear and convincing evidence establishes the existence of a mistake. However, if the evidence is clear and convincing both as to the existence of a mistake and as to the bid actually intended, and if the bid, both uncorrected and corrected, is the lowest bid received, a determination may be made to correct the bid and not permit withdrawal.

• If the evidence does not warrant a determination under the two paragraphs above, a determination may be made by the Purchasing Manager that a bidder may neither withdraw nor correct his bid.

• Any clerical mistake, apparent on the face of a bid, may be corrected by the Commission prior to award, if the staff member has first obtained from the bidder verification of what was actually intended. Examples of such apparent mistakes are:

obvious misplacement of a decimal point, typographical errors, and mistakes in the designation of the unit of measure. Correction shall be reflected in the award document.

• After bid opening an otherwise low bidder shall not be permitted to delete exceptions to the bid conditions or specifications which affect price or substantive obligations.

• Nothing in this Section is intended to prohibit the Commission from accepting a bid correction resulting in a reduction in price from the low bidder after bid opening, provided that such reduction is not conditioned on or does not result in the modification or deletion of any condition contained in the solicitation.

J. PROPOSAL PROTESTS

Any actual or prospective offeror who is aggrieved in connection with the solicitation of proposals or award of a purchase may protest to the Commission’s Purchasing Manager. A protest related to an invitation for bids shall be submitted in writing prior to the opening of bids, unless the aggrieved person did not know and should not have known of the facts giving rise to such protest prior to bid opening. The protest shall be submitted in writing and received within 10 calendar days after such aggrieved person knows or should have known of the facts giving rise to the protest.

The protest must include:

• the name and address of the protester;

• identification of the solicitation or purchase;

• statement of reasons for the protest;

• any supporting documentation to substantiate the claim made, unless the documentation is not available within the protest delivery time, in which instance the expected date the material will be available is to be stated; and

• the remedy sought.

The purchasing agent shall, upon written request, make available to the protester information submitted that bears on the substance of the protest except where information is proprietary or otherwise confidential. The protester shall submit any additional information requested by the Purchasing Manager within five calendar days after receipt of the request for such information. Failure of the protester to respond to a request for information may result in the resolution of the protest on the basis of available information.

The decision of the Purchasing Manager shall be final and conclusive; unless fraudulent, or:

• within 10 calendar days from receipt of the written decision, the protester mails or otherwise furnishes a written appeal to the Executive Director, or

• any person adversely affected by the decision commences an action in court.

The decision of the Executive Director shall be final and binding.

K. ETHICS IN PROCUREMENT

By submitting a Proposal, the Offeror agrees to adhere to the Commission’s policy on ethics in purchasing. This policy prohibits any person from offering, giving, or agreeing to give any Commission employee or former Commission employee gratitude or an offer of employment in connection with any aspect of Commission procurement. Further, payment or offers to pay contingent fees related to procurement of Commission purchases are prohibited except for retention of bona fide employees or bona fide established commercial selling agencies for the purpose of securing business. Potential offerors are urged to review the ethics policy in detail. Copies may be requested from the Purchasing Division (phone:

301/454-1600).

L. BRAND NAMES OR EQUAL ITEMS

Except as may be specifically indicated to the contrary elsewhere within the bidding or contract documents, the specification by description of or reference to any particular product or item of material or equipment by type, brand name, make, model, catalog number or design description is intended only to establish a standard of quality. Any product, material or equipment of equal quality which is also the functional equivalent of and possesses the salient characteristics found in the particular item so specified may be substituted upon the approval of the Commission. Unless specifically noted in the solicitation, bidders are not restricted to the specific brand, make or manufacturer named but may offer to the Commission any material that the bidder considers equivalent to that specified or indicated.

The Commission reserves the right to approve as equal, or to reject as not being equal, any article the bidder proposes to furnish which contains major or minor variations from specification requirements even though the article may comply substantially.

The product offered as "or equal" must be clearly disclosed in the bid proposal. If it is not, the Commission will not be under any obligation to examine such product to determine whether it is or is not equal, and will do so only when it is determined to be in the best interest of the Commission.

Bidders must submit descriptive literature and/or samples of "or equal" products.

Requests for approval of "or equal" products may be made prior to the time specified for bid opening. The requirements for such approval are the same as the requirements for substitutions which are covered next.

M. SUBSTITUTIONS

Substitutions are considered to be:

Any change to the specifications in the bid proposal other than an "or equal" product.

