836894wtpRiv.pdf

PDF 19 MB Posted

Attached to
South Rivanna Water Treatment Plant Flocculator Replacement
Solicitation number
446
Issued by
Charlottesville City, Chatham Town, Virginia

About this file

This is a project manual and invitation for bids (IFB No. 446) issued by the Rivanna Water and Sewer Authority in Albemarle County, Virginia, for the replacement of the flocculation system at the South Rivanna Water Treatment Plant. The project includes selective demolition and installation of three new flocculators, associated concrete supports, fiberglass reinforced plastic (FRP) baffle walls, flocculator drive motors, sprockets, chains, variable frequency drives (VFDs), and integration of additional input/outputs into the SCADA system. A non-mandatory online pre-bid meeting is scheduled for August 11, 2026, at 11:00 AM EST, with a site visit to follow. Bids are due on August 31, 2026, at 3:00 PM, with submission accepted either in-person at the Rivanna Administration Building (697 Moores Creek Lane, Charlottesville, VA 22902-9016) or electronically via the eVA system. The contractor shall achieve substantial completion within 500 consecutive calendar days from the notice to proceed, with final completion within 30 days thereafter. Liquidated damages are set at $750 per calendar day for work remaining beyond the completion deadline.

The contract award will be based on the lowest responsive and responsible bidder. Any bid exceeding $500,000 requires a standard bid bond equal to five percent of the bid amount, as well as standard performance and labor/material payment bonds. Virginia contractor licensing is required: Class A licensing for contracts of $150,000 or more, or Class B licensing for contracts between $30,000 and $150,000. The project engineer is Short Elliott Hendrickson Inc., with project management contacts including Nate Nickerson (434.202.6627) and Matt Nguyen (651.302.7670). The owner's project manager is David White III (434.977.2970, Ext. 158). Bidders must visit the site to assess existing conditions and are responsible for determining local conditions; failure to do so waives claims related to site conditions. The bid documents include detailed specifications for concrete work, electrical systems, fiberglass components, process equipment, and control systems, with technical data on FRP baffle wall systems and installation/maintenance guidelines provided by Enduro Composites.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Manual

South Rivanna Water Treatment Plant – Flocculator Replacement

IFB No. 446

Rivanna Water & Sewer Authority Albemarle County, Virginia

SEH No. RIVAN 189203

July 31, 2026 mnguyen Bidding Documents

This Page Left Blank Intentionally

Title Page

RIVAN 189203 00 01 01 - 1

South Rivanna Water Treatment Plant – Flocculator Replacement

IFB No. 446

Rivanna Water & Sewer Authority Albemarle County, Virginia

SEH No. RIVAN 189203

July 31, 2026

Certification

RIVAN 189203 00 01 05 - 1

DOCUMENT 00 01 05

CERTIFICATION

I hereby certify that this specification was prepared by me or under my direct supervision and that I am a duly Licensed Professional Engineer under the laws of the Commonwealth of Virginia.

ENGINEER Responsible for:

Specification Sections: Division 0, Division 1, Division 6, Division 40, Division 46

Drawings: C Sheets, P Sheets

ELECTRICAL ENGINEER Responsible for:

Specification Sections: Division 26

Drawings: E Sheets

7/17/2026

Certification

00 01 05 - 2 RIVAN 176136

STRUCTURAL ENGINEER Responsible for:

Specification Sections: Division 3

Drawings: S Sheets

JOEL ERIC RECTOR

Lic. No. 0402068329

HTLA OE F W VN IRO GM INM IAO

C

PROFESSIONAL ENGIN

EE

R

07/15/202607/17/2026

Project Directory

RIVAN 189203 00 01 08 - 1

DOCUMENT 00 01 08

PROJECT DIRECTORY

Project Name:

IFB No. 446 South Rivanna Water Treatment Plant – Flocculator Replacement Location: Albemarle County, Virginia

Owner Name: Rivanna Water and Sewer Authority Address: 695 Moores Creek Lane

Charlottesville, VA 22902 Contact: David White III | Project Manager Phone: 434.977.2970, Ext. 158 Fax: 434.293.8858 E-mail: dwhite@rivanna.org

Project Engineer Name: Short Elliott Hendrickson Inc.

Address: 3535 Vadnais Center Drive

Saint Paul, MN 55110 Contact: Matt Nguyen, PE Phone: 651.302.7670 Fax: 888.908.8166 E-mail: mnguyen@sehinc.com

Project Manager Name: Short Elliott Hendrickson Inc.

Address: 400 Locust Ave #2

Charlottesville, VA 22902 Contact: Nate Nickerson, PE Phone: 434.202.6627 Fax: 888.908.8166 E-mail: nnickerson@sehinc.com

END OF SECTION

mailto:dwhite@rivanna.org mailto:mnguyen@sehinc.com mailto:nnickerson@sehinc.com

Table of Contents

RIVAN 189203 00 01 10 - 1

DOCUMENT 00 01 10

TABLE OF CONTENTS

Number Document

Introductory Information 00 01 01 Title Page 00 01 05 Certification 00 01 08 Project Directory 00 01 10 Table of Contents

Bidding Requirements RA-1 Invitation for Bid RA-1a Instructions to Bidders 00 31 19 Existing Condition Information RA-1b Bid Form RA-1d Standard Bid Bond RA-1e Post Bid Modification RA-1f Intent to Award RA-1g Post Bid Informality

Contract Forms RA-2 Notice of Award RA-2a Performance Bond – Construction Contracts RA-2b Payment Bond – Labor and Material RA-2c Worker’s Compensation Certificate RA-3 Contract Between Owner and Contractor RA-4 Notice to Proceed

Conditions of the Contract RA-5 Schedule of Values and Certificate of Payment RA-5a Affidavit of Payment RA-5b Consent of Surety RA-6 Change Order RA-6a Work Directive RA-6b Field Order RA-7 Contractor Certificate of Substantial Completion RA-7a Substantial Architect and Engineer Completion Certificate RA-8 Contractor Certificate of Completion RA-8a Certificate of Completion by the Architect and Engineer RA General Conditions

DIVISION 1 - GENERAL REQUIREMENTS

Summary

01 11 00 Summary of Work 01 12 16 Work Sequence

Price and Payment Procedures 01 25 13 Product Substitution Procedures 01 29 10 Applications for Payment

Table of Contents

00 01 10 - 2 RIVAN 189203

Administrative Requirements 01 31 13 Coordination 01 31 19 Project Meetings 01 32 16 Progress Schedules 01 33 00 Submittal Procedures 01 35 23 Safety Requirements

