This is a bid proposal and contract document from the Virginia Department of Transportation (VDOT) for construction of a proposed trail in Mecklenburg County, Virginia. The project extends from Rudd's Creek to Skipwith Road along Route 9999 and is federally funded through the Surface Transportation Program (FHWA Number: STP-058-4(060), Project Number: 9999-058-091, M501). The scope of work includes clearing and grubbing, grading, pipe installation, asphalt concrete placement, erosion and sediment control, landscaping, signage, pavement markings, and establishment of permanent vegetation. Bids were due on October 28, 2026, at 10:00 AM through the electronic bidding system Bidx. The project completion date is June 2, 2028. The contract includes numerous line items with approximate quantities, including 1,875 cubic yards of borrow excavation, 4,313 tons of aggregate base material, 237 tons of asphalt concrete, 24,000 linear feet of temporary silt fence, and various amenities such as eight wooden benches, one overhead sign, and one trailhead sign. Special provisions address seasonal construction restrictions near a heron rookery (February 15 through July 31) and tree removal restrictions for bat habitat protection (April 1 through November 15).
Bids are evaluated on a lowest responsive and responsible bidder basis without discrimination. A bid bond equal to five percent of the bid amount is required. The contract includes predetermined minimum wage rates established by the U.S. Department of Labor for various classifications, ranging from $11.99 per hour for flaggers to $26.68 per hour for crane operators. Contractors must comply with Davis-Bacon prevailing wage requirements, maintain certified weekly payrolls, and implement FHWA contract provisions including nondiscrimination, safety standards, and drug-free workplace requirements. Optional price adjustment provisions are available for fuel, steel, and asphalt materials. The project is subject to federal labor standards, Disadvantaged Business Enterprise (DBE) requirements, and environmental compliance including the Endangered Species Act. Prequalification is mandatory for bidding. The contract documents reference the Virginia Department of Transportation Road and Bridge Specifications (2020 edition with 2022 supplement) and Standard Drawings (2016 edition with online revisions as of the advertisement date).
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ORDER NO.: B23
CONTRACT ID. NO.: C0000125508M01
Form C-6a
Rev. 3-22-05
CNSP (F) 1-9-06
COMMONWEALTH OF VIRGINIA
DEPARTMENT OF TRANSPORTATION
BID PROPOSAL AND CONTRACT
ROUTE NUMBER: 9999
FHWA NUMBER: STP-058-4(060)
PROJECT NUMBER: 9999-058-091, M501
COUNTY: MECKLENBURG
DISTRICT: RICHMOND
DESCRIPTION: PROPOSED TRAIL
FROM:
TO:
RUDD'S CREEK
SKIPWITH RD
DATE BID SUBMITTED: 10:00 AM WEDNESDAY, OCTOBER 28, 2026
Form C-118 Rev. 8-10-2026
COMMONWEALTH OF VIRGINIA
NOTICE TO BIDDERS
As a matter of information, the bidder’s attention is directed to the points noted herein. Every point enumerated below is fully covered by proposal documents that describe them in detail. Bidders should check their proposal against all requirements, as strict compliance with all provisions is mandatory.
1. Bids shall be filed electronically through Bidx (https://bidx.com/site/home) at the times designated in the Notice of Advertisement for Bids. For information see (https://cabb.virginiadot.org/)
2. Unless otherwise specified or permitted in the proposal, prices shall be submitted on all items shown in the proposal.
3. Proposals conditioned by proposed alternates, other than those specified or permitted, or by reserving the right to accept or reject an award or to enter into a contract pursuant to an award will not be considered.
4. A bid total shall be shown in each space provided.
5. Bid bonds shall conform to Section 102.07. The bid bond number shall be placed in the appropriate space in your electronic bid. As an alternative, you may complete the bottom line of Form C-24. The form may be emailed to the Construction Division at VDOTContracts@vdot.virginia.gov and must be received prior to the opening of bids.
6. Joint venture proposals shall show the Firm Name of each party and shall be signed by an authorized representative of each Firm. A letter shall be filed with the prequalification office describing responsibility of each firm and the amount of maximum capacity pledge by each firm of a joint venture.
Form C-24
Rev. 7-6-05
PROPOSAL GUARANTY
KNOW ALL MEN BY THESE PRESENTS, THAT WE _______________________________________ as principal, and ________________________________________ Surety, are held and firmly bound unto the
Commonwealth of Virginia as obligee, in the amount of FIVE PERCENT OF THE DOLLAR VALUE OF THE
BID, lawful money of the United States of America, for the payment of which, well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally and firmly by these presents.
SIGNED, sealed and dated this Day of , 20
WHEREAS, the above said principal is herewith submitting its proposal for:
PROJECT NUMBER: 9999-058-091, M501
NOW, THEREFORE, the condition of the above obligee is such, that if the aforesaid principal shall be awarded the contract upon said proposal and shall within the time specified in the Specifications after the notice of such award enter into a contract and give bond for the faithful performance of the contract, then this obligation shall be null and void; otherwise to remain in full force and effect and the principal and surety will pay unto the obligee the difference in money between the amount of the bid of the said principal and the amount for which the obligee may legally contract with another party to perform the said work if the latter amount be in excess of the former; but in no event shall the liability exceed the penal sum hereof.
(Principal*) (Surety Company)
By: By:
(Officer, Partner or Owner) (Seal) (Attorney-in-Fact**) (Seal)
(Principal*) (Address)
(Officer, Partner or Owner) (Seal) (Surety Company)
(Principal*) (Attorney-in-Fact**) (Seal)
(Officer, Partner or Owner) (Seal) (Address)
*Note: If the principal is a joint venture, each party thereof must be named and execution made by same hereon. If there is more than one surety to the bid bond, each surety must be named and execution shall be made by same hereon.
Electronic Bid Only: In lieu of completing the above section of the Contract Performance Bond, the Principal shall file an Electronic Bid Bond when bidding electronically. By signing below the Principal is ensuring the identified electronic bid bond has been executed and the Principal and Surety are firmly bound unto the Commonwealth of Virginia under the same conditions of the bid bond as shown above.
Electronic Bid Bond ID# Company/Bidder Name Signature and Title
**Attach copy of Power of Attorney
Form C-48 Rev. 10-03-25
SUBCONTRACTOR/SUPPLIER SOLICITATION AND UTILIZATION,
AND VENDOR SURVEY FORM (ALL VENDORS)
PROJECT NO. 9999-058-091, M501 CONTRACT I.D. NO. C0000125508M01
FHWA NO. STP-058-4(060) DATE SUBMITTED
All vendors submitting a bid as a Prime Contractor shall complete and submit with their bids the following information as requested for (1) Subcontractor/Supplier Solicitation, and Utilization, and (2) for Vendor Survey.
