Kessler Building Roof Replacement Project Manual

This is a Project Manual and Invitation to Bid (IFB #27-003M) prepared by Gardner Engineering, Inc. for Carroll County Public Schools (CCPS) for roof replacement services at The Kessler Building located at 191 Shaeffer Avenue in Westminster, Maryland. The project encompasses complete roof replacement including removal of the existing gravel-surfaced built-up roof system over a poured gypsum deck and installation of a new 2-ply modified bitumen roof system (Siplast Paradiene 20/30 FR) with continuous R-30 polyisocyanurate insulation, tapered insulation, DensDeck Prime coverboard, and associated flashings and metal work. Sealed bids are due electronically via Public Purchase no later than 11:00 a.m. on October 22, 2026. A pre-bid conference will be held on October 6, 2026, at 10:00 a.m. at the project site, with contractor representatives assembling in the parking lot. All questions must be submitted online via Public Purchase by October 13, 2026, at 4:00 p.m. Local Time. Work is anticipated to begin in Fall 2026, with allowable work hours Monday through Friday from 7:00 a.m. to 5:00 p.m., with noise-generating activities commencing no earlier than 8:00 a.m.

The bid basis is a lump sum price for all work plus unit pricing for variable quantities, with a base bid allowance of $50,000 for additional miscellaneous work. Bidders must provide unit rates for roof deck replacement (square foot), modified bitumen roof installation (square foot), roof drain bowl and strainer replacement (each), new wood nailers (2x6 and 2x8), and coverboard installation (square foot). The contractor must field-measure actual quantities to be replaced and assume 10 percent of the roof deck will require replacement. The contractor is responsible for obtaining all permits and must be certified by Siplast with a minimum of five years' experience installing similar roofing materials. CCPS reserves the right to reject any and all bids and to negotiate project price and time with the successful bidder. The contractor shall provide a 2-year warranty for materials and workmanship for the entire project, and the roofing membrane manufacturer will provide a 20-year NDL (Non-Deductible Labor) warranty. The contractor must comply with all applicable federal, state, and local codes, including OSHA requirements, fire safety standards, and fall protection standards, and assume full responsibility for site safety, water and dust protection, and any damage resulting from construction operations.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

The Kessler Building Roof Replacement

IFB #27-003M

September 2026

PROJECT MANUAL

FOR ROOF REPLACEMENT

at

The Kessler Building 191 Shaeffer Avenue Westminster, Maryland

Prepared For:

Carroll County Public Schools

125 North Court Street Westminster, MD 21157

Prepared By:

Gardner Engineering, Inc.

8335 Guilford Road, Suite I Columbia, Maryland 21046

Gardner Engineering Project: 5301

September 22, 2026

IFB #27-003M

DISCLOSURE STATEMENT

ALL INFORMATION CONTAINED IN OR DISCLOSED BY THIS DOCUMENT IS CONSIDERED

CONFIDENTIAL AND PROPRIETARY INFORMATION BY GARDNER ENGINEERING, INC. IT SHALL

NOT BE REPRODUCED IN WHOLE OR IN PART WITHOUT EXPRESS WRITTEN PERMISSION OF

GARDNER ENGINEERING, INC.

GARDNER ENGINEERING SHALL HAVE NO LIABILITY FOR THE USE OF THIS DESIGN

DOCUMENT IF IT IS USED FOR ANY PROJECT OTHER THAN THE INTENDED PROJECT.

IFB #27-003M

TABLE OF CONTENTS

BIDDING DOCUMENTS

1.0 INVITATION TO BID ..................................................................................... Page 5

2.0 INSTRUCTION TO BIDDERS ......................................................................... Page 5

3.0 BID FORM ................................................................................................ Page 7

4.0 SUBCONTRACTOR AND MATERIAL SUPPLIER LISTING .............................. Page 10

5.0 SUBSTITUTION LIST ................................................................................ Page 11

SPECIFICATIONS FOR ROOF REPLACEMENT

6.0 SUMMARY OF WORK .............................................................................. Page 13

7.0 PROJECT DIRECTORY ............................................................................ Page 14

8.0 GENERAL ADMINISTRATIVE PROVISIONS .................................................. Page 14

9.0 INSURANCE REQUIREMENTS ............................................................... Page 18

10.0 REFERENCES .................................................................................... Page 18

11.0 PLANS AND SPECIFICATIONS ............................................................... Page 18

12.0 SCHEDULES ....................................................................................... Page 19

13.0 QUALITY ASSURANCE ........................................................................ Page 20

14.0 CODE COMPLIANCE ............................................................................. Page 20

15.0 SUBMITTALS ...................................................................................... Page 20

16.0 WARRANTY ........................................................................................ Page 22

17.0 EXISTING CONDITIONS ....................................................................... Page 22

18.0 FIRE SAFETY ....................................................................................... Page 23

19.0 SAFETY REQUIREMENTS ................................................................... Page 23

20.0 FALL PROTECTION ............................................................................. Page 24

21.0 BUILDING PROTECTION.......................................................................Page 24

22.0 USE OF BUILDING UTILITIES ................................................................... Page 25

23.0 TRANSPORTATION AND HANDLING ........................................................ Page 25

24.0 MATERIAL REQUIREMENTS ............................................................... Page 26

IFB #27-003M

25.0 REHABILITATION PROCEDURES ......................................................... Page 29

26.0 FINAL CLEAN UP ................................................................................... Page 37

DRAWINGS

Drawing 1 – Site Plan and Details Drawings Drawing 2 – Detail Drawings

IFB #27-003M

1.0 INVITATION TO BID

Sealed Bids for furnishing all labor, materials and equipment services required for roof replacement at The Kessler Building in Westminster, Maryland will be received electronically via Public Purchase no later than 11:00 a.m. on October 22, 2026. Bids shall be completed in accordance with the Instructions to Bidders.

