Resurfacing Approximately 1. 62 miles of Existing Roadway on SR 2004
Solicitation number
123810
Issued by
Luzerne County, Pennsylvania

About this file

Summary

This is a Project Description document for the Pennsylvania Department of Transportation (PennDOT) detailing a roadway resurfacing project on State Route 2004 in Luzerne County across various municipalities in Pennsylvania. The project involves the resurfacing of approximately 5.31 miles of existing roadway to address pavement deficiencies and improve riding surface quality. The scope of work includes asphalt wearing courses, scratch courses, milling, line painting, shoulder backup, pavement markings, and guide rail installation. All work will be performed within the existing roadway limits, with maintenance and protection of traffic (MPT) to be completed in accordance with contract special provisions using short-term traffic patterns. The project aims to eliminate current potholes, depressions, rutting, and other pavement failures to decrease ongoing roadway maintenance costs.

The document does not contain specific information regarding pricing terms, bid response dates, due dates, site visit schedules, bidders' conferences, award dates, contract term details, set asides, incumbent information, or funding sources and amounts. These critical contractual details would typically be found in the associated bidding documents, specifications, or contract award notices not included in this project description file.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PROPOSAL Report - Project 123810

May 15, 2026 12:21:10 PM Page 1 of 48

PROPOSAL REPORT

Project: 123810 Bid

Package: 1

Current Let: 06/18/2026 11:00:00 AM

Version: Current Addendum

Count: 0

District: 04 County: Luzerne

SR/SEC/

Group ID: 2004/409/---

Description

SR 2004 Resurfacing

May 15, 2026 12:21:10 PM Page 2 of 48

TABLE OF CONTENTS

BID PACKAGE SUMMARY

PROJECT ITEMS AND QUANTITIES

SPECIAL PROVISIONS

00 - a00001 CONSTRUCTION RESTRICTIONS AND REQUIREMENTS G4010C - a00002 REQUIRED NOTIFICATIONS G51A - a00051 APPLICABLE DESIGNATED SPECIAL PROVISIONS (STATE) G113B - a00113 CONTRACT PROVISIONS - RIGHT-TO-KNOW LAW C164A - a00164 CHANGES TO SPECIFICATIONS: SECTION 106 C166A - a00166 CHANGES TO SPECIFICATIONS: SECTIONS 107 AND 608 C167A - a00167 CHANGES TO SPECIFICATIONS: APPENDIX C—DESIGNATED SPECIAL PROVISIONS and APPENDIX C, DSP 20

C168A - a00168 CHANGES TO SPECIFICATIONS: SECTIONS 110, 404, AND 507 G1401A - a01401 EQUAL EMPLOYMENT OPPORTUNITY WITH PREQUALIFICATION G1901B - a01901 INSURANCE--GENERAL APPLICATION G2201A - a02201 RAILROAD COMPANY CONTACT PERSON LCRA G2301B - a02301 MAINTENANCE AND PROTECTION OF RAILROAD TRAFFIC (LCRA) G2302A - a02302 Worker Protection and Investment G3401A - a03401 PREVAILING WAGE ACT G3501B - a03501 RECIPROCAL LIMITATIONS ACT REQUIREMENTS FOR CONSTRUCTION G90C - a080090 PUBLIC NOTIFICATION P1061D - b01061 Electronic Submission of Material Certifications through ECMS P1062D - b01062 Electronic Submission of Material Certifications through ECMS for Lump Sum Component items

G4011B - b04011 CONSTRUCTION/HOLIDAY RESTRICTIONS S41331A - b04131 SECTION 413.3(h)1.a Placing S6012B - b06012 - SECTION 601.3(f) BACKFILLING TRENCH S6092B - b06092-SECTION 609.2(f) MISCELLANEOUS MATERIALS I4413A - c0413 ITEM 4413-0255 SAMD, FOR DRIVEWAY AND SIDE ROAD I4491C - c0491 ITEM 4491-0019 VAR DEP MILLED MATERIAL RET BY CONTRACTOR, FOR

DRIVEWAY & SIDE ROAD ADJUSTMENT

I6091L - c0609 ITEM 0609-0009 EQUIPMENT PACKAGE I686A - c0686 ITEM 0686-0030 - CONSTRUCTION SURVEYING, TYPE B, MODIFIED 00 - c0901 ITEM 0901-0001 MAINTENACE AND PROTECTION OF TRAFFIC DURING

CONSTRUCTION

00 - c9009 ITEM 9000-0009 TEMPORARY MAILBOX RESET 00 - c9013 ITEM 9000-0013 STAMPED CROSSWALK IN ASPHALT ROADWAY I92121A - c9200 ITEM 9000 - 2121 SHOULDER BACKUP - R.A.P. (RECLAIMED ASPHALT

PAVEMENT) MATERIAL

I95000A - c9500 ITEM 9000-5000 - SNOWPOLE (ORANGE), 7' 0"

May 15, 2026 12:21:10 PM Page 3 of 48

I9018A - c9901 ITEM 9901-2350 RAILROAD PROTECTIVE SERVICES (100% STATE)

May 15, 2026 12:21:10 PM Page 4 of 48

BID PACKAGE SUMMARY

Project: 123810 Bid Package: 1

Project Type: Standard Posted:

Federal Project Status: Non - Federal (100% State) State Type of Work: RESURFACING/OVERLAYS

Prequalification Required: Yes Pre-Bid Meeting: None

408 Version: 2026-IE

Scheduled Let: 06/18/2026 11:00:00 AM Project Cost Range: $2,500,000.00 - $4,999,999.99 Anticipated NTP: 08/03/2026 Structure Work: 0.00%

Required Completion: 11/25/2026 Wage Rates: Yes

Description:

The purpose of the project is to improve deficiencies and provide a smoother riding surface, therefore, decrease the cost of ongoing roadway maintenance. The improvements to the roadway are to eliminate current potholes, depressions, rutting, and other pavement failures.This project is for the resurfacing of approximately 5.31 miles of existing roadway on STATE ROUTE 2004 in LUZERNE COUNTY, VARIOUS MUNICIPALITIES in the COMMONWEALTH OF PENNSYLVANIA.The resurfacing includes asphalt wearing courses, scratch courses, milling, line painting, shoulder backup, pavement markings, and guide rail. All work will be completed within the existing roadway. All maintenance and protection of traffic (MPT) will be completed in accordance with the special provisions of the contract and will consist of short-term patterns.