Any change to the specifications after the bid opening.

No substitution will be considered prior to receipt of bids unless a written request for approval has been received by the Commission at least five (5) work days prior to the date set for the opening of the bid. Each request must include the name of the material or equipment for which it is to be substituted as well as a complete description of the proposed substitute including, as appropriate, drawings, cuts, performance and test data, and any other information necessary for evaluation. The burden of proof of the merit of the proposed substitute is upon the bidder.

The decision made by the Commission's representative to approve or disapprove a proposed substitution will be final. If the representative approves any proposed substitution prior to receipt of bids, such approval will be set forth in a written addendum to the bid document. Bidders must not rely upon approvals made in any other manner.

The procedure described above also applies to requests for approval of "or equal" products prior to bid opening. The Commission is under no obligation to consider any substitution after the bid opening. However, if it is in the best interest of the Commission to consider a substitution, it may do so. Any substitutions that are accepted by the Commission after the bid opening will be provided for in the contract, or in an amendment to the contract, or by change order to the Contract or Purchase Order.

N. ANTI-DISCRIMINATION PROGRAM

By submitting a proposal, an offeror shall understand and agree to:

1. Not discriminate against minority, female and disabled-owned firms (MFDs) in the selection of subcontractors on Commission projects. For contracts with subcontracting opportunities, offerors are required to provide MFDs the opportunity to submit bids as subcontractors and to award those MFDs submitting low bids the subcontracts unless there are legitimate reasons not to do so. On certain contracts, the Commission will require offerors to submit standardized forms with their bids that indicate how they have complied with the subcontracting non-discrimination requirements. The Special Conditions section of the bid documents specifies whether these forms must be submitted.

2. Not discriminate against MFDs in their performance of work as subcontractors on Commission contracts.

3. Submit forms verifying payment to subcontractors throughout the course of a contract.

4. Not discriminate against any employee or applicant for employment because of age, sex, race, creed, disability or national origin. If a firm is determined by a final order of an administrative agency or a court to be in violation of federal, state or county non-discrimination laws, any agreement entered into by the Commission with a firm may be terminated or suspended in whole or in part by the Commission, and the firm may be debarred from bidding on future contracts with the Commission.

The subcontracting non-discrimination program shall apply not only to the initial contract award, but also to certain major change orders and amendments that serve to increase the dollar value of the initial contract.

Any violation of the Commission’s Anti-Discrimination Program may result in suspension or debarment of the violator as well as other civil or administrative remedies.

A minority-owned business is any entity that engages in commercial transactions and is at least 51 percent owned and controlled by one or more individuals from the following groups: African Americans (all persons having origins in and of the black racial groups of Africa), Hispanics (all persons of Mexican, Puerto Rican, Cuban, Central or South American, or other Spanish culture or origin, regardless of race), Asians or Pacific Islanders (all persons having origins in any of the Far East, Southeast Asia, the Indian Subcontinent, or the Pacific Islands), and Native Americans (all persons of American Indian, Aleut, Eskimo or Native Hawaiian background). A female-owned business is any entity that engages in commercial transactions and is at least 51 percent owned and controlled by one or more women. A disabled-owned business is any entity that engages in commercial transactions and is at least 51 percent owned and controlled by persons with physical or mental impairment that substantially limits one or more of the major life activities of the individual, as defined in the Americans with Disabilities Act of 1990.

Part 2. SCOPE OF SERVICES

A. PROJECT DESCRIPTION

The Montgomery County Department of Parks, part of the Maryland-National Capital Park and Planning Commission (M-NCPPC or Commission), is soliciting proposals to provide design-build services to design, permit, construct and energize a rooftop solar installation at Pauline Addie Betz Tennis Center. This project is part of a larger Parks Initiative to double solar production within the system in the next four years to support M-NCPPC’s priorities to:

• Meet Montgomery County Climate Action Plan goals to eliminate greenhouse gases from our operations by 2035

• Provide regional health benefits for our community through reduced regional air pollution

• Reduce electricity grid purchases.

The Basis of Design drawings are included with this RFP are provided for information purposes only. These drawings are intended to assist offerors in understanding system size, configuration, interconnection requirements, major equipment and overall project intent. The drawings are NOT issued for construction and should not be relied upon as final design documents.

The selected contractor shall be responsible for the complete design, engineering, permitting and preparation of construction documents necessary for the successful implementation of the project. The Commission reserves the right to determine the acceptability of all proposed equipment, materials, and design approach.