Quality Control 01 45 10 Quality Control for Building Structures

Temporary Facilities and Controls 01 51 00 Temporary Utilities 01 57 00 Temporary Controls

Product Requirements 01 60 00 Product Requirements

Miscellaneous 01 73 29 Cutting and Patching

Execution and Closeout Requirements 01 75 00 Starting and Adjusting 01 77 00 Closeout Procedures 01 78 23 Operation and Maintenance Data 01 78 37 Product Warranties

DIVISION 3 - CONCRETE

Concrete

03 11 00 Concrete Forming 03 20 00 Concrete Reinforcing 03 30 00 Cast in Place Concrete

DIVISION 6 – WOOD, PLASTICS AND COMPOSITES

Fiberglass

06 63 11 Fiberglass Reinforced Plastic Components

DIVISION 26 - ELECTRICAL

26 05 05 Selective Demolition for Electrical 26 05 10 Motors 26 05 19 Low-Voltage Electrical Power Conductors & Cables 26 05 26 Grounding & Bonding for Electrical Systems 26 05 29 Hangers and Supports for Electrical Systems 26 05 33.13 Conduit for Electrical Systems 26 05 33.16 Boxes for Electrical Systems 26 05 53 Identification for Electrical Systems 26 29 23 Variable Frequency Motor Controllers

DIVISION 40 - PROCESS INTEGRATION

40 81 00 Systems Integrator Summary of Work 40 90 00 Control Systems 40 92 20 Lockout Tagout Procedure Forms

DIVISION 46 – WATER EQUIPMENT

46 00 00 Process Equipment General Provisions 46 41 33 Flocculator Equipment 46 41 50 Baffle Walls

Form RA-1: Invitation for Bid

INVITATION FOR BIDS

(Construction Form RA-1)

Rivanna Water and Sewer Authority Charlottesville, VA

South Rivanna Water Treatment Plant – Flocculator Replacement Charlottesville, Virginia

IFB NO: 446 – SRWTP Flocculator Replacement

Project Description:

Replacement of the South Rivanna Water Treatment Plant (SRWTP) Flocculation System. The project includes replacement of the three (3) flocculators, associated concrete supports, FRP baffle walls, flocculator drive motors, sprockets and chains as well as and VFD’s as well as integration of additional Input/Outputs (I/O) into the SCADA system.

Due Date for Bids: Bids will be received and opened on August 31st, 2026 at 3 pm at the Rivanna Administration Building, 697 Moores Creek Lane, Charlottesville, VA 22902-9016, or by 3 pm for those submitting electronic bids via eVA’s electronic bidding system at https://eva.virginia.gov/index.html

Non-Mandatory Online Pre-Bid Meeting: August 11th, 11:00 am (EST) Meeting URL: bit.ly/IFB446 Meeting ID: 215 791 738 410 851 Passcode: q8dT7MX6

RWSA and SEH will coordinate a site visit for prospective bidders after the pre-bid meeting.

Additional questions shall be directed to Nate Nickerson (nnickerson@sehinc.com) with copies to David White (dwhite@rivanna.org).

Short Elliot Hendrickson Inc.

400 Locust Avenue, Suite 2 Charlottesville, VA 22902

DATE: July 31, 2026 https://eva.virginia.gov/index.html https://bit.ly/IFB446 mailto:nnickerson@sehinc.com mailto:dwhite@rivanna.org

RA-1a

11/27/2023 Rev 7/8/2026

INSTRUCTIONS TO BIDDERS

(Construction Form RA-1a)

The Invitation For Bids (“IFB”) consists of these Instructions To Bidders, the Bid Form, the General Conditions of the Construction Contract, the Supplemental General Conditions (if any), the Special Conditions (if any), the Forms to be used, and the Scope of Work as described by the Plans and Specifications, other documents listed in the Specifications, and any addenda which may be issued, all of which request qualified bidders to submit competitive prices or bids for providing the described work of the Contract.

As used herein, the terms “bidder” and “Contractor” both shall refer to the Person submitting a bid.

1. CONDITIONS AT SITE OR STRUCTURE: Bidders shall visit the Site and shall be responsible for ascertaining pertinent local conditions such as location, accessibility, general character of the Site, structure or building, and the character and extent of existing conditions, improvements or work within or adjacent to the Site. No Claims shall be submitted as a result of Bidder’s failure to have done so, but shall be deemed waived and will not be considered by the Owner. See Section 7 of the General Conditions entitled "Conditions at Site."

2. EXPLANATIONS TO BIDDERS: No oral explanation in regard to the meaning of drawings and specifications will be made and no oral instructions will be given before the award of the Contract. The Owner shall not be responsible for any conclusions, assumptions or interpretations made by bidders during the preparation of bids that are contrary to the Drawings and Specifications and their clear intent. Discrepancies, conflicts, errors, omissions or doubts as to the meaning of the Contract Documents shall be communicated in writing to the A/E for interpretation. Bidders must so act to assure that questions reach the A/E at least six (6) calendar days prior to the time set for the receipt of bids to allow a sufficient time for an addendum to reach all bidders before the submission of their bids. If, however, there are two (2) weeks or less between the first bid advertisement and the time set for receipt of bids, then bidders must submit questions so that they reach the A/E no later than three (3) business days prior to the time set for receipt of bids. Any interpretation made will be in the form of an addendum which will be forwarded to all bidders, and its receipt shall be acknowledged by the bidder on Bid Forms. If such discrepancies, conflicts, errors, omissions or doubts are reasonably apparent or should have been reasonably apparent to the bidder, and the bidder failed to submit questions to the A/E in the time and manner required herein and the Contract is awarded to the bidder, then any claims shall be deemed waived and the bidder shall not be entitled to additional compensation or time, or entitled to sue the Owner based on such discrepancies, conflicts, errors, omissions, or doubts.

3. TIME FOR COMPLETION:

(a) "Time for Completion" shall be designated by the Owner on the Invitation for Bids or other prebid documents and shall mean the number of consecutive calendar days

11/27/2023 Rev 7/8/2026 following the issuance of the Notice to Proceed which the Contractor has to substantially complete all Work required by the Contract. In some instances, the Time for Completion may be stated in the form of a Contract Completion Date based on a stipulated date of Notice to Proceed.

Unless otherwise specified, the Contractor shall achieve Final Completion within thirty (30) calendar days after the date of Substantial Completion.

(b) When the Notice to Proceed is issued, it will state a Contract Completion Date, which has been set by the Owner based on date of the Notice to Proceed and the Time for Completion.

