About this file
This is a Project Manual and Invitation for Bids issued by the Virginia Community College System for the Replace Diggs-Moore-Harrison Complex project at Virginia Peninsula Community College in Hampton, Virginia (Project Code 260-18341-000). The project involves construction of an approximately 75,000 square foot, three-story higher education academic building classified as Type II-B construction with mixed-use occupancies. The building will include a multi-function space, classrooms, offices, a Security Suite, Student Services, President's Suite, and Vice-Presidents' Suites. The sealed bid deadline is 2:00 PM on Wednesday, August 26, 2026, with bid opening at 2:00 PM on Thursday, August 27, 2026. A mandatory pre-bid conference will be held at 1:00 PM on Thursday, August 6, 2026, at Virginia Peninsula Community College's Hampton Campus in the Mary T. Christian Theatre. The contract award will be based on a lump sum basis for the Total Base Bid Amount, which includes Part A (building construction within 5 feet of the building perimeter), Part B (sitework beyond the 5-foot perimeter), and Parts C and D (unit price items for excavation of unsuitable material and rammed aggregate pier systems). The Contractor shall achieve Substantial Completion within 608 consecutive calendar days from the Notice to Proceed, with Final Completion within 30 days thereafter.
Bidders must be registered vendors in eVA and must be licensed by Virginia as either a Class A Contractor (for contracts $120,000 or more) or Class B Contractor (for contracts $10,000-$120,000). A Commonwealth of Virginia Standard Bid Bond equal to 5% of the total bid is required for bids exceeding $500,000, and Standard Performance Bonds and Labor and Material Payment Bonds are required upon contract award. The bid includes a fixed subcontract price of $299,999.00 for access control work (Section 281300) to be performed by Acme Technical Group, LLC, a pre-selected owner's subcontractor. Prevailing wage requirements apply to this project as it exceeds $250,000 in state funding, with wage rates established by the Virginia Department of Labor and Industry effective July 21, 2026. The project documents are available for download through eVA at www.eva.virginia.gov, and bidders are responsible for eVA vendor transaction fees. All bidders must submit a Small Business Procurement Plan identifying the proposed percentage of small business participation in the Total Base Bid Amount.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Virginia Community College System
300 Arboretum Place, Suite 200
Richmond, Virginia 23236
Virginia Peninsula Community College Replace Diggs-Moore-Harrison Complex Hampton, Virginia
Project Manual Volume 1
Division of Engineering and Buildings State Project No.: 260-18341-002
July 17, 2026
RRMM ARCHITECTS, PC
1317 EXECUTIVE BOULEVARD, Suite 200
CHESAPEAKE, VA 23320
T: 757/622-2828 F: 757/622-2430
THIS PAGE INTENTIONALLY LEFT BLANK
VIRGINIA COMMUNITY COLLEGE SYSTEM
VIRGINIA PENINSULA COMMUNITY COLLEGE STATE PROJECT NO. 260-18341-002
REPLACE DIGGS-MOORE-HARRISON COMPLEX RRMM PROJECT NO. 18113-00
TABLE OF CONTENTS 1
TABLE OF CONTENTS
VOLUME 1
CO Form #
BIDDING INFORMATION
Table of Contents ---
Seals ---
Bid Form DGS-30-220
Notice of Invitation to Bid DGS-30-256
Prebid Question Form DGS-30-272
Standard Bid Bond Form CO-10.2
GENERAL CONDITIONS & FORMS
General Conditions of the Construction Contract CO-7
Instructions to Bidders CO-7a
Prevailing Wage Determination from DOLI*
Listing of Required Structural and Special Inspections CO-6a and 6b
Workers Compensation Certificate of Insurance** CO-9a
Standard Performance Bond** CO-10
Standard Labor and Material Payment Bond** CO-10.1
Construction Change Order** CO-11
Change Order Estimate (General Contractor)** GC-1
Change Order Estimate (Subcontractor)** SC-1
Change Order Estimate (Sub-subcontractor)** SS-1
Schedule of Values and Certificate for Payment** CO-12
Affidavit of Payment of Claims** CO-13
Certificate of Completion by Architect/Engineer or Project Manager** CO-13.1
Architect/Engineer’s Certificate of Substantial Completion** CO-13.1a
Final Report of Structural & Special Inspections** CO-13.1b
Certificate of Completion by Contractor** CO-13.2
Certificate of Partial or Substantial Completion by Contractor** CO-13.2a
Submittal Register Format** ---
Special Requirements for Low Slope Roofing Membrane DGS-30-326
VEES Checklist DGS-30-382
Those forms listed above that are followed by ** may be found with the link to the DGS Forms
Center: https://dgs.virginia.gov/search/documents-and-forms/?filter=DEB
ATTACHMENTS
Attachment No. 1 Geotechnical Report
Attachment No. 2 UL Design
Assemblies https://dgs.virginia.gov/search/documents-and-forms/?filter=DEB
TABLE OF CONTENTS 2
SPECIFICATIONS
SECTION
DIVISION 0 – PROCUREMENT AND CONTRACTING REQUIREMENTS
007355 VSMP General Permit for Construction Activities
DIVISION 1 - GENERAL REQUIREMENTS
010100 Drawing Index
011000 Summary
012200 Unit Prices
012500 Substitution Procedures
012600 Contract Modifications Procedures
012900 Payment Procedures
013100 Project Management and Coordination
013200 Construction Progress Documentation
013300 Submittal Procedures
014000 Quality Requirements
014100 Special Inspection Services
014339 Mockups
015000 Temporary Facilities and Controls
016000 Product Requirements
017300 Execution
017419 Construction Waste Management and Disposal
017700 Closeout Procedures
017823 Operation and Maintenance Data
017839 Project Record Documents
017900 Demonstration and Training
018113.33 Sustainable Design Requirements- IgCC
019115 Building Enclosure Commissioning
DIVISION 02 - EXISTING CONDITIONS
This section is not used.