The vendor certifies this form accurately represents its solicitation and utilization or non-utilization, as indicated, of the firms listed below for performance of work on this contract. The vendor also certifies he/she has had direct contact with the named firms regarding participation on this project.
Vendor Signature:
Vendor ID No. Title:
Vendor’s Address: ____________________________________
City: __________________
State: __________________ Zip Code: _________
SUBCONTRACTOR/SUPPLIER SOLICITATION AND UTILIZATION (ALL)
VENDOR
NUMBER
NAME OF SUBCONTRACTOR/SUPPLIER TELEPHONE
NUMBER
UTILIZED
(Y/N)
NOTE: ATTACH ADDITIONAL PAGES, IF NECESSARY.
BIDDER MUST SIGN EACH ADDITIONAL SHEET TO CERTIFY ITS CONTENT AND COMPLETION OF FORM.
FEDERAL LAW REQUIRES ALL VENDORS SUBMITTING BIDS OR OFFERS PROVIDE THE INFORMATION
REQUESTED IN THIS FORM.
Form C-48 Rev. 10-03-25
VENDOR SURVEY
WHEN SUBMITTING A BID OR OFFER AS A PRIME CONTRACTOR, THE BIDDER MUST SUBMIT A
VENDOR SURVEY FOR THEMSELVES AND A VENDOR SURVEY FOR EACH SUBCONTRACTOR
AND SUPPLIER WHO SUBMITTED A BID OR QUOTE TO THE BIDDER.
VENDOR’S FULL LEGAL NAME: ________________________________________
VENDOR ID NO.: __________________
ADDRESS: ____________________________________
CITY: ____________________________________
STATE: _______________ ZIP CODE: _________
VENDOR’S YEARS IN BUSINESS: _____________
VENDOR’S ANNUAL GROSS RECEIPTS: ____ $ 0 - 25 million ____ $ 25 - 50 million ____ $ 50 - 75 million ____ More than $75 million
THE UNDERSIGNED, ON BEHALF OF VENDOR IDENTIFIED ABOVE, ACKNOWLEDGES AND CERTIFIES THAT THIS FORM ACCURATELY STATES THE INFORMATION CONTAINED HEREIN TO THE BEST OF VENDOR’S
KNOWLEDGE.
Printed Full Legal Name of Person Signing for Vendor
Signature: ____________________________________________
Form C-7 Rev. 2-2-24
SHEET 1
TERMS OF THE PROPOSAL\CONTRACT
SUBMITTED: 10:00 AM WEDNESDAY, OCTOBER 28, 2026
PROJECT NUMBER: 9999-058-091, M501
ROUTE NUMBER: 9999
FHWA NUMBER: STP-058-4(060)
DESCRIPTION: PROPOSED TRAIL
FROM:
TO:
RUDD'S CREEK
SKIPWITH RD
DISTRICT: RICHMOND COUNTY: MECKLENBURG
I/we declare that no other person, firm or corporation is interested in this proposal; that I/we have carefully examined the plans, job specifications, current Road and Bridge specifications, and all other documents pertaining thereto and thoroughly understand the contents thereof; that I/we meet the prequalification requirements for bidding on this proposal;
that I/we understand that the plans and current Road and Bridge specifications, are a part of this proposal; that all of the quantities shown herewith are a part of this proposal; that all the quantities shown herewith are approximate only; that I/we have examined the location of the proposed work and source of supply of materials; and that I/we agree to bind myself/ourselves upon award by the Commonwealth under this proposal to a contract with necessary surety bond to start work according to project specifications, and to complete all work in accordance with the plans, job specifications and current Road and Bridge Specifications within the time limit set forth in the contract.
COMPLETION DATE: JUNE 2, 2028
BID TOTAL $
Attached is a bond conforming to the requirements of the current Road and Bridge Specifications, it being understood that such bond is to be forfeited as liquidated damages if, upon acceptance of the terms of this proposal, I/we fail to execute the contract and furnish bond as provided in the current Road and Bridge Specifications.
(Names of Individual(S),Firm(S) Or Corporation)
Street Address City State Zip Code Vendor#/Fin#
Print Name Signature Title
In consideration of the commitments made as shown herein, the Commonwealth of Virginia by The Commonwealth Transportation Commissioner agrees to pay for all items of work performed and materials furnished at the unit price(s) and under the conditions set forth in this proposal, in witnessed by the affixing of the name below.
Contract Execution Date By
CHIEF ENGINEER
VIRGINIA DEPARTMENT OF TRANSPORTATION
Virginia Department of Transportation 09/02/2026Date Printed:
Schedule of Items Page: 2
Proposal ID: C0000125508M01 9999-058-091, M501
Order No.: B23
Oversight/State Project No.:
Federal Project No.: STP-058-4(060)
Contractor:
0001 REGULAR BID ITEMSSECTION:
Cat Alt Set ID: Cat Alt Mbr ID:
Bid AmountUnit Price Approximate Quantity and
UnitsDescription
Item ID Proposal
Line Number Dollars Cents Dollars Cents
Spec No.
0010 301SD20-0001
CLEARING AND GRUBBING LUMP SUM _________._____LUMP SUM
0020 302SD20-0030
18" CONC. PIPE LF
64.000
0030 302SD20-0201
18" END SECTION ES-1 EA
2.000
0040 303SD20-0004
GRADING LUMP SUM _________._____LUMP SUM
0050 303SD20-0007
BORROW EXCAVATION CY
1,875.000
0060 303SD20-0022
CHECK DAM ROCK TY. I EA
19.000
0070 303SD20-0023
CHECK DAM ROCK TY. II EA
1.000
0080 303SD20-0029
SILTATION CONTROL
EXCAVATION
CY
158.000
0090 303SD20-0034
TEMP. SILT FENCE TYPE A LF
24,000.000
0100 308SD20-0011
AGGR. BASE MATL. TY. I NO.
21A
TON
4,313.000
0110 312SD20-0003
CO.MAT.FINE AGGR.OR
AGGR.NO.10
TON
663.000
0120 315SD20-0004
ASPHALT CONCRETE TY. IM-
19.0A CONST
TON
121.000
0130 315SD20-0007
ASPHALT CONCRETE TY. SM-
9.5A CONST
TON
116.000
Schedule of Items Page: 3
Proposal ID: C0000125508M01 9999-058-091, M501
Order No.: B23
Oversight/State Project No.:
Federal Project No.: STP-058-4(060)
Contractor:
0001 REGULAR BID ITEMSSECTION:
Cat Alt Set ID: Cat Alt Mbr ID:
Bid AmountUnit Price Approximate Quantity and
UnitsDescription
Item ID Proposal
Line Number Dollars Cents Dollars Cents
Spec No.