1. Project Details

a. Desired Solar PV System Description: The proposed rooftop PV systems shall be sized to maximize energy production and cost savings. Further details are provided in Attachment B which include a conceptual layout. Proposals should be based on this preliminary design. The Basis of Design equipment is intended to meet Domestic Content bonus tax credit criteria. System designs must meet minimum FEOC requirements to ensure tax credit eligibility.

b. System Ownership: Upon Installation and acceptance, the systems shall be owned by M-NCPPC.

Site Details Solar PV Details Name Address Electric Load PV Type Estimated

PV Size kWh/year kW-DC

Pauline Addie Betz Tennis Center

7801 Democracy Blvd., Bethesda, MD 2081

Approx.

488,000

Rooftop 318

c. Monitoring: The Solar PV System shall include a remote monitoring platform capable of monitoring energy production and system performance on a continuous basis. The platform shall provide automated notifications and shall allow authorized M-NCPPC personnel access.

d. First Year Maintenance: The Contractor shall provide quarterly preventive maintenance services for each solar PV systems installed by the contractor.

2. Design Guidelines

The Proposer shall provide design documents for all project elements, including, but not limited to, structural, mechanical, and electrical drawings, as required for design development and permit approvals. The Proposer shall develop the design of new PV systems to optimize energy production and cost efficiency. The Proposer is responsible for verifying the building’s structural capacity, roof condition, and any shading constraints.

• Mounting systems shall limit roof penetrations. Mounting system design needs to meet applicable local building code requirements and amendments with respect to snow, wind, and earthquake loading factors.

• Conduit penetrations shall be minimized.

• Systems shall be fixed tilt with an orientation that maximizes energy production and cost savings.

• All roof access points shall be securely locked at the end of each day during construction.

• System layout shall meet local fire department, code and ordinance requirements for roof access.

3. Permitting

Rooftop solar projects in Montgomery County require two permits: a building permit (for the attachment of the solar panels) and an electrical permit (for the connection to the building's electrical service). The selected Contractor(s) shall prepare the design documents and permit applications for both permits for each project and submit to Department of Permitting Services (DPS) for approval. As a Commission project, the Work is exempt from building permit fees; however, trade permits and other required permit fees remain the responsibility of the Contractor.

The Contractor(s) shall be responsible for coordination with the local energy provider (Pepco) for utility interconnection. The Contractor(s) shall complete the two-part interconnection agreements. The system(s) cannot be energized prior to formal Authorization to Operate.

4. Code Specifications

All work shall comply with all Federal, State, Local laws, ordinances, rules, regulations, codes and guidelines. Only products that are listed, tested, identified, or labeled by Underwriters Laboratories (UL) or another nationally recognized testing laboratory shall be used as components in the project. Construction must comply with current adopted Montgomery County Building Code, which includes International Building Code, National Electric Code (NEC) and Fire Marshall (if applicable).

• Modules: System modules shall be certified to IEC 61215 (current edition, covering crystalline silicon and thin-film technologies) for performance and IEC 61730 / UL 61730 for safety. Modules shall be listed by a nationally recognized testing laboratory and included on the California Energy Commission (CEC) Eligible Equipment List.

• Inverters: Inverters shall be UL 1741 listed, including compliance with UL 1741 Supplement B (SB) for advanced inverter / IEEE 1547-2018 smart inverter functions as required by the applicable utility interconnection agreement. Inverters shall be included on the CEC Eligible Equipment List with a weighted CEC efficiency of 97% or higher.

• Rapid shutdown: For rooftop or building-integrated systems, rapid shutdown equipment shall comply with NEC 2017 §690.12 or the currently adopted NEC edition and shall be listed to UL 1741 or the applicable product standard.

5. Material Sourcing

The pricing proposal shall be based on a solar PV system designed to qualify for the applicable Domestic Content Bonus Credit.

6. Warranties

The Offeror must provide the below warranty coverage for modules, inverter, racking and workmanship.