DIVISION 03 - CONCRETE
032000 Concrete Reinforcing
033000 Cast-In-Place Concrete
DIVISION 04 - MASONRY
042000 Unit Masonry
047200 Cast Stone Masonry
TABLE OF CONTENTS 3
DIVISION 05 - METALS
051200 Structural Steel Framing
051213 Architecturally Exposed Structural Steel Framing
052100 Steel Joist Framing
053100 Steel Decking
054000 Cold-Formed Metal Framing
055000 Metal Fabrications
055113 Metal Pan Stairs
055213 Pipe and Tube Railings
057300 Decorative Metal Railings
057313 Glazed Smoke Baffle System
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
061000 Rough Carpentry
061600 Sheathing
064116 Plastic-Laminate-Faced Architectural Cabinets
066400 Plastic Paneling
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
070523 Pressure Testing and Air Barrier System for Air Tightness
070543 Composite Metal Hybrid (CMH) Continuous Insulation Cladding Support Systems
071326 Self-Adhering Sheet Waterproofing
072100 Thermal Insulation
072423 Direct Applied Exterior Finish Systems (EFS)
072726 Fluid-Applied Membrane Air Barriers
074213.13 Formed Metal Wall Panels
074213.23 Metal Composite Material Wall Panels
074243.02 High Pressure Laminate Phenolic Wall Panel System
074293 Soffit Panels
075216 Styrene-Butadiene-Styrene (SBS) Modified Bituminous Membrane Roofing
075419 Polyvinyl-Chloride (PVC) Roofing
076200 Sheet Metal Flashing and Trim
077100 Roof Specialties
077200 Roof Accessories
078100 Applied Fire Protection
078413 Penetration Firestopping
078443 Joint Firestopping
079200 Joint Sealants
079219 Acoustical Joint Sealants
TABLE OF CONTENTS 4
DIVISION 08 - OPENINGS
080671 Door Hardware Schedule
081113 Hollow Metal Doors and Frames
08116.13 Interior Aluminum Doors and Frames
081416 Flush Wood Doors
083113 Access Doors and Frames
083313 Coiling Counter Doors
083323 Overhead Coiling Doors
084113 Aluminum-Framed Entrances and Storefronts
084229.23 Sliding Automatic Entrances
084413 Glazed Aluminum Curtain Walls
085653 Security Windows
087100 Door Hardware
088000 Glazing
088300 Mirrors
089119 Fixed Louvers
DIVISION 09 - FINISHES
090561.13 Moisture Vapor-Emission Control
092116.23 Gypsum Board Shaft Wall Assemblies
092216 Non-Structural Metal Framing
092900 Gypsum Board
093013 Ceramic Tiling
095113 Acoustical Panel Ceilings
096513 Resilient Base and Accessories
096519 Resilient Tile Flooring
096536 Static-Control Resilient Flooring
096623 Resinous Matrix Terrazzo Flooring
096723 Resinous Flooring
096813 Tile Carpeting
098433 Sound-Absorbing Wall Units
099114 Exterior Painting (MPI Standards)
099124 Interior Painting (MPI Standards)
DIVISION 10 - SPECIALTIES
101100 Visual Display Units
101419 Dimensional Letter Signage
101423 Panel Signage
102113.19 Plastic Toilet Compartments
TABLE OF CONTENTS 5
102239 Vertically Lifting Folding Panel Partitions
102600 Wall Protection
102800 Toilet, Bath, and Laundry Accessories
104413 Fire Protection Cabinets
104416 Fire Extinguishers
105113 Metal Lockers
105300 Prefabricated Aluminum Canopies
DIVISION 11 – EQUIPMENT
113013 Residential Appliances
118129 Facility Fall Protection
DIVISION 12 - FURNISHINGS
122413 Roller Window Shades
123661.16 Solid Surfacing Countertops
123661.19 Quartz Agglomerate Countertops
DIVISION 14 - CONVEYING EQUIPMENT
142123.16 Machine Room-Less Electric Traction Passenger Elevators
TABLE OF CONTENTS 6
VOLUME 2
DIVISION 21- FIRE PROTECTION
211313 Wet-Pipe Sprinkler Systems
DIVISION 22- PLUMBING
220500 Plumbing
DIVISION 23- MECHANICAL
230100 Mechanical General Provisions
230500 Heating Ventilating and Air Conditioning
230593 Testing, Adjusting and Balancing (TAB)
230700 Mechanical Insulation
230800 Commissioning
230900 Automatic Temperature Controls
DIVISION 26- ELECTRICAL
260100 Electrical General Provisions
260500 Materials and Methods
260518 Metal Clad Cables
260519 Conductors
260526 Grounding
260529 Supporting Devices
260533 Raceways
260534 Electrical Boxes and Fittings
260573 Short-Circuit Coordination Study and Arc Flash Hazard Analysis
260670 Lightning Protection System for Concrete-Masonry Structures
260800 Electrical Commissioning Requirements
260923 Lighting Control Devices
262200 Dry-Type Transformers
262413 Main Distribution Switchboard
262416 Panelboards
262420 Motors and Controls
262710 Service and Distribution
262713 Service Entrance
262726 Wiring Devices and Device Plates
263100 Photovoltaic (Solar Electric) System
263214 Natural Gas-Powered Engine Generator and Associated Auto Trans Switches
TABLE OF CONTENTS 7
264313 Surge Protective Devices
265100 Interior Building Lighting
265600 Exterior Building Lighting
DIVISION 27 – COMMUNICATIONS
270100 Operation and Maintenance of Communications Systems
270500 Common Work Results for Communications
270526 Grounding and Bonding for Communications Systems
270529 Hangers and Supports for Communications Systems
270536 Cable Trays for Communications Systems
270543 Underground Ducts and Raceways for Communications Systems
270553 Identification for Communication Systems
270800 Commissioning Communications Systems
271100 Communications Rooms Equipment Fittings
271300 Communications Backbone Cabling
271500 Communications Horizontal Cabling
271600 Communications Connecting Cords, Devices, And Adapters
274116 Integrated Audiovisual Systems and Components
275316 Elevator Lobby Emergency Two-Way Communication System
275319 Distributed Antenna System Public Safety
275400 CATV (Community Antenna Television) System
DIVISION 28 – SECURITY
280000 Common Work Results for Electronic Safety and Security
