852207vadotB32_127208.pdf

PDF 5 MB Posted

Attached to
Culvert Rehab, Rt 346 (Rt 754 to Dead End)
Solicitation number
127208
Issued by
Patrick County, Virginia

About this file

This is a bid proposal and contract document from the Virginia Department of Transportation for culvert rehabilitation work in Patrick County, Virginia, on Route 346. The project involves culvert rehabilitation from 0.10 miles at the intersection of Route 754 to 0.75 miles to a dead end in the Salem District. Bids were submitted electronically through Bidx on November 18, 2026, at 10:00 AM. The project includes multiple work items such as check dam rock, siltation control excavation, temporary silt fence, concrete class A3 substructure maintenance, pipe rehabilitation (60-inch, method B, category D) as the lump sum primary item, high visibility fence, flowable backfill, temporary signage, flagger services, mobilization, and various seeding and fertilizer applications totaling approximately 1,114 square yards of rolled erosion control products. The contract completion date is May 7, 2027. The bid proposal requires submission of all items listed in the schedule, with pricing provided by bidders on individual line items and lump sum components.

The proposal requires a bid bond equal to five percent of the total bid value and mandates strict compliance with Virginia Department of Transportation Road and Bridge Specifications dated 2020 and supplemental specifications dated 2022. A Small, Women-owned, and Minority-owned Business (SWAM) participation form is included with a 0.00 percent requirement shown on the SWAM requirements form. The contract includes provisions for subcontractor solicitation and utilization documentation, mandatory drug-free workplace compliance, equal employment opportunity requirements, stormwater pollution prevention plan certification, progress schedule submissions with detailed baseline and update requirements, optional fuel adjustment for eligible items identified on Form C-21B, and prevailing wage rate compliance. Electronic or printed weigh tickets are acceptable for material measurement. The contract contains special provisions for flagger certification requirements, portable changeable message sign security protocols, security requirements for construction sites, and protections for bat species. Payment adjustments for fuel costs may apply to designated items based on monthly diesel fuel price indices from the U.S. Department of Energy. No separate payment is provided for progress schedule submissions or scheduling meetings.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ORDER NO.: B32

CONTRACT ID. NO.: C0000127208D48

Form C-6a Rev. 3-22-05

CNSP (S) 1-9-06

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

BID PROPOSAL AND CONTRACT

ROUTE NUMBER: 346

FHWA NUMBER: NONE

PROJECT NUMBER: 0346-070-736,D648

COUNTY: PATRICK

DISTRICT: SALEM

DESCRIPTION: CULVERT REHAB

FROM: 0.10 MI. INT. RTE. 754

TO: 0.75 MI. TO DEAD END

DATE BID SUBMITTED: 10:00 AM WEDNESDAY, NOVEMBER 18, 2026

Form C-118 Rev. 8-10-2026

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

NOTICE TO BIDDERS

As a matter of information, the bidder’s attention is directed to the points noted herein. Every point enumerated below is fully covered by proposal documents that describe them in detail. Bidders should check their proposal against all requirements, as strict compliance with all provisions is mandatory.

1. Bids shall be filed electronically through Bidx (https://bidx.com/site/home) at the times designated in the Notice of Advertisement for Bids. For information see (https://cabb.virginiadot.org/)

2. Unless otherwise specified or permitted in the proposal, prices shall be submitted on all items shown in the proposal.

3. Proposals conditioned by proposed alternates, other than those specified or permitted, or by reserving the right to accept or reject an award or to enter into a contract pursuant to an award will not be considered.

4. A bid total shall be shown in each space provided.

5. Bid bonds shall conform to Section 102.07. The bid bond number shall be placed in the appropriate space in your electronic bid. As an alternative, you may complete the bottom line of Form C-24. The form may be emailed to the Construction Division at VDOTContracts@vdot.virginia.gov and must be received prior to the opening of bids.

6. Joint venture proposals shall show the Firm Name of each party and shall be signed by an authorized representative of each Firm. A letter shall be filed with the prequalification office describing responsibility of each firm and the amount of maximum capacity pledge by each firm of a joint venture.

Form C-24 Rev. 7-6-05

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

PROPOSAL GUARANTY

KNOW ALL MEN BY THESE PRESENTS, THAT WE _______________________________________ as principal, and ________________________________________ Surety, are held and firmly bound unto the Commonwealth of Virginia as obligee, in the amount of FIVE PERCENT OF THE DOLLAR VALUE OF THE BID, lawful money of the United States of America, for the payment of which, well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally and firmly by these presents.

SIGNED, sealed and dated this day of , 20

WHEREAS, the above said principal is herewith submitting its proposal for:

PROJECT NUMBER: 0346-070-736,D648

NOW, THEREFORE, the condition of the above obligee is such, that if the aforesaid principal shall be awarded the contract upon said proposal and shall within the time specified in the Specifications after the notice of such award enter into a contract and give bond for the faithful performance of the contract, then this obligation shall be null and void; otherwise to remain in full force and effect and the principal and surety will pay unto the obligee the difference in money between the amount of the bid of the said principal and the amount for which the obligee may legally contract with another party to perform the said work if the latter amount be in excess of the former; but in no event shall the liability exceed the penal sum hereof.

(Principal*) (Surety Company)

By: By:

(Officer, Partner or Owner) (Seal) (Attorney-in-Fact**) (Seal)

(Principal*) (Address)

(Officer, Partner or Owner) (Seal) (Surety Company)

(Principal*) (Attorney-in-Fact**) (Seal)

(Officer, Partner or Owner) (Seal) (Address)

*Note: If the principal is a joint venture, each party thereof must be named and execution made by same hereon. If there is more than one surety to the bid bond, each surety must be named and execution shall be made by same hereon.

Electronic Bid Only: In lieu of completing the above section of the Contract Performance Bond, the Principal shall file an Electronic Bid Bond when bidding electronically. By signing below the Principal is ensuring the identified electronic bid bond has been executed and the Principal and Surety are firmly bound unto the Commonwealth of Virginia under the same conditions of the bid bond as shown above.