2.0 INSTRUCTION TO BIDDERS

The term Engineer or Architect within the Contract Documents refers to Gardner Engineering, Inc. unless specifically stated otherwise.

The term Owner within the Contract Documents refers to Carroll County Public Schools.

A pre-bid conference shall be held at the project site, at 10 a.m. on October 6, 2026.

Contractor representatives should assemble in the parking lot at 191 Shaeffer Avenue, Westminster, MD. It is highly recommended that all interested bidders attend the pre-bid meeting/site visit.

Questions and inquiries regarding the project must be submitted online via Public Purchase.

All questions must be received no later than October 13, 2026, by 4:00 P.M. Local Time.

The work is anticipated to begin in the Fall of 2026.

Addenda will be issued to Prime Contractors only. Prime Contractors shall be responsible for distributing addenda information to Subcontractors and materials suppliers. Extra costs will not be allowed for failure of Contractors and Subcontractors to incorporate addenda information.

The basis of Bid shall be a lump sum price for all Work. The Bid is to be completed in accordance with the Bid instructions, including allowances, as shown in the Bid Form. Unit prices, as indicated on the Bid Form, are also required for quantities that are variable.

The Owner reserves the right to reject any and all Bids and to waive irregularities and informalities in the Bids. The Owner reserves the right to negotiate project price and time with the successful Bidder.

The Bidder is required to submit the following information with the Bid. Joint Bids will not be accepted. The Contractor is to provide a 2-year warranty for materials and workmanship for the entire project.

On the Bid Form provided:

a. Provide full business address and telephone number.

b. Provide lump sum price for all work identified in these documents.

IFB #27-003M

c. Provide unit prices for the items listed on the Bid Form.

d. Upload all required forms via Public Purchase

The bids must be submitted via Public Purchase no later than October 22, 2026, 11:00AM Local Time. Submittals received through other delivery methods or after the designated deadline will be rejected.

It is the responsibility of the Bidder to examine the contract documents, visit the site, consider federal, state and local laws and regulations and notify CCPS of all conflicts, errors or discrepancies in the Contract Documents. Please note the Contractor shall be responsible for the field measurements of actual quantities to be replaced. Base bid price shall include cost of all work associated with the items outlined in this Project Manual. Quantities not provided but necessary for submittal of Base Bid shall be field measured by the Contractor.

As an attachment to the Bid Form, provide:

A. Evidence of qualification to perform work in The State of Maryland.

B. A list of subcontractors to be used and their scope of work (Form provided).

C. A listing of any substitutions proposed (Form provided). All proposed substitutions must be submitted with the bid on the form provided, so that the bid pricing can be adjusted accordingly for the proposed substitution, if accepted.

IFB #27-003M

3.0 BID FORM

Bidder will complete the work described in these documents for the prices indicated below.

PART I

Base Bid shall include an allowance of $50,000 for additional miscellaneous work.

Additional work performed will be deducted from this allowance using unit rates below. Any allowance money remaining at the end of the project shall be credited to Owner in last pay request.

BASE BID

All work as described in the Specifications for Roof Replacement at The Kessler Building; Base Bid lump sum (including allowances):

(use words)

(use figures)

The above price is based on S.F. of poured gypsum roof deck replacement.

The above price is based on S.F. of flat roof replacement, including new tapered insulation.

PART II

Unit costs for labor and materials to be added to, or subtracted from the Scope of Work, for quantities that are different than shown in the project plans and specifications. Base Bid quantities should be included as part of the Lump Sum cost provided above. All costs below shall include preparation work and finish work as required to provide a completed project.

A. Cost per square foot for roof deck replacement $

B. Cost per square foot for modified bitumen roof installation $

C. Cost per each roof drain bowl and strainer replacement $

D. Unit rate for new 2x6 nailers $

E. Unit rate for new 2x8 nailers $

F. Cost per S.F. for coverboard $

Contractor

IFB #27-003M

PART III

We hereby acknowledge receipt of:

Addendum , dated .

PART IV

Experience Modification Rating (EMR)

PART V

Bidder’s Proposed start date for Base Bid Work .

Bidder’s Proposed duration for Base Bid Work .

Contractor

IFB #27-003M

PART VI

Communications concerning this Bid shall be addressed to bidder at the following address:

THIS BID IS HEREBY SUBMITTED on

BY

(Corporation Name)

(Signature)

(Address)

(Corporate Seal)

Attest

(Secretary)

IFB #27-003M

4.0 SUBCONTRACTOR AND MATERIAL SUPPLIER LISTING

These subcontractors shall be licensed to perform in Maryland:

Portion of the Work: Subcontractor name and address:

Listing of Material Suppliers

USE ADDITIONAL SHEETS IF REQUIRED.

PROVIDE SIGNATURE IDENTICAL TO THAT SHOWN ON THE BID FORM

Bidder:

By:

IFB #27-003M

5.0 SUBSTITUTION LIST

The Contract Sum proposed by the undersigned on the bid form is for the Work as shown on the Drawings, described in the Specifications, and otherwise defined in the Contract Documents. However, the undersigned proposes the following substitutions for the Owner’s Representative(s) consideration. Should the Owner’s Representative(s) accept any or all of the proposed substitutions, the bidder's proposed Contract Sum will be reduced by the amount shown.