280100 Operation and Maintenance of Electronic Safety and Security
280526 Grounding and Bonding for Electronic Safety and Security
280529 Hangers and Supports for Electronic Safety and Security
280553 Identification for Electronic Safety and Security
281300 Access Control
281500 Integrated Access Control Hardware Devices
281600 Intrusion Detection System
282300 Video Surveillance System
282400 Interview Recording and Management System
283111 Digital, Addressable Fire-Alarm System
DIVISION 31 - EARTHWORK
311000 Site Cleaning
312000 Earth Moving
312333 Trenching and Backfilling
312500 Erosion and Sedimentation Controls
TABLE OF CONTENTS 8
313116 Termite Control
316200 Rammed Aggregate Piers
DIVISION 32 – EXTERIOR IMPROVEMENTS
321100 Base Courses (Pavements)
321216 Asphalt Paving
321220 Aggregates
321313 Concrete Paving
321623 Sidewalks
321723 Pavement Markings
329119 Landscape Grading
329200 Turf and Grasses
329300 Planting
DIVISION 33 – UTILITIES
331000 Water Utilities
333900 Sanitary Utility Sewerage Structures
334000 Storm Drainage Utilities
334020 Warning and Tracer Tape
END OF TABLE OF CONTENTS
PROFESSIONAL SEALS 1
Project Manual
Department of Engineering and Building
January 14, 2026
Architectural Civil Structural
Fire Protection Plumbing/Mechanical Electrical
PROFESSIONAL SEALS 2
THIS PAGE INTENTIONALLY LEFT BLANK
DGS-30-256
(Rev. 07/21) (VCCS Rev. 04/26)
Notice of Invitation for Bids Page 1 of 1
NOTICE OF INVITATION FOR BIDS (IFB)
VIRGINIA PENINSULA COMMUNITY COLLEGE, HAMPTON CAMPUS
REPLACE DIGGS-MOORE-HARRISON COMPLEX
PROJECT CODE # 260-18341-000
Sealed bids are invited for the construction of the Replace Diggs-Moore-Harrison Complex project at Virginia Peninsula Community College, Hampton Campus, Project Code # 260-18341-000 located in Hampton, Virginia. The project is generally described as an approximately 75,000 SF three-story higher education academic building and other Work, including site and utility work. The new building will include a large multi-function space, classrooms and offices, including a Security Suite, Student Services, the President’s Suite, and Vice-Presidents’ Suites, to support the campus. The building is a Type II-B construction mixed use with occupancies comprised of primarily Business along with limited areas of Assembly.
Sealed bids will be received electronically through eVA or at Virginia Community College System, Attention:
Mrs. Sibyl Roberts, 300 Arboretum Place, Suite 200, Richmond, Virginia 23236, Telephone (804) 819-4918.
PLEASE NOTE: For shipping/mailing, use Suite 390; for hand delivery, use Suite 200. The deadline for submitting bids is 2:00 P.M. sharp, as determined by the Bid Officer, on Wednesday, August 26, 2026. The bids will be opened publicly and read aloud beginning at 2:00 P.M., on the following day, Thursday, August 27, 2026, at the same location.
In person hand delivery is supported on bid day at the stated location. Building is open during regular business hours. All visitors need to sign in at the virtual receptionist (iPad on the wall in the main lobby.) Bids may be modified as per the Instructions to Bidders using fax number (804) 819-4762 and copying sroberts@vccs.edu.
A Standard Commonwealth Bid Bond is required (form CO-10.2) and Contract Security is required for any bid regardless of the bid amount.
eVA Vendor Registration: The bidder or offeror shall be a registered vendor in eVA. See the attached eVA Vendor Registration Requirements.
e-Builder: Contractor shall process Contract documents, Schedule of Values, Pay Applications, Potential Change Orders, and Change Orders electronically through the Owner’s web-based project management software, Trimble Unity e-Builder. There is no fee to use e-Builder. Owner will provide support or training to the Contractor as necessary.
Procedures for submitting a bid, claiming an error, withdrawal of bids and other pertinent information are contained in the Instructions to Bidders, which is part of the Invitation for Bids. Withdrawal due to error in bid shall be permitted in accord with Section 9 of the Instructions to Bidders and § 2.2-4330, Code of Virginia. The Owner reserves the right to reject any or all bids.
A pre-bid conference will be held at 1:00 P.M. on Thursday, August 6, 2026, at Virginia Peninsula Community College, Hampton Campus, 99 Thomas Nelson Drive, Hampton, Virginia 23666, in the Mary T. Christian Theatre, lower level, located in Templin Hall. Attendance is mandatory for those submitting a bid.
The contract shall be awarded on a lump sum basis as follows: the Total Base Bid Amount including any properly submitted and received bid modifications plus such successive Additive Bid Items as the Owner in its discretion decides to award in the manner set forth in Paragraph 12 of the Instructions to Bidders. ‘Notice of Award’ will be posted on eVA, Virginia Department of General Services’ central electronic procurement website, at https://eva.virginia.gov.
Contractor registration is required in accordance with Section 54.1-1103 of the Code of Virginia. See the Invitation for Bids for additional qualification requirements.
All executive branch agencies are directed to advance Executive Order 35, dated July 3, 2019.
The Invitation for Bids for the above project, including the drawings and the specifications containing the information necessary for bidding, are available for download from the eVA website at www.eva.virginia.gov.