Electronic Bid Bond ID Company/Bidder Name Signature and Title

**Attach copy of Power of Attorney

Form C-48 Rev. 10-8-2025

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

SUBCONTRACTOR/SUPPLIER SOLICITATION AND UTILIZATION FORM (ALL BIDDERS)

PROJECT NO. 0346-070-736,D648

CONTRACT ID. NO. C0000127208D48

FHWA NO. NONE DATE SUBMITTED

All bidders, including SWAM bidding as Prime Contractors, shall complete and submit the following information as requested in this form within ten (10) business days after the opening of bids.

The bidder certifies this form accurately represents its solicitation and utilization or non-utilization, as indicated, of the firms listed below for performance of work on this contract. The bidder also certifies he/she has had direct contact with the named firms regarding participation on this project.

BIDDER_________________________________SIGNATURE________________________________

TITLE_____________________________________________________________________________

SUBCONTRACTOR/SUPPLIER SOLICITATION AND UTILIZATION (ALL)

VENDOR

NUMBER

NAME OF SUBCONTRACTOR/SUPPLIER

TELEPHONE NUMBER

SWAM OR

NON-SWAM

UTILIZED

(Y/N)

NOTE: ATTACH ADDITIONAL PAGES, IF NECESSARY.

BIDDER MUST SIGN EACH ADDITIONAL SHEET TO CERTIFY ITS CONTENT AND COMPLETION OF FORM.

Form C-7 Rev. 2-2-24

TERMS OF THE PROPOSAL\CONTRACT

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

SUBMITTED: 10:00 AM WEDNESDAY, NOVEMBER 18, 2026

PROJECT NUMBER:

ROUTE NUMBER:

FHWA NUMBER:

DESCRIPTION:

FROM:

TO:

0346-070-736,D648

NONE

CULVERT REHAB

0.10 MI. INT. RTE. 754

0.75 MI. TO DEAD END

DISTRICT: SALEM COUNTY: PATRICK

I/we declare that no other person, firm or corporation is interested in this proposal; that I/we have carefully examined the plans, job specifications, current Road and Bridge specifications, and all other documents pertaining thereto and thoroughly understand the contents thereof; that I/we meet the prequalification requirements for bidding on this proposal;

that I/we understand that the plans and current Road and Bridge specifications, are a part of this proposal; that all of the quantities shown herewith are a part of this proposal; that all the quantities shown herewith are approximate only; that I/we have examined the location of the proposed work and source of supply of materials; and that I/we agree to bind myself/ourselves upon award by the Commonwealth under this proposal to a contract with necessary surety bond to start work according to project specifications, and to complete all work in accordance with the plans, job specifications and current Road and Bridge Specifications within the time limit set forth in the contract.

COMPLETION DATE: MAY 7, 2027

BID TOTAL $

Attached is a bond conforming to the requirements of the current Road and Bridge Specifications, it being understood that such bond is to be forfeited as liquidated damages if, upon acceptance of the terms of this proposal, I/we fail to execute the contract and furnish bond as provided in the current Road and Bridge Specifications.

(Names of Individual(S),Firm(S) Or Corporation)

Street Address City State Zip Code Vendor#/Fin#

Print Name Signature Title

In consideration of the commitments made as shown herein, the Commonwealth of Virginia by The Commonwealth Transportation Commissioner agrees to pay for all items of work performed and materials furnished at the unit price(s) and under the conditions set forth in this proposal, in witnessed by the affixing of the name below.

Contract Execution Date By

CHIEF ENGINEER

VIRGINIA DEPARTMENT OF TRANSPORTATION

Virginia Department of Transportation 10/02/2026Date Printed:

Schedule of Items Page: 2

Proposal ID: C0000127208D48 0346-070-736,D648 Order No.: B32

Oversight/State Project No.:

Federal Project No.: NONE

Contractor:

0001 REGULAR BID ITEMSSECTION:

Cat Alt Set ID: Cat Alt Mbr ID:

Bid AmountUnit Price Approximate Quantity and

UnitsDescription

Item ID Proposal

Line Number Dollars Cents Dollars Cents

Spec No.

0010 303SD20-0023

CHECK DAM ROCK TY. II EA

4.000

0020 303SD20-0029

SILTATION CONTROL

EXCAVATION

CY

44.000

0030 303SD20-0034

TEMP. SILT FENCE TYPE A LF

250.000

0040 404SD20-0021

CONCRETE CLASS A3

SUBSTRUCT. MAINT.

CY

4.000

0050 412SX20-0022

BR. SUBSTR. WID./REPAIR

PIPE REHABILITATION (60IN.,

METHOD B, CATEGORY D)

LUMP SUM _________._____LUMP SUM

ATTD

0060 507SD20-0027

HIGH VISIBILITY FENCE, 4

FEET

LF

600.000

0070 509SD20-0001

FLOWABLE BACKFILL CY

9.000

0080 512SD20-0014

TEMPORARY SIGN SF

72.000

0090 512SD20-0027

FLAGGER SERVICE HR

200.000

0100 513SD20-0001

MOBILIZATION LUMP SUM _________._____LUMP SUM

0110 603SD20-0002

TEMPORARY SEED LB

23.000

0120 603SD20-0003

REGULAR SEED LB

62.000

0130 603SD20-0004

OVERSEEDING LB

49.000

Schedule of Items Page: 3

Proposal ID: C0000127208D48 0346-070-736,D648 Order No.: B32

Oversight/State Project No.:

Federal Project No.: NONE

Contractor:

0001 REGULAR BID ITEMSSECTION:

Cat Alt Set ID: Cat Alt Mbr ID:

Bid AmountUnit Price Approximate Quantity and

UnitsDescription

Item ID Proposal

Line Number Dollars Cents Dollars Cents

Spec No.

0140 603SD20-0005

LEGUME SEED LB

3.000

0150 603SD20-0006

LEGUME OVERSEEDING LB

2.000

0160 603SD20-0014

FERTILIZER NITROGEN - N LB

23.000

0170 603SD20-0015

FERTILIZER PHOSPHOROUS

- P

LB

16.000

0180 603SD20-0016

FERTILIZER POTASSIUM - K LB

16.000

0190 603SD20-0017

LIME TON

1.260

0200 606SD20-0001

ROLLED EROSION CTRL

PRODUCT EC-2 TYPE 1

SY

1,114.000

Section: 0001 _________._____Total:

Total Bid: _________._____

Page

Bid Items Eligible For Fuel Adjustment

C0000127208D48

B32

Contract ID:

Order No.:

Instructions: This form shall be completed in accordance with the Special Provision for Optional Adjustment for Fuel. If you choose to have Fuel Adjustment applied to any of the items listed below, write the word "Yes" in the "OPTION" column beside the item. The form must be signed, dated, and submitted to the Contract Engineer within the timeframe required in the Special Provision.