0140 315SD20-0104
SAW-CUT ASPHALT
CONCRETE FULL DEPTH
LF
130.000
0150 414SD20-0003
EROSION CTRL. STONE CL. I,
EC-1
TON
7.000
0160 504SX20-0005
BENCH WOODEN BENCH EA
8.000
ATTD
0170 504SX20-0007
CONCRETE WHEEL STOPS EA
10.000
ATTD
0180 507SX20-0013
FENCE POST AND RAIL
VEHICLE CONTROL
LF
80.000
ATTD
0190 507SX20-0013
FENCE RAMM FLEX FENCE LF
690.000
ATTD
0200 508SD20-0004
DEMO. OF PAVEMENT
FLEXIBLE
SY
38.000
0210 512SD20-0013
TYPE 3 BARRICADE 8' EA
2.000
0220 512SD20-0014
TEMPORARY SIGN SF
208.000
0230 512SD20-0024
GROUP 2 CHANNELIZING
DEVICES
DAY
3,730.000
0240 512SD20-0027
FLAGGER SERVICE HR
160.000
0250 512SD20-0042
ERADICATE LINEAR PVMT
MRKG
LF
2,510.000
0260 512SX20-0015
BARRICADE FIXED WOODEN
BOLLARD
EA
8.000
ATTD
Schedule of Items Page: 4
Proposal ID: C0000125508M01 9999-058-091, M501
Order No.: B23
Oversight/State Project No.:
Federal Project No.: STP-058-4(060)
Contractor:
0001 REGULAR BID ITEMSSECTION:
Cat Alt Set ID: Cat Alt Mbr ID:
Bid AmountUnit Price Approximate Quantity and
UnitsDescription
Item ID Proposal
Line Number Dollars Cents Dollars Cents
Spec No.
0270 512SX20-0015
BARRICADE REMOVEABLE
WOODEN BOLLARD
EA
4.000
ATTD
0280 513SD20-0001
MOBILIZATION LUMP SUM _________._____LUMP SUM
0290 515SD20-0013
FLEXIBLE PAVE.PLANING 0"-
2"
SY
257.000
0300 517SD20-0001
CONSTRUCTION SURVEYING
CONSTR.
LUMP SUM _________._____LUMP SUM
0310 602SD20-0006
TOPSOIL CLASS B CY
887.000
0320 603SD20-0002
TEMPORARY SEED LB
220.000
0330 603SD20-0003
REGULAR SEED LB
591.000
0340 603SD20-0004
OVERSEEDING LB
473.000
0350 603SD20-0005
LEGUME SEED LB
27.000
0360 603SD20-0006
LEGUME OVERSEEDING LB
22.000
0370 603SD20-0008
HYDRAULIC EROSION
CONTROL PRODUCT TYPE 2
SY
13,008.000
0380 603SD20-0009
HYDRAULIC EROSION
CONTROL PRODUCT TYPE 3
SY
10,951.000
0390 603SD20-0014
FERTILIZER NITROGEN - N LB
220.000
Schedule of Items Page: 5
Proposal ID: C0000125508M01 9999-058-091, M501
Order No.: B23
Oversight/State Project No.:
Federal Project No.: STP-058-4(060)
Contractor:
0001 REGULAR BID ITEMSSECTION:
Cat Alt Set ID: Cat Alt Mbr ID:
Bid AmountUnit Price Approximate Quantity and
UnitsDescription
Item ID Proposal
Line Number Dollars Cents Dollars Cents
Spec No.
0400 603SD20-0015
FERTILIZER PHOSPHOROUS
- P
LB
154.000
0410 603SD20-0016
FERTILIZER POTASSIUM - K LB
154.000
0420 603SD20-0017
LIME TON
12.100
0430 605SX20-0013
LANDSCAPE PERMANENT
VEGETATIVE COVER
LUMP SUM _________._____LUMP SUM
ATTD
0440 605SX20-0015
LANDSCAPE GRASS
CHANNEL 2' WIDE
LF
250.000
ATTD
0450 606SD20-0001
ROLLED EROSION CTRL
PRODUCT EC-2 TYPE 1
SY
800.000
0460 700SD20-0003
REMOVE EXISTING 1 POST
SIGN STRUCTURE
EA
2.000
0470 700SD20-0034
SIGN POST STP-1, 2", 14
GAUGE
LF
345.000
0480 700SD20-0038
CONC. FOUND. STP-1, TY. A EA
28.000
0490 700SX20-0021
TRAFFIC SIGN THT
OVERHEAD SIGN (A)
EA
1.000
ATTD
0500 700SX20-0021
TRAFFIC SIGN THT
TRAILHEAD SIGN (A)
EA
1.000
ATTD
0510 701SD20-0001
SIGN PANEL SF
137.000
Schedule of Items Page: 6
Proposal ID: C0000125508M01 9999-058-091, M501
Order No.: B23
Oversight/State Project No.:
Federal Project No.: STP-058-4(060)
Contractor:
0001 REGULAR BID ITEMSSECTION:
Cat Alt Set ID: Cat Alt Mbr ID:
Bid AmountUnit Price Approximate Quantity and
UnitsDescription
Item ID Proposal
Line Number Dollars Cents Dollars Cents
Spec No.
0520 704SD20-0006
TYPE B CLASS I PVMT LINE
MRKG 4"
LF
4,032.000
0530 704SD20-0013
TYPE B CLASS II PVMT LINE
MRKG 8"
LF
80.000
0540 704SD20-0015
TYPE B CLASS II PVMT LINE
MRKG 24"
LF
80.000
Section: 0001 _________._____Total:
Total Bid: _________._____
Page
Bid Items Eligible For Fuel Adjustment
C0000125508M01
B23
Contract ID:
Order No.:
Instructions: This form shall be completed in accordance with the Special Provision for Optional Adjustment for Fuel. If you choose to have Fuel Adjustment applied to any of the items listed below, write the word "Yes" in the "OPTION" column beside the item. The form must be signed, dated, and submitted to the Contract Engineer within the timeframe required in the Special Provision.
FORM C-21B
Rev 12-21-05
0001 REGULAR BID ITEMSSECTION:
ltem Description Fuel Factor gal/unit Option Item
Number
_______BORROW EXCAVATION 0.290303SD20-0007
_______SILTATION CONTROL EXCAVATION 0.290303SD20-0029
_______AGGR. BASE MATL. TY. I NO. 21A 0.600308SD20-0011
_______ASPHALT CONCRETE TY. IM-19.0A CONST 3.500315SD20-0004
_______ASPHALT CONCRETE TY. SM-9.5A CONST 3.500315SD20-0007
_______EROSION CTRL. STONE CL. I, EC-1 0.600414SD20-0003
_______DEMO. OF PAVEMENT FLEXIBLE 0.200508SD20-0004
_______FLEXIBLE PAVE.PLANING 0"-2" 0.071515SD20-0013
Date:
Signature:
(Firm or Corporation)
(Vendor No.)