(c) The Contractor, in preparing and submitting its bid, is required to take into consideration adverse weather conditions specified in General Conditions Section 6.

4. PREPARATION AND SUBMISSION OF BIDS:

(a) Bids shall be submitted on the forms furnished, or copies thereof, and shall be signed in ink. Erasures or other changes in a bid must be explained or noted over the signature of the bidder. Bids containing any conditions, omissions, unexplained erasures, alterations or items not called for in the proposal, or irregularities of any kind, may be rejected by the Owner, in its sole discretion, as being incomplete or nonresponsive.

(b) Each bid must give the complete legal name and full business address of the bidder and be signed by the bidder, or the bidder's authorized representative. Bids by partnerships must be signed in the partnership name by one of the general partners of the partnership or an authorized representative, followed by the designation/title of the person signing, and a list of the partners. Bids by joint ventures must be signed in the joint venture name by one of the joint venturers or an authorized representative of one of the joint venturers, followed by the designation/title of the person signing, and a list of the joint venturers. Bids by corporations must be signed with the legal name of the corporation followed by the name of the state in which it is incorporated and by the signature and title of the person authorized to bind it in this matter. The name of each person signing shall be typed or printed below the signature. A signature on a bid by a person who identifies their title as "President," "Secretary," "Agent" or other designation without disclosing the principal firm, shall be held to be the bid of the individual signing. When requested by the Owner, satisfactory evidence of the authority of the officer signing on behalf of the corporation shall be furnished. Trade or fictitious names may be referenced by using "t/a _ _ _ ," but bids shall be in the legal name of the person or entity submitting the bid.

(c) Bids with the bid guarantee shall be enclosed in a sealed envelope which shall be

11/27/2023 Rev 7/8/2026 marked and addressed as indicated by the advertisement. NOTE: For bidders submitting electronic bids via eVA’s electronic bidding system, security for bid bonds must be submitted to the on premises address noted within the specific IFB by the bid due date. If a Contract is for one hundred fifty thousand dollars ($150,000) or more, or if the total value of all construction, removal, repair or improvements undertaken by the bidder within any twelve-month period is one million dollars ($1,000,000) or more, the bidder is required under Code of Virginia §§ 54.1-1100, et seq., to be licensed in Virginia as a "Class A Contractor." If a Contract is for thirty thousand dollars ($30,000) or more, but less than one hundred fifty thousand dollars ($150,000), or if the total value of all construction, removal, repair or improvements undertaken by the bidder within any twelve-month period is two hundred fifty thousand dollars ($250,000) or more, but less than one million dollars ($1,000,000), the bidder is required to be licensed in Virginia as a "Class B Contractor." The bidder shall place on the outside of the envelope containing the bid and shall place in the bid over its signature whichever of the following notations is appropriate and insert its Contractor license/registration number:

Licensed Class A Virginia Contractor No.

or Licensed Class B Virginia Contractor No.

If the bidder is not properly licensed in Virginia at the time the bid is submitted, or if the bidder fails to provide this information on its bid or on the envelope containing the bid and fails to promptly provide said Contractor license number to the Owner in writing when requested to do so before the opening of bids, the bidder shall be deemed to be in violation of Code of Virginia § 54.1-1115 and its bid will not be considered.

(d) The bidder must place its Employer Identification Number (SSN or FEIN) in the space provided on the Bid Form.

(e) Every bidder organized as a stock or nonstock corporation, limited liability company, business trust, or limited partnership or registered as a registered limited liability partnership must be authorized to transact business in the Commonwealth as a domestic or foreign business entity if so required by Title 13.1 or Title 50 of the Code of Virginia, as amended, or as otherwise required by law. Any bidder organized or authorized to transact business in the Commonwealth pursuant to Title

13.1 or Title 50 must include in its bid the identification number issued to it by the State Corporation Commission. Any bidder that is not required to be authorized to transact business in the Commonwealth as a foreign business entity under Title 13.1 or Title 50 or as otherwise required by law shall include in its bid or proposal a statement describing why the bidder is not required to be so authorized. A bidder required to be authorized to transact business in Virginia that fails to provide the required information shall not receive an award unless a waiver of this requirement and of any administrative policies and procedures established to implement Code of Virginia § 2.2-4311.2 is granted by the chief executive of the Owner.

11/27/2023 Rev 7/8/2026

If awarded the Contract, the bidder shall not allow its existence to lapse or its certificate of authority or registration to transact business in the Commonwealth, if so required under Title 13.1 or Title 50, to be revoked or cancelled at any time during the term of the Contract. Doing so shall be deemed to be a violation of Code of Virginia § 2.2-4311.2 and the bidder understands and agrees that the Owner may void the Contract if the bidder fails to comply with this provision.

(f) Code of Virginia, § 2.2-4376.2 shall be applicable to the Work of the Contract.

5. BID GUARANTEE:

(a) Any bid (including the Total Base Bid plus all Additive Bid Items) which exceeds five hundred thousand dollars ($500,000) shall be accompanied by a Standard Bid Bond, Form RA-1d, payable to the Owner as obligee in an amount equal to five percent (5%) of the amount of the bid (the “Bid Bond”).

NOTE: For bidders submitting electronic bids via eVA’s electronic bidding system, security for bid bonds must be submitted to the on-premises address noted within the specific IFB if they do not qualify for the following: The Owner agrees to accept a Bid Bond on which the Surety has utilized electronic signatures and/or electronic notarization if the electronic notarization meets the requirements of Virginia Code §§ 47.1-6.1, -7, and -12, and the Commonwealth of Virginia State Corporation Commission Bureau of Insurance and the Bid Bond contains any SURETY BOND SEAL ADDENDUM established by the Commonwealth of Virginia State Corporation Commission Bureau of Insurance.

The Bid Bond must be issued by a surety company which is legally authorized by the Virginia State Corporation Commission to do surety business in the Commonwealth of Virginia. Such Bid Bond shall guarantee the following: that the bidder will not withdraw its bid during the sixty (60) day period following the date of the opening of bids; that if the bid is accepted, the bidder will enter into the Contract with the Owner described in the IFB; that the bidder can and will submit a properly executed and authorized Standard Performance Bond and Standard Labor and Material Payment Bond on the forms included in the IFB. If the bidder withdraws its bid within the sixty (60) day period following bid opening, fails to enter into the Contract, or fails to provide the required Standard Performance Bond and Standard Labor and Material Payment Bond within ten (10) days after the bidder’s receipt of notice of acceptance of its bid, the bidder and the bidder’s surety shall be jointly and severally be liable to the Owner for the difference between the amount specified in the bidder’s bid and such larger amount for which the Owner may contract with another party to perform the work covered by said bid, up to the amount of the bid guarantee of 5% of the bidder’s total bid amount, as the damage to the Owner resulting from the bidder’s default. See Code of Virginia §2.2-4336.