Additional Information:

This is an ECMS project. All Addenda will be electronically posted.The location of the public bid opening is the Commonwealth Keystone Building, 7th Floor, Contract Awards Room, 400 North Street, Harrisburg. Allow sufficient time before the bid opening to obtain a visitor pass on the 5th Floor and to be escorted to the 7th Floor Contract Awards Room.

May 15, 2026 12:21:10 PM Page 5 of 48

PROJECT ITEMS AND QUANTITIES

Alt Item Work Class Code Unit Of

Measure Quantity Unit Price PDP Spec

Prov Add Action

0316-0437 E, F1 Ton 357.0000 N

SUPERPAVE ASPHALT MIXTURE DESIGN, FLEXIBLE BASE REPLACEMENT, PG 64S-22, 0.3 TO < 3 MILLION ESALs, 25.0

MM MIX

0413-0255 F Ton 8,637.0000 N

SUPERPAVE ASPHALT MIXTURE DESIGN, WEARING COURSE, PG 64S-22, 0.3 TO < 3 MILLION ESALS, 9.5 MM MIX, SRL- H

4413-0255 F Ton 488.0000 N Std

SUPERPAVE ASPHALT MIXTURE DESIGN, WEARING COURSE, PG 64S-22, 0.3 TO < 3 MILLION ESALS, 9.5 MM MIX, SRL-

H , FOR DRIVEWAY AND SIDE ROAD ADJUSTMENTS

0413-1021 F Ton 2,879.0000 N

SUPERPAVE ASPHALT MIXTURE DESIGN, WEARING COURSE (SCRATCH), PG 64S-22, 0.3 TO < 3 MILLION ESALS, 9.5

MM MIX, SRL-H

0413-9999 X Dollar 45,172.0000 $1.00 Y

PERCENT WITHIN LIMITS (PWL) LOT INCENTIVE/DISINCENTIVE

0450-1324 F1 Ton 20.0000 N

SUPERPAVE ASPHALT MIXTURE DESIGN, WEARING COURSE, MANUAL PATCHING, PG 64S-22, < 0.3 MILLION ESALS, 9.5

MM MIX, SRL-M

0460-0003 F4 Square Yard 195,935.0000 N

ASPHALT TACK COAT (NTT/CNTT)

0461-0002 F4 Gallon 208.0000 N

ASPHALT PRIME COAT

0491-0013 F3 Square Yard 95,937.0000 N MILLING OF ASPHALT PAVEMENT SURFACE, 2" DEPTH, MILLED MATERIAL RETAINED BY CONTRACTOR

4491-0019 F3 Square Yard 4,064.0000 N Std

MILLING OF ASPHALT PAVEMENT SURFACE, VARIABLE DEPTH, MILLED MATERIAL RETAINED BY CONTRACTOR , FOR

DRIVEWAY AND SIDE ROAD ADJUSTMENTS

0605-2701 K Each 4.0000 N

BICYCLE SAFE INLET GRATE

0605-2781 K Set 10.0000 N

TYPE M FRAME AND BICYCLE SAFE GRATE

0606-0050 C1, K Set 6.0000 N

GRADE ADJUSTMENT OF EXISTING INLETS

0607-0013 K Vertical Foot 15.0000 N

REBUILT INLET BOX

0608-0001 X Lump Sum 1.0000 N

MOBILIZATION

0609-0003 X Lump Sum 1.0000 N

May 15, 2026 12:21:10 PM Page 6 of 48

INSPECTOR'S FIELD OFFICE AND INSPECTION FACILITIES, TYPE B

0609-0009 X Lump Sum 1.0000 N Std

EQUIPMENT PACKAGE

0619-0459 J1, J3 Each 1.0000 N

PERMANENT IMPACT ATTENUATING DEVICE, TYPE II, TEST LEVEL 3, TANGENT (MASH)

0620-0400 J Each 2.0000 N

TERMINAL SECTION, SINGLE

0620-0503 C1, J Linear Foot 288.0000 N

REMOVE EXISTING GUIDE RAIL (CONTRACTOR'S PROPERTY)

0620-0900 C1, J Each 2.0000 N

REMOVE CONCRETE ANCHORAGE

0620-1600 J Linear Foot 238.0000 N

TYPE 31-S GUIDE RAIL

0686-0030 X Lump Sum 1.0000 N Std

CONSTRUCTION SURVEYING, TYPE B, MODIFIED

0689-0005 X Lump Sum 1.0000 N

CPM SCHEDULE, WITH UPDATES

0690-0001 X Dollar 1,000.0000 $1.00 Y

INTERNAL FACILITATION

0901-0001 Q Lump Sum 1.0000 N Proj

MAINTENANCE AND PROTECTION OF TRAFFIC DURING CONSTRUCTION

0901-0320 O Linear Foot 196,296.0000 N

4" STANDARD PAVEMENT MARKINGS, PAINT & BEADS, YELLOW

0901-0330 O Linear Foot 57,930.0000 N

4" STANDARD PAVEMENT MARKINGS, PAINT & BEADS, WHITE

0901-0331 O Linear Foot 16,272.0000 N

6" STANDARD PAVEMENT MARKINGS, PAINT & BEADS, WHITE

0937-0107 J, R Each 8.0000 N

GUIDE RAIL MOUNTED DELINEATOR TYPE B, (W/W)

0937-0114 J, R Each 8.0000 N

GUIDE RAIL MOUNTED DELINEATOR TYPE D, (W/W)

0941-0001 R Each 3.0000 N

RESET POST MOUNTED SIGNS, TYPE B

0956-0101 P8 Linear Foot 1,648.0000 N

LOOP SENSOR

0960-0005 O2 Linear Foot 3,567.0000 N

6" WHITE HOT THERMOPLASTIC PAVEMENT MARKINGS

May 15, 2026 12:21:10 PM Page 7 of 48

0960-0026 O2 Linear Foot 294.0000 N

24" WHITE HOT THERMOPLASTIC TRANSVERSE PAVEMENT MARKINGS

0960-0127 O2 Each 1.0000 N

WHITE HOT THERMOPLASTIC LEGEND, "RR CROSSING", 6' - 6", 12' LANE WIDTH (INCLUDES "X", "RR", AND 2

TRANSVERSE BANDS)