Bid Items Eligible For Steel Price Adjustment
C0000125508M01
B23
Contract ID:
Order No.:
Instructions: This form shall be completed in accordance with the Special Provision. If you choose to have Steel Price Adjustment applied to any of the items listed below, write the word "Yes" in the "OPTION" column beside the item. The form must be signed, dated, and submitted to the Contract Engineer within the timeframe required in the Special Provision.
Rev 12-21-08
FORM C-21C
0001 REGULAR BID ITEMSSECTION:
ltem Description Option Item
Number
_______SIGN POST STP-1, 2", 14 GAUGE700SD20-0034
_______TRAFFIC SIGN THT TRAILHEAD SIGN (A)700SX20-0021
_______TRAFFIC SIGN THT OVERHEAD SIGN (A)700SX20-0021
Date:
Signature:
(Firm or Corporation)
(Vendor No.)
Bid Items Eligible For Asphalt Adjustment within this Project
C0000125508M01
B23
Contract ID:
Order No.:
0001 REGULAR BID ITEMSSECTION:
ltem Description Item
Number
ASPHALT CONCRETE TY. IM-19.0A CONST315SD20-0004
ASPHALT CONCRETE TY. SM-9.5A CONST315SD20-0007
Determination of Major Items
1C0000125508M01Contract ID:
ltem Description Item
Number
AGGR. BASE MATL. TY. I NO. 21A308SD20-0011
TEMP. SILT FENCE TYPE A303SD20-0034
BORROW EXCAVATION303SD20-0007
FORMS and SCHEDULE OF ITEMS PRECEDE SPCNs, SPs and SUPPLEMENTAL SPECS.
CN100-000026-09 GEN. PROJ. REQUIRE., SSS/SPS/SPCNS 12-11-25 (SPCN) 1
CN103-000100-01 SEC 103.02—AWARD OF CONTRACT 6-17-25 (SPCN) 1
CN105-000140-00 SEC 105.14—MAINTENANCE DURING CONSTRUCTION 12-20-24 (SPCN) 2
CN105-000150-00 SECURITY REQUIREMENTS FOR PCMS 1-30-26 (SPCN) 2
CN245-000100-01 SEC 245.03—TESTING & DOCUMENTATION 1-10-24 (SPCN) 3
CQ107-000130-00 DRUG-FREE WORKPLACE 7-3-19 (SPCN) 5
CQ107-000150-00 EQUAL EMPLOYMENT OPPORTUNITY 5-11-22 (SPCN) 5
POST AND RAIL VEHICULAR CONTROL 7/20/26 (SPCN) 6
WOODEN BENCH 7/20/26 (SPCN) 6
RAMM FLEX FENCE 7/20/26 (SPCN) 7
THT OVERHEAD SIGN (A) 7/20/26 (SPCN) 7
THT TRAILHEAD SIGN (A) 7/20/26(SPCN) 8
FIXED WOODEN BOLLARD AND REMOVABLE WOODEN BOLLARD 8
SEASONAL CONSTRUCTION RESTRICTIONS NEAR HERON ROOKERY 8
GRASS CHANNEL 9/26/16 9
TREE REMOVAL TIME OF YEAR RESTRICTION FOR BAT HABITAT 9 /9/26 12
ESTABLISHING PERMANENT VEGETATION 8/16/21 13
SP0F0-000100-00 PREDETERMINED MIN. WAGE RATES R-7-12-16 15
SP0F0-000130-03 FHWA 1273—CONTRACT PROVISIONS, FED-AID 7-9-26 19
SP0F0-000150-01 AFFIRMATIVE ACTION / EEO NOTICE 7-17-17 42
SP102-000120-00 NON-DISCRIMIN. EMPLOY. & CONTRACT. PRACTICES (EO-61) 1-10-17 48
SP107-000110-00 C-45–SWPPP GEN. PERMIT–CONTRACTOR CERTIFICATION R-10-27-16 49
*SP107-000120-00 ELEC. SUBMISSION OF DBE AND PAYROLLS 1-21/20 50
SP107-001510-06 INTERIM DBE REQUIREMENTS 1-26-26 52
SP107-003100-00 MADE IN THE USA REQUIREMENTS 10-03-25 56
SP108-000100-01 PROG. SCHED. FOR CAT. I PROJECTS 3-21-22 63
*SP109-000100-05 ASPHALT MATERIAL PRICE ADJUSTMENT 7-8-24 78
SP109-000110-00 OPTIONAL ADJUSTMENT FOR FUEL R-7-12-16 80
SP109-000120-01* PRICE ADJUSTMENT FOR STEEL 7-2-19 82
SP109-000130-01 ELECTRONIC OR PRINTED WEIGH TICKETS 3-10-25 87
SP700-000180-03 MODIFICATIONS TO AASHTO’S SIGN STRUCT. SPEC. 9-29-20 93
SP801-000100-01 LANE CLOSE COORD (LCC)/LANE CLOSE IMPLEMENT (LCI) 9-20-17 98
SQ105-000611-01 SEC 105.06 — SUBCONTRACTING (FED FUNDED PROJECTS) 2-9-17 (SP) 100
SQ107-001300-00 PREVAILING WAGE RATES 10-12-2023 101
SS109-002020-01 SEC 109 — MEASUREMENT AND PAYMENT 5-1-23 105
SS211-002020-03 SEC 211 – ASPHALT CONCRETE 3-18-24 108
SS220-002020-01 SEC 220 – CONCRETE CURING MATERIALS 8-28-20 113
SS223-002020-02 SEC 223 – STEEL REINFORCEMENT 4-4-23 114
SS234-002020-01 SEC 234 – GLASS BEADS AND RETROREFLECTIVE OPTICS 5-6-22 115
SS235-002020-01 SEC 235 – RETROREFLECTORS 5-6-22 116
SS236-002020-01 SEC 236 – WOOD PRODUCTS 5-14-21 117
SS246-002020-02 SEC 246 – PAVEMENT MARKING 5-6-22 121
SS248-002020-02 SEC 248 – STONE MATRIX ASPHALT CONCRETE 3-18-24 129
SS305-002020-02 SEC 305 – SUBGRADE AND SHOULDERS 12-20-23 131
SS308-002020-01 SEC 308 - SUBBASE COURSE 7-13-21 133
SS309-002020-01 SEC 309 - AGGREGATE BASE COURSE 7-13-21 134
SS315-002020-05 SEC 315 – ASPHALT CONCRETE PLACEMENT 5-27-25 135
SS317-002020-01 SEC 317— STONE MATRIX ASPHALT CONCRETE PLACEMENT 6-21-24 154
SS318-002020-01 SEC 318 — PAVEMENT INTERLAYERS 8-2-23 156
SS319-002020-02 SEC 319 – THIN HOT MIX ASPHALT CONCRETE OVERLAY 3-18-24 157
TABLE OF CONTENTS FOR PROVISIONS
SS321-002020-02 SEC 321 – TRENCH WIDENING 5-4-23 161
SS407-002020-02 SEC 407 – STEEL & METAL STRUCT 11-01-22 163
SS411-002020-01 SEC 411 – PROT. COAT. OF METAL 11-01-22 165
SS512-002020-03 SEC 512 – MAINTAINING TRAFFIC 7-1-22 166
SS704-002020-02 SEC 704 – PAVEMENT MARKINGS AND MARKERS 5-6-22 179
PRECAST CONCRETE WHEEL STOPS 10/22/24 185
THT STANDARD TRAIL DESIGNS 187
PERMITS 214
cn100-000026-09 December 11, 2025 (SPCN)
GENERAL PROJECT REQUIREMENTS, SUPPLEMENTAL SPECIFICATIONS (SSs), SPECIAL PROVISIONS (SPs) AND SPECIAL PROVISION COPIED NOTES (SPCNs)
This project shall be constructed according to: the Plans; the Virginia Department of Transportation Road and Bridge Specifications, dated 2020 and the Supplement thereto, dated 2022; the Virginia Department of Transportation Road and Bridge Standards, dated 2016, with revisions issued online as of the advertisement date for this project incorporated; the Virginia Work Area Protection Manual, version 11.0;
the Virginia MUTCD version 11.0; and the Supplemental Specifications, Special Provisions and Special Provision Copied Notes in this Contract. The status in the Contract of each of these documents will be according to Section 105.12 of the Specifications.