Specified product Drawing Proposed Proposed or material: number or Substitution: reduction in

Spec. Section: Contract Sum:

Manufacturers who have provided unsatisfactory past installations must provide evidence in writing that the reason for the unsatisfactory product has been corrected.

PROVIDE SIGNATURE IDENTICAL TO THAT SHOWN ON THE BID FORM

Bidder:

By:

IFB #27-003M

SPECIFICATIONS

FOR ROOF REPLACEMENT

at

The Kessler Building 191 Shaeffer Avenue Westminster, Maryland

Prepared For:

Carroll County Public Schools

125 North Court Street Westminster, MD 21157

Prepared By:

Gardner Engineering, Inc.

8335 Guilford Road, Suite I Columbia, Maryland 21046

Gardner Engineering Project: 5301

September 22, 2026

IFB #27-003M

6.0 SUMMARY OF WORK

The building is located at 191 Shaeffer Avenue in Westminster, Maryland. The building was reportedly constructed circa 1950. Carroll County Public Schools (CCPS) is currently utilizing the space as storage and offices. Multiple leaks are present throughout the roof, with the exception of the northern section, which was replaced a few years ago. The north area of the roof is not included in this project. The current roof is a gravel-surfaced built-up roof system over a poured gypsum deck. Portions of the deck have been replaced with fiber-cement panels. Due to the quantity and severity of the leaks, as well as moisture encountered in the inspection openings, it is anticipated that a large portion of the roof deck will require repair or replacement. Fastener pull tests are anticipated to be completed throughout all areas of the roof deck to confirm if the gypsum roof deck is salvageable.

The purpose of this document is to outline the scope of work for the roof replacement at The Kessler Building. It is the intention that the roof replacements be performed in Fall 2026.

The following is a summary of work:

A. The roof membrane and coverboard shall be replaced with a 2-ply modified bitumen systems meeting UL Class A Fire Resistance requirements and all current ASCE wind uplift requirements. The new roof membrane shall be a Siplast roof system, consisting of flat insulation adhered directly to the deck, tapered insulation, DensDeck Prime coverboard, Paradiene 20 base ply, and a Paradiene 30 FR cap sheet, set in cold adhesive.

The roof insulation shall be continuous R-30 insulation, with tapered insulation on top.

B. The original roof deck is 2 inches of poured gypsum and a 1-1/4 inch form board, with some areas previously replaced with fiber-cement panels (Tectum-type panels). The form boards have previously been tested by CCPS and were negative for asbestos. It is anticipated that much of the roof deck is either wet, or has been previously wet. It is anticipated that large portions of the poured gypsum roof deck will require replacement.

Some areas of previously replaced roof deck may also require replacement. Replacement shall consist of type B galvanized steel decking fastened to the bulb tees or steel joists, and polyisocyanurate insulation fastened to the steel (assume 1-3/4 inch for bidding purposes). Bidders shall assume 10% of the roof deck will require replacement.

Please note that unit rates provided on the bid form for roof deck replacement are for both Add and Deduct.

C. Minor repairs to the existing roof deck may be made using a quick-setting bagged gypsum mix.

D. A minimum of 10 adhesion tests of the flat insulation to the existing deck (poured gypsum and fiber-cement panels) shall be performed. Roofing manufacturer shall provide direction for the testing method.

E. At roof perimeter and interior curbs, install new wood nailers, as needed, as a result of the increased insulation height. Multiple plies of wood nailers will likely be required, depending on the taper plan provided by the manufacturer.

F. All areas of existing metal coping shall be replaced. Cleats shall be utilized to secure the copings.

IFB #27-003M

G. Two small abandoned curbs shall be removed and decked over.

H. Existing equipment, vents, counter flashings, etc. shall be raised so that there is a minimum of 8 inches of base flashing. All counter flashings shall be replaced.

I. Existing drain bowls and strainers shall be replaced. Contractor is responsible for connecting the new drains to the existing piping.

J. Existing scuppers at the southwest corner of the roof shall remain and shall have all metal replaced and flashed. All metal on the exterior wall for the scuppers shall be replaced.

Install new conductor heads, downspouts and splash blocks for all scuppers.

K. Replace all existing penetration pockets with new penetration pockets.

L. Install new specified insulation, cover board and two-ply modified bitumen roof membrane, and base flashings where needed. Apply the manufacturer supplied granules to all bleed-out.

7.0 PROJECT DIRECTORY

Owner: Carroll County Public Schools (CCPS) 125 North Court Street Westminster, MD 21157

Location: The Kessler Building 191 Shaeffer Avenue Westminster, MD 21157

Engineer: Gardner Engineering, Inc.

8335 Guilford Road, Suite I, Columbia, Maryland 21046 Attn: Kevin J. Gardner; email: kjgardner@gardner-engineering.com Phone: 410-480-1500 Fax: 410-480-1501

8.0 GENERAL ADMINISTRATIVE PROVISIONS

The following provisions shall apply to this project:

A. Various standards and specifications are incorporated in the technical sections of these specifications by reference. In all such instances, the reference shall mean the latest edition, including amendment or revision in effect as of the date of this specification, unless a specific issue is identified otherwise. In the event that referenced specifications or standards contain general requirements in conflict with the Contract Documents, the more stringent requirements shall govern.

B. Examine the site and verify dimensions and conditions necessary for completion of the Work. Notify The Owner and Engineer should the conditions vary from those described in this document.

mailto:kjgardner@gardner-engineering.com

IFB #27-003M

C. Existing conditions are reflected correctly to the best of the Owner's knowledge. Should conditions be encountered which are not as indicated, minor modification necessary to accommodate new Work shall be made as required at no additional expense to The Owner.