• Panels: Minimum 25-year manufacturer warranty on power output

• Inverters: Minimum 10-year manufacturer warranty on power output

• Racking: Minimum 20-year manufacturer warranty on racking components

Offerors shall note if labor is covered for manufacturer replacements

• Workmanship: Minimum 10 years

7. TAB and Commissioning

The selected Contractor(s) shall Test and Balance the systems. The Contractor(s) shall perform all testing necessary to demonstrate proper installation and system performance. Minimum requirements include:

• Verification of electrical connections, grounding, and system integrity

• Functional testing of inverters, disconnects, and monitoring systems

• Confirmation of utility interconnection and system energization

• Verification of system output consistent with design expectations

• All equipment specifications match the proposed equipment specifications

• The physical layout aligns with the as-built diagrams with variations to proposed system noted

• The electrical system as laid out and connected aligns with the as built one-line diagrams including fuses, relays and switches with variation to proposed system noted

• Racking attachments are secure and any penetrations properly sealed per racking and roof manufacturer recommendations

• Each array passes the open circuit voltage and current test

• The manual disconnect switches (AC Disconnections and DC Disconnections) operate correctly

Following acceptance of the TAB, the Commission will engage an independent third party to Commission the system. The Contractor(s) shall be responsible for making corrections or modifications to the system(s) should they be required based on the Commissioning Agent’s evaluation and report.

The Commission’s independent Commissioning Agent will ensure, at a minimum, that:

• All equipment specifications match the proposed equipment specifications

• The physical layout aligns with the as-built diagrams with variations to proposed system noted

• The electrical system as laid out and connected aligns with the as built one-line diagrams including fuses, relays and switches with variation to proposed system noted

• Racking attachments are secure and any penetrations properly sealed per racking and roof manufacturer recommendations

• Each array passes the open circuit voltage and current test

• The manual disconnect switches (AC disconnects and DC disconnects) operate correctly

• System is properly mapped and communicating in the monitoring software

8. Inspection & Training

The Contractor(s) shall provide on-site training and provide written and digital documentation for Commission staff, including:

• System overview and components

• Monitoring system use and data interpretation – transfer to M-NCPPC monitoring

• Routine inspection and maintenance procedures

• Emergency shutdown procedures

• Warranty registrations, start dates, end dates, and RMA process

• As-built plan sets

9. System Monitoring

Monitoring of system performance (separate from utility meter monitoring requirements) is required. The regularly collected data should reflect, but not be limited to, the following:

• Average and accumulated output (kWh/day, kWh/year, and cumulative kWh) versus building load

• Actual vs. projected system output based on actual weather data

• Capacity factor

• Provide alerts & notifications for failure or underperformance

B. PHASES AND TASKS (TABLE B)

The project includes design, permitting and construction of a solar installation to be fully operational by December 10, 2027, to qualify for federal tax credits. The following Table B is an overview of the tasks by project Phase that will be required for each project. The list is not exhaustive, and additional items may be required.

PHASE PROJECT

INVOICE CONTRACTOR TASKS &

DELIVERABLES

NOTES

Project Kick-off

10% of Design

Fee

• Project Kick-off Meeting including:

- Project Schedule

- Quality Control Plan

- Design Management

Plan

- Schedule of Values

• Field Visits for Design Confirmations

• Initial Solar PV Description

• Outline Equipment Details & Specifications

• Review Incentive Documentation Process & Timeline

• Monitoring System Approach

• Interconnection agreement with PEPCO Part I

• Confirm design direction and any deviations from RFP conceptual plans and specifications

50% Construction Documents

45% of Design

Fee

• 50% Construction Documents & Specifications

• Project Schedule Update

• Review meeting with Parks

• DPS Design Consultation

• All submissions should be in PDF format

• Allow 12 Work Days for the Commission to review design submissions and provide comments to Contractor

90% Construction Documents

30% of Design

Fee

• 90% Construction

Documents & Specifications

• Project Schedule Update

• Review meeting with Parks

100% CD/

Permit Submission

10% of Design

Fee

• 100% Construction Documents & Specifications

• Supporting documentation

• Project Schedule Update

• Review meeting with Parks

Permitting/ Conformed Set

5% on Design

Fee

• Conformed set is the final permitted set, including all specifications, project data and supporting documentation for construction.

C. PROGRESS COORDINATION

1. Meetings

a. Schedule regular progress meetings during the Design Phase. Schedule bi-weekly meetings during the Construction Phase.

b. Provide weekly updates throughout design and construction on the project progress via email, phone call or virtual meeting.

c. Schedule review meetings after each Design Phase submission (Kick Off, 50%

CD and 90% CD, Permit Submissions).