Special Provision Copied Notes in this Contract are designated with “(SPCN)” after the date.
The information at the top and left of each Special Provision Copied Note in this Contract is file reference information for Department use only. The information in the upper left corner above the title of each Supplemental Specification and Special Provision in this Contract is file reference information for Department use only.
cn103-000100-01 June 17, 2025 (SPCN)
SECTION 103.02—AWARD OF CONTRACT of the Specifications is replaced in its entirety with the following:
103.02 – Award of Contract
The Board, or the Commissioner as authorized under § 33.2-209 of the Code of Virginia, will award the Contract to the lowest responsive and responsible bidder without discrimination on the grounds of race, color, gender, national origin, status as a military family, or other basis prohibited by law. In the event of a tie bid, the tie will be decided by lot.
The award date will not be later than midnight on the 60th day after the opening of bids. If the Board, or the Commissioner where authorized by law, has not awarded the Contract within this period due to any circumstances not attributable to the bidder, the bidder may withdraw his bid without penalty or prejudice unless the time limit is extended by mutual consent.
After approval for the award of contracts, the Department will provide written notice of award to the successful bidder and will post the Ballots on the Department’s bidding webpage. The Ballot serves as public Notice of Award for a contract. The date of the Notice of Award is the “Approved” date appearing at the top of the Ballot that lists the Contract.
cn105-000140-00 December 20, 2024 (SPCN)
SECTION 105.14—MAINTENANCE DURING CONSTRUCTION of the Specifications is amended by the following:
Section 105.14(a)3 – Flagging Traffic is replaced with the following:
3. Flagging Traffic: Flaggers shall be able to communicate to the traveling public in English while performing the job duty as a flagger at the flagger station.
All flaggers shall possess a valid, current flagger certification card, be it a physical or electronic card, at all times while performing flagging duties.
Flaggers shall be certified by the VDOT Basic or Intermediate Work Zone Traffic Control Training course or by the ATSSA’s classroom Flagger Certification Program.
The following constitutes a valid flagger certification card:
• Cards issued by VDOT following completion of the Basic Work Zone course;
• Cards issued by VDOT following completion of the Intermediate Work Zone course;
• Cards issued by ATSSA following completion of a Flagger course;
• Cards issued by VDOT following completion of the Flagger-only course, provided the cards were issued on or before December 31, 2024, and have not yet reached the expiration date
(two years after date of issuance).
Flaggers who fail to possess a valid, current, flagger certification card, or refuse to allow inspection of same upon request, shall be removed from the flagging site, and operations requiring flagging shall be suspended by the Engineer. Suspended operations requiring flagging may resume once a certified flagger arrives on-site to perform flagging duties in accordance with applicable requirements. Flaggers improperly performing duties may be subject to flagger certification revocation at the sole discretion of the Engineer.
cn105-000150-00 January 30, 2026 (SPCN)
SECURITY REQUIREMENTS FOR PORTABLE CHANGEABLE MESSAGE SIGNS — The Contractor shall secure portable changeable message sign (PCMS) control cabinets with a grade 3 or stronger standard lock at all times unless maintenance is actively being conducted on the sign.
A password shall be required to change the PCMS message. The Contractor shall change the manufacturer's default password for ALL electronic signs. Electronic signs that support the use of complex passwords shall include at least 14 characters consisting of the following criteria:
• At least one special character
• At least one alphabetical character
• At least one numerical character
• A combination of upper-case and lower-case letters
Electronic signs that do not support the use of complex passwords shall be changed using the maximum number of characters and character types permitted by the manufacturer.
Password credentials are prohibited from being stored, displayed, or written on or within the sign. Any QR codes affixed to the sign shall be removed.
For all PCMS with remote or wireless accessibility, the Engineer will authorize remote access prior to this functionality being enabled. Prior to authorization, the Contractor shall update the PCMS to the most recent compatible software and firmware version available from the manufacturer. Following authorization and prior to use, the Contractor shall establish a remote connection to verify that access to the PCMS is password protected.
Electronic signs shall only post approved and documented messages. The Contractor shall log all messages posted with date and times for each public message.
The Contractor has the option for their signs to be connected to the Department’s Operations Technology (OT) network for management by Traffic Operations Center (TOC) staff. By using this method, messages are transmitted and posted by the TOC control room staff with all records and logging managed within the VDOT Advanced Traffic Management System (ATMS). Electronic message signs connected to the OT network shall follow the security requirements described below:
1. All electronic signs connected to the network shall be secured with a digital lock installed on the sign control cabinet.
2. Connected signs shall only be remotely accessible through secure communications that originated from the Department’s OT network.