FORM C-21B

Rev 12-21-05

0001 REGULAR BID ITEMSSECTION:

ltem Description Fuel Factor gal/unit Option Item

Number

_______SILTATION CONTROL EXCAVATION 0.290303SD20-0029

_______CONCRETE CLASS A3 SUBSTRUCT. MAINT. 1.892404SD20-0021

Date:

Signature:

(Firm or Corporation)

(Vendor No.)

Form C-111S 6-7-16

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

MINIMUM SWAM REQUIREMENTS

PROJECT NUMBER: 0346-070-736,D648

Federal Project No.: NONE

* * * INSTRUCTIONS * * *

THIS FORM CAN BE USED BY THE CONTRACTOR TO SUBMIT THE NAMES OF SWAM FIRMS TO BE UTILIZED ON THE PROJECT. THE CONTRACTOR SHALL INDICATE THE DESCRIPTION OF THE CATEGORY (S, M, SP or H) AND THE TYPE OF WORK THAT EACH SWAM WILL PERFORM AND THE ALLOWABLE CREDIT PER ITEM(S). ADDITIONAL SHEETS TO SHOW THE ALLOWABLE CREDIT PER ITEM MAY BE ATTACHED IF NECESSARY. PLEASE NOTE: THE AMOUNT OF ALLOWABLE CREDIT FOR A SWAM SUPPLIER IS 60% OF THE TOTAL COST OF THE MATERIALS OR SUPPLIES OBTAINED AND 100% FOR A SWAM MANUFACTURER OF THE MATERIALS AND SUPPLIES OBTAINED. A CONTRACTOR MAY COUNT 100% OF THE FEES PAID TO A SWAM HAULER FOR THE DELIVERY OF MATERIALS AND SUPPLIES TO THE PROJECT SITE, BUT NOT

FOR THE COST OF THE MATERIALS AND SUPPLIES THEMSELVES.

SWAM REQUIREMENT %

PERCENT ATTAINED BY BIDDER %

NAMES(S) AND CERTIFICATION NO.

OF SWAM(S) TO BE USED

USED AS

SUBCONTR. (S)

MFG. (M)

SUPPLIER (SP)

HAULER (H)

TYPE OF WORK AND ITEM

NO(S)

$ AMOUNT OF

ALLOWABLE

CREDIT PER

ITEM

TOTAL $

TOTAL CONTRACT VALUE $ x REQUIRED SWAM % = $

I/WE CERTIFY THAT THE PROPOSED SWAM(S) SUBMITTED WILL BE USED ON THIS CONTRACT AS STATED HEREON AND ASSURE THAT DURING THE LIFE OF THE CONTRACT. I/WE WILL MEET OR EXCEED THE PARTICIPATION

ESTABLISHED HEREON BY THE DEPARTMENT.

BY

BIDDER SIGNATURE

BY

TITLE DATE

0.00

Form C-112S 6-7-16

COMMONWEALTH OF VIRGINIA

DEPARTMENT OF TRANSPORTATION

CERTIFICATION OF BINDING AGREEMENT

WITH

SMALL, WOMEN-OWNED, AND MINORITY-OWNED BUSINESS FIRMS

PROJECT NO: 0346-070-736,D648

Federal Project No.: NONE

This form is to be submitted in accordance with the Department’s Special Provision for Section 107.15.

It is hereby certified by the below signed Contractors that there exists a written quote, acceptable to the parties involved preliminary to a binding subcontract agreement stating the details concerning the work to be performed and the price which will be paid for the aforementioned work. This document is not intended to, nor should it be construed to, contain the entire text of the agreement between the contracting parties.

This document does not take the place of, nor may it be substituted for, an official subcontracting agreement in those situations that may require such an agreement. A copy of the fully executed subcontract agreement shall be submitted to the Engineer within fourteen (14) business days after contract execution.

It is further certified that the aforementioned mutually acceptable quote and fully executed subcontract agreement represent the entire agreement between the parties involved and that no conversations, verbal agreements, or other forms of non-written representations shall serve to add to, delete, or modify the terms as stated.

The prime Contractor further represents that the aforementioned mutually acceptable quote and fully executed subcontract agreement shall remain on file for a period of not less than one year following completion of the prime's contract with the Department or for such longer period as provisions of governing Federal or State law or regulations may require. For purposes of this form, the term Prime Contractor shall refer to any Contractor utilizing a SWAM subcontractor, regardless of tier, in which they are claiming SWAM credit toward the contract goal.

Contractors further jointly and severally represent that said binding agreement is for the performance of a "commercially useful function" as that term is employed in 49 C.F.R. Part 26.55 (c), (d).

SWAM Contractor

By:

Signature Title

Date:

*Subcontractor

By:

Signature Title

Date:

* TO BE SIGNED BY THE SUBCONTRACTOR ONLY IF THEY HAVE A CONTRACT WITH THE ABOVE SWAM FIRM

Prime Contractor

By:

Signature Title

Date:

FORMS and SCHEDULE OF ITEMS PRECEDE SPCNs, SPs and SUPPLEMENTAL SPECS.