D. Perform a thorough survey of property and all affected areas of the building and grounds prior to starting the Work in order to document existing damage. Damaged items identified on this list will not be the responsibility of Contractor unless further damaged by Contractor during execution of Project. Contractor shall provide a copy of the precondition survey to the Owner and Engineer prior to the start of work.

E. Consider any damage to property not identified in the pre-construction damage survey as having resulted from execution of this Contract. Damages as a result of the Contractor’s work shall be corrected by the Contractor at no additional expense to the Owner.

F. Contractor shall ensure water and dust do not enter building at locations associated with the repairs.

G. Dust protection shall be constructed in accordance with the Contractor’s approved (by the Owner) Dust Control Plan. Contractor shall be responsible for damage to cars, building, building components or other personal property as a result of the Work or by Contractor’s personnel. Comply with regulatory requirements related to silica dust.

H. Contractor may need to temporarily support/brace/relocate various components and shall take every precaution to prevent damage from water, dust, vibration, impact, etc.

to fire alarms, pull stations, call stations, electrical equipment, sprinkler heads, emergency generators, fire pumps, lighting components, etc. during the project.

I. Where Contractor must run equipment, air hoses, electric cords, etc. through areas not contained inside work areas, Contractor shall ensure no vehicular or pedestrian hazard is created by the presence of the equipment, etc.

J. Contractor shall protect the existing building components affected by the work.

Contractor shall be responsible for damage to the existing building components as a result of the Work or by Contractor’s personnel.

K. The Contractor shall obtain and pay for any and all permits required, to perform the work, by the governing authority having jurisdiction. The Contractor shall submit copies of all permits required to the Engineer and The Owner(s) prior to the start of work.

L. The Contractor (after award of Contract) shall attend a pre-construction meeting with the Owner’s Representative and the Engineer for the purpose of finalizing the project schedule, to review repair procedures, and to coordinate work with the Owner and his Engineer. At the meeting, the Contractor shall provide emergency names and phone numbers (accessible 24 hours a day, 7 days a week) to Owner's representative.

M. Contractor shall provide Owner’s designated Representative with an accurate schedule that reflects the location of equipment and manpower and their intended use and any other ongoing Work. Contractor shall update this schedule on a regular basis as the Work progresses as needed to provide the Owner with a minimum of seven days notice prior to mobilizing a new area of work. This schedule will include a list of the Work items required to complete the Contract, the duration, sequence, and dependency on the Work of other contractors. The Owner’s Representative will review and revise the Work Schedule as necessary, with Contractor's cooperation. Work Schedule shall also include hours of expected operation as well as daily activity. The Owner shall confirm the schedule does not interfere with CCPS prior to Contractor’s mobilization to the new area of work.

IFB #27-003M

N. Allowable work hours are Monday through Friday 7 AM to 5 PM. Noise generating activity cannot commence prior to 8 AM or as governed by the local jurisdiction.

Holiday and weekend work may be performed with written permission from the Owner’s Representative.

O. Building access to all areas except the immediate Work area shall be maintained at all times. Work areas shall not block access to any portion of the building (excluding the immediate Work area). Contractor shall not block emergency egress. Provide overhead protection, if necessary, to keep emergency egress open.

P. Provide all equipment, materials and manpower to complete the Work outlined in this document.

Q. Coordinate Work with others (if present), such that no delay with this project or the Work of others occurs.

R. Contractor shall limit use of premises for Work, for storage, and for access to allow for The Owner’s occupancy. Storage of equipment shall be at a location designated by The Owner’s Representative. Obtain approval from the Owner’s Representative for on-site storage of materials.

S. Contractor shall assume full responsibility for protection and safekeeping of products stored on site under this Contract.

T. Contractor shall have readily available at all times on site the Safety Data Sheets (SDS) for any material or solution which is stored or intended for use on site. Material or solutions will not be permitted on site without SDS information.

U. Contractor shall obtain and pay for use of additional storage or work areas needed for operations under this Contract.

V. Locate utilities that might be affected by the Work. Contractor is solely responsible for maintaining all utilities in operable condition, for repairing any damaged utilities, and for the safety of the workers and public.

W. Contractor may connect to existing power service (if available). Contractor shall provide temporary electric feeder from existing electrical service at locations as directed by the Owner’s Representative. Power consumption shall not disrupt the Owner's need for continuous service. Otherwise, Contractor shall provide utilities as needed to effectively complete the Work.

X. The Owner will pay cost of energy used if the source of power is from the building.

Exercise measures to conserve energy.

Y. Provide main service disconnect and over-current protection at convenient location.

Z. Provide power outlets for construction operations, with branch wiring and distribution boxes located as required. All circuits shall be outfitted with ground fault circuit interrupters. Provide flexible 3-wire power cords suitable for outdoor use, maximum length of 100 feet, minimum 10 gauge.

AA. Provide all power equipment with qualified operating personnel for the safe and efficient use of equipment. Provide equipment with all safety devices as required by OSHA, local codes and ordinances, state codes and the equipment manufacturers.

BB. Contractor may connect to existing water source for construction operations (if available). Otherwise, Contractor shall provide water as needed.

CC. The Owner will pay cost of water used. Exercise measures to conserve water.

DD. Construction personnel shall not use existing bathroom facilities unless approved by Owner. Otherwise, provide enclosed portable self-contained toilet facilities, secluded

IFB #27-003M

from public view in a location designated by the Owner’s Representative. Maintain daily in clean and sanitary condition.