(b) Code of Virginia § 2.2-4338 contains provisions allowing for alternative forms of bid security in lieu of a Bid Bond. A bidder’s use of an alternative form of Security as listed

11/27/2023 Rev 7/8/2026 in Code of Virginia § 2.2-4338.B must be approved by the Owner prior to the bidder’s submission of its bid on the Bid Receipt date and time to be accepted in lieu of a Bid Bond.

(c) The Bid Bond or other alternative bid security will be returned to all but the three lowest bidders after the formal opening of bids. The remaining Bid Bonds or bid security will be returned to the bidders after the Owner and the accepted bidder have executed the Contract and the required Standard Performance Bond and the Standard Labor and Material Payment Bond for the Contract have been received and approved by the Owner.

(d) If the Contract and required bonds have not been executed by the accepted bidder within sixty (60) days after the date of the opening of the bids, then the Bid Bond or other bid security of any bidder will be returned upon a bidder’s request, provided the bidder has not been notified of the acceptance of its bid prior to the date of such request.

6. WITHDRAWAL OR MODIFICATION OF BIDS: Bids may be withdrawn or modified by written or telefaxed notice received at the designated location from bidders prior to the deadline fixed for bid receipt, or the bidder shall give notice in writing of his claim of right to withdraw his bid within two business days after the conclusion of the bid opening procedure and shall submit original work papers with such notice. E-mail withdrawals and modifications are not acceptable. The withdrawal or modification may be made by the person who signed the bid or by an individual(s) who is authorized by the bidder on the face of the bid. Written modifications may be made on the bid form itself, on the envelope in which the bid is enclosed, or on a separate document. Written modifications, whether the original is delivered or telefaxed, must be signed by the person making the modification or withdrawal. The modification must state specifically what is to be modified and by what amount or it must state the item to be modified and what the corrected amount should be.

7. RECEIPT OF BIDS:

(a) Bids will be received at or before the date and time stated within the bid documents by one of two different methods:

Mail/Hand Delivery: On premises at the address noted within this notice at the time (local) and date noted within this notice.

or

Electronic: Invitation for Bids will be posted to the eVA site where potential vendors may submit electronically their bids to the Authority through the eVA site*.

*-Prospective bidders who use the eVA site must register through that site. This https://eva.virginia.gov/index.html

11/27/2023 Rev 7/8/2026 site is managed by the Commonwealth of Virginia, Department of Purchase and Supply (New Supplier Registration Guide). Rivanna Water & Sewer Authority does not maintain this site or have any input or control over the registration process. Once the bid due date and time has been reached, the Authority will first read the bids that were properly received on premises. Second, the Authority will then open the electronic bids and read them aloud.

(b) It is the responsibility of the bidder to assure that its bid and any bid modifications are delivered to the place designated for receipt of bids by the date and hour (deadline) set for receipt of bids. Therefore, it is the bidder’s responsibility to take into account all factors which may impact on its bid deliverer / courier’s ability to deliver the bid and to implement whatever actions are necessary to have the bid delivered to the proper bid receipt location prior to the bid receipt deadline. No bids or bid modifications submitted or offered after the date and hour designated for receipt of bids will be accepted or considered.

(c) The Bid Officer is the Owner's representative designated to receive bids at the time and place noted in the IFB and to open the bids received at the appointed time.

(d) The official time used for the receipt of responses is determined by reference to the clock designated by the Bid Officer. The Bid Officer shall determine when the Bid Receipt Deadline has arrived and shall announce that the Deadline has arrived and that no further bids or bid modifications will be accepted. All bids and bid modifications in the possession of the Bid Officer and their assistants at the time the announcement is completed are deemed to be timely, whether or not the bid envelope has been physically date/time stamped or otherwise marked by the time the Bid Officer makes the deadline announcement.

(e) In the event the bid receipt occurs during a period of suspended Rivanna business operations, the receipt and opening will be delayed one business day.

8. OPENING OF BIDS:

(a) Bids will be opened at the time and place stated in the IFB or as modified by subsequent Addenda, and their contents publicly announced. The Bid Officer shall decide when the specified time for bid opening has arrived. No responsibility will be attached to any officer or agent for the premature opening of a bid not properly addressed and identified.

(b) The provisions of Code of Virginia § 2.2-4342, as amended, shall be applicable to the inspections of bids received.

(c) In the event the bid opening date occurs during a period of suspended Rivanna business operations, the opening will be delayed until the next business day at the same time.

https://dgs.virginia.gov/globalassets/business-units/dps/documents/vendors/newsupplierregistrationqrg101922pdf.pdf

11/27/2023 Rev 7/8/2026

9. ERRORS IN BIDS: A bidder may withdraw its bid from consideration if the price bid was substantially lower than the other bids due solely to a mistake therein, provided the bid was submitted in good faith, and the mistake was a clerical mistake as opposed to a judgment mistake, and was actually due to an unintentional arithmetic error or an unintentional omission of a quantity of work, labor or material made directly in the compilation of a bid, which unintentional arithmetic error or unintentional omission can be clearly shown by objective evidence drawn from inspection of original work papers, documents and materials used in the preparation of the bid sought to be withdrawn.

In accordance with Code of Virginia § 2.2-4330(B)(2), to withdraw its bid the bidder must submit to the Owner its original work papers, documents and materials used in the preparation of the bid within two (2) business days after the opening of bids. Such work papers must be submitted in an envelope or package separate and apart from the envelope containing the bid and marked clearly as to the contents and shall be delivered to the Owner by the bidder in person or by registered mail. The bids shall be opened at the time designated in the IFB, as amended by addendum. Once the bids have been opened, the bidder shall have two (2) business days after the opening of bids within which to claim in writing any mistake as defined herein and withdraw its bid. The Contract shall not be awarded by the Owner until such two-day period has elapsed. Such mistake shall be proved only from the original work papers, documents and materials delivered to the Owner. This procedure in Code of Virginia § 2.2-4330(B)(2) shall not apply to when the entire bid is required to be submitted on a unit price basis.

Failure of a bidder to submit its original work papers, documents and materials used in the preparation of its bid shall constitute a waiver by that bidder of its right to withdraw its bid due to a mistake. No bid may be withdrawn under this section when the result would be the awarding of the Contract on another bid of the same bidder or of another bidder in which the ownership of the withdrawing bidder is more than five (5%) percent.