0960-0222 O2 Each 4.0000 N

WHITE HOT THERMOPLASTIC LEGEND, "RIGHT ARROW", 12' - 0" X 3' - 0"

0960-0224 O2 Each 18.0000 N

WHITE HOT THERMOPLASTIC LEGEND, "LEFT ARROW", 12' - 0" X 3' - 0"

0960-0228 O2 Each 1.0000 N

WHITE HOT THERMOPLASTIC LEGEND, "THRU AND LEFT ARROW", 20' - 0" X 3' - 7"

0962-1000 O Linear Foot 38,620.0000 N

4" WHITE WATERBORNE PAVEMENT MARKINGS

0962-1001 O Linear Foot 10,848.0000 N

6" WHITE WATERBORNE PAVEMENT MARKINGS

0962-1005 O Linear Foot 130,864.0000 N

4" YELLOW WATERBORNE PAVEMENT MARKINGS

9000-0009 X Each 1.0000 N Proj

TEMPORARY MAILBOX RESET

9000-0013 F, K Square Yard 791.0000 N Proj

STAMPED CROSSWALK IN ASPHALT ROADWAY

9000-2121 C1, F3 Ton 50.0000 N Std

SHOULDER BACKUP - R.A.P. (RECLAIMED ASPHALT PAVEMENT) MATERIAL

9000-5000 R Each 2.0000 N Std

SNOWPOLE (ORANGE), 7' 0"

9901-2350 X Dollar 5,000.0000 $1.00 Y Std

RAILROAD PROTECTIVE SERVICES (100% STATE)

May 15, 2026 12:21:10 PM Page 8 of 48

1.

2.

3.

4.

5.

6.

1.

2.

3.

7.

8.

9.

10.

11.

12.

13.

14.

15.

16.

17.

SPECIAL PROVISIONS

Special Provision: 00 - a00001 CONSTRUCTION RESTRICTIONS AND REQUIREMENTS Addendum:

Action:

Item(s) Associated:

Header:

CONSTRUCTION RESTRICTIONS AND REQUIREMENTS

Provision Body:

CONSTRUCTION REQUIREMENTS:

An initial PA One Call must be placed within ten (10) days of when contract work is to begin. For each SR on the contract, place a PA One Call dig ticket 3 days before work is to begin.

Contact the District Traffic Engineer, Robert Kretschmer, at 570-963-4019 prior to the pre-construction conference to receive copies of any signalized intersection diagrams for the project.

Submit all asphalt and concrete mixture designs for Department approval a minimum of two weeks prior to the first placement.

If more than one asphalt or concrete material supplier is used, ensure that each source has Department approved mix designs.

Once the project is initiated, make every effort to perform continuous construction operations and minimize the length of the project. Continuous construction operations are defined as providing active construction staffing, equipment, and sufficient material each workday.

Complete the milling and/or resurfacing/repair of the project roadways in the following order:

SR 2004 Segment 0010 to Segment 0030 for MPMS 123812 SR 2004 Segment 0040/0041 to Segment 0050/0051 for MPMS 123811 SR 2004 Segment 0090 to Segment 0140 for MPMS 123810

Utilize and allocate crews, equipment, and materials as necessary for the completion of work activities within the specified work periods to deliver the project on the specified completion date, uphold project milestones, and meet all contractual requirements.

Complete the final wearing course within 14 consecutive calendar days of placing the scratch/leveling course.

When a project location calls for replacement of existing traffic loop sensors, the item will be paid for one time only. Any traffic loop sensor damaged during construction of ADA ramps, or other preparatory operations, will be repaired/replaced at no cost to the Department.

Traffic loops must be re-installed after placement of scratch course and prior to placement of the overlay.

Maintain functional drainage structures and drainage courses throughout construction of the project.

Any additional damages to existing pavement areas caused by the contractor adjacent to construction operations must be repaired at no additional cost to the Department.

Protect any material being hauled to or away from the construction site. Cover any loads which create dust or other undesirable conditions. Loads of waste material emitting any liquid drippings are not allowed on any public roadway. Clean or sweep any public roadway affected during construction of this project to the satisfaction of the representative at no additional cost to the Department.

The Department has not provided additional time in the contract for acquiring waste areas and/or permits for these waste areas, if required. Comply with all non-department permits as well as the construction schedule as required in this contract.

Monitor traffic control devices as specified in the Special Provisions entitled "Item 0901-0001 Maintenance and Protection of Traffic During Construction" and the Traffic Control Plan. Be prepared to correct any deficiencies immediately. Failure to correct deficiencies in a timely fashion may result in a project shutdown. No additional contract time will be allowed to compensate for time lost resulting from a failure to meet requirements of this provision.

Be responsible for any damages to existing utilities caused by contractor operations. Contact the applicable authority immediately in the event of any damage.

Provide all property owners and/or residents affected by construction along the project notification of impending work. Provide information in accordance with the special provision titled PUBLIC NOTIFICATION.

May 15, 2026 12:21:10 PM Page 9 of 48

18.

19.

20.

21.

22.

23.

24.

25.

26.

27.

28.

29.

30.

31.

32.

33.

34.

35.

36.

37.

38.

39.

40.

1.

2.

3.

4.

5.

Pavement joints for each state route must be sealed within 30 calendar days after patching is complete.

All shoulder reconstruction, joint repair, and base repair areas must be filled with asphalt and returned to the milled surface (long term operations) or finished grade (short term operations) at the end of each workday/work shift.

Prior to beginning milling operations, field view the locations of the existing pavement markings and prepare sketches and/or reference in the field so that they can be reproduced.

When applicable, paint all centerlines, broken white lines and edge lines before roadway is open to traffic, or when directed.

Complete all permanent pavement markings within 30 calendar days of placing the final wearing course. After October 31st, place permanent pavement markings within 7 calendar days after the completion of paving. Place thermoplastic pavement markings within 72 hours of resurfacing.