3. Connected signs shall only be posted with messages from the Department’s ATMS systems or designated backup systems.
4. Community strings (both public and private strings) shall be changed from default settings.
5. All vendor cloud connections shall be removed from the connected sign. TOC system administration staff will configure VPN connections exclusively to the Department’s OT network.
6. All connected electronic signs shall adhere to the Cabinet Security Standards found in the
Department’s OT Cybersecurity Program Manual.
cn245-000100-01 January 10, 2024 (SPCN)
SECTION 245.03—TESTING AND DOCUMENTATION of the Specifications is amended by the following:
Section 245.03(e) – Prefabricated Geocomposite Pavement Underdrain is replaced by the following:
Prefabricated Geocomposite Pavement Underdrain: Prefabricated geocomposite pavement underdrain shall consist of a polymeric drainage core allowing water inflow from both sides, encased in a nonwoven filter fabric envelope having sufficient flexibility to withstand bending and handling without damage.
Prefabricated geocomposite pavement underdrain shall conform to the following:
1. Core: The drainage core shall be made from an inert, polymeric material resistant to commonly encountered chemicals and substances in the pavement environment and shall have a thickness of not less than 3/4 inch. Outer surfaces shall be smooth to prevent excessive wear of bonded filter fabric.
Physical Properties Test Method Requirements
Compressive strength ASTM D1621, D2412, and D6364
Min. 40 psi at 20% max.
deflection immediately after 24 hrs of specimen conditioning at 0 deg F and at 125 deg F
Water flow rate (after 100 hr at 10 psi normal confining pressure and gradient of no more than 0.1)
ASTM D4716 Min. 15 gal/min/ft width for 12-in specimen length
2. Filter Fabric: Geotextile shall be bonded to and tightly stretched over both sides of the core. Geotextile shall not sag or block the flow channels, shall have a life equivalent to that of the core material, and shall conform to the requirements of Section 245.03(c) of the Specifications.
Section 245.03(f) – Geocomposite Wall Drains is replaced by the following:
Geocomposite Wall Drains: Prefabricated geocomposite wall drain shall consist of a polymeric drainage core with a nonwoven filter fabric (single sided or double sided) having sufficient flexibility to withstand bending and handling without damage. Geocomposite wall drains shall conform to the following:
1. Core: The drainage core shall be made from an inert, polymeric material resistant to commonly encountered chemicals and substances in the roadway. Outer surfaces shall be smooth to prevent excessive wear of bonded filter fabric.
Physical Property Test Method Requirements
Compressive strength ASTM D1621, D2412, and D6364
Min. 40 psi at 20% max.
deflection immediately after 24 hrs of specimen conditioning at 0 degree F and at 125 degree F
Water flow rate (after 100 hr at 10 psi normal confining pressure and gradient of no more than 1.0)
ASTM D4716 Min. 15 gal/min/ft width (for 12-in specimen length)
2. Filter Fabric: Geotextile shall be bonded to and tightly stretched over the core. Geotextile shall not sag or block the flow channels, shall have a life equivalent to that of the core material, and shall conform to the requirements of Section 245.03(c) of the Specifications.
Section 245.03(g) – Geomembrane Moisture Barrier is replaced by the following:
Geomembrane Moisture Barrier: Geomembrane moisture barrier shall be resistant to biological attack.
Geomembrane shall be constructed of PVC and shall conform to the requirements of ASTM D7176 for PVC 30 or higher grades. In addition, geomembrane shall comply with the requirements of ASTM D7408 for bond seam strength and peel strength.
DRUG-FREE WORKPLACE – The Contractor shall:
• Provide a Drug-Free Workplace for the Contractor’s employees.
• Post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in the Contractor’s workplace and specifying the actions that will be taken against employees for violations of such prohibition.
• State in all solicitations or advertisements for employees placed by or on behalf of the Contractor that the Contractor maintains a Drug-Free Workplace.
• Include the provisions of the foregoing clauses in every Subcontract or purchase order of over $10,000, so that the provisions will be binding upon each Subcontractor or vendor.
For the purposes of this provision, “Drug-Free Workplace” means a site for the performance of work done in connection with the Contract. The Contractors employees, and those of his Subcontractors, shall be prohibited from engaging in the unlawful manufacture, sale, distribution, dispensation, possession, or use of any controlled substance or marijuana during the performance of the Work.
CQ107-000150-00 May 11, 2022 (SPCN)
EQUAL EMPLOYMENT OPPORTUNITY
Section 107.14(a)1 – Required by §2.2-4201 and §2.2-4311 of the Code of Virginia is replaced with the following:
1. Required by §2.2-4201 and §2.2-4311 of the Code of Virginia: During the performance of this Contract, the Contractor agrees as follows:
a. The Contractor shall not discriminate against any employee or applicant for employment because of race, religion, color, sex, or national origin, age, disability, or other basis prohibited by state law relating to discrimination in employment, except where religion, sex, or national origin is a bona fide occupational qualification reasonably necessary to the normal operation of the Contractor. The Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices setting forth the provisions of this nondiscrimination clause, including the names of all contracting agencies with which the Contractor has contracts of over $10,000.
b. The Contractor shall, in all solicitations or advertisements for employees placed by or on behalf of the Contractor, state that such contractor is an equal opportunity employer. However, notices, advertisements and solicitations placed in accordance with federal law, rule or regulation shall be deemed sufficient for the purpose of meeting the requirements of this chapter.
c. If the Contractor employs more than five employees, the Contractor shall (i) provide annual training on the Contractor's sexual harassment policy to all supervisors and employees providing services in the Commonwealth, except such supervisors or employees that are required to complete sexual harassment training provided by the Department of Human Resource Management, and (ii) post the Contractor's sexual harassment policy in (a) a conspicuous public place in each building located in the Commonwealth that the Contractor owns or leases for business purposes and (b) the Contractor's employee handbook.
The Contractor shall include the provisions of subdivisions a, b, and c in every subcontract or purchase order of over $10,000, so that such provisions shall be binding upon each subcontractor or vendor.
Nothing contained in this chapter shall be deemed to empower any agency to require any contractor to grant preferential treatment to, or discriminate against, any individual or any group because of race, color, religion, sex, or national origin on account of an imbalance that may exist with respect to the total number or percentage of persons of any race, color, religion, sex, or national origin employed by such contractor in comparison with the total number or percentage of persons of such race, color, religion, sex, or national origin in any community or in the Commonwealth.
UPC125508 7/20/2026
POST AND RAIL VEHICULAR CONTROL will be measured in linear feet of railing fabricated, delivered and installed where shown in the Contract Documents. Details of the post and rail vehicular control design and installation shall be in accordance with the Contract Documents, Plans, and Standard Drawings provided for Post and Rail Vehicular Control. Shop drawings shall be supplied in accordance with Section
105.10 of the VDOT Road and Bridge Specification for review and approval by the Department prior to fabrication or installation. All materials shall meet the applicable section of the VDOT Road and Bridge Specification, Division II, Materials. Fabrication and installation shall meet all applicable sections of the VDOT Road and Bridge Specification, Division IV, Bridges and Structures and Division V, Incidental Construction.