No bidder who is permitted to withdraw a bid shall, for compensation, supply any material or labor to or perform any subcontract or other work agreement for the person or firm to whom the Contract is awarded or otherwise benefit, directly or indirectly, from the performance of the project for which the withdrawn bid was submitted. The person or firm to whom the Contract was awarded and the withdrawing bidder are jointly liable to the Owner in an amount equal to any compensation paid to or for the benefit of the withdrawing bidder without such approval.

If the apparent low bid is withdrawn under authority of this section, the lowest remaining bid shall be deemed to be the low bid on the project.

10. REJECTION OF BIDS: The Owner reserves the right to cancel the IFB, to reject any and all bids at its sole discretion when such rejection is in the interest of the Owner, or to reject the bid of any bidder who is determined to be not responsive or not responsible. See Code of Virginia § 2.2-4319.

11/27/2023 Rev 7/8/2026

11. DETERMINATION OF RESPONSIBILITY

Each bidder shall be prepared, if so requested by the Owner, to present evidence of its experience, qualifications and financial ability to carry out the terms of the Contract.

Prior to award of the Contract, an evaluation will be made to determine if the low bidder has the capability, in all respects, to perform fully the contract requirements and the moral and business integrity and reliability which will assure good faith performance, and who has been prequalified, if required. Factors to be evaluated include, but are not limited to:

(a) sufficient financial ability to perform the contract as evidenced by the bidder's ability to obtain payment and performance bonds from an acceptable surety;

(b) appropriate experience to perform the Work described in the bid documents;

(c) any judgments entered against the bidder, or any officers, directors, partners or owners for breach of a contract for construction;

(d) any substantial noncompliance with the terms and conditions of prior construction contracts with a public body without good cause where the substantial noncompliance is documented; or

(e) a conviction of the bidder or any officer, director, partner, project manager, procurement manager, chief financial officer, or owner in the last five years of a crime relating to governmental or nongovernmental construction or contracting;

and/or

(f) any current debarment of the contractor, any officer, director or owner, from bidding or contracting by any public body of any state, any state agency, or any agency of the federal government.

The Owner reserves the right to disqualify or refuse to accept the bid of any bidder who has been convicted, or entered a plea of guilty or nolo contendere, in any federal or state court to any charge involving any unlawful, corrupt or collusive practice involving a public contract whether federal, state, or local, or who has been determined in any judicial proceeding to have violated any antitrust, bid-rigging or collusive practice statute in connection with any public contract, or against whom such formal criminal prosecution or other judicial proceeding has been initiated.

A bidder who, despite being the apparent low bidder, is determined not to be a responsible bidder shall be notified in writing in conformance with the procedures in Code of Virginia § 2.2-4359.

12. AWARD OF CONTRACT

(a) Basis for Contract Award: The Contract, if awarded, will be awarded to the lowest responsive and responsible bidder, if any, provided its bid is reasonable and it is in the best interest of the Owner to accept it and subject to the Owner's right to reject any and all bids and to waive informality in the bids and in the bidding. The Bid Form may contain a multi-part Base Bid and may contain Additive Bid Items.

11/27/2023 Rev 7/8/2026

Determination of the lowest responsible bidder, if any, will be based on the Total Base Bid Amount entered on the Bid Form including any properly submitted bid modifications plus as many Additive Bid Items taken in sequence as the Owner in its discretion chooses to Award in the best interest of the Owner. Where the sum of the values entered in the multiple parts do not agree with the Total Base Bid amount, the written Total Base Bid Amount entered on the bid form including any properly submitted bid modifications shall take precedence over the numerical Total Base Bid Amount.

In the event that the Total Base Bid from the lowest responsible bidder exceeds available funds, the Owner may negotiate the Total Base Bid amount with the apparent low bidder to obtain a Contract Price within available funds, pursuant to Code § 2.2-4318 and Section 12(c) herein.

(b) Informalities: The Owner reserves the right to waive any informality in the bids when such waiver is in the interest of the Owner.

(c) Negotiation With Lowest Responsible Bidder: If award of the Contract to the lowest responsive and responsible bidder is precluded because of limitations on available funds, under the provisions of Code § 2.2-4318 the Owner reserves the right to negotiate the Total Base Bid amount with the lowest responsive, responsible bidder to obtain a Contract Price within the available funds. This may involve changes in either the features or scope of the work included in the Base Bid. Such negotiations with the apparent low bidder may include reducing the quantity, quality, or other cost saving mechanisms involving items in the Total Base Bid.

Negotiations for Additive Bid Items are excluded. The Owner shall notify the lowest responsive and responsible bidder that such a situation exists and the Owner and bidder shall then conduct their negotiations in person, by mail, by telephone or by any means they find convenient. If an acceptable Contract can be negotiated, any changes to the IFB documents agreed upon in the negotiations shall be summarized in a "Post Bid Modification" and included in the Contract. If an acceptable Contract cannot be negotiated, the Owner shall terminate negotiations and reject all bids.

(d) Notice of Intent to Award or Notice of Award: The “Notice of Intent to Award” or the “Notice of Award” will be posted at the Owner’s standard location for posting notices such as the Owner’s Website. Any bidder who desires to protest the award or decision to award a contract shall submit the protest in writing to the public body no later than ten days after the posting of the Notice of Award or Notice of Intent to Award, whichever comes first. See Code of Virginia § 2.2-4360.

13. CONTRACT SECURITY: For contracts which exceed five hundred thousand dollars ($500,000), the Standard Performance Bond (RA-2a) and the Standard Labor and Material Payment Bond (RA-2b) shall be required, as specified in the IFB. For construction contracts up to $500,000, where Bid Bond requirements are waived, prospective contractors may be prequalified in accordance with Code of Virginia § 2.2-4317. See General Conditions and Code of Virginia § 2.2-4337 and § 2.2-4338. The Owner reserves

11/27/2023 Rev 7/8/2026 the right to require such bonds for contracts up to five hundred thousand dollars ($500,000).

If the Owner so elects, the requirement shall be set forth in the IFB.

14. CERTIFICATION: The bidder, by its signature on the Bid Form, certifies that neither its organization nor any of its officers, directors, partners or owners is currently barred from bidding on contracts by any public body or agency of another state, or any agency of the federal government. See "Disqualification of Contractors" in the Bid Form.

15. ETHICS IN PUBLIC CONTRACTING: The provisions, requirements and prohibitions as contained in Code of Virginia §2.2-4367 et seq., pertaining to bidders, offerors, contractors, and subcontractors are applicable to this project.