Authorized Official of Owner/Agency Commonwealth of Virginia
State Board for Community Colleges Attachment: eVA Vendor Registration Requirements
DGS-30-384
(Rev. 01/21)
Vendor eVA Registration Requirements eVA Business-to-Government Vendor Registration, Contracts, and Order: The eVA
Internet electronic procurement solution, web site portal www.eVA.virginia.gov, streamlines and automates government purchasing activities in the Commonwealth. The eVA portal is the gateway for vendors to conduct business with state agencies and public bodies. All vendors desiring to provide construction and/or professional services to the
Commonwealth shall participate in the eVA Internet e-procurement solution by completing the free eVA Vendor Registration. All bidders or offerors must register in eVA and pay the
Vendor Transaction Fees specified below; failure to register will result in their bid/proposal being rejected.
Vendor transaction fees are determined by the date the original purchase order is issued and the current fees can be found on the eVA website at https://eva.virginia.gov/eva-billing.html.
eVA Orders and Contracts: The solicitation/contract will result in one (1) purchase order(s) with the eVA applicable transaction fee assessed for each order.
http://www.eva.virginia.gov/ https://eva.virginia.gov/eva-billing.html https://eva.virginia.gov/eva-billing.html
DGS-30-055 CO-7A
(Rev. 02/26) Page 1 of 9
INSTRUCTIONS TO BIDDERS
The Invitation For Bids (“IFB”) consists of the Notice, these Instructions To Bidders, the Bid Form, the Pre-Bid Question Form, the General Conditions of the Construction Contract, the Supplemental General Conditions (if any), the Special Conditions (if any), the Forms to be used, and the Scope of Work as described by the Plans and Specifications, other documents listed in the Specifications, and any addenda which may be issued, all of which request qualified bidders to submit competitive prices or bids for providing the described work of the Contract.
As used herein, the terms “bidder” and “Contractor” both shall refer to the Person submitting a bid.
eVA Vendor Registration: The bidder shall be a registered vendor in eVA. See the attached eVA Vendor
Registration Requirements.
1. CONDITIONS AT SITE OR STRUCTURE: Bidders shall visit the Site and shall be responsible for ascertaining pertinent local conditions such as location, accessibility, general character of the Site, structure or building, and the character and extent of existing conditions, improvements or work within or adjacent to the Site. No Claims shall be submitted as a result of Bidder’s failure to have done so, but shall be deemed waived and will not be considered by the Owner. See Section 7 of the General Conditions entitled "Conditions at Site."
2. EXPLANATIONS TO BIDDERS: No oral explanation in regard to the meaning of drawings and specifications will be made and no oral instructions will be given before the award of the Contract. The Owner shall not be responsible for any conclusions, assumptions or interpretations made by bidders during the preparation of bids that are contrary to the Drawings and Specifications and their clear intent.
Discrepancies, conflicts, errors, omissions or doubts as to the meaning of the Contract Documents shall be communicated in writing to the A/E for interpretation. Bidders must use the "Prebid Question Form" provided in the bid documents. Bidders must so act to assure that questions reach the A/E at least six (6) days prior to the time set for the receipt of bids to allow a sufficient time for an addendum to reach all bidders before the submission of their bids. If, however, there are two (2) weeks or less between the first bid advertisement and the time set for receipt of bids, then bidders must submit questions so that they reach the A/E no later than three (3) days prior to the time set for receipt of bids. Any interpretation made will be in the form of an addendum to the Specifications which will be forwarded to all bidders, and its receipt shall be acknowledged by the bidder on Bid Forms. If such discrepancies, conflicts, errors, omissions or doubts are reasonably apparent or should have been reasonably apparent to the bidder, and the bidder failed to submit questions to the A/E in the time and manner required herein and the Contract is awarded to the bidder, then any claims shall be deemed waived and the bidder shall not be entitled to additional compensation or time, or entitled to sue the Owner based on such discrepancies, conflicts, errors, omissions, or doubts.
3. TIME FOR COMPLETION:
(a) "Time for Completion" shall be designated by the Owner on the Invitation for Bids or other prebid documents and shall mean the number of consecutive calendar days following the issuance of the Notice to Proceed which the Contractor has to substantially complete all Work required by the Contract. In some instances, the Time for Completion may be stated in the form of a Contract Completion Date based on a stipulated date of Notice to Proceed.
Unless otherwise specified, the Contractor shall achieve Final Completion within thirty (30) days after the date of Substantial Completion.
(b) When the Notice to Proceed is issued, it will state a Contract Completion Date, which has been set by the Owner based on date of the Notice to Proceed and the Time for Completion.
(Rev. 02/26) Page 2 of 9
(c) The Contractor, in preparing and submitting its bid, is required to take into consideration normal weather conditions. Normal weather does not mean statistically average weather, but rather means a range of weather patterns which might be anticipated based on weather conditions and events for the past ten (10) years. Normal weather conditions shall be determined from the public historical records available, including the U.S. Department of Commerce, Local Climatological Data Sheets, Oceanic and Atmospheric Administration/Environmental Data and Information Service, National Climatic Center and the National Weather Service. The data sheets to be used shall be for the locality or localities closest to the Site. No additional compensation, costs or damages will be paid to the Contractor because of normal weather conditions, including normal adverse weather to be anticipated during the Project. An extension of time for abnormal adverse weather conditions which directly impact the Work will be considered by the Owner as set forth in the General Conditions.
(d) If the Owner designates the public historical climatological records to be used to establish normal weather patterns, the bidder shall use those records in estimating and preparing its bid. If the Owner requests each bidder to indicate the weather pattern records used in preparation of a bid, each bidder may select the public historical climatological records upon which it will rely in preparing its bid.
In the latter situation, each bidder shall designate in the space provided which of such climatological data records were used in preparing the bid. A bidder's failure to designate climatological records when submitting a bid shall not disqualify a bid, but shall constitute a waiver of any claim or request for an extension of time as the result of abnormal adverse weather. In either case, the bid submitted and the Time for Completion shall be presumed to have been based upon normal weather patterns, including normal adverse weather, as derived from the climatological records used.