EE. Construct Work in stages to accommodate the Owner's use of premises during construction.

FF. Provide temporary barriers to restrict unintentional access to the work area, without preventing emergency egress.

GG. Contractor shall provide necessary signage and barriers to redirect pedestrians safely around the work area. Means and methods used to redirect pedestrians shall not hinder pedestrian access through the areas of work in the event of an emergency.

HH. Clean-up shall be performed daily as required to prevent accidents to personnel, protect all Work in place, and to allow completion of the project in an orderly manner.

Construction clean-up shall consist of the removal of all mud, oil, grease, sand, gravel, soil, trash, scrap, debris, and excess materials, from any drive, or walking surface, that may cause the tripping or sliding of persons or equipment. Loose materials or debris being removed from the site by the Contractor's vehicles, which becomes deposited on the roadways or other outside access areas, shall be cleaned up and removed immediately.

II. Roll-off dumpsters, if allowed, shall be placed at a location approved by the Owner’s Representative prior to dumpster placement.

JJ. Protect existing finish work that is to remain as is and is exposed during execution of the work.

KK. The Contractor shall repair and/or replace areas of the site damaged during construction operations including sidewalks, curbs, pavements, site furnishing, railings, lighting fixtures, etc., immediately after completion of all operations in that area. Repairs must, as a minimum standard, be equal to or exceed the condition which existed prior to the start of work under this Contract, in accordance with the requirements of General Conditions of the Contract.

LL. Payment by the Owner for any materials, equipment, or labor incorporated into the Work shall not be deemed to be an acceptance by Owner’s designated Representative.

The risk of loss of such materials, equipment, or cost of labor spent to install such, shall remain with the Contractor, and the Contractor shall be fully responsible for such materials, equipment, or labor to the same extent as if the Owner had not paid or accepted real property, until after final inspection and approval by Owner’s designated Representative. Stolen, damaged, vandalized, missing, or weather damaged equipment or material shall be considered the property of the Contractor until final acceptance by Owner’s designated Representative.

MM. Any request for an extension of time is to be made immediately upon occurrence of conditions which, in the opinion of the Contractor, warrant such an extension with reasons clearly stated and detailed proof given for all delays beyond the Contractor’s control, these to be made in writing to the Owner. No time extension will be allowed except by formal approval of Owner’s designated Representative.

NN. Once substantial completion has been awarded, a reasonable time will be allowed, to the Contractor by the Owner’s designated Representative, for the Contractor to complete any remaining "punch list" items.

OO. Upon completion of the project, or as directed by Owner’s designated Representative, the Contractor shall remove all temporary items, material, and equipment from the site, same to become his property, and leave the premises.

IFB #27-003M

PP. Acknowledge, by execution of the Contract, awareness and familiarity with the contents and requirements of the regulations, codes, standards, and guidance documents. Assume responsibility for the performance of the Work in strict compliance with these documents and for every instance of failure to comply with these documents. Where conflict exists between these documents and the Contract Documents, the more stringent requirements shall apply.

9.0 INSURANCE REQUIREMENTS

Contractor shall obtain, pay the premiums for and keep in force during the term of this agreement insurance written by companies licensed and authorized to conduct business in the State of Maryland and acceptable to the Owner in dollar amounts specified by the Owner.

Contractor’s insurance shall name the Owner and Engineer as additional insureds.

Contractor’s insurance shall be considered primary in all cases. Refer to CCPS contract documents for additional requirements.

10.0 REFERENCES

A. All codes and standards applicable to the Work governed by this specification shall be the most recent edition of federal, state and local codes and standards. All applicable codes and standards shall be strictly adhered to, including, but not limited to the following:

1. American National Standards Institute (ANSI);

2. American Society for Testing and Materials (ASTM);

3. Sealant , Waterproofing and Restoration Institute (SWRI);

4. National Institute for Occupational Safety and Health (NIOSH);

5. Occupational Safety and Health Administration (OSHA) guidelines;

6. The International Building Code (IBC);

7. National Roofing Contractors Association (NRCA);

8. Sheet Metal and Air Conditioning Contractors National Association (SMACNA);

9. Single-Ply Roofing Institute (SPRI);

10. National Emission Standards for Hazardous Air Pollutants (NESHAP) regulations;

11. The U.S. Environmental Protection Agency (EPA);

12. Underwriters Laboratory (UL);

11.0 PLANS AND SPECIFICATIONS

A. Contractor shall notify Owner of any omissions, contradictions or conflicts at least three days before bid date. Owner will provide necessary corrections or additions to plans and specifications by addendum. If Contractor does not so notify Owner of any such condition, it will be assumed that the Contractor has included the necessary items in the bid to complete this specification.

B. It is the intent that this be a completed project as far as the contract documents set forth. It is not the intent that different phases of work on this project be delegated to various trades and subcontractors by the contract documents. Contractor shall make its own contracts with various subcontractors, setting forth the work these subcontractors will be held responsible for. Contractor alone will be held responsible for the completed project.

C. If the Contractor feels a conflict exists between what is considered good roofing practice and these specifications, Contractor shall state in writing all objections prior to submitting bid.

IFB #27-003M

D. It is the Contractor's responsibility during the course of the work, to bring to the attention of the Owner's representative any defective membrane, insulation or deck discovered where not previously identified.

E. Contractor shall notify Engineer of specification or detail items which conflict with manufacturer recommended procedures.