16. BUILDING PERMITS: The Virginia Uniform Statewide Building Code shall apply to the Work and shall be administered by the Building Official. The Building Permit will be obtained and paid for by the Contractor. All other permits, local license fees, business fees, taxes, or similar assessments imposed by the appropriate political subdivision shall be obtained and paid for by the Contractor. See Section 25 of the General Conditions for utility connection fees and services.

17. BID DOCUMENTS: Bid Documents are the property of the Owner and a deposit in an amount as stated in the Invitation for Bids is required for each paper set or for each set provided on removable electronic media as a guarantee of the safe return of the documents within ten (10) days of bid opening. This deposit will be refunded in full on not more than two paper sets or sets provided on removable electronic media to each bidder who submits a Contract bid and who returns the documents in good condition. Refund will be made on paper sets and sets provided on removable electronic media to non-bidders and Subcontractors in the amount of half of the deposit when the sets are returned in good condition within 10 days. A deposit is not required for downloading of electronic construction documents through an FTP site. A non-refundable shipping charge may be required for paper sets or sets provided on removable electronic media if stated in the Notice or the IFB.

18. GENERAL CONDITIONS: The General Conditions are incorporated in the bid documents. If a copy of the General Conditions is not included in the bid documents, the bidder may obtain a copy of the current edition of the General Conditions at no cost by written request to the A/E and/or the Owner.

19. PREBID CONFERENCE: See the IFB for requirements for a prebid conference and whether such conference is mandatory or optional.

20. INSPECTION OF BID DOCUMENTS: Copies of the IFB documents including Plans and Specifications and the General Conditions will be available for inspection at the locations listed in the Notice of the IFB.

21. DRUG-FREE WORKPLACE REQUIRED: Bidders are reminded that Code of Virginia § 2.2-4312 requires that the during the performance of the Contract resulting from this

11/27/2023 Rev 7/8/2026 solicitation, the Contractor agrees to: (i) provide a drug-free workplace for the Contractor's employees; (ii) post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in the Contractor's workplace and specifying the actions that will be taken against employees for violations of such prohibition; (iii) state in all solicitations or advertisements for employees placed by or on behalf of the Contractor that the Contractor maintains a drug-free workplace; and (iv) include the provisions of the foregoing clauses in every Subcontract or purchase order of over $10,000, so that the provisions will be binding upon each Subcontractor or vendor.

For the purposes of this section, "drug-free workplace" means a site for the performance of work done in connection with a specific Contract awarded to a Contractor in accordance with this solicitation, the employees of whom are prohibited from engaging in the unlawful manufacture, sale, distribution, dispensation, possession or use of any controlled substance or marijuana during the performance of the contract.

Existing Condition Information

RIVAN 189203 00 31 19 - 1

DOCUMENT 00 31 19

EXISTING CONDITION INFORMATION

PART 1 GENERAL

1.01 FLOCCULATOR BAFFLE WALL INFORMATION

A. Product data and preliminary shop drawings of the existing FRP baffle wall assemblies in Flocculators No.1 and No. 2 that are to be removed and re-installed are provided for Bidders’ information. Bidder should be cognizant that the provided drawings do not reflect as-built or record drawings. Contractor shall be responsible for verifying existing baffle wall installation and dimensions.

B. The attached shop drawings titled: Section 00 31 19a – Existing Baffle Wall Details.

END OF SECTION

FRP Water & Wastewater Systems

2.75”

8” 8” 8”

24” Cover

1⁄4”

Enduro “H” Structural Baffl e & Partition Wall

As a global leader for FRP structural systems, En-duro developed the “H” Series baffl e panel and the innovative SlideGuide assembly system.

The 1⁄4” thick, Enduro “H” series are the strongest FRP baffl e panels available and are utilized in both bolted and non-bolted installations. In the Slide- Guide system, the “H” baffl e panels, which do not require fastening, are inserted between and held in place by FRP angles. With a long and proven track record of outstanding performance, the Enduro “H” series and SlideGuide assembly has led a move-ment away from concrete and wood to the Enduro FRP baffl e system.

System Overview

Enduro “H” slotted fl ow-thru baffl e wall system Settling Basin

Typical Details

Baffl e Panel Stacking

SlideGuide Concrete Wall SlideGuide 12S12 FRP Column

FRP Angle

SS adhesive anchor

H series baffl e

Bolted 12F12 FRP Column Bolted 12S12 FRP Column

H series baffl e

FRP column

H series baffl e H series baffl e

FRP column

H series baffl e

H series baffl e FRP column

SS bolt with nut & washer

H series baffl e

FRP column

SS bolt with nut & washer

Enduro FRP Water & Wastewater Systems Catalog_FINAL_02_08-24-10.indd 20 5/8/2011 11:37:40 AM

Section 00 31 19a - EXISTING BAFFLE WALL DETAILS

Enduro “H” Structural Baffl e & Partition Wall

Part 1 – General

1.01 Description of Work

The scope of this specifi cation shall include materials for the fi berglass reinforced plastic (FRP) Baffl e Wall System including FRP baffl e wall panels; FRP columns; FRP angles; column base plates/angles; fasteners and connections.

1.02 Design Criteria

A. Design Load (greater of water differential or wind load)

1. Water Differential: _____ in. (uniform load over wall)

2. Wind Load: _____ lbs./SF uniform load

B. Defl ection Limit and Factor of Safety

1. Baffl e Panels: L/D=_____; Max Defl =Panel Depth;

FOS = 2.0

2. Columns: L/D=100; FOS=2.5

Part 2 – Products

2.01 Manufacturer

Standard for design, characteristics, and performance is Enduro H Series Baffl e Wall manufactured by Enduro Systems, Inc.

2.02 Materials

A. FRP Baffl e Panels, Columns, and Angles

1. FRP baffl e panels, columns, angles, and associated comp-onents shall be ANSI/NSF Standard 61 certifi ed for potable water application (as required).

2. FRP Baffl e Panels shall exhibit these minimum properties:

Stiffness (EI) 1,780,000 lb-in2/ft Moment Capacity 39,200 lb-in/ft

3. FRP structural materials shall exhibit these minimum prop-erties:

Tensile Strength 48,000 psi ASTM D 638 Flexural Strength 58,000 psi ASTM D 790 Flexural Modulus 2,000,000 psi ASTM D 790 Izod Impact (Notched) 25 ASTM D 256 Water Absorption .25% maximum ASTM D 570

4. FRP Materials shall include UV stabilized polyester resin;

surfacing veil at top and bottom sides; gray color.