4. PREPARATION AND SUBMISSION OF BIDS:
(a) Bids shall be submitted on the forms furnished, or copies thereof, and shall be signed in ink, or in the case of bids submitted electronically, signatures shall be in accordance with Code of Virginia § 59.1-479 et seq. The Owner’s agreement to accept electronic bids, if made, will be indicated in the IFB. Erasures or other changes in a bid must be explained or noted over the signature of the bidder.
Bids containing any conditions, omissions, unexplained erasures, alterations or items not called for in the proposal, or irregularities of any kind, may be rejected by the Owner as being incomplete or nonresponsive.
(b) Each bid must give the complete legal name and full business address of the bidder and be signed by the bidder, or the bidder's authorized representative. Bids by partnerships must be signed in the partnership name by one of the general partners of the partnership or an authorized representative, followed by the designation/title of the person signing, and a list of the partners. Bids by joint ventures must be signed in the joint venture name by one of the joint venturers or an authorized representative of one of the joint venturers, followed by the designation/title of the person signing, and a list of the joint venturers. Bids by corporations must be signed with the legal name of the corporation followed by the name of the state in which it is incorporated and by the signature and title of the person authorized to bind it in this matter. The name of each person signing shall be typed or printed below the signature. A signature on a bid by a person who identifies their title as "President," "Secretary," "Agent" or other designation without disclosing the principal firm, shall be held to be the bid of the individual signing. When requested by the Owner, satisfactory evidence of the authority of the officer signing on behalf of the corporation shall be furnished. Trade or fictitious names may be referenced by using "t/a _ _ _ ," but bids shall be in the legal name of the person or entity submitting the bid.
(c) Bids with the bid guarantee shall be enclosed in a sealed envelope which shall be marked and addressed as indicated by the advertisement. If a Contract is for one hundred twenty thousand dollars ($120,000) or more, or if the total value of all construction, removal, repair or improvements undertaken by the bidder within any twelve-month period is seven hundred fifty
(Rev. 02/26) Page 3 of 9 thousand dollars ($750,000) or more, the bidder is required under Code of Virginia §§ 54.1-1100, et seq., to be licensed in Virginia as a "Class A Contractor." If a Contract is for ten thousand dollars
($10,000) or more, but less than one hundred twenty thousand dollars ($120,000), or if the total value of all construction, removal, repair or improvements undertaken by the bidder within any twelve-month period is one hundred fifty thousand dollars ($150,000) or more, but less than seven hundred fifty thousand dollars ($750,000), the bidder is required to be licensed in Virginia as a
"Class B Contractor." The bidder shall place on the outside of the envelope containing the bid and shall place in the bid over its signature whichever of the following notations is appropriate and insert its Contractor license/registration number:
Licensed Class A Virginia Contractor No. ______________ or Licensed Class B Virginia Contractor No. ______________
If the bidder is not properly licensed in Virginia at the time the bid is submitted, or if the bidder fails to provide this information on its bid or on the envelope containing the bid and fails to promptly provide said Contractor license number to the Owner in writing when requested to do so before the opening of bids, the bidder shall be deemed to be in violation of Code of Virginia § 54.1-1115 and its bid will not be considered.
(d) Following guidance from the Board for Contractors, the Owner may, as a part of determining whether the bidder is "responsible," require the apparent low bidder to submit a listing of its Subcontractors along with the license number and classification or specialty of each. See DEP’T OF
PROF’L AND OCCUPATIONAL REGULATION, BD. FOR CONTRACTORS POLICIES & INTERPRETATIONS, No. 2959 (July 11, 2016) (“A licensed contractor may bid on work, or enter into a contract for work, which is outside the scope of [its] license classification(s) provided that [it] subcontracts that work, to properly licensed contractors, and the work of the subcontractors is incidental to the contract.”).
(e) The bidder must place its Employer Identification Number (SSN or FEIN) in the space provided on the Bid Form.
(f) Every bidder organized as a stock or nonstock corporation, limited liability company, business trust, or limited partnership or registered as a registered limited liability partnership must be authorized to transact business in the Commonwealth as a domestic or foreign business entity if so required by Title 13.1 or Title 50 of the Code of Virginia, as amended, or as otherwise required by law. Any bidder organized or authorized to transact business in the Commonwealth pursuant to Title 13.1 or Title 50 must include in its bid the identification number issued to it by the State Corporation Commission. Any bidder that is not required to be authorized to transact business in the Commonwealth as a foreign business entity under Title 13.1 or Title 50 or as otherwise required by law shall include in its bid or proposal a statement describing why the bidder is not required to be so authorized. A bidder required to be authorized to transact business in Virginia that fails to provide the required information shall not receive an award unless a waiver of this requirement and of any administrative policies and procedures established to implement Code of Virginia § 2.2-4311.2 is granted by the chief executive of the Owner.
If awarded the Contract, the bidder shall not allow its existence to lapse or its certificate of authority or registration to transact business in the Commonwealth, if so required under Title 13.1 or Title 50, to be revoked or cancelled at any time during the term of the Contract. Doing so shall be deemed to be a violation of Code of Virginia § 2.2-4311.2 and the bidder understands and agrees that the Owner may void the Contract if the bidder fails to comply with this provision.
(g). Code of Virginia, § 2.2-4376.2 shall be applicable to the Work of the Contract.
5. BID GUARANTEE:
(Rev. 02/26) Page 4 of 9
(a) Any bid (including the Total Base Bid plus all Additive Bid Items) which exceeds five hundred thousand dollars ($500,000) shall be accompanied by a Commonwealth of Virginia Standard Bid Bond, Form CO-10.2, payable to the Owner as obligee in an amount equal to five percent (5%) of the amount of the bid (the “Bid Bond”). The Owner agrees to accept a Bid Bond on which the Surety has utilized electronic signatures and/or electronic notarization if the electronic notarization meets the requirements of Virginia Code §§ 47.1-6.1, -7, and -12, and the Commonwealth of Virginia State Corporation Commission Bureau of Insurance and the Bid Bond contains any SURETY BOND SEAL ADDENDUM established by the Commonwealth of Virginia State Corporation Commission Bureau of Insurance. For construction contracts up to $500,000, where bid bond requirements have been waived by Owner as stated in the IFB, prospective Contractors may be prequalified in accordance with Code of Virginia § 2.2-4317.A Bid Bond may be required for Contracts having bids of up to five hundred thousand dollars ($500,000) if such requirement is stated in the IFB. The Bid Bond must be issued by a surety company which is legally authorized by the Virginia State Corporation Commission to do surety business in the Commonwealth of Virginia.