The contract unit price shall include preparation of shop drawings, fabrication, delivery and installation and shall include all tools, equipment, labor, materials, and incidentals necessary for the post and rail vehicular control, complete in place.
Payment will be made under:
Pay Item Pay Unit
Post and Rail Vehicular Control Linear Foot (LF)
UPC125508 7/20/26
WOODEN BENCH will be measured per bench fabricated, delivered and installed where shown in the Contract Documents. Details of the wooden bench design and installation shall be in accordance with the Contract Documents, Plans, and Standard Drawings for Wooden Bench / Horse Mount.
The bench shall be installed using either the buried post or concrete pad foundation, as determined to be appropriate based on-site conditions and as approved by the Department. Shop drawings shall be supplied in accordance with Section 105.10 of the VDOT Road and Bridge Specification for review and approval by the Department prior to fabrication or installation. All materials shall meet the applicable section of the VDOT Road and Bridge Specification, Division II, Materials. Fabrication and installation shall meet all applicable sections of the VDOT Road and Bridge Specification, Division IV, Bridges and Structures.
This price shall include preparation of shop drawings, fabrication, delivery and installation and shall include all tools, equipment, labor, materials, and incidentals necessary for the Wooden Bench, complete in place.
Wooden Bench Each (EA)
UPC122508 7/20/2026
RAMM FLEX FENCE will be measured in linear feet of fencing fabricated, delivered and installed where shown in the Contract Documents. Details of the post and rail vehicular control design and installation shall be in accordance with the Contract Documents, Plans, and Standard Drawings provided for RAMM Flex Fencing. Shop drawings shall be supplied in accordance with Section 105.10 of the VDOT Road and Bridge Specification for review and approval by the Department prior to fabrication or installation. All materials shall meet the applicable section of the VDOT Road and Bridge Specification, Division II, Materials.
Fabrication and installation shall meet all applicable sections of the VDOT Road and Bridge Specification, Division IV, Bridges and Structures and Division V, Incidental Construction.
This price shall include preparation of shop drawings, fabrication, delivery and installation and shall include all tools, equipment, labor, materials, and incidentals necessary for the post and rail vehicular control, complete in place.
RAMM Flex Fence Linear Foot (LF)
THT OVERHEAD SIGN (A) will be measured per each overhead sign fabricated, delivered and installed at the locations shown in the Contract Documents.
Details of the overhead sign design and installation shall be in accordance with the Contract Documents, Plans, and Standard Drawings provided for THT Overhead Sign (A). Shop drawings shall be submitted in accordance with Section 105.10 of the VDOT Road and Bridge Specification for review and approval by the Department prior to fabrication or installation. Shop drawing shall include all design details and calculations for the overhead sign structure and foundation in accordance with Section 105.10(c)(4). All materials shall meet the applicable section of the VDOT Road and Bridge Specification, Division II, Materials. Fabrication and installation shall meet all applicable sections of the VDOT Road and Bridge Specification, Division IV, Bridges and Structures and Division VII, Traffic Control Devices.
The contract unit price shall include all costs associated with preparing shop drawings, fabrication, delivery and installation and shall include all tools, equipment, labor, materials, and incidentals necessary for the signpost, complete in place.
THT Overhead Sign (A) Each (EA)
THT TRAILHEAD SIGN (A) will be measured per each trailhead sign fabricated, delivered and installed where shown in the Contract Documents. Details of the overhead sign design and installation shall be in accordance with the Contract Documents, Plans, and Standard Drawings provided for THT Trailhead Sign (A). Shop drawings shall be supplied in accordance with Section 105.10 of the VDOT Road and Bridge Specification for review and approval by the Department prior to fabrication or installation. Shop drawings shall include complete sign footing details. All materials shall meet the applicable section of the VDOT Road and Bridge Specification, Division II, Materials. Fabrication and installation shall meet all applicable sections of the VDOT Road and Bridge Specification, Division IV, Bridges and Structures and Division VII, Traffic Control Devices. The contract unit price shall include ll costs associated with preparing shop drawings, fabrication, delivery and installation and shall include all tools, equipment, labor, materials, and incidentals necessary for the sign post, complete in place.
THT Trailhead Sign (A) Each (EA)
FIXED WOODEN BOLLARD and REMOVABLE WOODEN BOLLARDwill be measured per each bollard fabricated, delivered and installed where shown in the contract documents. Details of the wooden bollard design and installation shall be in accordance with the Contract Documents, Plans, and Standard Drawings provided for Wooden Bollard, Fixed or Removable. Shop drawings shall be supplied in accordance with Section 105.10 of the VDOT Road and Bridge Specification for review and approval by the Department prior to fabrication or installation. All materials shall meet the applicable section of the VDOT Road and Bridge Specification, Division II, Materials. Fabrication and installation shall meet all applicable sections of the VDOT Road and Bridge Specification, Division IV, Bridges and Structures.
Bollards will be measured in units of each and will be paid for contract unit price per each. This price shall include preparation of shop drawings, fabrication, delivery and installation and shall include all tools, equipment, labor, materials, and incidentals necessary to complete the work for the Wooden Bollard, Fixed or Removable, complete in place.
Fixed Wooden Bollard Each (EA)
Removable Wooden Bollard Each (EA)
UPC125508 8/12/26
SEASONAL CONSTRUCTION RESTRICTIONS NEAR HERON ROOKERY
Trail construction and major maintenance activities requiring heavy machinery within 0.5-mile of the heron rookery (Station 43+00 through 53+00) shall be avoided between February 15th through July 31st to minimize disturbance during the nesting season.
SPECIAL PROVISION FOR
GRASS CHANNEL
September 26, 2016 9999-058-091, M501
I. DESCRIPTION
This work shall consist of constructing, inspecting, and maintaining grass channels in conformity with the lines, grades, and thickness as shown on the Plans and as directed by the Engineer.
II. MATERIALS
(a) Gravel and aggregate shall consist of clean, washed stone of the appropriate size classification conforming to Section 203 of the Specifications.
i. Bedding Stone, if called for in lieu of turf or landscaping in channel bed, shall be #1 aggregate conforming to Section 203 of the Specifications unless otherwise specified.
(b) Drainage fabric shall conform to Section 245.
(c) Geosynthetics shall conform to Section 245 of the specifications
(d) Soil Compost Amendments shall conform to the Special Provision for Compost Amended Soil and shall be installed as shown on the plans.