CN100-000026-09 GEN. PROJ. REQUIRE., SSS/SPS/SPCNS 12-11-25 (SPCN)

CN103-000120-01 SEC 103.02—AWARD OF CONTRACT 6-17-25 (SPCN)

CN105-000140-00 SEC 105.14—MAINTENANCE DURING CONSTRUCTION 12-20-24 (SPCN)

CN105-000150-00 SECURITY REQUIREMENTS FOR PCMS 1-30-26 (SPCN)

CN105-000610-00 SEC 105.06—SUBCONTRACTING R-7-12-16 (SPCN)

CN245-000100-01 SEC 245.03—TESTING & DOCUMENTATION 1-10-24 (SPCN)

CQ107-000130-00 DRUG-FREE WORKPLACE 7-3-19 (SPCN)

CQ107-000150-00 EQUAL EMPLOYMENT OPPORTUNITY 5-11-22 (SPCN)

CQ522-000100-03 PROTECTION OF BAT SPECIES 1-17-18 (SPCN)

SP102-000120-00 NON-DISCRIMIN. EMPLOY. & CONTRACT. PRACTICES (EO-61) 1-10-17

SP107-000110-00 C-45–SWPPP GEN. PERMIT–CONTRACTOR CERTIFICATION R-10-27-16

SP108-000100-01 PROG. SCHED. FOR CAT. I PROJECTS 3-21-22

SP109-000110-00 OPTIONAL ADJUSTMENT FOR FUEL R-7-12-16

SP109-000130-01 ELECTRONIC OR PRINTED WEIGH TICKETS 3-10-25

SP801-000100-01 LANE CLOSE COORD (LCC)/LANE CLOSE IMPLEMENT (LCI) 9-20-17

SQ107-001510-01 SEC 107.15 — USE OF SWAM BUSINESSES 6-7-21

SQ107-001620-00 PREVAILING WAGE RATES 5-11-2021

SS109-002020-01 SEC 109 — MEASUREMENT AND PAYMENT 5-1-23

SS211-002020-03 SEC 211 – ASPHALT CONCRETE 3-18-24

SS220-002020-01 SEC 220 – CONCRETE CURING MATERIALS 8-28-20

SS223-002020-02 SEC 223 – STEEL REINFORCEMENT 4-4-23

SS234-002020-01 SEC 234 – GLASS BEADS AND RETROREFLECTIVE OPTICS 5-6-22

SS235-002020-01 SEC 235 – RETROREFLECTORS 5-6-22

SS236-002020-01 SEC 236 – WOOD PRODUCTS 5-14-21

SS246-002020-02 SEC 246 – PAVEMENT MARKING 5-6-22

SS248-002020-02 SEC 248 – STONE MATRIX ASPHALT CONCRETE 3-18-24

SS305-002020-02 SEC 305 – SUBGRADE AND SHOULDERS 12-20-23

SS308-002020-01 SEC 308 - SUBBASE COURSE 7-13-21

SS309-002020-01 SEC 309 - AGGREGATE BASE COURSE 7-13-21

SS315-002020-05 SEC 315 – ASPHALT CONCRETE PLACEMENT 5-27-25

SS317-002020-01 SEC 317— STONE MATRIX ASPHALT CONCRETE PLACEMENT 6-21-24

SS318-002020-01 SEC 318 — PAVEMENT INTERLAYERS 8-2-23

SS319-002020-02 SEC 319 – THIN HOT MIX ASPHALT CONCRETE OVERLAY 3-18-24

SS321-002020-02 SEC 321 – TRENCH WIDENING 5-4-23

SS407-002020-02 SEC 407 – STEEL & METAL STRUCT 11-01-22

SS411-002020-01 SEC 411 – PROT. COAT. OF METAL 11-01-22

SS512-002020-03 SEC 512 – MAINTAINING TRAFFIC 7-1-22

SS704-002020-02 SEC 704 – PAVEMENT MARKINGS AND MARKERS 5-6-22

PIPE REHABILITATION 11-7-16 13

TABLE OF CONTENTS FOR PROVISIONS

cn100-000026-09 December 11, 2025 (SPCN)

GENERAL PROJECT REQUIREMENTS, SUPPLEMENTAL SPECIFICATIONS (SSs), SPECIAL PROVISIONS (SPs) AND SPECIAL PROVISION COPIED NOTES (SPCNs)

This project shall be constructed according to: the Plans; the Virginia Department of Transportation Road and Bridge Specifications, dated 2020 and the Supplement thereto, dated 2022; the Virginia Department of Transportation Road and Bridge Standards, dated 2016, with revisions issued online as of the advertisement date for this project incorporated; the Virginia Work Area Protection Manual, version 11.0;

the Virginia MUTCD version 11.0; and the Supplemental Specifications, Special Provisions and Special Provision Copied Notes in this Contract. The status in the Contract of each of these documents will be according to Section 105.12 of the Specifications.

Special Provision Copied Notes in this Contract are designated with “(SPCN)” after the date.

The information at the top and left of each Special Provision Copied Note in this Contract is file reference information for Department use only. The information in the upper left corner above the title of each Supplemental Specification and Special Provision in this Contract is file reference information for Department use only.

cn103-000120-01 June 17, 2025 (SPCN)

SECTION 103.02—AWARD OF CONTRACT of the Specifications is replaced in its entirety with the following:

103.02 – Award of Contract

The Board, or the Commissioner as authorized under § 33.2-209 of the Code of Virginia, will award the Contract to the lowest responsive and responsible bidder without discrimination on the grounds of race, color, gender, national origin, status as a military family, or other basis prohibited by law, subject to the provisions, if applicable, in § 2.2-4324 of the Code of Virginia.

The award date will not be later than midnight on the 60th day after the opening of bids. If the Board, or the Commissioner as authorized by law, has not awarded the Contract within this period due to any circumstances not attributable to the bidder, the bidder may withdraw his bid without penalty or prejudice unless the time limit is extended by mutual consent.

After approval for the award of contracts, the Department will provide written notice of award to the successful bidder and will post the Ballots on the Department’s bidding webpage. The Ballot serves as public Notice of Award for a contract. The date of the Notice of Award is the “Approved” date appearing at the top of the Ballot that lists the Contract.

cn105-000140-00 December 20, 2024 (SPCN)

SECTION 105.14—MAINTENANCE DURING CONSTRUCTION of the Specifications is amended by the following:

Section 105.14(a)3 – Flagging Traffic is replaced with the following:

3. Flagging Traffic: Flaggers shall be able to communicate to the traveling public in English while performing the job duty as a flagger at the flagger station.

All flaggers shall possess a valid, current flagger certification card, be it a physical or electronic card, at all times while performing flagging duties.

Flaggers shall be certified by the VDOT Basic or Intermediate Work Zone Traffic Control Training course or by the ATSSA’s classroom Flagger Certification Program.