Construction Phase

• Pre-construction meeting including:

- Safety Plan

- Submittal Log

- Construction Project

Schedule

• Construction Progress

Reports

• Shop drawings and other submittals

• Substantial Completion

Report

• Punch List

• Quality Control Plan (QCP)

• TAB & Commissioning

Coordination

• Final Completion

(Retainage Release) Certificate of Final Completion

• Finalized Interconnection agreement with

PEPCO

• Electronic submittal via approved cloud-based platform

• Allow 7 Workdays for Owner Review of RFI’s

• Allow 14 Workdays for Owner review of submittals

• At a minimum, the QCP should conform to “IEC 62446 Grid-Connected PV Systems – Minimum Requirements for System Documentation, Commissioning Tests, and Inspections.”

Post Construction Phase

• Submission documentation for available rebates and incentives

• Final Inspections

• Maintenance & Operations

Manual

• Safety Manual

• Warranties

• As-Built Drawings

Recurring Deliverables

• Agendas and Meeting Minutes

• Regulatory and Utility Agency Submissions

• Project Schedule Updates

• Electronic submittal -platform TBD

d. Provide minutes of all meetings to the M-NCPPC Project Manager (PM) and Construction Manager (CM) within seven (7) calendar days.

e. The Contractor shall work cooperatively with M-NCPPC staff, representatives from other public agencies, and the community being served.

f. The Contractor shall work with representatives from all regulatory agencies to obtain all necessary permits. Schedule a “Design Consultation” with plan review staff at DPS prior to submitting for permit.

2. Scheduling and Reporting

a. The Contractor shall actively manage the Work to ensure compliance with the Project Schedule and shall provide timely and continuous progress updates to the M-NCPPC Project Manager and Construction Manager.

b. The Contractor shall submit Preliminary Project Schedule and Schedule of Values within two (2) weeks following the Notice to Proceed (NTP). A detailed Project Schedule shall be submitted two (2) weeks after the Kick-Off Meeting, at the commencement of each Project Phase, and anytime the schedule indicates a delay exceeding one (1) week (“Project Schedule Slip”). For any Project Schedule Slip, the contractor shall provide a written explanation and a mitigation plan addressing both the cause and the measures proposed to prevent additional delays.

c. The Contractor shall prepare and submit all project schedules using Microsoft Project or similar scheduling software approved by M-NCPPC.

3. General Requirements

a. The Design Build Contractor shall furnish all labor, materials, and professional services required to design, permit, construct, and complete the Project so that the facility is fully ready for its intended use, including but not limited to obtaining all regulatory approvals.

b. The work shall include all labor, supervision, materials and equipment, whether expressly stated or incidental, that are necessary to perform and complete the project in accordance with the contract documents.

c. All work shall comply with all Federal, State, and Local laws, ordinances, rules, regulations, codes, and guidelines.

d. The work shall comply with the 2010 ADA Standards for Accessible Design, as applicable.

e. Design and construction of the project shall comply with the Park Development Division’s Design Guidelines, Standard Specifications for Construction and Standard Details. Standard specs and details will be provided to the selected Contractor and may be modified to be project-specific with the approval of the M- NCPPC PM and/or CM. Specifications shall include, but not be limited to, asphalt, concrete and construction waste management.

f. Construction documentation, including but not limited to specifications, shall comply with the requirements of the M-NCPPC Design-Build General Conditions (Part 3).

g. When construction crews are working, all approved permit drawings and related documents shall be on site at all times.

h. Unless a deviation is approved by the M-NCPPC PM and CM and implemented via a properly executed Change Order, all work shall be provided on a schedule determined at the beginning of the project and within the established budget.

i. If any unforeseen physical conditions are encountered at the site, a written notice stating the date and circumstances shall be submitted to the M-NCPPC CM for a Change Order Request prior to performing any Work. The written notice must be submitted within ten (10) days of discovery of the condition and must include an approximate cost and an estimate of the timeframe to complete the work. See General Conditions (Part 3) for specific requirements regarding Contract Changes and Amendments.

D. PROJECT SCHEDULE

Request for Proposals Issued: November 2026 Bids Due: December 2026 Notice to Proceed: March 2027 Design and Permitting: March 2027 – April 2027 Construction Activities: April – November 2027 Solar Systems Operational: December 10, 2027

E. DELIVERABLES

1. M-NCPPC will provide an AutoCAD sheet template to the Contractor.

2. Issue permit submissions to the M-NCPPC PM for review prior to formal submission to external agencies.

3. Incorporate all regulatory review comments into the final design documents

(Conformed Set) prior to construction.

4. Provide copies of all submissions, back-up documentation and correspondence with all Regulatory and Utility Agencies within seven (7) calendar days after agency approval.