Such Bid Bond shall guarantee the following: that the bidder will not withdraw its bid during the thirty (30) day period following the date of the opening of bids; that if the bid is accepted, the bidder will enter into the Contract with the Owner described in the IFB; that the bidder can and will submit a properly executed and authorized Standard Performance Bond and Standard Labor and Material Payment Bond on the forms included in the IFB. If the bidder withdraws its bid within the thirty (day) period following bid opening, fails to enter into the Contract, or fails to provide the required Standard Performance Bond and Standard Labor and Material Payment Bond within ten (10) days after the bidder’s receipt of notice of acceptance of its bid, the bidder and the bidder’s surety shall be jointly and severally be liable to the Owner for the difference between the amount specified in the bidder’s bid and such larger amount for which the Owner may contract with another party to perform the work covered by said bid, up to the amount of the bid guarantee of 5% of the bidder’s total bid amount, as the damage to the Owner resulting from the bidder’s default. See Code of Virginia §2.2-4336.
(b) Code of Virginia § 2.2-4338 contains provisions allowing for alternative forms of bid security in lieu of a Bid Bond. A bidder’s use of an alternative form of Security as listed in Code of Virginia § 2.2-4338.B must be approved by the Owner prior to the bidder’s submission of its bid on the Bid Receipt date and time to be accepted in lieu of a Bid Bond.
(c) The Bid Bond or other alternative bid security will be returned to all but the three lowest bidders after the formal opening of bids. The remaining Bid Bonds or bid security will be returned to the bidders after the Owner and the accepted bidder have executed the Contract and the required Standard Performance Bond and the Standard Labor and Material Payment Bond for the Contract have been received and approved by the Owner.
(d) If the Contract and required bonds have not been executed by the accepted bidder within thirty (30) days after the date of the opening of the bids, then the Bid Bond or other bid security of any bidder will be returned upon a bidder’s request, provided the bidder has not been notified of the acceptance of its bid prior to the date of such request.
6. WITHDRAWAL OR MODIFICATION OF BIDS: Bids may be withdrawn or modified by written or telefaxed notice received at the designated location from bidders prior to the deadline fixed for bid receipt.
E-mail withdrawals and modifications are not acceptable. The withdrawal or modification may be made by the person who signed the bid or by an individual(s) who is authorized by the bidder on the face of the bid.
Written modifications may be made on the bid form itself, on the envelope in which the bid is enclosed, or on a separate document. Written modifications, whether the original is delivered or telefaxed, must be signed by the person making the modification or withdrawal. The modification must state specifically what is to be modified and by what amount or it must state the item to be modified and what the corrected amount should be.
7. RECEIPT OF BIDS:
(Rev. 02/26) Page 5 of 9
(a) Bids will be received at or before the date and the hour and in the place and manner stipulated in the IFB as may be modified by subsequent Addenda. If bids are to be received electronically, bids shall be submitted via the electronic bid receipt system specified in the IFB.
(b) It is the responsibility of the bidder to assure that its bid and any bid modifications are delivered to the place designated for receipt of bids by the date and hour (deadline) set for receipt of bids. Therefore, it is the bidder’s responsibility to take into account all factors which may impact on its bid deliverer / courier’s ability to deliver the bid and to implement whatever actions are necessary to have the bid delivered to the proper bid receipt location prior to the bid receipt deadline. No bids or bid modifications submitted or offered after the date and hour designated for receipt of bids will be accepted or considered.
(c) The Bid Officer is the Owner's representative designated to receive bids at the time and place noted in the IFB and to open the bids received at the appointed time.
(d) The official time used for the receipt of responses is determined by reference to the clock designated by the Bid Officer. The Bid Officer shall determine when the Bid Receipt Deadline has arrived and shall announce that the Deadline has arrived and that no further bids or bid modifications will be accepted. All bids and bid modifications in the possession of the Bid Officer and their assistants at the time the announcement is completed are deemed to be timely, whether or not the bid envelope has been physically date/time stamped or otherwise marked by the time the Bid Officer makes the deadline announcement.
(e) In the event the bid receipt occurs during a period of suspended state business operations, the receipt and opening will be delayed one business day.
8. OPENING OF BIDS:
(a) Bids will be opened at the time and place stated in the IFB or as modified by subsequent Addenda, and their contents publicly announced. The Bid Officer shall decide when the specified time for bid opening has arrived. No responsibility will be attached to any officer or agent for the premature opening of a bid not properly addressed and identified. Bid opening shall be no sooner than twenty-four (24) hours after the time set for receipt of bids.
(b) The provisions of Code of Virginia § 2.2-4342, as amended, shall be applicable to the inspections of bids received.
(c) In the event the bid opening occurs during a period of suspended state business operations, the opening will be delayed until the next business day.
9. ERRORS IN BIDS: A bidder may withdraw its bid from consideration if the price bid was substantially lower than the other bids due solely to a mistake therein, provided the bid was submitted in good faith, and the mistake was a clerical mistake as opposed to a judgment mistake, and was actually due to an unintentional arithmetic error or an unintentional omission of a quantity of work, labor or material made directly in the compilation of a bid, which unintentional arithmetic error or unintentional omission can be clearly shown by objective evidence drawn from inspection of original work papers, documents and materials used in the preparation of the bid sought to be withdrawn.