The following constitutes a valid flagger certification card:

Cards issued by VDOT following completion of the Basic Work Zone course;

Cards issued by VDOT following completion of the Intermediate Work Zone course;

Cards issued by ATSSA following completion of a Flagger course;

Cards issued by VDOT following completion of the Flagger-only course, provided the cards were issued on or before December 31, 2024, and have not yet reached the expiration date (two years after date of issuance).

Flaggers who fail to possess a valid, current, flagger certification card, or refuse to allow inspection of same upon request, shall be removed from the flagging site, and operations requiring flagging shall be suspended by the Engineer. Suspended operations requiring flagging may resume once a certified flagger arrives on-site to perform flagging duties in accordance with applicable requirements. Flaggers improperly performing duties may be subject to flagger certification revocation at the sole discretion of the Engineer.

cn105-000150-00 January 30, 2026 (SPCN)

SECURITY REQUIREMENTS FOR PORTABLE CHANGEABLE MESSAGE SIGNS — The Contractor shall secure portable changeable message sign (PCMS) control cabinets with a grade 3 or stronger standard lock at all times unless maintenance is actively being conducted on the sign.

A password shall be required to change the PCMS message. The Contractor shall change the manufacturer's default password for ALL electronic signs. Electronic signs that support the use of complex passwords shall include at least 14 characters consisting of the following criteria:

At least one special character At least one alphabetical character At least one numerical character A combination of upper-case and lower-case letters

Electronic signs that do not support the use of complex passwords shall be changed using the maximum number of characters and character types permitted by the manufacturer.

Password credentials are prohibited from being stored, displayed, or written on or within the sign. Any QR codes affixed to the sign shall be removed.

For all PCMS with remote or wireless accessibility, the Engineer will authorize remote access prior to this functionality being enabled. Prior to authorization, the Contractor shall update the PCMS to the most recent compatible software and firmware version available from the manufacturer. Following authorization and prior to use, the Contractor shall establish a remote connection to verify that access to the PCMS is password protected.

Electronic signs shall only post approved and documented messages. The Contractor shall log all messages posted with date and times for each public message.

The Contractor has the option for their signs to be connected to the Department’s Operations Technology (OT) network for management by Traffic Operations Center (TOC) staff. By using this method, messages are transmitted and posted by the TOC control room staff with all records and logging managed within the VDOT Advanced Traffic Management System (ATMS). Electronic message signs connected to the OT network shall follow the security requirements described below:

1. All electronic signs connected to the network shall be secured with a digital lock installed on the sign control cabinet.

2. Connected signs shall only be remotely accessible through secure communications that originated from the Department’s OT network.

3. Connected signs shall only be posted with messages from the Department’s ATMS systems or designated backup systems.

4. Community strings (both public and private strings) shall be changed from default settings.

5. All vendor cloud connections shall be removed from the connected sign. TOC system administration staff will configure VPN connections exclusively to the Department’s OT network.

6. All connected electronic signs shall adhere to the Cabinet Security Standards found in the

Department’s OT Cybersecurity Program Manual.

cn105-000610-00 July 12, 2016 (SPCN)

SECTION 105.06—SUBCONTRACTING of the Specifications is amended to replace the first paragraph with the following:

No portion of the Contract shall be subcontracted or otherwise disposed of without the written consent of the Engineer, except for work that is $25,000 or less per subcontractor, where the cumulative total of the sublets not requiring the Engineer’s written consent will not exceed 10 percent of the original contract value. This will not, however, waive the requirements for prequalification, and will be considered part of the percentage the Contractor is allowed to subcontract. The Contractor shall notify the Engineer of the name of the firm to whom the work will be subcontracted, and the amount and items of work involved. Such notification shall be made and verbal approval given by the Engineer prior to the subcontractor beginning work.

cn245-000100-01 January 10, 2024 (SPCN)

SECTION 245.03—TESTING AND DOCUMENTATION of the Specifications is amended by the following:

Section 245.03(e) – Prefabricated Geocomposite Pavement Underdrain is replaced by the following:

Prefabricated Geocomposite Pavement Underdrain: Prefabricated geocomposite pavement underdrain shall consist of a polymeric drainage core allowing water inflow from both sides, encased in a nonwoven filter fabric envelope having sufficient flexibility to withstand bending and handling without damage.

Prefabricated geocomposite pavement underdrain shall conform to the following:

1. Core: The drainage core shall be made from an inert, polymeric material resistant to commonly encountered chemicals and substances in the pavement environment and shall have a thickness of not less than 3/4 inch. Outer surfaces shall be smooth to prevent excessive wear of bonded filter fabric.

Physical Properties Test Method Requirements

Compressive strength ASTM D1621, D2412, and D6364

Min. 40 psi at 20% max.

deflection immediately after 24 hrs of specimen conditioning at 0 deg F and at 125 deg F

Water flow rate (after 100 hr at 10 psi normal confining pressure and gradient of no more than 0.1)

ASTM D4716 Min. 15 gal/min/ft width for 12-in specimen length

2. Filter Fabric: Geotextile shall be bonded to and tightly stretched over both sides of the core. Geotextile shall not sag or block the flow channels, shall have a life equivalent to that of the core material, and shall conform to the requirements of Section 245.03(c) of the Specifications.

Section 245.03(f) – Geocomposite Wall Drains is replaced by the following:

Geocomposite Wall Drains: Prefabricated geocomposite wall drain shall consist of a polymeric drainage core with a nonwoven filter fabric (single sided or double sided) having sufficient flexibility to withstand bending and handling without damage. Geocomposite wall drains shall conform to the following:

1. Core: The drainage core shall be made from an inert, polymeric material resistant to commonly encountered chemicals and substances in the roadway. Outer surfaces shall be smooth to prevent excessive wear of bonded filter fabric.

Physical Property Test Method Requirements

Compressive strength ASTM D1621, D2412, and D6364

Min. 40 psi at 20% max.

deflection immediately after 24 hrs of specimen conditioning at 0 degree F and at 125 degree F

Water flow rate (after 100 hr at 10 psi normal confining pressure and gradient of no more than 1.0)

ASTM D4716 Min. 15 gal/min/ft width (for 12-in specimen length)

2. Filter Fabric: Geotextile shall be bonded to and tightly stretched over the core. Geotextile shall not sag or block the flow channels, shall have a life equivalent to that of the core material, and shall conform to the requirements of Section 245.03(c) of the Specifications.