5. A Project Progress Report and an updated Project Schedule shall be provided with each invoice.

6. See Table B: Tasks & Deliverables for details on deliverables per project Phase.

F. Material Content Credit

The Offerors’ base bid shall be based on Domestic Content Materials. If during the design process a non-Domestic Content, FEOC (Foreign Entity of Concern Compliant) or foreign content alternate is proposed and accepted, the contractor shall provide credit to M-NCPPC for the value of the difference in cost. Any such credit will be implemented via a bi-lateral contract change order.

The contractor shall provide documentation of the cost of the specified domestic content materials and of the alternate materials to calculate the credit value.

Part 3. GENERAL CONDITIONS – DESIGN BUILD

THE MARYLAND-NATIONAL CAPITAL PARK AND PLANNING COMMISSION

General Conditions – Design Build (Rev. 140919)

1. DEFINITIONS AND RESPONSIBILITIES

1.1. Definitions

Whenever and wherever throughout the Bidding and Contract Documents the words, or pronouns used in their stead, terms and phrases or the abbreviations defined in this Section appear, they shall have and be given the meanings set forth herein. Unless otherwise specifically defined in this Section, however, or unless the context of their usage clearly requires a different meaning, all words, terms and phrases not having a well known or commonly accepted special usage in the construction industry, or a well established technical meaning, shall be given their ordinary meaning.

Any use of masculine pronouns herein includes both the feminine and neuter genders, and vice versa. The use of the singular tense includes the plural, and the plural the singular.

The headings provided are listed for convenience only, and do not add to, alter or modify the meaning of the substantive text.

1.1.1. Words, Terms and Phrases

ADDENDUM (ADDENDA) - Written or graphic documents issued by the Commission prior to the time of bid opening, which revise or interpret the Bidding Documents by addition, deletion, clarification or correction.

AMENDMENT - A written document issued by the Commission, subsequent to the award and execution of the Contract and signed by the Contractor and the Commission, in which the Contractor and Commission mutually agree to undertake work beyond the scope of a Change Order.

APPROVED EQUAL - Those materials or equipment which possess the salient characteristics of and which in terms of quality, design and performance are functionally equivalent or superior to those of any specified item of material or equipment.

AS-BUILT DRAWINGS – Revised set of Contract Drawings submitted by Contractor to the Commission upon Substantial Completion. They reflect all changes made in the specifications and working drawings during the construction process, and show the exact dimensions, geometry, and location of all elements of the work completed under the Contract.

AWARD - The decision by Commission to execute a contract after all necessary approvals have been obtained.

BID(S) - A completed and executed written offer contained upon the Bid Form, which is submitted to the Commission pursuant to and in accordance with an Invitation For Sealed Bids and which sets forth the price, scope of work, schedule and description of the supplies, materials, services and construction, or construction-related Work which the Bidder proposes to furnish and perform on behalf of the Commission in response to an Advertisement For Bids.

BID BOND - See "PROPOSAL GUARANTY."

BID FORM - The approved form on which the Commission requires bids to be set forth and submitted.

BIDDER - A legal entity formally submitting a Bid for the Work contemplated, acting directly or through a duly authorized representative.

BIDDING DOCUMENTS - The documents which set forth the design concepts, Commission’s design criteria, pricing requirements and other conditions for the Work to be performed, describing the procedures and requirements for submitting a Bid, and indicating the terms and conditions upon which bids for a contract to be awarded by the Commission will be evaluated. Such documents typically include, the Advertisement For Bids, the Invitation for Sealed Bids, the Instructions to Bidders and any Supplemental Instructions to Bidders, the Bid Forms, the Contract and all Contract Forms, the General Conditions and any Supplemental General Conditions, Special Conditions or other Conditions of the Contract, drawings issued by the Commission, and all Addenda or Amendments thereto.

BUSINESS - A corporation, partnership, individual, sole proprietorship, joint venture or any other legal entity through which commercial activity is conducted.

CALENDAR DAY - Every day shown on the calendar, Saturdays, Sundays and holidays included.

CHANGE - An alteration or addition to, or deletion from, the requirements of the Contract Documents authorized to be made under the Contract.

CHANGE ORDER - A written document signed and issued by an authorized representative of the Commission, subsequent to the award and execution of the Contract, directing a Contractor to make alterations or additions to, or deletions from, the requirements of the Contract Documents which the Changes Clause of the Contract…