Open all lanes of traffic at the end of each work shift to unrestricted flow. If a notched wedge (longitudinal) joint is constructed as specified in 409.3(k)1.c, replace any centerline paint obscured as a result of this work at no cost to the department. If such a joint is not constructed, abutting lanes must be at the same elevation before normal traffic can be restored. If, for some unforeseen circumstance (i.e. equipment breakdown, severe weather etc.), both lanes are not open at the end of the day, provide the necessary traffic signing and protection, as directed, at no additional cost to the Department.

Maintain one open lane of traffic at all times, in all areas of this project, as required in the maintenance and protection of traffic plans.

Coordinate work with the following projects, or any other projects in or near the limits of work.

ECMS 119492 (South River Street Streetscape) ECMS 121597 (SR 2005 Resurfacing) ECMS 121083 (CenterPoint South Commerce & Trade Park Improvements)

Coordinate with any local events taking place during the duration of the project.

The contractor must notify all private property owners with driveways to keep them informed of work that will close off their access. He will try to work with the owner to avoid any conflict of schedule of any special events or deliveries at that location.

Notify the Project Manager and Contact Jessica Ruddy, District 4-0 Community Relations Coordinator, at (570) 963-4044 for a media release of work two weeks prior to start of work. Include project specific details.

Notify the Department a minimum of fourteen (14) calendar days prior to beginning milling operations.

The top of every manhole, valve box, or other access facility must be reset to the same elevation as the proposed pavement surface as per Publication 16 (DM-5) chapter 1, section 1.3.D.1.A.(10) Begin placing shoulder back-up material (when indicated) within two (2) calendar days following the completion of roadway resurfacing. Application of prime coat to occur no later than two calendar days after the shoulder back-up has been installed.

Review guide rail and provide any comments or questions in PPCC within 30 days after Notice to Proceed. A time extension will not be issued for any comments or questions submitted after this timeframe.

Any guide rail (panels, posts, etc.) removed must be reinstalled at the end of each day, if not behind concrete barrier. No blunt ends will be permitted.

Comply with all local municipal zoning ordinances regarding construction related noise.

Make driveway adjustments, when required, using material from the resurfacing operation unless otherwise indicated or directed.

Utilize a Material Transfer Vehicle (MTV) in accordance with the requirements stipulated in Publication 408 Section 108.05(c)5 for any daily paving operation.

All existing utilities remain in their current locations, excluding any relocations specifically outlined in the contact. To verify utility locations, please coordinate with utility companies through the PA One Call service.

All paving joints shall be sealed using the specified Rubberized Joint Sealing Material accordance with Publication 408, Section 705.4(c) Contractor must use a paver for patches greater than 6’ wide.

For night work, provide an approved lightening plan before scheduled night work. Provide necessary number of illumination devices to illuminate the work area to the satisfaction of the Inspector-in-charge. These illumination devices required for night work will be considered incidental to this Item 0901-0001 “Maintenance and Protection of Traffic During Construction” and will not be paid separately.

CONSTRUCTION RESTRICTIONS:

Do not store any equipment or stockpile any material within 30 feet of any roadway lane open to traffic unless protected by temporary barrier.

Do not block or park in driveways of businesses or residents with construction equipment or vehicles of any kind.

No Value Engineering of the superpave asphalt material is allowed on this project.

Do not close any lane on any state route to traffic until physical work is ready to begin.

Do not store equipment or stockpile material in any wetland or waterway. Do not park any equipment or vehicles overnight near any waterway that would allow oil, gas, hydraulic fluid, or other contaminants to enter the waterway.

May 15, 2026 12:21:10 PM Page 10 of 48

6.

7.

8.

9.

10.

Do not operate off-road equipment on any State-owned bridge or roadway.

Do not perform night work between segment 10 and segment 50. Work in these segments is not to be performed between the hours of 6 PM and 7 AM.

No Asphalt or Concrete work is to be performed within the project limits prior to April 1st of any calendar year unless prior approval is granted by the District Executive.

Do not extend the work zone traffic control pattern beyond a 3,000 ft. maximum, unless directed to do so by the inspector in charge. A minimum of 3 miles distance is required between multiple lane closures in same direction of traffic. Any shifting of lanes within the 3 miles must be coordinated and approved by the District Traffic Engineer.

No vibratory rolling within the project limits. The department will allow oscillating rolling. Density requirements for asphalt paving operations outlined in Publication 408 will not be waived.

Project Specific Details:

Special Provision: G4010C - a00002 REQUIRED NOTIFICATIONS Addendum:

REQUIRED NOTIFICATIONS

Provision Body:

Provide the following notification to the Inspector-in-Charge of the following:

Start of physical work – seven calendar days Width, height, or weight restrictions to any roadway – ten working days (excluding State holidays). This information should be on the form M-937R.

Removal of width, height, or weight restrictions to any roadway – immediately upon removal. This information should be on the form M-937RO.

Start of any operation affecting traffic (lane closures, total closures, etc.) -- seven calendar days with a confirmation the morning of the operation.

You will not be permitted to close or restrict any roadway until ten working days (excluding State holidays) after such notification is received by the District Permits Unit.

No time extensions will be granted for failure to submit the required notices.

Also, directly notify local residents, school districts, local and county emergency management agencies (EMAs) of work that impacts those entities at the start of the project and again no less than four calendar days in advance of such work. Provide documentation of such notifications to the Inspector-in-Charge.

Regardless of these provisions, provide notification to any entities that are affected by your operations sufficiently ahead of the operations to allow those entities to adjust their operations accordingly.

Special Provision: G51A - a00051 APPLICABLE DESIGNATED SPECIAL PROVISIONS (STATE)

May 15, 2026 12:21:10 PM Page 11 of 48

APPLICABLE DESIGNATED SPECIAL PROVISIONS (STATE)

Provision Body:

APPLICABLE DESIGNATED SPECIAL PROVISIONS. The following Designated Special Provisions are found in Appendix C and apply to this bid proposal.

DSP4. Diverse Business (DB) Requirements for Non-Federally Funded Construction Projects.

DSP9. Special Supplement - Anti-Pollution Measures - August 26, 1999.

DSP15. Commonwealth Standard Terms and Conditions.

Special Provision: G113B - a00113 CONTRACT PROVISIONS - RIGHT-TO-KNOW LAW

CONTRACT PROVISIONS - RIGHT TO KNOW LAW

Provision Body:

I. Contract Provisions – Right to Know Law 8-K-1532

a. The Pennsylvania Right-to-Know Law (RTKL), 65 P.S. §§ 67.101-3104, applies to this Contract.

b. If the Department needs assistance in any matter arising out of the RTKL related to this Contract, the Department will notify the Contractor using the legal contact information provided in this Contract. The Contractor, at any time, may designate a different contact for such purpose upon reasonable prior written notice to the Department.

c. Upon written notification from the Department that it requires assistance in responding to a request under the RTKL for information related to this Contract that may be in the Contractor’s possession, constituting, or alleged to constitute, a public record in accordance with the RTKL (“Requested Information”), the Contractor will:

1. Provide the Department, within 10 calendar days after receipt of written notification, access to, and copies of, any document or information in the Contractor’s possession arising out of this Contract that the Department reasonably believes is Requested Information and may be a public record under the RTKL; and

2. Provide such other assistance as the Department may reasonably request, in order to comply with the RTKL with respect to this Contract.

d. If the Contractor considers the Requested Information to include a request for a Trade Secret or Confidential Proprietary Information, as those terms are defined by the RTKL, or other information that the Contractor considers exempt from production

May 15, 2026 12:21:10 PM Page 12 of 48 under the RTKL, notify the Department and provide, within 7 calendar days of receiving the written notification, a written statement signed by a representative of the Contractor explaining why the requested material is exempt from public disclosure under the RTKL.

e. The Department will rely upon the written statement from the Contractor in denying a RTKL request for the Requested Information unless the Department determines that the Requested Information is clearly not protected from disclosure under the RTKL. Should the Department determine that the Requested Information is clearly not exempt from disclosure, provide the Requested Information within 7 calendar days of receipt of written notification of the Department’s determination.

f. Failing to provide the Requested Information within the time period required by these provisions, indemnify and hold the Department harmless for any damages, penalties, costs, detriment or harm that the Department may incur as a result of this failure, including any statutory damages assessed against the Department.

g. The Department will reimburse the Contractor for any costs associated with complying with these provisions only to the extent allowed under the fee schedule established by the Office of Open Records or as otherwise provided by the RTKL if the fee schedule is inapplicable.

h. The Contractor may file a legal challenge to any Department decision to release a record to the public with the Office of Open Records, or in the Pennsylvania Courts, however, indemnify the Department for any legal expenses incurred by the Department as a result of such a challenge and hold the Department harmless for any damages, penalties, costs, detriment or harm that the Department may incur as a result of the failure, including any statutory damages assessed against the Department, regardless of the outcome of such legal challenge. As between the parties, agree to waive all rights or remedies that may be available as a result of the Department’s disclosure of Requested information pursuant to the RTKL.

i. The Contractor’s duties relating to the RTKL are continuing duties that survive the expiration of this Contract and continue as long as the Requested Information remains in the Contractor's possession.

Special Provision: C164A - a00164 CHANGES TO SPECIFICATIONS: SECTION 106

CHANGES TO SPECIFICATIONS: SECTION 106

Provision Body:

SECTION 106—CONTROL OF MATERIAL

106.10(a) Buy America Provisions. Revise last paragraph to read as follows:

Products manufactured of foreign steel or iron materials may be used, provided the cumulative cost of such products as they are delivered to the project does not exceed 0.1% of the total contract amount, or $2,500, whichever is greater.

Add 106.11 BUILD AMERICA, BUY AMERICA ACT PROVISIONS.

106.11 BUILD AMERICA, BUY AMERICA ACT PROVISIONS—

(a) Build America, Buy America Act. The Federal Bipartisan Infrastructure Law (Public Law 117-58) includes the Build America, Buy America Act that requires all iron, steel, manufactured products, and construction materials used to be produced in the United States.

May 15, 2026 12:21:10 PM Page 13 of 48

The term produced in the United States defined as:

1. Iron or Steel Products. All manufacturing processes from the initial melting stage through the application of coatings occurred in the United States according to Section 106.10(a).

2. Manufactured Product. Final assembly of all manufactured products permanently incorporated into the project must be manufactured in the United States.

2.a A manufactured product, not predominantly steel or iron, is defined as an article, material, or supply that has been processed into a specific form and shape, or combined with other articles, materials, or supplies to create a product with different properties than the individual articles, materials, or supplies.

2.b Predominantly steel or iron is defined as greater than or equal to 50 percent of the total cost of the manufactured product.

2.c Manufactured products that are predominantly steel or iron must comply with Buy America provisions according to Section 106.10(a).

2.d If an article, material, or supply meets this definition but could also be classified as an excluded material or other product category, that article, material, or supply is not a manufactured product.

2.e Mixtures of excluded materials delivered to a work site without final form for incorporation into a project are also not manufactured products.

2.f Manufactured products where the final assembly did not occur in the United States may be used, provided the cumulative cost of such manufactured products is no more than the lesser of $1 million or 5% of total applicable costs for the project.

3. Construction Materials.

3.a All manufacturing processes for construction materials occurred in the United States.

3.b Construction materials includes an article, material, or supply that is or consists primarily of:

non-ferrous metals, plastic and polymer-based products including polyvinylchloride, composite building materials, and polymers used in fiber optic cables, glass including optic glass, lumber, or drywall

Items that consist of two or more of the listed materials that have been combined together through a manufacturing process, and items that include at least one of the listed materials combined with a material that is not listed through a manufacturing process, should be treated as manufactured products, rather than as construction materials.

3.c Limitation with Respect to Aggregates. Shall not include cement and cementitious materials, aggregates such as stone, sand, or gravel, or aggregate binding agents or additives.

3.d Construction materials where all manufacturing processes did not occur in the United States may be used, provided the cumulative cost of such construction materials is no more than the lesser of $1 million of 5% of total applicable costs for the project.

Special Provision: C166A - a00166 CHANGES TO SPECIFICATIONS: SECTIONS 107 AND 608

May 15, 2026 12:21:10 PM Page 14 of 48

CHANGE TO SPECIFICATIONS: SECTIONS 107, AND 608

Provision Body:

SECTION 107—LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC

Section 107.28 EROSION AND SEDIMENT POLLUTION CONTROL PLANS AND PERMITS. Revise to read as follows:

107.28 EROSION AND SEDIMENT POLLUTION CONTROL PLANS AND PERMITS—Install and maintain erosion and sediment (E&S) pollution control devices as indicated or submit an alternate plan for accomplishing equal or better temporary and permanent erosion and water pollution control. If an alternate plan is submitted, do not start work until the plan is approved by the County Conservation District and the Department. If a National Pollutant Discharge Elimination System (NPDES) Permit is involved, do not start work until the plan is approved by the DEP or the authorized County Conservation District and the Department. Concrete clean out areas, either contractor designed or indicated within the contract documents, are incidental to the contract items.

When a general or individual NPDES Permit is involved:

At the preconstruction conference, submit a Preparedness, Prevention and Contingency (PPC) Plan and identify a licensed professional (Professional Engineer, Geologist, Land Surveyor or Landscape Architect) registered in the Commonwealth and if applicable, their designee to be present onsite and responsible for implementing critical stages of the

Do not start earth disturbance activities until an environmental preconstruction meeting is held with DEP or delegated

CCD.

Within 14 days of completing the construction of a stormwater control measure (SCM) as determined by the licensed professional or designee, submit a completed Chapter 102 SCM Construction Certification Form for each SCM to the Representative through PPCC. Form CS-102 has information required to complete the Chapter 102 Form(s). Ensure the General Project and SCM Information, Construction Information, and Licensed Professional Certification sections are completed by the identified licensed professional responsible for overseeing the critical stages of the approved PCSM plan.

Prepare an as-built (record) PCSM Plan to be sealed and signed by the identified licensed professional registered in the Commonwealth. All construction survey, plan preparation, and engineering required for the as-built (record) PCSM Plan will be incidental to the contract items. The as-built (record) PCSM Plan must accurately reflect deviations from the approved PCSM Plan including, but not limited to, plan locations, dimensions, inverts/elevations, materials used and grading. Update the as-built (record) PCSM Plan as construction of the project’s PCSM features progresses. Have the identified licensed professional immediately notify the Representative of all deviations from the approved PCSM Plan. Deviations to the approved PCSM Plan must be submitted for approval. Assist with the determination and documentation if the as-built deviations require a permit amendment or if the PCSM features must be removed and replaced as indicated on the PCSM Plan.

Assist the Representative in performing visual site inspections weekly and after each precipitation event greater than 0.25 inches to ensure the project's E&S Best Management Practices (BMPs) are functioning properly. Immediately initiate corrective actions, at no additional cost to the Department, upon notification by the Representative of noncompliance with the provisions of this section that the Representative has determined requires immediate corrective action under Department policies. For all other notifications of noncompliance, initiate corrective actions within 24 hours. Failure or refusal to promptly comply with such notice upon receipt may, at the Department’s sole discretion, result in: the withholding payment of estimates for work completed until the requirements of the E&S Plan are met, assessment of E&S noncompliance liquidated damages as specified in Section 108.07(d) or issuance of a written order stopping all or part of the work until the corrective action has been taken and the requirements of the E&S Plan are met. No claims for extension of time, costs, or damages arising from, related to, or based upon such notices of noncompliance or stop orders will be granted, paid, or considered.

approved Post Construction Stormwater Management (PCSM) Plan.

May 15, 2026 12:21:10 PM Page 15 of 48

Nothing in this Section is to be interpreted to relieve the Contractor of its obligation to fully and timely comply with all applicable laws and any permits for the project. The time periods set forth in this Section do not supersede any more stringent time periods required by applicable laws or permits for the project.

If corrective action or noncompliance with the provisions of this Section result from design errors/omissions or a precipitation event exceeding the design storm criteria as specified in applicable Department publications; the cost and/or time required for the performance of the corrective actions for noncompliance notices or stop work orders will be considered as specified in Section 110.03 and Section 108.06, as applicable.

Utilize Department, DEP, or other authorized agency’s form(s) included in the contract or project permits unless directed otherwise by the Representative, DEP, the County Conservation District or other authorized regulatory agency.

For the purpose of determining compliance with the provisions of this section, “substantial completion” will be considered to have been attained when all of the following project milestones have been reached:

Either a semi-final or final inspection has been performed, physical work is complete, and an Environmental Commitments and Mitigation Tracking System (ECMTS) Sheet has been executed if applicable to the project.

Earth disturbance activity has been permanently stabilized and sufficient vegetative growth has been achieved to meet permit conditions (uniform 70% perennial vegetative cover) and agreed to by DEP or delegated CCD.

Installation of PCSM SCMs have occurred if applicable. Upon completion of PCSM conversions and facilities, the County Conservation District must approve the removal of all remaining E&S BMPs.

Once a project with a general or individual NPDES Permit has reached substantial completion, submit to the Representative a DEP Notice of Termination (NOT) Form ensuring Sections 2, 3, 4, 7 and 8, are fully executed. The NOT is to be accompanied by the required as-built (record) PCSM Plan, the final certification by the licensed professional and the Contractor’s executed portion of the ECMTS Construction Tracking Signature Sheet.

608 MOBILIZATION

Section 608.4(b)3. Revise to read as follows:

3. When all physical work has been satisfactorily completed and the following certificates and documents, as required, have been properly furnished, the final payment will be made as specified in Section 608.4(a):

Certified Payroll Records

Final DBE/DB payment amounts and, if necessary, shortfall justification

Material Certifications

Form CS-4225H, Highway Lighting In-Service Guarantee Notification

As built drawings for Design/Build projects

Form RW-397A, Right to Enter (a property) and Release Form from property owner, if applicable

Form CS-4345, Borrow and/or Waste Management

Contractor Evaluations of the design of the project; and

Work Order Information (i.e. Force Account documentation)

Post Construction Stormwater Management As-built drawings and all documentation required for submission of the Notice of Termination for projects with NPDES permits.

May 15, 2026 12:21:10 PM Page 16 of 48

Special Provision: C167A - a00167 CHANGES TO SPECIFICATIONS: APPENDIX C—DESIGNATED SPECIAL PROVISIONS and APPENDIX C, DSP 20

Addendum:

CHANGES TO SPECIFICATIONS : APPENDIX C—DESIGNATED SPECIAL PROVISIONS and APPENDIX C, DSP 20

Provision Body:

APPENDIX C—DESIGNATED SPECIAL PROVISIONS. Revise to read as follows:

APPENDIX C

DESIGNATED SPECIAL PROVISIONS

General: This appendix to Publication 408 contains standard required provisions. The Contractor shall comply with the below appendices, as applicable.

Standard Documents: Designated Special Provisions (DSPs) that are referenced in this Appendix are:

DSP4. Diverse Business (DB) Requirements for Non-Federally Funded Construction Projects. This provision is applicable to contracts funded with state funds, without federal funds.

DSP7. Disadvantaged Business Enterprise (DBE) Requirements for Federally-funded Construction Projects. This provision is applicable to any Federally-funded (in part or whole) contract for a construction project.

DSP8. F. A. R.—Required Contract Provisions Federal-Aid Construction Contracts – FHWA-1273 (Revised October 23, 2023). See attachments to the Proposal. This provision is applicable to any federally funded (in part or whole) contract for a construction project.

DSP9. Special Supplement—Anti-Pollution Measures – August 26, 1999. This provision is applicable to all contracts.

DSP12. Executive Order 11246, with Appendices A and B. This provision is applicable to contracts with federal funds (in part or whole).

DSP13. Buy America. This provision is applicable to contracts with federal funds (in part or whole, and to state-funded projects when any federal funds were allocated at any phase of the work on the overall-project but not under the current contract (for example, design), even if the construction contract is 100% state-funded.

DSP15. Commonwealth Standard Terms and Conditions. This provision is applicable to all contracts.

DSP16. Lobbying Certification Form. This provision is applicable to contracts with federal funds and a contract amount $100,000 or greater. If applicable, the Contractor shall complete this form and return it to PennDOT during contract execution. (Form is located in ECMS File Cabinet and must be completed and uploaded to the Contractor Checklist in ECMS).

DSP17. Federal Audit Clause. This provision is applicable to contracts with federal funds. As used in this DSP, “[Name of Subrecipient]” refers to the Contractor.

DSP19. The United States Department of Transportation (USDOT) Standard Title VI/Non-Discrimination Assurances. This provision is applicable to contracts with federal funds. The Contractor’s signature on an agreement will be deemed a signature on this exhibit.

As used in this DSP, the term “Subrecipient” refers to the Contractor.

DSP20. FAR 52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act- Covered Foreign Entities. This provision is applicable to contracts with federal funds (in part or whole).

May 15, 2026 12:21:10 PM Page 17 of 48

• APPENDIX C—DESIGNATED SPECIAL PROVISION 20 (DSP20) FAR 52.240-1 - PROHIBITION ON UNMANNED AIRCRAFT SYSTEMS MANUFACTURED OR ASSEMBLED BY AMERICAN SECURITY DRONE ACT-COVERED FOREIGN ENTITIES (NOV 2024). Revise to read as follows:

APPENDIX C

DESIGNATED SPECIAL PROVISION 20 (DSP20)

FAR 52.240-1 -PROHIBITION ON UNMANNED AIRCRAFT SYSTEMS MANUFACTURED OR ASSEMBLED

BY AMERICAN SECURITY DRONE ACT-COVERED FOREIGN ENTITIES (NOV 2024)

(a) Definitions. As used in this clause—

American Security Drone Act-covered foreign entity means an entity included on a list developed and maintained by the Federal Acquisition Security Council (FASC) and published in the System for Award Management (SAM) at https://www.sam.gov (section 1822 of the National Defense Authorization Act for Fiscal Year 2024, Pub. L. 118-31, 41 U.S.C. 3901 note prec.).

FASC-prohibited unmanned aircraft system means an unmanned aircraft system manufactured or assembled by an American Security Drone Act-covered foreign entity.

Unmanned aircraft means an aircraft that is operated without the possibility of direct human intervention from within or on the aircraft (49 U.S.C. 44801(11)).

Unmanned aircraft system means an unmanned aircraft and associated elements (including communication links and the components that control the unmanned aircraft) that are required for the operator to operate safely and efficiently in the national airspace system (49 U.S.C. 44801(12)).

(b) Prohibition. The Contractor is prohibited from—

(1) Delivering any FASC-prohibited unmanned aircraft system, which includes unmanned aircraft (i.e., drones) and associated elements (sections 1823 and 1826 of Pub. L. 118-31, 41 U.S.C. 3901 note prec.);

(2) On or after December 22, 2025, operating a FASC-prohibited unmanned aircraft system in the performance of the contract (section 1824 of Pub. L. 118-31, 41 U.S.C. 3901 note prec.); and

(3) On or after December 22, 2025, using Federal funds for the procurement or operation of a FASC-prohibited unmanned aircraft system (section 1825 of Pub. L. 118-31, 41 U.S.C. 3901 note prec.).

(c) Procedures. The Contractor shall search SAM at https://www.sam.gov for the FASC-maintained list of American Security Drone Act-covered foreign entities prior to proposing, or using in performance of the contract, any unmanned aircraft system. Additionally, the Contractor shall ensure any effort or expenditure associated with a FASC-prohibited unmanned aircraft system is consistent with a corresponding exemption, exception, or waiver determination expressly stated in the contract.

(d) Exemptions, exceptions, and waivers. The prohibitions in this clause do not apply where the agency has determined an exemption, exception, or waiver applies and the contract indicates that such a determination has been made. [See sections 1823 through 1825 and 1832 of Public Law 118-31 (41 U.S.C. 3901 note prec.) for statutory requirements pertaining to exemptions, exceptions, and waivers.].

(e) Subcontracts. The Contractor shall insert the substance of this clause, including this paragraph (e), in all subcontracts and other contractual instruments, including subcontracts for the acquisition of commercial products or commercial services.

Special Provision: C168A - a00168 CHANGES TO SPECIFICATIONS: SECTIONS 110, 404, AND 507

May 15, 2026 12:21:10 PM Page 18 of 48

CHANGE TO SPECIFICATIONS: SECTIONS 110, 404, AND 507

Provision Body:

SECTION 110—PAYMENT

Section 110.06 MATERIAL STORED OR ON HAND. Revise to read as follows:

110.06 MATERIAL STORED OR ON HAND—

(a) Stored Material. The Representative may authorize payment for certain material, using Form CS-110, before its incorporation into the work. Upon the Contractor's request submitted through the PennDOT Project Collaboration Center’s (PPCC) Material-Stored Material (CS-110) workflow and the Representative's acceptance in PPCC, the Contractor may be paid 100% of the cost of the material, less the pro‑rata share of the retainage, if any; provided the quantity of stored material does not exceed the total estimated quantity required to complete the project and the cost is at least $1,000 but does not exceed 90% of the contract price of the applicable contract item or component item. Load-Transfer Units are only eligible for 90% of the cost of the material. The cost of the material is that amount to be paid by the Contractor as evidenced by invoices. Fabricated structural steel that is to receive a protective coating may be approved for prepayment at 75% of the contract price of the applicable contract item or component item, before application of the coating, provided the structure has been fully fabricated and preassembly of field connections has been made.

Payment for stored material will not be authorized until the material has been delivered to the project site or an approved location in the vicinity of the project, is inspected by the Representative to ensure the material is in a satisfactory condition and of sufficient quantity, is stored in an approved manner, and conforms to the requirements specified in this Section and Section 106.03. Identify stored material by project designation and set apart from other materials. Fabricated precast/prestressed bridge structure elements indicated on an S-number structure plan are eligible for prepayment when they are approved to ship. Other materials to be stored less than 30 days are not eligible for prepayment. In determining eligibility for prepayment, the beginning date for evaluating whether the required 30-day minimum storage period will be met will be the date the material is delivered to the project or approved storage location, or the date the invoice is submitted to the Department, whichever is the latter. Material originally determined to be ineligible for prepayment due to the minimum storage period requirement, that is then stored for more than 30 days, is eligible for prepayment on the next estimate, provided the invoice has been submitted to the Department. If the Representative determines, because of required fabrication at an off‑site location, that it is not feasible or practicable to store material in the vicinity of the project, the material may be stored at an approved location, which is not in the vicinity of the project, at the Contractor’s expense.

With the exception of structural steel to be incorporated into fabricated structural steel components for main bridge members, as specified in Section 110.06(a)1., only end product manufactured material or fully fabricated products that are awaiting installation and/ or incorporation into the finished work are eligible for prepayment. Ingredients of a finished product are not eligible for prepayment.

Aggregates, cements, and other bulk material are not eligible for prepayment. Beams containing precast components or secondary precast elements detailed on the structure component item schedule or both are eligible for prepayment. Living or perishable plant materials are not eligible for prepayment before planting.

Assume full control and responsibility for the protection of the stored material from the elements and against loss or damage by any cause. In the event any stored material becomes lost, stolen, impaired, or damaged while stored, the monetary value of the lost, stolen, impaired, or damaged material as may have been paid for in a current estimate will be deducted from a subsequent estimate.

Retain the title to the prepaid material until issuance of the acceptance certificate.

Payment for acceptable stored material will be made on current estimates against the applicable contract item. The amount paid will be proportionately recouped as the material is incorporated into the work. The cost of surplus stored material previously paid on a current estimate but not ultimately incorporated in the final measured work will not be included in the final payment. Surplus stored material is the property of the Contractor. Remove surplus material from the project and dispose of in a satisfactory manner.

Pay the material provider the amount due, as shown on the invoices within 7 calendar days of receipt of payment from the Department. Provide evidence of payment upon request. Failure to make invoice payments as specified will cause the appropriate monies to be deducted from future estimates and will cause the disapproval of further prepayment requests.

1. Prepayment for Structural Steel. Structural steel to be incorporated into fabricated structural steel components for main bridge members may be approved for payment up to 60% of the contract price of the applicable contract item or component item; provided the quantity, cost, delivery, inspection, and storage requirements of Section 110.06(a) are met. The cost of the structural steel is that amount to be paid by the Fabricator as evidenced by invoices. Invoices for approved structural steel are to include the material quantity and Department project identification (i.e., ECMS number, SR & Section, and county), and must be accompanied by

May 15, 2026 12:21:10 PM Page 19 of 48 certification, as specified in Section 106.03(b)3., and proof of payment (e.g., a copy of a canceled check or receipt, or a certified letter from the structural steel supplier acknowledging receipt of payment).

Payment for approved structural steel will be made on current estimates against the applicable contract item. The amount paid will be proportionately recouped as the fabricated structural steel components are incorporated into the work. Pay the Fabricator the amount due, as shown on the invoices, within 7 calendar days of receipt of payment from the Department. When payment is made, the structural steel becomes the property of the Department. Have the Fabricator furnish a transfer of ownership document within 7 calendar days of receipt of payment and promptly submit the documentation to the Department.

Only approved structural steel to be incorporated into fabricated structural steel components for main bridge members is eligible for prepayment. Handling, transportation, and storage of structural steel materials including, but not limited to, any storage site rental, security, and weather protection, are to be borne by the Contractor and included in the contract price for the applicable contract item.

SECTION 404—EVALUATION OF ASPHALT PAVEMENT RIDE QUALITY AND PAYMENT OF INCENTIVE

Section 404.1 DESCRIPTION. Revise to read as follows:

404.1 DESCRIPTION. This work evaluates an asphalt pavement surface profile and determines the ride-quality incentive associated with the pavement surface profile.

(a) General Requirements. Determine the ride quality of finished pavement surfaces, including overlaid bridge approach slabs and overlaid bridge decks. At least two of the following construction operations must be indicated in areas included in ride-quality lot measurements:

Profile milling as specified in Section 492.

Asphalt Base course.

Asphalt Scratch course.

Asphalt Leveling course.

Asphalt Binder course.

Asphalt Wearing course.

In the presence of the Representative, measure the pavement surface profile according to PTM No. 428.