5. Factory cut edges and drilled holes shall be sealed with ANSI/NSF approved material.

6. FRP baffl e panels shall be Enduro Series H, 2.75 x .25 profi le; 2.75” depth; 1⁄4” nominal thickness; 50% glass fi ber reinforcing (by wt.); with top, horizontal ribs sloped downward not less than 10 degrees to minimize sediment build-up.

7. FRP Columns shall be Enduro Type ________ with 50% glass fi ber reinforcing (by wt.). Column base plates or angles shall be 304/316 Stainless Steel.

8. FRP Angles shall be 3⁄8” thick and 90 degrees.

B. Hardware

1. Fasteners, anchors, and other structural hardware shall be 304/316 Stainless Steel.

2. Submerged anchors shall be epoxy adhesive type.

For expanded specifi cation, please contact us.

Specifi cation: Fiberglass Reinforced Plastic Baffl e Wall - H Series

Maximum spans are based on non-fi xed connection with panels being restrained by SlideGuide angles on each side.

Please contact Enduro for Load/Span data with a bolted H Series installation.

Load Span Table

Water Differential 2” 3” 4” 5” 6” 8” 10” 12” Uniform Load 10.4 psf 15.6 psf 20.8 psf 26.0 psf 31.2 psf 41.6 psf 52.0 psf 62.4 psf

Span (Ft) L/D FOS L/D FOS L/D FOS L/D FOS L/D FOS L/D FOS L/D FOS L/D FOS 9 >360 >6 >360 >6 >360 >6 >360 >6 >360 >6 309 >6 247 >6 206 5.2 10 >360 >6 >360 >6 >360 >6 >360 >6 300 >6 225 >6 180 5.0 150 4.2 11 >360 >6 >360 >6 339 >6 271 >6 226 >6 169 5.2 135 4.2 113 3.5 12 >360 >6 348 >6 261 >6 209 >6 174 5.8 130 4.4 104 3.5 13 >360 >6 273 >6 205 >6 164 5.9 137 5.1 103 3.7 14 328 >6 219 >6 164 >6 131 5.1 109 4.5 15 267 >6 178 >6 134 5.6 107 4.5 16 220 >6 147 >6 110 4.9 17 183 >6 122 5.8 92 4.3 18 155 >6 103 5.2

19 131 >6 10 113 >6 21 97 5.7

Enduro FRP Water & Wastewater Systems Catalog_FINAL_02_08-24-10.indd 21 5/8/2011 11:38:18 AM

FRP Technical Data

Corrosion Resistance - Resin Systems Typical Properties of Structural FRP Two standard composite resin systems are available. For most applica-tions, isophthalic polyester fire-retardant (FR-P) is the more widely used. A vinyl ester composite fire-retardant resin system (FR-VE) is recommended where strong acids (such as hydrochloric acid), strong alkalies (such as caustic soda), organic solvents and halogenated organic conditions exist.

An abbreviated Guide is provided below to assist in the selection of the proper resin system for individual application.

FR = Fire-Retardant;

P = Polyester Resin;

VE = Vinyl Ester Resin;

(*) = Not recommended to exceed this temperature;

Call = Call for recommendations.

Chemicals 75°F 160°F Acetic Acid 5% FR-P FR-P Acetic Acid 25% FR-P FR-VE-210° (*) Ammonium Hydroxide 10% FR-P FR-VE-150° Ammonium Nitrate FR-P FR-P Calcium Chloride FR-P FR-P Chlorine Dioxide 15% FR-P FR-VE-150° (*) Chromic Acid 5% FR-P FR-VE-150° (*Call) Diesel Fuel No.1 FR-P FR-P Diesel Fuel No. 2 FR-P FR-P Ethylene Glycol FR-P FR-P Fatty Acids 100% FR-P FR-P Ferric Chloride FR-P FR-VE Hydrochloric Acid 1% FR-P FR-P Hydrochloric Acid 15% FR-P FR-VE-180° (*) Hydrochloric Acid 37% FR-P FR-VE-150° (*) Hydrogen Sulfide FR-P-140° FR-VE-210° Magnesium Chloride FR-P FR-P Methyl Alcohol 10% FR-P FR-VE-150° (*) Nitric Acid 5% FR-P FR-P Nitric Acid 20% FR-VE FR-VE-120° (*) Phosphoric Acid 10% FR-P FR-P Phosphoric Acid 30% FR-P FR-P Phosphoric Acid 85% FR-P FR-P Sodium Bicarbonate 10% FR-P FR-P Sodium Bisulfate FR-P FR-P Sodium Carbonate FR-P FR-VE Sodium Chloride FR-P FR-P Sodium Hydroxide 1-50% FR-VE FR-VE-120° (*) Sodium Hypochlorite 5% FR-P FR-VE-120° (*) Sulfuric Acid 0-30% FR-P FR-P Sulfuric Acid 30-50% FR-VE FR-VE Sulfuric Acid 50-70% FR-VE FR-VE-180° (*)

Mechanical (coupon) FR-P FR-VE Logitudinal Direction Ultimate Tensile Strength, PSI (ASTM D638) 42,000 42,000 Ultimate Compressive Strength, PSI (ASTM D695) 37,000 37,000 Ultimate Flexural Strength, PSI (ASTM D790) 32,000 35,000 Tensile Modulus, PSI x 106 2.5 3.0 Compressive Modulus, PSI x 106 2.5 2.5 Flexural Modulus, PSI x 106 1.6 2.0 Ultimate Shear Strength, PSI 5,500 7,000 Ultimate Bearing Stress, PSI 30,000 35,000 Izod Impact Strength, Ft.-Lbs. per inch of notch (ASTM D256) (sample thickness 1⁄8” except 1⁄4” for rod) 25 30 Electrical Electric Strength, short term in oil, 1⁄8”, vpm (ASTM D149)* 200 200 Electric Strength, short term in oil, KV per inch 35 35 Dielectric Constant, 60 Hz. (ASTM D150)* 5.6 5.2 Dissipation Factor, 60 Hz. (ASTM D150)* 0.03 0.03 Arc Resistance, seconds (ASTM D495)** 120 120 Fire Retardant Properties Flame Resistance, ign/burn, seconds (FTMS 406-2023) 75/75 75/75 Intermittent Flame Test, rating (HLT-15) 100 100 Flammability Test, (ASTM D635)