(e) Check Dams - Unless otherwise specified or directed the Engineer, check dams shall be constructed of riprap, aggregate, railroad ties, pressure treated logs or timbers, or concrete and be in conformance with the SWM Miscellaneous Special Provision.
(f) Topsoil shall conform to Section 244 of the Specifications and shall be installed according to Section 602 of the Specifications.
III. PROCEDURES
The contractor shall meet with the Engineer before starting work on grass channels. The contractor shall prepare a construction and maintenance schedule for each grass channel. Items to be included in the schedule are planned installation dates, mowing frequency, erosion repair, invasive species control, trash removal, and functionality checking. The contractor shall begin installation of the grass channel after approval by the Engineer.
a) The contractor shall verify the general boundaries of the contributing drainage area and the as-built inlet elevations to ensure they conform to original design. Subtle differences in site grading, drainage, and paving elevations can produce hydraulically important differences for proposed grass channels. The contractor and the Engineer shall communicate, in writing; any modifications identified during the preconstruction meeting and any modifications based on field conditions that are needed.
b) Grass channels shall be maintained free of construction vehicle traffic. When this is not possible the contractor shall integrate the conveyance into a temporary drainage network, providing temporary channel stabilization during construction activities.
i. Final grading of grass channels shall begin after the contributing drainage area has been stabilized with vegetation or final pavement. It may be necessary to block certain curb or other inlets while the grass channel area is being constructed and stabilized, if possible.
ii. Excavate the channel with light tracked equipment to avoid compacting the swale soil.
iii. The contractor shall clean all debris and sediment from the facility and return the channel to design grade and contour before inspection by the Engineer and, after approval by the Engineer, install any subsequent features.
c) Temporary erosion and sediment controls shall be installed as needed to divert stormwater away from the grass channel during construction until it is completed and stabilized. Install protection measures such as erosion control fabrics as needed to protect side slopes from erosion during construction.
d) Aggregate required for level spreaders or splash pads shall consist of clean, washed stone of the appropriate size classification.
e) Contaminated aggregate shall be cleaned or removed before starting fine grading or completing the facility. Geotextiles shall be installed as shown on the plans.
f) Soil Compost Amendments, if specified on the plans for the channel bed, shall be installed according to the Special Provision for Compost Amended Soil. These amendments shall be installed to the depth and by the method shown on the construction plans.
i. Install pretreatment facilities, driveway culverts, and check dams according to the
Specifications, the SWM Miscellaneous Special Provision, and as shown on the plans.
Type, size, and materials shall conform to the plans unless otherwise directed by the Engineer.
ii. Install grass or alternate vegetation and ground cover specified in the planting plan for grass channels. Install sod, fabric, or non-erosive lining in the inlet channel and/or filter strips where indicated on the plans.
g) The contractor shall notify the Engineer the facility is ready for inspection when complete and request an inspection. Correct any items noted as unacceptable. Stabilize all disturbed areas and then remove all facility sediment controls and unblock curb openings or other upstream diversions only after the Engineer approves the facility.
IV. TOLERANCES
(a) Slopes surrounding grass channels shall be graded to 3:1 or flatter, unless otherwise specified. All tolerances shall conform to Section 303.05(b) of the Specifications.
(b) Grass channel finished grade shall conform to Section 305.03(c) of the Specifications.
V. INSPECTION AND MAINTENANCE
The contractor shall maintain facilities in temporary or final condition during construction by mowing and performing regular maintenance until the project is accepted by the Engineer so that efficacy of the newly constructed facility is not degraded. Any deficiencies or damage shall be corrected at no additional cost to the Department. The contractor shall ensure that the facilities conform to these specifications before the facilities are accepted.
The contractor shall perform required maintenance which includes, but is not limited to:
• Clearing sediment buildup at curb cuts, pretreatment facilities such as gravel diaphragms or pavement edges that prevent flow from getting into the bed and check for signs of bypassing flows.
• Immediately stabilizing bare or eroding areas in the contributing drainage area or around the grass channel area with grass cover or other appropriate lining. Fertilizers may be needed to promote initial planting growth in accordance with the VDOT nutrient management plan program.
• Checking for any winter or salt-killed vegetation and replacing it with hardier species as directed by the Engineer.
• Repairing rills or gully erosion as directed by the Engineer.
• Watering at least once a week the first two months after seeding or sodding and then as needed during first April to October growing season.
• Checking the project for evidence of ponding, dead plants, or concentrated flows and taking remedial action to return the areas to conformity with the design in accordance with the specifications and as directed by the Engineer.
• Checking inflow points for clogging and removing any sediment as directed by the Engineer.
• If water remains on the surface more than 24 hours after a storm, grade adjustments may be needed as directed by the Engineer.
VI. MEASUREMENT AND PAYMENT
Grass channels (width) will be measured in linear feet for the bottom width specified and will be paid for at the Contract unit price per linear foot. This price shall include furnishing and installing drainage the grass channel of the given with along with required seeding and sodding. Pretreatment options, rip rap, topsoil and stabilization, temporary erosion and sediment control, and fertilizer should be measured and paid for in accordance with the VDOT Road and Bridge Specifications. Check dams, if required, should be measured and paid for in accordance with the Special Provision for Stormwater Miscellaneous Items.
Payment for these items shall be full compensation for the transport of all materials, excavation, installation and the initial maintenance period before project acceptance.
Grass channel (width) Linear Foot
TREE REMOVAL TIME OF YEAR RESTRICTION FOR BAT HABITAT
September 9th, 2024 9999-058-091, M501
I. Background This project is in an environmentally sensitive area for bat species protected under the Endangered Species Act (16 USC 1531 et seq., hereinafter “the Act”) and the Virginia Endangered Species Act (29.1-563 et seq.).
The removal of trees greater than or equal to 0 inches diameter at breast height (DBH) is restricted, as it may result in adverse impacts to bat species by removing habitat, and is prohibited during the Time of Year Restriction period.
Tree removal activities associated with this project shall conform to Section 107.01 of the Specifications, the Act, and this Special Provision.
II. Requirements
1. Time of Year Restriction. No trees greater than or equal to 0 inches DBH shall be removed from April 1st- November 15th unless otherwise allowed by the Engineer as approved by the District Environmental Manager.
2. Unless other restrictions exist in the Contract prohibiting tree removal, the Contractor is allowed to proceed with tree removal operations outside of the Time of Year Restriction in accordance with Section 601 of the Specifications and within the established clearing limits as shown on the Plans, and as directed by the Engineer.
3. Notification and Cessation of Work
If the Contractor does not comply with this requirement, the work may be suspended and administered in accordance with Section 108 of the Specifications.
III.…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .