835454waterFredWater.pdf

PDF 10 MB Posted

Attached to
Whetzel Well Raw Water Line Relocation
Solicitation number
27E05
Issued by
Fauquier County, Virginia

About this file

This is a bidding document package for Frederick Water (Frederick County Sanitation Authority d/b/a Frederick Water) in Virginia for the construction of the Whetzel Well Raw Water Line Relocation project. The project involves construction of approximately 4,700 linear feet of 12-inch HDPE raw water line, including associated fittings, bends, valves, air release valves, tie-ins to existing facilities, testing, and restoration. Bids will be received until August 20, 2026 at 2:00 PM local time at the Administration Building located at 315 Tasker Road, Stephens City, VA 22655. A non-mandatory pre-bid conference will be held on July 28, 2026 at 9:00 AM via Microsoft Teams; interested parties should contact Connie Morrison-Henry, Purchasing Manager, at chenry@frederickwater.com for access. Bidding documents are available at https://www.frederickwater.com/bid-specs or through the eVA Virginia Marketplace. Site visits are required and must be scheduled through Brandon Abshire at babshire@frederickwater.com during normal working hours. The contract will be awarded to the lowest responsive and responsible bidder. Substantial completion is required within 180 calendar days of the contract commencement date, with final completion and readiness for final payment within 210 calendar days.

The contract will be awarded on a lump sum (stipulated price) basis. Bid security in the form of a bid bond or cashier's check equal to 5 percent of the maximum bid price is required. Liquidated damages are assessed at $500 per day for failure to achieve substantial completion and $500 per day for failure to complete remaining work after substantial completion. Progress payments will be made monthly at 95 percent of completed work value, with 5 percent retainage prior to substantial completion. Upon substantial completion, payment will increase to 100 percent of completed work less an amount equal to 150 percent of the engineer's estimate for remaining punch list items. Final payment will be made upon final completion and acceptance. A performance bond and payment bond will be required. All bidders must demonstrate authorization to do business in Virginia and provide current Virginia contractor license numbers. Bidders must submit statements of qualifications including financial data, previous experience, current commitments, and information regarding proposed subcontractors and suppliers.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FREDERICK WATER

WHETZEL WELL RAW WATER LINE RELOCATION

SUPPLEMENTAL SPECIFICATIONS

ISSUE FOR BID

17 JULY 2026

CONTACT:

Connie Morrison-Henry, Purchasing Manager 540-866-0126 chenry@frederickwater.com

PROJECT NO. 27E05

TABLE OF CONTENTS TOC-1

Division Section Title Pages

C-111 AD FOR BIDS FOR CONST CONTRACT 2018

C-200_2018 INSTRUCTIONS TO BIDDERS

C-410_ 2018 BID FORM

NON-COLLUSION AFFIDAVIT

C-430_2018 BID BOND

C-451_2018 QUALIFICATIONS STATEMENT

C-510_2018 NOTICE OF AWARD

C-520_2018 AGREEMENT STIPULATED PRICE

C-550_2018 NOTICE TO PROCEED

C-610_ PERFORMANCE BOND 2018 FW

C-615_ PAYMENT BOND 2018 FW

C-620_2018 APPLICATION FOR PAYMENT2

C-625_2018 CERTIFICATE OF SUBSTANTIAL COMPLETION

C-626_2018 NOTICE OF ACCEPTABILITY

C-700_ GENERAL CONDITIONS 2018 FW

C-800_2018 - CUSTOMIZED

C-940_2018 WORK CHANGE DIRECTIVE

C-941_2018 CHANGE ORDER

C-942_2018 FIELD ORDER

DIVISION 01 – GENERAL REQUIREMENTS

011000- SUMMARY

012600 - CONTRACT MODIFICATION PROCEDURES

012900 - PAYMENT PROCEDURES

013100 - PROJECT MANAGEMENT AND COORDINATION

013100b- (RFI) FORM

013200 - CONSTRUCTION PROGRESS DOCUMENTATION

013233 - PHOTOGRAPHIC DOCUMENTATION

013300 - SUBMITTAL PROCEDURES

014000 - QUALITY REQUIREMENTS

014200 - REFERENCES

016000 - PRODUCT REQUIREMENTS

017300 - EXECUTION

017419 - CONSTRUCTION WASTE MANAGEMENT AND DISPOSAL

017700 - CLOSEOUT PROCEDURES

017823 - OPERATION AND MAINTENANCE DATA

017839 - PROJECT RECORD DOCUMENTS

DIVISION 02 - EXISTING CONDITIONS

028310 - CHAIN LINK FENCES

DIVISION 31 - EARTHWORK

311000 -. SITE CLEARING

312000 - EARTH MOVING

312319 - DEWATERING

315000 - EXCAVATION SUPPORT AND PROTECTION

PROJECT NO. 27E05

TABLE OF CONTENTS TOC-2

DIVISION 32 - EXTERIOR IMPROVEMENTS

329201.-.

DIVISION 33-

330500-

330505-

331100-

331216-

331243-

EROSION AND SEDIMENT CONTROL

UTILITIES

COMMON WORK RESULTS FOR UTILITIES

OPEN-CUT ROADWAY CROSSING

WATER UTILITY DISTRIBUTION PIPING

WATER UTILITY DISTRIBUTION VALVES

MAGNETIC FLOW METER

END OF TABLE OF CONTENTS

EJCDC® C-111, Advertisement for Bids for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, and American Society of Civil Engineers. All rights reserved.

General Notice

ADVERTISEMENT FOR BIDS

Frederick Water Frederick County, Virginia

Whetzel Well Raw Water Line Relocation

Frederick Water (Owner) is requesting Bids for the construction of the following Project:

Whetzel Well Raw Water Line Relocation

Bids for the construction of the Project will be received at the Administration Building located at 315 Tasker Rd., Stephens City, VA 22655, until August 20, 2026 at 2:00 PM local time. At that time the Bids received will be publicly opened and read.

The Project includes the following Work:

The Whetzel Well Raw Water Line Relocation consists of the construction of approximately 4,700 LF of 12-inch HDPE raw water line, including associated fittings, bends, valves, air release valves, tie-ins to existing facilities, testing, and restoration.

Obtaining the Bidding Documents

Information and Bidding Documents for the Project can be found at the Owner’s website (https://www.frederickwater.com/bid-specs) or the e-VA Virginia Marketplace (https://eva.virginia.gov/).

Bidding Documents may be downloaded from the designated website. The designated website will be updated periodically with addenda, reports, and other information relevant to submitting a Bid for the Project. All official notifications, addenda, and other Bidding Documents will be offered only through the designated website. Neither Owner nor Engineer will be responsible for Bidding Documents, including addenda, if any, obtained from sources other than the designated website.

Pre-bid Conference

A non-mandatory pre-bid conference for the Project will be held on July 28, 2026 at 9 a.m. via Microsoft Teams. Contact Connie Morrison-Henry, Purchasing Manager (chenry@frederickwater.com) for access to the pre-bid conference.

Instructions to Bidders.

For all further requirements regarding bid submittal, qualifications, procedures, and contract award, refer to the Instructions to Bidders that are included in the Bidding Documents.

This Advertisement is issued by:

Owner: Frederick Water

By: Connie Henry Title: Purchasing Manager Date: July 17, 2026

EJCDC® C-200, Instructions to Bidders for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, TOC Page1 of 1

INSTRUCTIONS TO BIDDERS FOR CONSTRUCTION CONTRACT

TABLE OF CONTENTS

Page

Article 1— Defined Terms

Article 2— Bidding Documents

Article 3— Qualifications of Bidders

Article 4— Pre-Bid Conference

Article 5— Site and Other Areas; Existing Site Conditions; Examination of Site; Owner’s Safety Program;

Other Work at the Site

Article 6— Bidder’s Representations and Certifications

Article 7— Interpretations and Addenda

Article 8— Bid Security

Article 9— Contract Times

Article 10— Substitute and “Or Equal” Items

Article 11— Subcontractors, Suppliers, and Others

Article 12— Preparation of Bid

Article 13— Basis of Bid

Article 14— Submittal of Bid

Article 15— Modification and Withdrawal of Bid

Article 16— Opening of Bids

Article 17— Bids to Remain Subject to Acceptance

Article 18— Evaluation of Bids and Award of Contract

Article 19— Bonds and Insurance

Article 20— Signing of Agreement

Article 21— Additional Requirements

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, ARTICLE 1—DEFINED TERMS

1.01 Terms used in these Instructions to Bidders have the meanings indicated in the General Conditions and Supplementary Conditions.

ARTICLE 2—BIDDING DOCUMENTS

2.01 Bidder shall obtain a complete set of Bidding Requirements and proposed Contract Documents (together, the Bidding Documents). See the Agreement for a list of the Contract Documents. It is Bidder’s responsibility to determine that it is using a complete set of documents in the preparation of a Bid. Bidder assumes sole responsibility for errors or misinterpretations resulting from the use of incomplete documents, by Bidder itself or by its prospective Subcontractors and Suppliers.

2.02 Bidding Documents are made available for the sole purpose of obtaining Bids for completion of the Project and permission to download or distribution of the Bidding Documents does not confer a license or grant permission or authorization for any other use. Authorization to download documents, or other distribution, includes the right for plan holders to print documents solely for their use, and the use of their prospective Subcontractors and Suppliers, provided the plan holder pays all costs associated with printing or reproduction. Printed documents may not be re-sold under any circumstances.

2.03 Bidder may obtain complete sets of Bidding Documents from the Owner’s website (https://www.frederickwater.com/bid-specs) or the eVA Virginia Marketplace (https://eva.virginia.gov/). Owner will not maintain a plan holders list. Interested sub-contractors and suppliers are encouraged to refer to the list of attendees that will be issued after the pre-bid conference.

2.04 Plan rooms (including construction information subscription services, and electronic and virtual plan rooms) may distribute the Bidding Documents, or make them available for examination.

Owner is not responsible for omissions in Bidding Documents or other documents obtained from plan rooms, or for a Bidder’s failure to obtain Addenda from a plan room.

2.05 Electronic Documents

A. When the Bidding Requirements indicate that electronic (digital) copies of the Bidding Documents are available, such documents will be made available to the Bidders as Electronic Documents in the manner specified.

1. Bidding Documents will be provided in Adobe PDF (Portable Document Format) (.pdf) that is readable by Adobe Acrobat Reader (Latest Version). It is the intent of the Engineer and Owner that such Electronic Documents are to be exactly representative of the paper copies of the documents. However, because the Owner and Engineer cannot totally control the transmission and receipt of Electronic Documents nor the Contractor’s means of reproduction of such documents, the Owner and Engineer cannot and do not guarantee that Electronic Documents and reproductions prepared from those versions are identical in every manner to the paper copies.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, B. Unless otherwise stated in the Bidding Documents, the Bidder may use and rely upon complete sets of Electronic Documents of the Bidding Documents, described in Paragraph 2.05.A above. However, Bidder assumes all risks associated with differences arising from transmission/receipt of Electronic Documents versions of Bidding Documents and reproductions prepared from those versions and, further, assumes all risks, costs, and responsibility associated with use of the Electronic Documents versions to derive information that is not explicitly contained in printed paper versions of the documents, and for Bidder’s reliance upon such derived information.

C. After the Contract is awarded, the Owner will provide or direct the Engineer to provide for the use of the Contractor documents that were developed by Engineer as part of the Project design process, as Electronic Documents in native file formats.

1. Electronic Documents that are available in native file format include:

a. Civil Site Plans

2. Release of such documents will be solely for the convenience of the Contractor. No such document is a Contract Document.

3. Unless the Contract Documents explicitly identify that such information will be available to the Successful Bidder (Contractor), nothing herein will create an obligation on the part of the Owner or Engineer to provide or create such information, and the Contractor is not entitled to rely on the availability of such information in the preparation of its Bid or pricing of the Work. In all cases, the Contractor shall take appropriate measures to verify that any electronic/digital information provided in Electronic Documents is appropriate and adequate for the Contractor’s specific purposes.

4. In no case will the Contractor be entitled to additional compensation or time for completion due to any differences between the actual Contract Documents and any related document in native file format.

ARTICLE 3—QUALIFICATIONS OF BIDDERS

3.01 Bidder is to submit the following information with its Bid to demonstrate Bidder’s qualifications to perform the Work:

A. Written evidence establishing its qualifications such as financial data, previous experience, and present commitments.

B. A written statement that Bidder is authorized to do business in the state where the Project is located, or a written certification that Bidder will obtain such authority prior to the Effective Date of the Contract.

C. Bidder’s state or other contractor license number, if applicable.

D. Subcontractor and Supplier qualification information.

E. EJCDC C-451 Statement of Qualifications.

F. Other required information regarding qualifications.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,

3.02 A Bidder’s failure to submit required qualification information within the times indicated may disqualify Bidder from receiving an award of the Contract.

3.03 No requirement in this Article 3 to submit information will prejudice the right of Owner to seek additional pertinent information regarding Bidder’s qualifications.

ARTICLE 4—PRE-BID CONFERENCE

4.01 A non-mandatory pre-bid conference will be held at the time and location indicated in the Advertisement or invitation to bid. Representatives of Owner and Engineer will be present to discuss the Project.

4.02 Information presented at the pre-Bid conference does not alter the Contract Documents. Owner will issue Addenda to make any changes to the Contract Documents that result from discussions at the pre-Bid conference. Information presented, and statements made at the pre-bid conference will not be binding or legally effective unless incorporated in an Addendum.

ARTICLE 5—SITE AND OTHER AREAS; EXISTING SITE CONDITIONS; EXAMINATION OF SITE; OWNER’S

SAFETY PROGRAM; OTHER WORK AT THE SITE

5.01 Site and Other Areas

A. The Site is identified in the Bidding Documents. By definition, the Site includes rights-of-way, easements, and other lands furnished by Owner for the use of the Contractor. Any additional lands required for temporary construction facilities, construction equipment, or storage of materials and equipment, and any access needed for such additional lands, are to be obtained and paid for by Contractor.

5.02 Existing Site Conditions

A. Subsurface and Physical Conditions; Hazardous Environmental Conditions

1. The Supplementary Conditions identify the following regarding existing conditions at or adjacent to the Site:

a. Those reports of explorations and tests of subsurface conditions at or adjacent to the Site that contain Technical Data.

b. Those drawings known to Owner of existing physical conditions at or adjacent to the Site, including those drawings depicting existing surface or subsurface structures at or adjacent to the Site (except Underground Facilities), that contain Technical Data.

c. Reports and drawings known to Owner relating to Hazardous Environmental Conditions that have been identified at or adjacent to the Site.

d. Technical Data contained in such reports and drawings.

2. Owner will make copies of reports and drawings referenced above available to any Bidder on request. These reports and drawings are not part of the Contract Documents, but the Technical Data contained therein upon whose accuracy Bidder is entitled to rely, as provided in the General Conditions, has been identified and established in the Supplementary Conditions. Bidder is responsible for any interpretation or conclusion

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, Bidder draws from any Technical Data or any other data, interpretations, opinions, or information contained in such reports or shown or indicated in such drawings.

3. If the Supplementary Conditions do not identify Technical Data, the default definition of Technical Data set forth in Article 1 of the General Conditions will apply.

B. Underground Facilities: Underground Facilities are shown or indicated on the Drawings, pursuant to Paragraph 5.05 of the General Conditions, and not in the drawings referred to in Paragraph 5.02.A of these Instructions to Bidders. Information and data regarding the presence or location of Underground Facilities are not intended to be categorized, identified, or defined as Technical Data.

5.03 Other Site-related Documents

A. In addition to the documents regarding existing Site conditions referred to in Paragraph 5.02.A, the following other documents relating to conditions at or adjacent to the Site are known to Owner and made available to Bidders for reference:

1. Sliwinski WTP and Quarry Pump Station Record Drawings

Owner will make copies of these other Site-related documents available to any Bidder on request.

B. Owner has not verified the contents of these other Site-related documents, and Bidder may not rely on the accuracy of any data or information in such documents. Bidder is responsible for any interpretation or conclusion Bidder draws from the other Site-related documents.

C. The other Site-related documents are not part of the Contract Documents.

D. Bidders are encouraged to review the other Site-related documents, but Bidders will not be held accountable for any data or information in such documents. The requirement to review and take responsibility for documentary Site information is limited to information in (1) the Contract Documents and (2) the Technical Data.

E. No other Site-related documents are available.

5.04 Site Visit and Testing by Bidders

A. Bidder is required to visit the Site and conduct a thorough visual examination of the Site and adjacent areas. During the visit the Bidder must not disturb any ongoing operations at the Site.

B. Bidders are responsible for requesting and scheduling a site from Frederick Water.

C. Bidders visiting the Site are required to arrange their own transportation to the Site.

D. All access to the Site other than during a regularly scheduled Site visit must be coordinated through the following Owner or Engineer contact for visiting the Site: Brandon

Abshire at babshire@frederickwater.com. Bidder must conduct the required Site visit during normal working hours.

E. Bidder is not required to conduct any subsurface testing, or exhaustive investigations of Site conditions.

F. On request, and to the extent Owner has control over the Site, and schedule permitting, the Owner will provide Bidder general access to the Site to conduct such additional

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, examinations, investigations, explorations, tests, and studies as Bidder deems necessary for preparing and submitting a successful Bid. Owner will not have any obligation to grant such access if doing so is not practical because of existing operations, security or safety concerns, or restraints on Owner’s authority regarding the Site. Bidder is responsible for establishing access needed to reach specific selected test sites.

G. Bidder must comply with all applicable Laws and Regulations regarding excavation and location of utilities, obtain all permits, and comply with all terms and conditions established by Owner or by property owners or other entities controlling the Site with respect to schedule, access, existing operations, security, liability insurance, and applicable safety programs.

H. Bidder must fill all holes and clean up and restore the Site to its former condition upon completion of such explorations, investigations, tests, and studies.

5.05 Owner’s Safety Program

A. Site visits and work at the Site may be governed by an Owner safety program. If an Owner safety program exists, it will be noted in the Supplementary Conditions.

5.06 Other Work at the Site

A. Reference is made to Article 8 of the Supplementary Conditions for the identification of the general nature of other work of which Owner is aware (if any) that is to be performed at the Site by Owner or others (such as utilities and other prime contractors) and relates to the Work contemplated by these Bidding Documents. If Owner is party to a written contract for such other work, then on request, Owner will provide to each Bidder access to examine such contracts (other than portions thereof related to price and other confidential matters), if any.

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Express Representations and Certifications in Bid Form, Agreement

A. The Bid Form that each Bidder will submit contains express representations regarding the Bidder’s examination of Project documentation, Site visit, and preparation of the Bid, and certifications regarding lack of collusion or fraud in connection with the Bid. Bidder should review these representations and certifications, and assure that Bidder can make the representations and certifications in good faith, before executing and submitting its Bid.

B. Before submitting bids, each bidder must examine bid documents thoroughly; familiarize itself with federal, state, and local laws, ordinances, rules, and regulations affecting the work;

and correlate observations with requirements of the bid documents.

C. If Bidder is awarded the Contract, Bidder (as Contractor) will make similar express representations and certifications when it executes the Agreement.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, ARTICLE 7—INTERPRETATIONS AND ADDENDA

7.01 Owner on its own initiative may issue Addenda to clarify, correct, supplement, or change the Bidding Documents.

7.02 Bidder shall submit all questions about the meaning or intent of the Bidding Documents to Engineer in writing. Contact information and submittal procedures for such questions are as follows:

7.03 Via email to Connie Morrison-Henry, Purchasing Manager at chenry@frederickwater.com

7.04 Interpretations or clarifications considered necessary by Engineer in response to such questions will be issued by Addenda and will be posted on Frederick Water’s website and eVA, consistent with the Advertisement. Questions received less than seven days prior to the date for opening of Bids may not be answered.

7.05 Only responses set forth in an Addendum will be binding. Oral and other interpretations or clarifications will be without legal effect. Responses to questions are not part of the Contract Documents unless set forth in an Addendum that expressly modifies or supplements the Contract Documents.

ARTICLE 8—BID SECURITY

8.01 A Bid must be accompanied by Bid security made payable to Owner in an amount of 5 percent of Bidder’s maximum Bid price (determined by adding the base bid) and in the form of a Bid bond issued by a surety meeting the requirements of Paragraph 6.01 of the General Conditions or a cashier's check. Such Bid bond will be issued in the form included in the Bidding Documents.

8.02 The Bid security of the apparent Successful Bidder will be retained until Owner awards the contract to such Bidder, and such Bidder has executed the Contract, furnished the required Contract security, and met the other conditions of the Notice of Award, whereupon the Bid security will be released. If the Successful Bidder fails to execute and deliver the Contract and furnish the required Contract security within 15 days after the Notice of Award, Owner may consider Bidder to be in default, annul the Notice of Award, and the Bid security of that Bidder will be forfeited, in whole in the case of a penal sum bid bond, and to the extent of Owner’s damages in the case of a damages-form bond. Such forfeiture will be Owner’s exclusive remedy if Bidder defaults.

8.03 The Bid security of other Bidders that Owner believes to have a reasonable chance of receiving the award may be retained by Owner until the earlier of 7 days after the Effective Date of the Contract or 61 days after the Bid opening, whereupon Bid security furnished by such Bidders will be released.

8.04 Bid security of other Bidders that Owner believes do not have a reasonable chance of receiving the award will be released within 7 days after the Bid opening.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, ARTICLE 9—CONTRACT TIMES

9.01 The number of days within which, or the dates by which, the Work is to be (a) substantially completed and (b) ready for final payment, and (c) Milestones (if any) are to be achieved, are set forth in the Agreement.

9.02 Provisions for liquidated damages, if any, for failure to timely attain a Milestone, Substantial Completion, or completion of the Work in readiness for final payment, are set forth in the Agreement.

ARTICLE 10—SUBSTITUTE AND “OR EQUAL” ITEMS

10.01 The Contract for the Work, as awarded, will be on the basis of materials and equipment specified or described in the Bidding Documents without consideration during the bidding and Contract award process of possible substitute or “or-equal” items. In cases in which the Contract allows the Contractor to request that Engineer authorize the use of a substitute or “or-equal” item of material or equipment, application for such acceptance may not be made to and will not be considered by Engineer until after the Effective Date of the Contract.

10.02 All prices that Bidder sets forth in its Bid will be based on the presumption that the Contractor will furnish the materials and equipment specified or described in the Bidding Documents, as supplemented by Addenda. Any assumptions regarding the possibility of post-Bid approvals of “or-equal” or substitution requests are made at Bidder’s sole risk.

ARTICLE 11—SUBCONTRACTORS, SUPPLIERS, AND OTHERS

11.01 A Bidder must be prepared to retain specific Subcontractors and Suppliers for the performance of the Work if required to do so by the Bidding Documents or in the Specifications. If a prospective Bidder objects to retaining any such Subcontractor or Supplier and the concern is not relieved by an Addendum, then the prospective Bidder should refrain from submitting a Bid.

11.02 The apparent Successful Bidder, and any other Bidder so requested, must submit to Owner a list of the Subcontractors or Suppliers proposed for the following portions of the Work within five days after Bid opening:

11.03 If requested by Owner, such list must be accompanied by an experience statement with pertinent information regarding similar projects and other evidence of qualification for each such Subcontractor or Supplier. If Owner or Engineer, after due investigation, has reasonable objection to any proposed Subcontractor or Supplier, Owner may, before the Notice of Award is given, request apparent Successful Bidder to submit an acceptable substitute, in which case apparent Successful Bidder will submit a substitute, Bidder’s Bid price will be increased (or decreased) by the difference in cost occasioned by such substitution, and Owner may consider such price adjustment in evaluating Bids and making the Contract award.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,

11.04 If apparent Successful Bidder declines to make any such substitution, Owner may award the Contract to the next lowest Bidder that proposes to use acceptable Subcontractors and Suppliers.

Declining to make requested substitutions will constitute grounds for forfeiture of the Bid security of any Bidder. Any Subcontractor or Supplier, so listed and against which Owner or Engineer makes no written objection prior to the giving of the Notice of Award will be deemed acceptable to Owner and Engineer subject to subsequent revocation of such acceptance as provided in Paragraph 7.07 of the General Conditions.

ARTICLE 12—PREPARATION OF BID

12.01 The Bid Form is included with the Bidding Documents.

A. All blanks on the Bid Form must be completed in ink and the Bid Form signed in ink. Erasures or alterations must be initialed in ink by the person signing the Bid Form. A Bid price must be indicated for each section, Bid item, alternate, adjustment unit price item, and unit price item listed therein.

B. If the Bid Form expressly indicates that submitting pricing on a specific alternate item is optional, and Bidder elects to not furnish pricing for such optional alternate item, then Bidder may enter the words “No Bid” or “Not Applicable.”

12.02 If Bidder has obtained the Bidding Documents as Electronic Documents, then Bidder shall prepare its Bid on a paper copy of the Bid Form printed from the Electronic Documents version of the Bidding Documents. The printed copy of the Bid Form must be clearly legible, printed on 8½ inch by 11-inch paper and as closely identical in appearance to the Electronic Document version of the Bid Form as may be practical. The Owner reserves the right to accept Bid Forms which nominally vary in appearance from the original paper version of the Bid Form, providing that all required information and submittals are included with the Bid.

12.03 A Bid by a corporation must be executed in the corporate name by a corporate officer (whose title must appear under the signature), accompanied by evidence of authority to sign. The corporate address and state of incorporation must be shown.

12.04 A Bid by a partnership must be executed in the partnership name and signed by a partner (whose title must appear under the signature), accompanied by evidence of authority to sign. The official address of the partnership must be shown.

12.05 A Bid by a limited liability company must be executed in the name of the firm by a member or other authorized person and accompanied by evidence of authority to sign. The state of formation of the firm and the official address of the firm must be shown.

12.06 A Bid by an individual must show the Bidder’s name and official address.

12.07 A Bid by a joint venture must be executed by an authorized representative of each joint venturer in the manner indicated on the Bid Form. The joint venture must have been formally established prior to submittal of a Bid, and the official address of the joint venture must be shown.

12.08 All names must be printed in ink below the signatures.

12.09 The Bid must contain an acknowledgment of receipt of all Addenda, the numbers of which must be filled in on the Bid Form.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,

12.10 Postal and e-mail addresses and telephone number for communications regarding the Bid must be shown.

12.11 The Bid must contain evidence of Bidder’s authority to do business in the state where the Project is located, or Bidder must certify in writing that it will obtain such authority within the time for acceptance of Bids and attach such certification to the Bid.

12.12 If Bidder is required to be licensed to submit a Bid or perform the Work in the state where the Project is located, the Bid must contain evidence of Bidder’s licensure, or Bidder must certify in writing that it will obtain such licensure within the time for acceptance of Bids and attach such certification to the Bid. Bidder’s state contractor license number, if any, must also be shown on the Bid Form.

ARTICLE 13—BASIS OF BID

13.01 Base Bid

A. Bidders must submit a Bid on a lump sum basis as set forth in the Bid Form.

ARTICLE 14—SUBMITTAL OF BID

14.01 A Bid must be received no later than the date and time prescribed and at the place indicated in the Advertisement or invitation to bid and must be enclosed in a plainly marked package with the Project title, and, if applicable, the designated portion of the Project for which the Bid is submitted, the name and address of Bidder, and must be accompanied by the Bid security and other required documents. If a Bid is sent by mail or other delivery system, the sealed envelope containing the Bid must be enclosed in a separate package plainly marked on the outside with the notation “BID ENCLOSED.” A mailed Bid must be addressed to the location designated in the Advertisement.

A. Bid package must contain the following project title notation: “Whetzel Well Raw Water Line Relocation”

B. Bid package must contain the following Bidder license and contact notation: “Contractor’s Current Virginia License No. “ and Bidder name, address, and primary contact name, title, phone and email address.

C. Bid package must contain the following Owner contact notation: Connie Henry, Purchasing Manager Frederick Water, 315 Tasker Road, Stephens City, VA 22655.

D. All in-person bids must be hand delivered to Frederick Water’s Purchasing Manager or her designee.

E. Bidders are cautioned to check with their preferred shipping or delivery companies for any schedule alterations or closings that may impact the delivery.

14.02 Bids received after the date and time prescribed for the opening of bids, or not submitted at the correct location or in the designated manner, will not be accepted and will be returned to the Bidder unopened.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, ARTICLE 15—MODIFICATION AND WITHDRAWAL OF BID

15.01 Bids may be modified or withdrawn by an appropriate document duly executed (in the manner that a bid must be executed) and delivered to the place where bids are to be submitted at any time prior to the date and time for the opening of bids.

15.02 No bidder shall withdraw, modify, or cancel any part of a bid for the number of days stated on the bid form following this date and time except as provided by Code of Virginia Section 2.2-4330(a) Procedure (1).

15.03 Withdrawal of Bids After Date for Submission: In accordance with Section 2.2-4330(a) Procedure

(1) the bidder shall give notice in writing of their claim of right to withdraw their bid within 2 business days after the conclusion of the bid opening procedure and shall submit original work papers with such notice. Failure to submit contractor’s work papers will be considered as a waiver of any right of withdrawal of bids after the date for submission.

ARTICLE 16—OPENING OF BIDS

16.01 Bids will be opened at the time and place indicated in the advertisement or invitation to bid and, unless obviously non-responsive, read aloud publicly. An abstract of the amounts of the base Bids and major alternates, if any, will be made available to Bidders after the opening of Bids.

16.02 The Bid abstract will be posted on Frederick Water’s website following the bid opening.

(https://www.frederickwater.com/bid-specs)

ARTICLE 17—BIDS TO REMAIN SUBJECT TO ACCEPTANCE

17.01 All Bids will remain subject to acceptance for the period of time stated in the Bid Form, but Owner may, in its sole discretion, release any Bid and return the Bid security prior to the end of this period.

ARTICLE 18—EVALUATION OF BIDS AND AWARD OF CONTRACT

18.01 Owner reserves the right to reject any or all Bids, including without limitation, nonconforming, nonresponsive, unbalanced, or conditional Bids. Owner also reserves the right to waive all minor Bid informalities not involving price, time, or changes in the Work.

18.02 Owner will reject the Bid of any Bidder that Owner finds, after reasonable inquiry and evaluation, to not be responsible.

18.03 If Bidder purports to add terms or conditions to its Bid, takes exception to any provision of the Bidding Documents, or attempts to alter the contents of the Contract Documents for purposes of the Bid, whether in the Bid itself or in a separate communication to Owner or Engineer, then Owner will reject the Bid as nonresponsive.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,

18.04 If Owner awards the contract for the Work, such award will be to the responsible Bidder submitting the lowest responsive Bid.

18.05 Evaluation of Bids

A. In evaluating Bids, Owner will consider whether the Bids comply with the prescribed requirements, and such alternates, unit prices, and other data, as may be requested in the Bid Form or prior to the Notice of Award.

18.06 In evaluating whether a Bidder is responsible, Owner will consider the qualifications of the Bidder and may consider the qualifications and experience of Subcontractors and Suppliers proposed for those portions of the Work for which the identity of Subcontractors and Suppliers must be submitted as provided in the Bidding Documents.

18.07 Owner may conduct such investigations as Owner deems necessary to establish the responsibility, qualifications, and financial ability of Bidders and any proposed Subcontractors or Suppliers.

18.08 Negotiation with the Lowest Bidder: Unless all bids are canceled or rejected, Owner reserves the right to negotiate with the lowest responsive and responsible bidder to obtain a contract price within the funds available to Owner whenever such low bid exceeds Owner’s available funds for the project. Owner shall initiate such negotiations by written notice to the lowest responsive, responsible bidder that its bid exceeds the available funds and Owner wishes to negotiate a lower contract price. The times, places and manner of negotiating shall be agreed to by Owner and the lowest responsive, responsible bidder. Contract modifications as a result of negotiations will be issued as a change order issued concurrently with the Notice of Award and Agreement in accordance with the procedures identified in the General Conditions and/or Agreement.

ARTICLE 19—BONDS AND INSURANCE

19.01 Article 6 of the General Conditions, as may be modified by the Supplementary Conditions, sets forth Owner’s requirements as to performance and payment bonds, other required bonds (if any), and insurance. When the Successful Bidder delivers the executed Agreement to Owner, it must be accompanied by required bonds and insurance documentation.

19.02 Article 8, Bid Security, of these Instructions, addresses any requirements for providing bid bonds as part of the bidding process.

ARTICLE 20—SIGNING OF AGREEMENT

20.01 When Owner issues a Notice of Award to the Successful Bidder, it will be accompanied by the unexecuted counterparts of the Agreement along with the other Contract Documents as identified in the Agreement. Within 15 days thereafter, Successful Bidder must execute and deliver the required number of counterparts of the Agreement and any bonds and insurance documentation required to be delivered by the Contract Documents to Owner. Within 10 days thereafter, Owner will deliver one fully executed counterpart of the Agreement to Successful Bidder, together with printed and electronic copies of the Contract Documents as stated in Paragraph 2.02 of the General Conditions.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, ARTICLE 21—ADDITIONAL REQUIREMENTS

21.01 Bidders must comply with the President’s Executive Order #11246, prohibiting discrimination in employment regarding race, color, creed, sex or national origin, and Executive Orders #12138 and #11625 regarding utilization of MBE/WBE firms. Bidders must certify that they do not or will not maintain or provide for their employees any facilities that are segregated on the basis of race, color, creed or national origin; and bidders must comply with the Civil Rights Act of 1964.

21.02 Bidders must comply with all Occupational Safety and Health Administration (OSHA), State Occupational Health Standards, and any other applicable rules and regulations.

EJCDC® C-410, Bid Form for Construction Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, BID FORM FOR

WHETZEL WELL RAW WATER LINE RELOCATION,

FREDERICK COUNTY, VA

The terms used in this Bid with initial capital letters have the meanings stated in the Instructions to Bidders, the General Conditions, and the Supplementary Conditions.

ARTICLE 1—OWNER AND BIDDER

1.01 This Bid is submitted to:

Frederick Water Connie Henry, Purchasing Manager 315 Tasker Road Stephens City, VA 22655

1.02 The undersigned Bidder proposes and agrees, if this Bid is accepted, to enter into an Agreement with Owner in the form included in the Bidding Documents to perform all Work as specified or indicated in the Bidding Documents for the Whetzel Well Raw Water Line Relocation in strict accordance with the Drawings and Project Manual prepared by Frederick Water dated July 17, 2026, together with the addenda issued during bidding period for the prices and within the times indicated in this Bid and in accordance with the other terms and conditions of the Bidding Documents.

ARTICLE 2—ATTACHMENTS TO THIS BID

2.01 The following documents are submitted with and made a condition of this Bid:

A. Required Bid security;

B. Evidence of authority to do business in the state of the Project;

C. Contractor’s license number as evidence of Bidder’s State Contractor’s License;

D. Required EJCDC C-451 Bidder Qualification Statement with supporting data;

E. Non-Collusion Affidavit

F. SCC Form

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, ARTICLE 3—BASIS OF BID—LUMP SUM BID AND UNIT PRICES

3.01 Lump Sum Bids

A. Bidder will complete the Work in accordance with the Contract Documents for the following lump sum (stipulated) price:

1. Lump Sum Price (Base Bid)

1. Lump Sum Bid Price for Whetzel Well Raw Water Line Relocation to complete the Work associated with the drawing set titled “Whetzel Well Raw Water Line Relocation” dated July 17, 2026 and applicable specifications.

Base Bid (Item 1):

ARTICLE 4—TIME OF COMPLETION

4.01 Bidder agrees that the Work will be substantially complete and will be completed and ready for final payment in accordance with Paragraph 15.06 of the General Conditions on or before the dates or within the number of calendar days indicated in the Agreement.

4.02 Bidder accepts the provisions of the Agreement as to liquidated damages.

ARTICLE 5—BIDDER’S ACKNOWLEDGEMENTS: ACCEPTANCE PERIOD, INSTRUCTIONS, AND RECEIPT OF

ADDENDA

5.01 Bid Acceptance Period

A. This Bid will remain subject to acceptance for 60 days after the Bid opening, or for such longer period of time that Bidder may agree to in writing upon request of Owner.

5.02 Instructions to Bidders

A. Bidder accepts all of the terms and conditions of the Instructions to Bidders, including without limitation those dealing with the disposition of Bid security.

5.03 Receipt of Addenda

A. Bidder hereby acknowledges receipt of the following Addenda:

Addendum Number Addendum Date

ARTICLE 6—BIDDER’S REPRESENTATIONS AND CERTIFICATIONS

6.01 Bidder’s Representations

A. In submitting this Bid, Bidder represents the following:

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,

1. Bidder has examined and carefully studied the Bidding Documents, including Addenda.

2. Bidder has visited the Site, conducted a thorough visual examination of the Site and adjacent areas, and become familiar with the general, local, and Site conditions that may affect cost, progress, and performance of the Work.

3. Bidder is familiar with all Laws and Regulations that may affect cost, progress, and performance of the Work.

4. Bidder has carefully studied the reports of explorations and tests of subsurface conditions at or adjacent to the Site and the drawings of physical conditions relating to existing surface or subsurface structures at the Site that have been identified in the Supplementary Conditions, with respect to the Technical Data in such reports and drawings.

5. Bidder has carefully studied the reports and drawings relating to Hazardous Environmental Conditions, if any, at or adjacent to the Site that have been identified in the Supplementary Conditions, with respect to Technical Data in such reports and drawings.

6. Bidder has considered the information known to Bidder itself; information commonly known to contractors doing business in the locality of the Site; information and observations obtained from visits to the Site; the Bidding Documents; and the Technical Data identified in the Supplementary Conditions or by definition, with respect to the effect of such information, observations, and Technical Data on (a) the cost, progress, and performance of the Work; (b) the means, methods, techniques, sequences, and procedures of construction to be employed by Bidder, if selected as Contractor; and

(c) Bidder’s (Contractor’s) safety precautions and programs.

7. Based on the information and observations referred to in the preceding paragraph, Bidder agrees that no further examinations, investigations, explorations, tests, studies, or data are necessary for the performance of the Work at the Contract Price, within the Contract Times, and in accordance with the other terms and conditions of the Contract.

8. Bidder is aware of the general nature of work to be performed by Owner and others at the Site that relates to the Work as indicated in the Bidding Documents.

9. Bidder has given Engineer written notice of all conflicts, errors, ambiguities, or discrepancies that Bidder has discovered in the Bidding Documents, and of discrepancies between Site conditions and the Contract Documents, and the written resolution thereof by Engineer is acceptable to Contractor.

10. The Bidding Documents are generally sufficient to indicate and convey understanding of all terms and conditions for performance and furnishing of the Work.

11. The submission of this Bid constitutes an incontrovertible representation by Bidder that without exception the Bid and all prices in the Bid are premised upon performing and furnishing the Work required by the Bidding Documents.

6.02 Bidder’s Certifications

A. The Bidder certifies the following:

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,

1. This Bid is genuine and not made in the interest of or on behalf of any undisclosed individual or entity and is not submitted in conformity with any collusive agreement or rules of any group, association, organization, or corporation.

2. Bidder has not directly or indirectly induced or solicited any other Bidder to submit a false or sham Bid.

3. Bidder has not solicited or induced any individual or entity to refrain from bidding.

4. Bidder has not engaged in corrupt, fraudulent, collusive, or coercive practices in competing for the Contract. For the purposes of this Paragraph 8.02.A:

a. Corrupt practice means the offering, giving, receiving, or soliciting of anything of value likely to influence the action of a public official in the bidding process.

b. Fraudulent practice means an intentional misrepresentation of facts made (a) to influence the bidding process to the detriment of Owner, (b) to establish bid prices at artificial non-competitive levels, or (c) to deprive Owner of the benefits of free and open competition.

c. Collusive practice means a scheme or arrangement between two or more Bidders, with or without the knowledge of Owner, a purpose of which is to establish bid prices at artificial, non-competitive levels.

d. Coercive practice means harming or threatening to harm, directly or indirectly, persons or their property to influence their participation in the bidding process or affect the execution of the Contract.

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, BIDDER hereby submits this Bid as set forth above:

Bidder:

By:

Name:

Title:

Date:

(typed or printed name of organization)

(individual’s signature)

(typed or printed)

(typed or printed)

If Bidder is a corporation, a partnership, or a joint venture, attach evidence of authority to sign.

Attest:

Title:

Address for giving notices:

Bidder’s Contact:

Phone:

Email:

Address:

Bidder’s Contractor License No.: (if applicable)

NON-COLLUSION AFFIDAVIT

Each of the undersigned, being first duly sworn, deposes and says that:

is the of and is the of , which entity(ies) are submitting a Bid for the

(the “Project”).

A. I, the firm, corporation or officers, agents or employees thereof have neither directly nor indirectly entered into any combination or arrangement with any person, firm, or corporation or entered into any agreement, participated in any collusion, or otherwise taken any action in restraint of free competitive bidding in connection with such contract, the effect of which is to prevent competition or increase the cost of construction or maintenance of the Project.

Signed at , this day of , 2026

County (City), State

(Name of Firm) (Signature) Title (Print)

STATE of COUNTY (CITY) of

I , a Notary Public in and for the State and County (City) aforesaid, hereby certify that this day personally appeared before me and made oath that he/she is duly authorized to make the above statements and that such statements are true and correct.

Subscribed and sworn to before me this day of , 2026

My Commission expires:

Notary Public

[Duplicate or modify this form as necessary so that it accurately describes the entity submitting the Proposal and so that it is signed on behalf of Proposer by an authorized representative thereof, or, if Proposer is a joint venture or other association other than a corporation, limited liability company or partnership, so that it is signed by an authorized representative of each member of the Proposer.]

EJCDC® C-430, Bid Bond (Penal Sum Form).

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies, BID BOND (PENAL SUM FORM)

Bidder

Address (principal place of business):

Surety

Name:

Address (principal place of business):

Owner Bid

Name:

Frederick County Sanitation Authority d/b/a Frederick Water

Project (name and location):

Address (principal place of business): Whetzel Well Raw Water Line Relocation, Frederick County, VA

315 Tasker Road

Stephens City, VA 22655

Bid Due Date:

Bond

Penal Sum:

Date of Bond:

Surety and Bidder, intending to be legally bound hereby, subject to the terms set forth in this Bid Bond, do each cause this Bid Bond to be duly executed by an authorized officer, agent, or representative.

Bidder Surety

(Full formal name of Bidder)

By:

(Signature)

Name:

(Printed or typed)

Title:

Attest:

(Signature)

Name:

(Printed or typed)

Title:

(Full formal name of Surety) (corporate seal)

By:

(Signature) (Attach Power of Attorney)

Name:

(Printed or typed)

Title:

Attest:

(Signature)

Name:

(Printed or typed)

Title:

Notes: (1) Note: Addresses are to be used for giving any required notice. (2) Provide execution by any additional parties, such as joint venturers, if necessary.

EJCDC® C-430, Bid Bond (Penal Sum Form).

Copyright© 2018 National Society of Professional Engineers, American Council of Engineering Companies,

1. Bidder and Surety, jointly and severally, bind themselves, their heirs, executors, administrators, successors, and assigns to pay to Owner upon default of Bidder the penal sum set forth on the face of this Bond.

Payment of the penal sum is the extent of Bidder’s and Surety’s liability. Recovery of such penal sum under the terms of this Bond will be Owner’s sole and exclusive remedy upon default of Bidder.

2. Default of Bidder occurs upon the failure of Bidder to deliver within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents.

3. This obligation will be null and void if:

3.1. Owner accepts Bidder’s Bid and Bidder delivers within the time required by the Bidding Documents (or any extension thereof agreed to in writing by Owner) the executed Agreement required by the Bidding Documents and any performance and payment bonds required by the Bidding Documents, or

3.2. All Bids are rejected by Owner, or

3.3. Owner fails to issue a Notice of Award to Bidder within the time specified in the Bidding Documents (or any extension thereof agreed to in writing by Bidder and, if applicable, consented to by Surety when required by…

This is the start of the file's text. The full file is on GovTribe.