Surface Burning Characteristics, maximum (ASTM E84) 15 15 Transverse Direction Ultimate Tensile Strength, PSI 7,000 10,000 Ultimate Compressive Strength, PSI 15,000 20,000 Ultimate Flexural Strength, PSI 10,000 14,000 Tensile Modulus, PSI x 106 0.8 1.0 Compressive Modulus, PSI x 106 1.0 1.2 Flexural Modulus, PSI x 106 0.8 1.0 Ultimate Shear Strength, PSI 5,500 6,000 Ultimate Bearing Stress, PSI 30,000 35,000 Izod Impact Strength, Ft.-Lbs. per inch of notch (ASTM D256) 4 5 Barcol Hardness (ASTM D2583-75) 50 50 Full Section in Bending Modulus of Elasticity, PSI x 106 2.5 3.0 Tensile Strength, PSI 20,000 25,000 Compressive Strength, PSI 20,000 25,000 Thermal Thermal Coefficient of Expansion, Inches/Inch/°F (ASTM D696)** 5 x 10-6 5 x 10-6

Thermal Conductivity, BTU per Sq. Ft./Ht./ °F/In. (ASTM C-1776-76) 4 4 Specific Heat, BTU/Lb/°F 0.28 0.28 Other Density, Lbs./In.3 (ASTM D792) 0.065 0.065 Specific Gravity (ASTM D792) 1.80 1.80 Water Absorption, Max. % by weight (24 hour immersion) (ASTM D570) .50 .50 average time of burning 5 seconds, average extent of burning 15mm

* Speciman tested perpendicular to laminate face.

Note: 1 PSI = 6.894 K Pa, 1 Ft.-Lb./In. = 5.443 kg-m/m ** Indicates reported value measured in logitudinal direction.

Note: Depending on the specific glass content and resin, the strength and stiffness properties may be significantly higher.

Bolted Installation

SlideGuide Installation

Information contained in this chart is based on data from raw material suppliers and collected from several years of actual industrial applications. Temperatures are not the minimum nor the maximum (except where specifically stated) but represent standard test conditions. The products may be suitable at higher temperatures, but individual test data should be required to establish such suitability. The recommendations or sug-gestions contained in this chart are made without guarantee or representation as to results. We suggest that you evaluate these recommendations and suggestions in your own laboratory or by actual field trial prior to use.

RELEASED

REV:DRAWN BY: CHK BY: DATE: DWG NO: SHEET:

H.O. NO:

THIS DOCUMENT IN DESIGN AND DETAIL IS

THE PROPERTY OF ENDURO COMPOSITES;

ANY USE OR DISCLOSURE WITHOUT THE

WRITTEN PERMISSION OF ENDURO

COMPOSITES IS STRICTLY FORBIDDEN.

16602 CENTRAL GREEN BLVD. HOUSTON, TX. 77032

PHONE: 713-358-4000 | FAX: 713-358-4100

NOTES:

REVISED BYECO #DATEREV

"H" BAFFLE WALL SYSTEM FOR

OBSERVATORY AND SOUTH RIVANNA

WTP - ALBEMARLE COUNTY, VA

SUBMITTAL DRAWINGS

0054865 0054865-01-001

1 8/13/2020 20200002 M.FLORES

M.FLORES J.CHAISSON 8/13/2020 1

"H" BAFFLE WALL FOR

OBSERVATORY AND SOUTH RIVANNA WTP

ALBEMARLE COUNTY, VA

SUBMITTAL DRAWINGS

1.

GENERAL NOTES:

FOR, THE ACTUAL CONDITION OF EXISTING STRUCTURES THAT SUPPORT THE SYSTEM

AQUASPAN "H" BAFFLE WALLS TO BE PROVIDED IN ACCORDANCE WITH

ENDURO QUOTE NO. 19-112-B REVISION .0

FRP BAFFLE PANEL MATERIALS ARE:2. POLYESTER (NSF) RESIN, AND GRAY OR

CHARCOAL GRAY IN COLOR.

RESIN, AND GRAY ORFRP STRUCTURAL COMPONENTS ARE: POLYESTER (NSF)3.

CHARCOAL GRAY IN COLOR.

STD FABRICATION TOLERANCES (U.N.O.) ARE FOR BAFFLE PANEL LENGTHS: ±1/4";4.

FOR BEAMS/COLUMNS: ±1/8" UP TO 8', ±1/4" UP TO 24' AND ±1/2" ABOVE 24'.

CUSTOMER TO VERIFY ALL DIMENSIONS PRIOR TO ANY FABRICATION.5.

DRAWING SET. APPLY A SEALER TO FIELD CUT EDGES, DRILLED HOLES AND WHERE

EVER ANY SURFACE ABRASIONS HAVE BEEN SUSTAINED DURING THE CONSTRUCTION

PROCESS. ENDURO RECOMMENDS "SHERWIN WILLIAMS DURA PLATE 235PW"

(NSF COMPLIANT MULTI PURPOSE EPOXY PAINT).

CUSTOMER SHALL FIELD DRILL, CUT OR NOTCH COMPONENTS AS DESCRIBED IN THIS6.

OMISSIONS THAT DEVIATE FROM THE SCOPE THAT IS DESCRIBED IN THIS DRAWING SET

MINIMUM CONCRETE STRENGTH = 4,000 PSI IS ASSUMED.

LEVELING, FILLING OR GROUTING OF CONCRETE SURFACES IS TO BE DONE BY OTHERS.

CONCRETE SURFACES SHALL BE SMOOTH, LEVEL AND FREE OF CRACKS AND VOIDS.7.

OR INSTALLATION GUIDELINES FOR EVALUATION AND APPROVAL.

CONTACT ENDURO BEFORE IMPLEMENTING ANY MODIFICATIONS, SUBSTITUTIONS OR8.

INDEPENDENT DETERMINATION OF, AND ACCEPTS NO RESPONSIBILITY OR LIABILITY

OR THE ACTUAL LOADS TO WHICH ENDURO'S COMPONENTS WILL BE SUBJECTED.

CONSISTENT WITH ENDURO'S STATED ASSUMPTIONS. ENDURO DOES NOT MAKE ANY

OTHER CRITERIA SPECIFIED BY THE CUSTOMER OR CUSTOMER'S ENGINEER AND

ENDURO'S BAFFLE WALL COMPONENTS ARE DESIGNED TO MEET THE LOAD CASE AND9.

WIND =

BAFFLE WALL DESIGN LOADS

DESIGN LOAD COMBINATIONS

POS. WATER DIFF. =

L/D RATIO F.O.S.

BAFFLE PANELS:

NEG.

This is the start of the file's text. The full file is on GovTribe.