12.0 SCHEDULES

A. Work shall be accomplished on a daily progressive basis. Any request for an extension of time is to be made immediately upon occurrence of conditions which, in the opinion of the Contractor, warrant such an extension with reasons clearly stated and detailed proof given for all delays beyond the Contractor’s control. No time extension will be allowed except by formal approval of the Owner.

B. The Contractor shall submit a written statement or produce a firm commitment from a supplier and/or suppliers that they have in stock, or can readily obtain all materials needed to expedite all phases of the work on this contract, within the time frames allowed. At no time or for any reason will an extension of time for completion be granted due to the lack of materials. Failure to fulfill this is grounds for termination of the contract by the Owner.

C. Work shall commence after the execution of the contract and within the timeframe negotiated between the Owner and the Contractor. If material receipt is cause for delay, submit to the Owner a letter from the manufacturer stating materials, Purchase Order date and anticipated shipping dates. No work shall begin until all materials are on site and inspected by the Contractor for completeness.

D. Notification of Completion: Contractor shall notify the manufacturer by means of manufacturer's printed Notification of Completion form of job completion in order to schedule a final inspection date.

13.0 QUALITY ASSURANCE

A. Primary roofing materials (for each type of roof) shall be from single source manufacturer that has been successfully producing the specified types of primary products for not less than 10 years. Secondary or accessory products shall be acceptable to the manufacturer of the primary roofing products.

B. ACCEPTABLE CONTRACTOR. Contractor shall have a minimum of 5 years’ experience in successfully installing the same or similar roofing materials and be certified in writing by the roofing materials manufacturer to install the primary roofing products.

C. Contractor and all Roofing Subcontractors, shall be certified by Siplast.

D. Contractor may subcontract any phase or portion of the Work. However, each subcontractor must be approved by the Owner and such subcontract shall not relieve Contractor from enforcing the use of all required safety equipment by subcontractor and its employees providing any phase of the Work. Require and verify that all materials and methods used by subcontractor are consistent with materials, methods and procedures specified in the Contract Documents

IFB #27-003M

E. SCOPE OF WORK. The work to be performed under this specification shall include but is not limited to the following: Attend necessary job meetings and furnish competent and full time, supervision, experienced roof mechanics, all materials, tools, and equipment necessary to complete, in an acceptable manner, the roof installation in accordance with this specification. Comply with the latest written application instructions of the manufacturer of the primary roofing products. In addition, application practice shall comply with requirements and recommendations contained in the latest edition of the guidelines by the NRCA.

F. LOCAL REGULATIONS. Conform to regulations of public agencies, including any specific requirements of the city and/or state of jurisdiction.

G. MANUFACTURER REQUIREMENTS. Ensure that the primary roofing materials manufacturer provides direct trained company personnel to attend necessary job meetings, perform periodic inspections as necessary, and conduct a final inspection upon successful completion of the project.

H. Owner will pay for first inspection and first re-inspection by the Engineer. Any re-inspection required after first re-inspection will be at the Contractor’s expense.

14.0 CODE COMPLIANCE

A. Work to be performed under this Contract shall be done so in strict compliance with all applicable codes for each Section of work.

B. The Contractor shall obtain and pay for any and all permits required, to perform the work, by the local jurisdiction and the local governing authority having jurisdiction. The Contractor shall provide copies of all permits required to Owner prior to any on-site work.

C. Failure to comply with those codes shall result in immediate work stoppage until that portion of the work is replaced to meet applicable codes. All costs as a result of repair or replacement due to non-code compliance shall be the full responsibility of the Contractor. Time extension will not be granted for additional time required to rectify non-compliance work.

15.0 SUBMITTALS

All material submittals shall be presented in a submittal log following the notice of award and prior to Contractor mobilization to the site. The log shall consist of an organized binder for the Engineer’s review and approval. After approval, one copy shall be kept by the Owner’s Representative, one by the Engineer, and the third shall remain on site at all times with the SDS sheets. Work shall be stopped immediately by the Engineer if for any reason the Contractor does not have SDS information readily available at the site. Work shall not commence until all submittals are submitted by the Contractor and reviewed/approved by the Engineer.

A. Provide manufacturer’s literature indicating performance characteristics and compliance with the standards referenced in this Specification for the following materials:

1) Metal decking and fasteners

IFB #27-003M

2) Gypsum repair material

3) Insulation fasteners and plates

4) Metal Flashing Materials

5) Pipe Vent, Furnace Vent and Exhaust Vent Flashings

6) Roofing Mastic

7) Flat Roofing Membrane and Adhesive

8) Insulation/Coverboard

9) Metal Coping

10) Drains

11) Downspouts

12) Sealants

13) Other related materials

B. Submit a detailed schedule for the project defining the sequence of work and the work areas to be addressed during each phase or location. The Owner will require this schedule be updated routinely (i.e., weekly) so that tenants and property management can be kept advised. Work Schedule shall also include hours of expected operation as well as daily activity. The Owner’s Representative will review and revise the Work Schedule as necessary, with Contractor's cooperation.

C. Submit a schedule of values.

D. Submit a Construction Permit (or letter from local jurisdiction indicating that a permit is not required) PRIOR to beginning work.

E. Documentation on equipment and supplemental materials to be used in the performance of the Work outlined herein.

F. Warranty information as outlined in Warranty Section. A sample warranty for Contractor’s two-year warranties, and Flat Roof Membrane Manufacturer’s 20 year NDL warranty.

G. Submittals required prior to contract award shall include:

1. A letter from the proposed primary roofing manufacturers confirming that the bidder is an acceptable Contractor authorized to install the proposed system.

2. A letter from the primary roofing manufacturers stating that the proposed application will comply with the manufacturer's requirements in order to qualify the project for the specified guarantee and ASCE-07 wind uplift standards, ANSI/SPRI ES1, and UL Class A ratings.

3. Detailed information from the flat roof membrane manufacturer regarding insulation and roof membrane attachment procedures. This submittal shall be used to verify insulation and roof membrane attachment are in compliance with ASCE-07 wind uplift standards.

I. Certificate(s) of insurance, showing required coverage limits, for the Contractor and all Subcontractors and listing the Owner, Managing Agent and Gardner Engineering as additional insured. Other additional insureds shall be incorporated upon request by the Owner.

J. Safety Data Sheets for all materials being used.

IFB #27-003M

K. Project Contact List

L. Proposed demolition method including equipment to be used.

M. Insulation taper/saddle/cricket plan from Roof Insulation Manufacturer

N. Prior to final payment, the Contractor shall submit the following items, which shall be in a written form acceptable to the Owner:

1. Applicable release of liens (covering the Owner);

2. Any warranty information from the Contractor and Flat Roof Manufacturer.

3. Any available product operational or maintenance information

16.0 WARRANTY

Contractor and Manufacturer shall furnish the following warranties for this project:

A. Twenty-Year NDL Flat Roof System Guarantee: Upon successful completion of the project, and after all post installation procedures have been completed, furnish the Owner with the roof system Manufacturer's 20 year labor and materials roof system guarantee.

The roof system guarantee shall include the roofing and flashing membranes, insulation, sheet metal flashing, edge metal and all fasteners. All repair or replacement costs covered under the guarantee shall be borne by the roofing membrane manufacturer. The guarantee shall be a term type, without deductibles or limitations on coverage amount, and be issued at no additional cost to the Owner.

B. Contractor’s 2-Year workmanship and material guarantee: Contractor shall guarantee workmanship and materials for a period of 2 years. The workmanship and materials guarantee shall include both the roofing and flashing membranes and all metal. All repair or replacement costs covered under the guarantee shall be borne by the roofing Contractor.

17.0 EXISTING CONDITIONS

A. It shall be the responsibility of the Contractor to assess the existing conditions prior to work commencement.

1. Contractor shall document existing building deficiencies or damage and submit to the Engineer prior to work commencement. The Contractor shall retain a copy of documentation for his records.

2. The Contractor shall take photographs of the existing building deficiencies or damage to the Engineer prior to work commencement.

3. Any deficiencies or damage noted after work commencement shall be deemed the responsibility of the Contractor and shall be replaced or repaired at the Contractor's expense.

4. Contractor shall examine the underside of the exposed roof deck, where possible, to avoid damage or conflict from fastener attachment with utilities or mechanical items below.

IFB #27-003M

5. Building space directly under roof area covered by this specification will be utilized by on-going operations. Do not interrupt owner operations unless prior written approval is received from the owner, including water, sound and odor disturbances.

6. Contractor shall be responsible for lost revenue as a result of contractor actions.

7. Access to roof for removal of existing roofing and supply of new roofing material, sheet metal, etc. shall be from exterior only, unless specifically approved by the Owner.

B. Field dimensions: It shall be the responsibility of the Contractor to verify all field dimensions for installation prior to bid submittal. All work required to make the system complete shall be the sole responsibility of the Contractor after bid submittal.

18.0 FIRE SAFETY

A. Contractor shall coordinate safety plan with on-site personnel.

B. Fire Extinguishers: Provide sizes, numbers and locations as would be reasonably effective in extinguishing fires during early stages, by trained personnel at project site.

Contractor shall utilize TYPE ABC Multi-Purpose Dry Chemical fire extinguishers only on the project. Post warning and quick instruction at each extinguisher location, and instruct all personnel at project site, at time of their first arrival, on proper use of extinguishers and other available facilities at project site.

C. The use and storage of LP gas cylinders on the job site will be in strict compliance with the most current edition of NFPA 58, Liquefied Petroleum Gases. Owner reserves the right to inspect all operations involving LP gas, at any time and without prior notice, to ensure full compliance with the above referenced code.

D. All exterior building exits will be kept clear and accessible at all times during the course of the contract. If it becomes necessary to block, obstruct or in any way restrict egress from a marked emergency exit, the Owner will be notified at least two business days in advance.

19.0 SAFETY REQUIREMENTS

A. All application, material handling, and associated equipment shall conform to and be operated in conformance with OSHA safety requirements. Familiarize every member of the application crew with all fire and safety regulations recommended by OSHA, NRCA and other industry or local governmental groups. Contractor shall be solely responsible for site safety.

B. Comply with federal, state, local and Owner fire and safety requirements.

C. Advise Owner whenever work is expected to be hazardous to Owner, occupants, employees, and/or operators.

D. The use of lead containing or asbestos containing materials is prohibited on the project, except for lead flashing at roof drain and pipe vent locations as noted.

IFB #27-003M

E. Maintain a crewman as a floor area guard whenever roof decking is being repaired or replaced.

F. Maintain fire extinguishers within easy access.

G. Contractor is required to comply with state laws regarding notification.

H. Comply with OSHA’s Fall Protection Standard.

I. Comply with OSHA’s Overhead Protection Standard when lifting materials or working over pedestrian walkways or exits.

J. Erect and maintain barricades, which will prevent persons from entering the construction zone. Barricades shall include plywood barriers, construction zone type (orange fencing) and police/type barricades as required or as directed by the Owner.

Barricade far enough from job site to avoid splatter or spray of bitumen or other material.