Section 245.03(g) – Geomembrane Moisture Barrier is replaced by the following:

Geomembrane Moisture Barrier: Geomembrane moisture barrier shall be resistant to biological attack.

Geomembrane shall be constructed of PVC and shall conform to the requirements of ASTM D7176 for PVC 30 or higher grades. In addition, geomembrane shall comply with the requirements of ASTM D7408 for bond seam strength and peel strength.

CQ107-000130-00 July 3, 2019 (SPCN)

DRUG-FREE WORKPLACE – The Contractor shall:

Provide a Drug-Free Workplace for the Contractor’s employees.

Post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in the Contractor’s workplace and specifying the actions that will be taken against employees for violations of such prohibition.

State in all solicitations or advertisements for employees placed by or on behalf of the Contractor that the Contractor maintains a Drug-Free Workplace.

Include the provisions of the foregoing clauses in every Subcontract or purchase order of over $10,000, so that the provisions will be binding upon each Subcontractor or vendor.

For the purposes of this provision, “Drug-Free Workplace” means a site for the performance of work done in connection with the Contract. The Contractors employees, and those of his Subcontractors, shall be prohibited from engaging in the unlawful manufacture, sale, distribution, dispensation, possession, or use of any controlled substance or marijuana during the performance of the Work.

CQ107-000150-00 May 11, 2022 (SPCN)

EQUAL EMPLOYMENT OPPORTUNITY

Section 107.14(a)1 – Required by §2.2-4201 and §2.2-4311 of the Code of Virginia is replaced with the following:

1. Required by §2.2-4201 and §2.2-4311 of the Code of Virginia: During the performance of this Contract, the Contractor agrees as follows:

a. The Contractor shall not discriminate against any employee or applicant for employment because of race, religion, color, sex, or national origin, age, disability, or other basis prohibited by state law relating to discrimination in employment, except where religion, sex, or national origin is a bona fide occupational qualification reasonably necessary to the normal operation of the Contractor. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this nondiscrimination clause, including the names of all contracting agencies with which the Contractor has contracts of over $10,000.

b. The Contractor shall, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that such contractor is an equal opportunity employer. However, notices, advertisements and solicitations placed in accordance with federal law, rule or regulation shall be deemed sufficient for the purpose of meeting the requirements of this chapter.

c. If the Contractor employs more than five employees, the Contractor shall (i) provide annual training on the Contractor's sexual harassment policy to all supervisors and employees providing services in the Commonwealth, except such supervisors or employees that are required to complete sexual harassment training provided by the Department of Human Resource Management, and (ii) post the Contractor's sexual harassment policy in (a) a conspicuous public place in each building located in the Commonwealth that the Contractor owns or leases for business purposes and (b) the Contractor's employee handbook.

The Contractor shall include the provisions of subdivisions a, b, and c in every subcontract or purchase order of over $10,000, so that such provisions shall be binding upon each subcontractor or vendor.

Nothing contained in this chapter shall be deemed to empower any agency to require any contractor to grant preferential treatment to, or discriminate against, any individual or any group because of race, color, religion, sex, or national origin on account of an imbalance that may exist with respect to the total number or percentage of persons of any race, color, religion, sex, or national origin employed by such contractor in comparison with the total number or percentage of persons of such race, color, religion, sex, or national origin in any community or in the Commonwealth.

CQ522-000100-03 January 17, 2018 (SPCN)

PROTECTION OF BAT SPECIES — If bats are observed roosting on a structure, the Contractor shall immediately notify the Engineer and suspend work in the immediate vicinity of the bats until authorized to continue.

SP102-000120-00 January 10, 2017

SPECIAL PROVISION FOR

NON-DISCRIMINATION IN EMPLOYMENT AND CONTRACTING PRACTICES

I. Description

This Special Provision implements Executive Order 61, ensuring equal opportunity and access for all Virginians in state contracting and public services.

II. Non-Discrimination

The Contractor shall maintain a non-discrimination policy, which prohibits discrimination by the Contractor on the basis of race, sex, color, national origin, religion, sexual orientation, gender identity, age, political affiliation, disability, or veteran status. This policy shall be followed in all employment practices, subcontracting practices, and delivery of goods or services. The Contractor shall also include this requirement in all subcontracts valued over $10,000.

III. Measurement and Payment

Conformance with this Special Provision will not be measured for individual payment, and will be considered incidental to the Work.

SP107-000110-00 October 27, 2016 C-45

STORMWATER POLLUTION PREVENTION PLAN (SWPPP) AND THE VIRGINIA POLLUTANT

DISCHARGE ELIMINATION SYSTEM (VPDES) GENERAL PERMIT FOR THE DISCHARGE OF

STORMWATER FROM CONSTRUCTION ACTIVITIES

CONTRACTOR CERTIFICATION STATEMENT

Order No.: Project Number:

Route: Contract ID. #:

I certify under penalty of law that I understand the terms and conditions of the project contract, plans, permits, specifications and standards related to the erosion and sediment control, stormwater management and stormwater pollution prevention plan requirements for the affected activities associated with this project, and the requirements of the VPDES General Permit for the Discharge of Stormwater from Construction Activities (the VPDES Construction Permit) , if applicable to this project, issued by the Virginia Department of Environmental Quality. The VPDES Construction Permit authorizes the storm water discharges associated with the construction activities from the project site identified and described in the bid documents and subsequent contract including any onsite or off-site support facility areas located within VDOT right of way or easement and required for the complete fulfillment of the work therein.

Signature:

Name:

Title:

Contracting Firm:

Address:

Phone Number:

* Project Address/Location:

Certified on this date:

* Include any off-site support facility areas located within VDOT right of way or easement.

(Note: This form must be returned with performance and payment bonds)

B32

0346-070-736,D648

C0000127208D48

SP108-000100-01 March 21, 2022

PROGRESS SCHEDULES FOR CATEGORY I PROJECTS

Section 103.06(e) Progress Schedule of the Specifications is deleted and replaced by this provision.

Section 108.03 Progress Schedule of the Specifications is deleted and replaced by this provision.

I. General Requirements

The Contractor shall develop and maintain a Progress Schedule for the entire duration of the Project, which shall be used by all involved parties to plan and execute all work required to complete the Project.