In accordance with Code of Virginia § 2.2-4330(B)(2), the bidder must submit to the Owner its original work papers, documents and materials used in the preparation of the bid within one day after the date fixed for submission of bids. Such work papers must be submitted in an envelope or package separate and apart from the envelope containing the bid and marked clearly as to the contents and shall be delivered to the Owner by the bidder in person or by registered mail prior to the time fixed for the opening of bids and may not be withdrawn until after the two-hour period (referred to later) has elapsed. The bids shall be opened at the time designated in the IFB, as amended by addendum. Bid opening is usually one day following the time fixed by
(Rev. 02/26) Page 6 of 9 the Owner for the submission of bids, but no sooner. Once the bids have been opened, the bidder shall have two (2) hours after the opening of bids within which to claim in writing any mistake as defined herein and withdraw its bid. The Contract shall not be awarded by the Owner until such two-hour period has elapsed.
Such mistake shall be proved only from the original work papers, documents and materials delivered to the Owner prior to bid opening. This procedure in Code of Virginia § 2.2-4330(B)(2) shall not apply to when the entire bid is required to be submitted on a unit price basis.
Failure of a bidder to submit its original work papers, documents and materials used in the preparation of its bid on or before the time, date and place required shall constitute a waiver by that bidder of its right to withdraw its bid due to a mistake.
No bid may be withdrawn under this section when the result would be the awarding of the Contract on another bid of the same bidder or of another bidder in which the ownership of the withdrawing bidder is more than five (5%) percent.
No bidder who is permitted to withdraw a bid shall, for compensation, supply any material or labor to or perform any subcontract or other work agreement for the person or firm to whom the Contract is awarded or otherwise benefit, directly or indirectly, from the performance of the project for which the withdrawn bid was submitted. The person or firm to whom the Contract was awarded and the withdrawing bidder are jointly liable to the Owner in an amount equal to any compensation paid to or for the benefit of the withdrawing bidder without such approval.
If the apparent low bid is withdrawn under authority of this section, the lowest remaining bid shall be deemed to be the low bid on the project.
10. REJECTION OF BIDS: The Owner reserves the right to cancel the IFB, to reject any and all bids at its sole discretion when such rejection is in the interest of the Owner, or to reject the bid of any bidder who is determined to be not responsive or not responsible. See Code of Virginia § 2.2-4319.
11. DETERMINATION OF RESPONSIBILITY
Each bidder shall be prepared, if so requested by the Owner, to present evidence of its experience, qualifications and financial ability to carry out the terms of the Contract.
Prior to award of the Contract, an evaluation will be made to determine if the low bidder has the capability, in all respects, to perform fully the contract requirements and the moral and business integrity and reliability which will assure good faith performance, and who has been prequalified, if required. Factors to be evaluated include, but are not limited to:
(a) sufficient financial ability to perform the contract as evidenced by the bidder's ability to obtain payment and performance bonds from an acceptable surety;
(b) appropriate experience to perform the Work described in the bid documents;
(c) any judgments entered against the bidder, or any officers, directors, partners or owners for breach of a contract for construction;
(d) any substantial noncompliance with the terms and conditions of prior construction contracts with a public body without good cause where the substantial noncompliance is documented; or
(e) a conviction of the bidder or any officer, director, partner, project manager, procurement manager, chief financial officer, or owner in the last five years of a crime relating to governmental or nongovernmental construction or contracting; and/or
(f) any current debarment of the contractor, any officer, director or owner, from bidding or contracting by any public body of any state, any state agency, or any agency of the federal government.
(Rev. 02/26) Page 7 of 9
The Owner reserves the right to disqualify or refuse to accept the bid of any bidder who has been convicted, or entered a plea of guilty or nolo contendere, in any federal or state court to any charge involving any unlawful, corrupt or collusive practice involving a public contract whether federal, state, or local, or who has been determined in any judicial proceeding to have violated any antitrust, bid-rigging or collusive practice statute in connection with any public contract, or against whom such formal criminal prosecution or other judicial proceeding has been initiated.
A bidder who, despite being the apparent low bidder, is determined not to be a responsible bidder shall be notified in writing in conformance with the procedures in Code of Virginia § 2.2-4359.
12. AWARD OF CONTRACT
(a) Basis for Contract Award: The Contract, if awarded, will be awarded to the lowest responsive and responsible bidder, if any, provided its bid is reasonable and it is in the best interest of the Owner to accept it and subject to the Owner's right to reject any and all bids and to waive informality in the bids and in the bidding. The Bid Form contains a multi-part Base Bid and may contain Additive Bid Items. Determination of the lowest responsible bidder, if any, will be based on the Total Base Bid Amount entered on the Bid Form including any properly submitted bid modifications plus as many Additive Bid Items taken in sequence as the Owner in its discretion chooses to Award. Where the sum of the values entered in the multiple parts do not agree with the Total Base Bid amount, the Total Base Bid amount entered on the bid form, including any properly submitted bid modifications, shall take precedence.
In the event that the Total Base Bid from the lowest responsible bidder exceeds available funds, the Owner may negotiate the Total Base Bid amount with the apparent low bidder to obtain a Contract Price within available funds, pursuant to Code § 2.2-4318 and Section 12(c) herein.
(b) Informalities: The Owner reserves the right to waive any informality in the bids when such waiver is in the interest of the Owner.
(c) Negotiation With Lowest Responsible Bidder: If award of the Contract to the lowest responsive and responsible bidder is precluded because of limitations on available funds, under the provisions of Code § 2.2-4318 the Owner reserves the right to negotiate the Total Base Bid amount with the lowest responsive, responsible bidder to obtain a Contract Price within the available funds. This may involve changes in either the features or scope of the work included in the Base Bid. Such negotiations with the apparent low bidder may include reducing the quantity, quality, or other cost saving mechanisms involving items in the Total Base Bid. Negotiations for Additive Bid Items are excluded. The Owner shall notify the lowest responsive and responsible bidder that such a situation exists and the Owner and bidder shall then conduct their negotiations in person, by mail, by telephone or by any means they find convenient. If an acceptable Contract can be negotiated, any changes to the IFB documents agreed upon in the negotiations shall be summarized in a "Post Bid Modification" and included in the Contract. If an acceptable Contract cannot be negotiated, the Owner shall terminate negotiations and reject all bids.