K. Provide temporary barriers to restrict unintentional access to the work area, without preventing emergency egress. Provide and maintain all safety barricades as required by local and state codes and laws, and as necessary for the protection of workers and the public. Contractor shall provide necessary signage and barriers to redirect vehicles and pedestrians safely around the work area. Detour and caution signage shall be commercially available traffic signs, such as used for highway construction. Provide barricades and perform work in a manner such that products are not tracked by pedestrians or vehicles.

L. Erect temporary protection, such as fences, canopies and railings where required by authorities having jurisdiction, or where appropriate, for protection of the public.

M. All temporary ladders or means of access to the roof shall be removed and secured at the end of each workday.

N. Contractor is solely responsible for job site safety.

20.0 FALL PROTECTION

A. The Contractor shall fully comply with OSHA’s Fall Protection Standards. The Contractor shall assume all financial responsibilities for compliance with the standard and any project delays as a result of non-compliance. The Contractor shall submit verification (e.g., Certificate of Training) that employees have been trained on OSHA’s Fall Protection standard.

B. Provide the name of the Contractor’s on-site “competent person” who will be responsible for recognizing and warning his/her employees of fall hazards.

C. Provide a list of the OSHA approved fall protection systems that the Contractor will utilize on the project.

21.0 BUILDING PROTECTION

A. Contractor shall perform necessary preventive measures to ensure water and dust/debris do not enter the building at any time during the duration of the project.

IFB #27-003M

Contractor shall be responsible for any damages, loss of business, etc. caused by water or dust entering the building as a result of the roof construction.

B. The Contractor shall at all times prevent dust, trash and asphalt spray migration due to demolition or other construction related activities by means of temporary plastic or solid barriers. Where barriers meet adjacent walls, seal with duct-tape. Maintain protection for areas below the roof level at all times. Cover equipment, etc. with drop clothes.

C. If necessary, provide filters over intakes for protection from dust.

D. Coordinate the closure of air intakes to prevent the migration of fumes into the building.

E. Locate utilities that might be affected by the Work. Contractor is solely responsible for maintaining all utilities in operable condition, for repairing any damaged utilities, and for the safety of the workers and public.

D. Protect facilities against falling debris by solid sheeting and plastic.

E. Keep hallways and aisles clear of debris at all times during construction.

22.0 USE OF BUILDING UTILITIES

A. Contractor shall provide enclosed portable self-contained toilet facilities, secluded from public view. Maintain daily in clean and sanitary condition.

B. Contractor may connect to existing power service. Provide temporary electric feeder from existing building electrical service at locations as directed by Owner. Power consumption shall not disrupt Owner's need for continuous service. Owner will pay cost of energy used. Exercise measures to conserve energy. Contractor shall provide generators for electric if power service at the building is not available.

C. Provide main service disconnect and over-current protection at convenient location.

D. Provide power outlets for construction operations, with branch wiring and distribution boxes located at each roof area. All circuits shall be outfitted with ground fault circuit interrupters. Provide flexible 3-wire power cords suitable for outdoor use, maximum length of 100 feet, minimum 10 gauge.

E. Permanent convenience receptacles may not be utilized during construction.

F. Contractor may connect to existing common area water source for construction operations (if available). Otherwise, Contractor shall provide water as needed to effectively complete. Owner will pay cost of water used. Exercise measures to conserve water.

23.0 TRANSPORTATION AND HANDLING

A. Arrange deliveries of products in accordance with construction schedules. Coordinate to avoid conflict with work and conditions at the site.

B. Deliver products in undamaged condition, in manufacturer's original containers or packaging, with identifying labels intact and legible.

IFB #27-003M

C. Assume full responsibility for protection and safekeeping of products stored on site under this Contract.

D. Immediately on delivery, inspect shipments to assure compliance with requirements of contract documents and approved submittals, and that products are properly protected and undamaged. Any materials that are found to be damaged or stored in any manner other than stated above will be automatically rejected, removed and replaced at the Contractor's expense.

E. Store materials out of direct exposure to the elements. Store roll goods on a clean, flat and dry surface. All material stored on the roof overnight shall be stored on pallets. Rolls of roofing must be stored on ends. Store materials on the roof in a manner so as to preclude overloading of roof deck and building structure. Store materials such as solvents, adhesives and asphalt cutback products away from open flames, sparks or excessive heat. Cover all material using a breathable cover such as tarpaulins; other non-breathable plastic coverings are not acceptable.

F. Handle all materials in such a manner as to preclude damage and contamination with moisture or foreign matter. Handle rolled goods to prevent damage to edges or ends.

Any material that has deteriorated or has been contaminated shall not be used and shall be immediately removed from the site.

G. Stack preformed and pre-finished sheet metal components to prevent twisting, bending, or abrasion and to provide ventilation.

H. If sheet metal material is furnished with strippable protective film, film should be removed immediately after installation to prevent damage to the coating if left exposed to sunlight.

I. Use only access to buildings as designated by the Owner. Do not drive vehicles on landscaped areas unless otherwise directed by the Owner. The Contractor shall repair or replace, as directed by the Owner, any damaged areas caused by this contract. The Contractor shall bear all costs for repair.

J. Contractor shall limit use of premises for Work, for storage, and for access to allow for Owner occupancy. Storage of equipment shall be at location designated by Owner. Obtain approval of Owner for on-site storage of materials.

K. Contractor shall obtain and pay for use of additional storage or work areas needed for operations under this Contract.

24.0 MATERIAL REQUIREMENTS

A…

This is the start of the file's text. The full file is on GovTribe.