The Progress Schedule will be used by the Department to monitor the project, assess progress, and evaluate the effects of time-related issues on the project. Unless specifically stated otherwise, ‘days’ shall be understood as calendar days.

At the Pre-Construction Conference, in accordance with Section 105.02 or as mutually agreed upon by the Engineer and the Contractor, the Contractor shall attend a Scheduling Conference with the Engineer to discuss the Contractor’s overall plan to accomplish the Work. The Contractor shall also discuss its detail work plan for the initial sixty (60) days; as well as project specific requirements and other key issues that are expected to impact the Progress Schedule or are necessary for the preparation, maintenance, and submittal of the Progress Schedule.

II. Progress Schedule Submissions

Unless otherwise directed in writing by the Engineer, the Contractor shall prepare, maintain, and submit a Progress Schedule in accordance with the following requirements:

1. Baseline Progress Schedule

Within fifteen (15) days of the Contract execution date or within seven (7) days prior to beginning work, whichever occurs first, the Contractor shall submit to the Engineer for review and acceptance, a Baseline Progress Schedule representing the Contractor’s original complete detailed plan to accomplish the entire scope of the Project according to the Contract. Upon acceptance by the Engineer, the Baseline Progress Schedule shall become the Schedule of Record (SOR). The Baseline Progress Schedule submission shall consist of:

A. Baseline Schedule – A logic driven Baseline Schedule depicting all detailed activities required to complete the entire scope of the Project, including as applicable, work to be performed by subcontractors, the Department, and other involved parties. The Baseline Schedule shall be prepared and submitted according to the following:

(1) Software: The Baseline Schedule shall be prepared using any scheduling software of the

Contractor’s choosing that is capable of meeting the detail requirements as specified herein. However, an electronic backup copy of the Baseline Schedule shall be submitted in any of the following acceptable file formats Primavera P6 (XER), Microsoft Project (MPP, XML), or Microsoft Excel (XLS) based on the software.

(2) Project ID and Name: The Project ID and Name for each submission shall be unique and defined as follows:

(a) For Project Schedules prepared in the Primavera P6 software, the Project ID shall be defined using the Contract ID as a prefix followed by a short ID indicating the specific version of the schedule (PS01, BS, BSR1, etc.). For example, Baseline Schedule (C000XXXXXXX_BS, C000XXXXXXX_BSR1, etc.). And the Project Name shall reflect the Project Description as shown in the Contract, appended to indicate the specific version of the schedule (e.g., Route 10 Over I-95 Bridge Replacement Baseline Schedule).

(b) For Project Schedules prepared in the Microsoft Project software, the Project Name (Title) shall be defined using the Contract ID as a prefix followed by a short ID indicating the specific version of the schedule (PS01, BS, BSR1, etc.). For example, Baseline Schedule (C000XXXXXXX_BS, C000XXXXXXX_BSR1, etc.).

(3) Work Breakdown Structure (WBS): The Baseline Schedule shall be organized using a logical Project Work Breakdown Structure (WBS). The Work shall be broken down to an appropriate level of WBS nodes and sub-nodes to allow for a hierarchical grouping and summarization of related activities required to complete each phase, feature, deliverable, or work package, as appropriate. Each WBS element shall be defined using a short alpha-numeric WBS Code and a WBS Name describing the WBS element. At a minimum, the WBS shall include as applicable:

(a) Level 1: “Milestones” node for all Contract and other key milestones; “Preliminary” node for all pre-construction activities; and “Construction” node for all construction activities.

(b) Level 2: Under the “Preliminary” node, Level 2 “Submittals”, “VDOT Review”, “Materials” sub-nodes for all initial activities such as submittals, VDOT reviews, long lead materials, etc. Under the “Construction” node, Level 2 “General/Start-up”, “Phase” or “Feature of Work”, and “Close-out” sub-nodes, as applicable.

(c) Level 3: Under the “Phase” or “Feature of Work” node, Level 3 sub-nodes for “Sub-features” or “Location” for all associated construction activities, as applicable.

(4) Level of Details: The Work shall be broken down into discrete activities to an appropriate level of detail to allow for identification of work by the responsible party; as well as the type, amount, and specific location of work the activity represents.

(5) Activity Definition: Activities shall be discrete and shall be defined as follows:

(a) Each activity shall be defined using a unique Activity ID which shall remain unchanged throughout the duration of the Project. If an activity is deleted in a subsequent submission, the corresponding Activity ID shall not be used for any other activity. If the Project Schedule is prepared and submitted using Microsoft Project, then a “Unique Activity ID” Custom Field shall be defined using the “Text1” data field with formula set to equal “Unique ID”.

(b) Each activity shall be defined using an Activity Name to indicate the type of work, phase (or stage), and specific location in which the work occurs, as applicable (e.g., Drive Steel Piles - Phase 1 - Abut A). For work to be performed by the Department or other contractors, and third parties, the Activity Name shall include “VDOT” or the name of the corresponding responsible party.

(c) Activity durations shall be defined in whole days based on the assigned calendar. For activities such as “Concrete Cure Time”, that are not restricted by a standard working calendar, activity durations shall be expressed in terms of calendar days. Activity durations shall be limited to twenty (20) work days, unless otherwise accepted by the Engineer. Longer durations may be allowed as approved by the Engineer for certain administrative, level of effort, or procurement activities that are typically performed over longer periods of time.

(6) Calendars: Each activity shall be assigned a project-level calendar to establish the planned work days per week and any non-work days for holidays, weather days, or other restrictions, as applicable. Regardless of the actual or planned work hours/day, all calendars shall be based on a standard 8 work hours/day, with the same daily start and finish times. If the Project Schedule is prepared and submitted using Microsoft Project, then a “Calendar” Custom Field shall be defined using the “Text2” field with formula set to equal “Task Calendar”. Once the Baseline Schedule is accepted, any changes to calendars shall be identified and explained in the accompanying Schedule Narrative.

(7) Network Logic: Logic relationships shall be assigned to each activity to establish the sequence in which the Contractor plans to accomplish the Work and as follows:

(a) Activity relationship types shall be limited to finish-to-start (FS), start-to-start (SS), and finish-to-finish (FF).

(b) All activities, except the first activity shall be assigned at least one predecessor relationship and all activities, except the last activity shall be assigned at least one successor relationship.

(c) If an activity is assigned as a predecessor with a start-to-start (SS) relationship, then the activity must also be assigned as a predecessor to another related activity with a finish-to-start (FS) or finish-to-finish (FF) relationship, as applicable.

(d) The Contractor shall avoid the use of redundant logic relationships when possible.

(e) The use of lag shall be prohibited unless approved by the Engineer. The Contractor shall remove any lag and replace with an activity upon the request of the Engineer.

When lags are used, the Contractor shall provide an explanation for use of the lags in the Schedule Narrative.

(8) Constraints: Use of Constraints shall be limited to milestones specified in the Contract, unless approved by the Engineer. Constraints shall be applied as follows:

(a) For Contracts that include a specified milestone that restricts the start date of an activity, the activity shall be constrained with a “Start No Later Than” or “Start No Earlier Than” constraint, as applicable, with the date specified in the Contract.

(b) For Contracts that include a specified milestone that establishes a completion date deadline such as Interim Completion or Substantial Completion, the Contract milestone activity shall be constrained with a “Finish On or Before” (Finish No Later Than) constraint, with the date specified in the Contract.

(c) Constraints such as “Start On” (Must Start On) or “Finish On” (Must Finish On) that delays the start or finish date of an activity to the specified date as allowed by network logic, or “Mandatory Start” or “Mandatory Finish” that violate network logic are prohibited.

(9) Progress As-built Information: The Baseline Schedule shall reflect the current status of the Project and all known information at the time of submission. The Baseline Schedule shall include any progress as-built information showing actual dates for all completed and on-going activities, as of the Data Date, as applicable. The Baseline Schedule shall be calculated using a Data Date as follows:

a) If the Baseline Schedule includes progress as-built information, then the Data Date shall be within three (3) days of the date of submission.

b) If the Baseline Schedule does not include progress as-built information, then the Data Date shall be the Contract execution date or the planned start date of the first activity, whichever is earlier.

B. Baseline Schedule Narrative – A Baseline Schedule Narrative describing the Contractor’s overall plan to accomplish the Work. The Baseline Schedule Narrative shall be the basis for the Baseline Schedule and shall provide the following supporting information, as applicable:

1. Milestones: Current status of the Project milestones including, as applicable Contract milestones and other key events such as major traffic switches.

2. Work By Others: Work to be performed by the Department and other involved parties (e.g., utilities), including activities requiring coordination; and a description of when the work must be performed to avoid impacts to the Work.

3. Overall Sequence of Work: Explanation of the proposed overall sequence of Work, including where the Work will begin and how the Work and crews will flow through the Project.

4. Project Critical Path: Description of the project critical path indicating the series of operations that are expected to drive the completion date of the project. A listing of the Project Schedule critical path activities will not be accepted as a substitute.

5. Scheduling Assumptions: Scheduling assumptions including, the general procedures and anticipated daily production rates for major operations that are expected to drive the schedule.

6. Lags: Identification of all logic relationships with Lag and explanation for the use of each

Lag.

7. Constraints: Identification of all schedule Constraints used in the Baseline Schedule and an explanation for the use of each Constraint.

8. Calendars: Description of the project calendar(s) used in the Baseline Schedule, identifying the Calendar and the proposed number of work days per week, number of shifts per day, and number of hours per day. Also, the anticipated number of non-working days per month shall be identified for each calendar with considerations, as applicable, for holidays, normal adverse weather conditions; as well as seasonal or other known or specified restrictions (i.e. traffic, local events, environmental, permits, utility, etc.).

9. Resource Plan: The Contractor’s resource plan indicating the number and type of crews, crew make-up, and major equipment needed to accomplish the Work as planned. The resource plan shall also explain how the Contractor plans on meeting the resource requirements as reflected on the Baseline Schedule.

10. DBE Participation: Log of the applicable DBE participation activities in the schedule and the DBE firms performing the work for which the Contractor intends to claim credit for attaining the DBE goal required in the Contract. The list shall indicate the start/finish dates and durations of the DBE participation activities.

11. Issues and Concerns: Any known or foreseeable issues or concerns that are currently affecting or anticipated to affect the schedule. Also, describe how the issues will affect the schedule and any actions taken or needed to avoid or mitigate the impact.

C. Baseline Progress Earnings Schedule – A Baseline Progress Earnings Schedule showing the anticipated monthly earnings for the entire Project. A Baseline Progress Earnings Schedule is not required for projects with overall contract duration of ninety (90) days or less. The Baseline Progress Earnings Schedule submission shall be prepared using the VDOT Form C-13C as follows:

1. The Breakdown of Contract Items form shall be completed to show the bid items and costs associated with each Major Work Category.

2. The C-13C (Baseline) form shall be completed to show all required information and the monthly anticipated earnings for each Major Work Category.

3. The C-13C (Update) form shall be completed to show the current Projected Completion

Date, Current Estimate Date, and actual monthly earnings, and anticipated earnings for each Major Work Category as of the Current Estimate Date.

4. The Controls Chart Data form shall be completed to show the Actual Monthly Earnings for each estimate date, as of the Current Estimate Date.

2. Update Progress Schedule

After the Baseline Progress Schedule is accepted, on a monthly basis thereafter, and within seven

(7) days after the estimate date, the Contractor shall submit an Update Progress Schedule submission to the Engineer for review and acceptance. The Update Progress Schedule submission shall represent the current status of the Project and the Contractor’s current plan to complete the remaining Work. The Update Progress Schedule submission shall consist of:

A. Update Schedule – An Update Schedule, which shall be based on a copy of the most recent accepted Project Schedule and shall be prepared according to the following:

(1) The Project ID for each submission shall be updated to indicate the specific Update Schedule version (e.g., C000XXXXXXX_U01, C000XXXXXXX_U01R1, C000XXXXXXX_U02). And the Project Name shall be updated to indicate the specific version of the schedule.

(2) All activities completed prior to the Data Date shall be updated to show actual start and actual finish dates. And all on-going activities shall be updated to show actual start dates and remaining duration to indicate the amount of time required to complete the remaining work as of the Data Date. Actual dates on or after the Data Date are prohibited.

(3)…