(d) Notice of Intent to Award or Notice of Award: The Notice of Award or the Notice of Intent to
Award will be posted at the Agency’s standard location for posting notices as shown on the
“Notice of Invitation to Bid”. In addition, the Agency may also post such notice on the Agency’s Website and/or the DGS central electronic procurement Website. Any bidder who desires to protest the award or decision to award a contract shall submit the protest in writing to the public body no later than ten days after the posting of the Notice of Award or Notice of Intent to Award, whichever comes first. See Code of Virginia § 2.2-4360.
13. CONTRACT SECURITY: For contracts which exceed five hundred thousand dollars ($500,000), the Standard Performance Bond (CO-10) and the Standard Labor and Material Payment Bond (CO-10.1) shall
(Rev. 02/26) Page 8 of 9 be required, as specified in the IFB. For construction contracts up to $500,000, where Bid Bond requirements are waived, prospective contractors may be prequalified in accordance with Code of Virginia § 2.2-4317. See General Conditions and Code of Virginia § 2.2-4337 and § 2.2-4338. The Owner reserves the right to require such bonds for contracts up to five hundred thousand dollars ($500,000). If the Owner so elects, the requirement shall be set forth in the IFB.
14. CERTIFICATION: The bidder, by its signature on the Bid Form, certifies that neither its organization nor any of its officers, directors, partners or owners is currently barred from bidding on contracts by any Agency of the Commonwealth of Virginia, or any public body or agency of another state, or any agency of the federal government. See "Disqualification of Contractors" in the Bid Form.
15. ETHICS IN PUBLIC CONTRACTING: The provisions, requirements and prohibitions as contained in Code of Virginia §2.2-4367 et seq., pertaining to bidders, offerors, contractors, and subcontractors are applicable to this project.
16. BUILDING PERMITS: Because this is a Project of the Commonwealth of Virginia, codes or zoning ordinances of local political subdivisions do not apply. However, the Virginia Uniform Statewide Building Code shall apply to the Work and shall be administered by the Building Official for State-owned Buildings.
The Building Permit will be obtained and paid for by the Owner. All other permits, local license fees, business fees, taxes, or similar assessments imposed by the appropriate political subdivision shall be obtained and paid for by the Contractor. See Section 25 of the General Conditions for utility connection fees and services.
17. UTILIZATION OF SMALL BUSINESSES: It is the policy of the Commonwealth of Virginia to maximize the participation of small businesses in state contracting. The participation of these businesses directly and through partnerships, joint ventures, subcontracts and other contractual opportunities may be encouraged for this Project based on the Owner’s requirements (if applicable) on the Bid Form. Bidders shall provide a Small Business Procurement Plan in conjunction with their sealed bid. The Small Business Procurement Plan shall identify the bidder’s proposed percentage of participation by small businesses in the Total Base Bid amount, and is indicated on the Bid Form. An entry on the line for “Contractor’s Proposed Small Business Participation” is required for the bid to be considered responsive. If the bidder is a DSBSD certified small business, the proposed percentage of small business participation shall be entered as 100%. A bidder may enter a proposed percentage of small business participation of 0% and be considered responsive unless the Bid Form states that the Owner requires a specific percentage of small business participation, in which case the bidder shall enter a percentage equal to or greater than the Owner’s required small business participation percentage for the bid to be considered responsive.
18. BID DOCUMENTS: Bid Documents are the property of the Owner and a deposit in an amount as stated in the Invitation for Bids is required for each paper set or for each set provided on removable electronic media as a guarantee of the safe return of the documents within ten (10) days of bid opening. This deposit will be refunded in full on not more than two paper sets or sets provided on removable electronic media to each bidder who submits a Contract bid and who returns the documents in good condition. Refund will be made on paper sets and sets provided on removable electronic media to non-bidders and Subcontractors in the amount of half of the deposit when the sets are returned in good condition within 10 days. A deposit is not required for downloading of electronic construction documents through an FTP site. A non-refundable shipping charge may be required for paper sets or sets provided on removable electronic media if stated in the Notice or the IFB.
19. GENERAL CONDITIONS: The General Conditions are incorporated in the bid documents. If a copy of the General Conditions is not included in the bid documents, the bidder may obtain a copy of the current edition of the General Conditions at no cost by written request to the A/E and/or the Agency where the bid documents are obtained. Copies may also be obtained from the DGS Forms Center (available online at https://dgs.virginia.gov/engineering-and-buildings/documents-and-forms/deb).
20. PREBID CONFERENCE: See the IFB for requirements for a prebid conference and whether such conference is mandatory or optional.
(Rev. 02/26) Page 9 of 9
21. INSPECTION OF BID DOCUMENTS: Copies of the IFB documents including Plans and Specifications and the General Conditions will be available for inspection at the Agency, at the A/E's office, and at the locations listed in the Notice of the IFB.
22. DRUG-FREE WORKPLACE REQUIRED: Bidders are reminded that Code of Virginia § 2.2-4312 requires that the during the performance of the Contract resulting from this solicitation, the Contractor agrees to: (i) provide a drug-free workplace for the Contractor's employees; (ii) post in conspicuous places, available to employees and applicants for employment, a statement notifying employees that the unlawful manufacture, sale, distribution, dispensation, possession, or use of a controlled substance or marijuana is prohibited in the Contractor's workplace and specifying the actions that will be taken against employees for violations of such prohibition; (iii) state in all solicitations or advertisements for employees placed by or on behalf of the Contractor that the Contractor maintains a drug-free workplace; and (iv) include the provisions of the foregoing clauses in…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .