Project 123508: Clinton County SR 220 Bridge Rehabilitation
This is a Pennsylvania Department of Transportation (PennDOT) proposal report for a federally-funded bridge rehabilitation and roadway improvement project in Clinton County, specifically on State Route 0220 in Castanea and Lamar Townships. The project encompasses approximately 2,221 linear feet (0.42 miles) of work on both eastbound and westbound segments and includes concrete deck repairs, bridge superstructure jacking, rocker bearing resets, silicone joint sealants, metal expansion bearing assembly replacement, superpave asphalt mixture design for wearing courses, rumble strip removal, and pavement markings. The project is classified as Standard Deck Rehabilitation work with an estimated cost range of $1,000,000 to $2,499,999.99. Prequalification is required for bidders. The scheduled bid opening is June 4, 2026, at 11:00 AM at the Commonwealth Keystone Building in Harrisburg, Pennsylvania. The anticipated Notice to Proceed (NTP) is July 20, 2026, with a required completion date of November 16, 2026. The project includes 66% structure work, is subject to the 2026-IE version specifications, and is designated as an ECMS (Electronic Contract Management System) project with all addenda posted electronically.
The project is federally-funded through the National Highway System (NHS) and requires compliance with federal and state prevailing wage rates. Designated Special Provisions (DSPs) applicable to the contract include provisions for Disadvantaged Business Enterprise (DBE) requirements (0% DBE goal), Federal-Aid Construction Contract provisions (FHWA-1273), anti-pollution measures, Executive Order 11246 equal employment opportunity requirements, Buy America and Build America provisions, lobbying certifications, federal audit clauses, and prohibitions on unmanned aircraft systems from covered foreign entities. The project requires Worker Protection and Investment Certification (Form BOP-2201) to be submitted within 7 calendar days after bid opening. Material certifications must be submitted electronically through ECMS using DocuSign PDF forms, with Level 1, 2, or 3 certification levels required for Bulletin 15 materials. The contract includes extensive erosion and sediment pollution control requirements, traffic control coordination with related projects (ECMS 121645), and comprehensive pavement ride-quality evaluation provisions with incentive payment schedules based on International Roughness Index (IRI) and Mean Roughness Index (MRI) measurements. Payment for materials stored on-site may be authorized at up to 100% of cost for qualified items meeting storage and timing requirements.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PROPOSAL Report - Project 123508
April 30, 2026 14:52:34 PM Page 1 of 44
PROPOSAL REPORT
Project: 123508 Bid
Package: 1
Current Let: 06/04/2026 11:00:00 AM
Version: Current Addendum
Count: 0
District: 02 County: Clinton
SR/SEC/
Group ID: 220/P66/---
Description
Clinton Co SR 220 Brdg Rehab
April 30, 2026 14:52:34 PM Page 2 of 44
TABLE OF CONTENTS
BID PACKAGE SUMMARY
PROJECT ITEMS AND QUANTITIES
SPECIAL PROVISIONS
G50B - a00050 APPLICABLE DESIGNATED SPECIAL PROVISIONS (FEDERAL) G113B - a00113 CONTRACT PROVISIONS - RIGHT-TO-KNOW LAW G401A - a00401 ADVANCE NOTICE OF TRAFFIC RESTRICTIONS G901B - a00901 ALTERNATE EROSION AND SEDIMENT POLLUTION CONTROL PLAN G1101B - a01101 CONSTRUCTION PROCEDURES - EROSION AND SEDIMENT POLLUTION
CONTROL
G1601A - a01601 E.E.O. COVERED AREA G2302A - a02302 Worker Protection and Investment G4401C - a04401 UTILITIES--FOR USE ON PROJECTS WITH MINIMUM OR NO EXCAVATION C164A - a07000 CHANGES TO SPECIFICATIONS: SECTION 106 C166A - a07010 CHANGES TO SPECIFICATIONS: SECTIONS 107 AND 608 C168A - a07015 CHANGES TO SPECIFICATIONS: SECTIONS 110, 404, AND 507 C167A - a07020 CHANGES TO SPECIFICATIONS: APPENDIX C—DESIGNATED SPECIAL PROVISIONS and APPENDIX C, DSP 20
00 - a10500 CONSTRUCTION RESTRICTION - PROJECT COORDINATION G100B - a14200 CONSTRUCTION RESTRICTIONS DUE TO AREA SPECIAL EVENTS P1061D - b01061 Electronic Submission of Material Certifications through ECMS P1062D - b01062 Electronic Submission of Material Certifications through ECMS for Lump Sum Component items
S3099C - b03130 SECTION 313/413 - SUPERPAVE MIXTURE DESIGN S6012B - b06012 - SECTION 601.3(f) BACKFILLING TRENCH 00 - c 00300 ITEM 9000-0213 – UNFORESEEN REINFORCEMENT BARS, EPOXY COATED I901B - c00100 ITEMS 4901-0340 TO 0350 - STANDARD PAVEMENT MARKINGS, TAPE, INCLUDES MAINTAINING AND REMOVAL
00 - c00200 ITEM 1018-0050 - REMOVAL OF PORTION OF EXISTING BRIDGE 00 - c00400 ITEM 9000-0222 - CONCRETE BRIDGE DECK UNDERSIDE REPAIR, TYPE 2 I1090B - c00500 ITEM 9000-0267 - RESET ROCKER BEARINGS I9705C - c00600 ITEM 9000-0273 - SILICONE SEALANT FOR BRIDGE JOINT 00 - c00700 ITEM 9000-0282 - UNFORESEEN FABRICATED STRUCTURAL STEEL REPAIRS I1090E - c00800 ITEM 9000-0290 - REPLACE METAL EXPANSION BEARING ASSEMBLY I1090C - c00900 ITEM 9000-0330 - JACKING BRIDGE SUPERSTRUCTURE I70C - c01000 ITEM 9000-5103 - ELECTRONIC TICKETING (E-TICKETING) FOR CONSTRUCTION
CONCRETE
April 30, 2026 14:52:34 PM Page 3 of 44
BID PACKAGE SUMMARY
Project: 123508 Bid Package: 1
Project Type: Standard Posted:
Federal Project Status: PENNDOT Oversight NHS State Type of Work: DECK REHABILITATION
Prequalification Required: Yes Pre-Bid Meeting: None
408 Version: 2026-IE
Scheduled Let: 06/04/2026 11:00:00 AM Project Cost Range: $1,000,000.00 - $2,499,999.99 Anticipated NTP: 07/20/2026 Structure Work: 66.00%
Required Completion: 11/16/2026 DBE: 0% Wage Rates: Yes
Description:
The description and location of the project is as follows: For the improvement of certain sections of STATE HIGHWAY in CLINTON COUNTY, CASTANEA and LAMAR TOWNSHIPS, Commonwealth of Pennsylvania, STATE ROUTE 0220, SECTION P66. The project being situated as follows:On State Route 0220 East Bound from Segment 0090/Offset 0589 to Segment 0210/Offset 1491.On State Route 0220 West Bound from Segment 0091/Offset 0574 to Segment 0211/Offset 1716.For rehabilitation of the existing structures to include concrete deck repairs, jacking bridge superstructure, resetting rocker bearings, silicone sealant for bridge joints, replacement of metal expansion bearing assembly, Roadway includes Superpave Asphalt Mixture Designs for the wearing course of rumble strip removal area, pavement markings, and miscellaneous construction for a total construction length of approximately 2221 linear feet (0.42 miles) as indicated on the approved drawings included in the bid package.
Additional Information:
This is an ECMS project. All Addenda will be electronically posted.The location of the public bid opening is the Commonwealth Keystone Building, 7th Floor, Contract Awards Room, 400 North Street, Harrisburg. Allow sufficient time before the bid opening to obtain a visitor pass on the 5th Floor and to be escorted to the 7th Floor Contract Awards Room.
April 30, 2026 14:52:34 PM Page 4 of 44
PROJECT ITEMS AND QUANTITIES
Alt Item Work Class Code Unit Of
Measure Quantity Unit Price PDP Spec
Prov Add Action
0413-0398 F Square Yard 296.0000 N
SUPERPAVE ASPHALT MIXTURE DESIGN, WEARING COURSE, PG 64E-22, 3 TO < 10 MILLION ESALS, 9.5 MM MIX, 1 1/2"
DEPTH, SRL-H
0460-0001 F4 Square Yard 296.0000 N
ASPHALT TACK COAT
0491-0012 F3 Square Yard 296.0000 N MILLING OF ASPHALT PAVEMENT SURFACE, 1 1/2" DEPTH, MILLED MATERIAL RETAINED BY CONTRACTOR
0608-0001 X Lump Sum 1.0000 N
MOBILIZATION
0627-3019 J1 Linear Foot 480.0000 N
TEMPORARY BARRIER, TEST LEVEL 3, BARRIER DEFLECTION DISTANCE < /=1'
0643-0001 J1 Linear Foot 2,568.0000 N
TEMPORARY CONCRETE BARRIER, STRUCTURE MOUNTED
0660-0005 F3 Linear Foot 2,660.0000 N MILLED ASPHALT PAVEMENT SHOULDER/GORE RUMBLE STRIPS FOR INTERSTATES, EXPRESSWAYS AND FREEWAYS
0689-0003 X Lump Sum 1.0000 N
CPM SCHEDULE
0690-0001 X Dollar 1,000.0000 $1.00 Y
INTERNAL FACILITATION
0696-0610 J1 Each 2.0000 N
TEMPORARY IMPACT ATTENUATING DEVICE, TYPE V (STANDARD), TEST LEVEL 3
0901-0001 Q Lump Sum 1.0000 N
MAINTENANCE AND PROTECTION OF TRAFFIC DURING CONSTRUCTION
0901-0120 Q Each 2.0000 N
SPEED DISPLAY SIGN
0901-0240 Q, R Square Foot 200.0000 N
ADDITIONAL TRAFFIC CONTROL SIGNS
4901-0340 O2, O3 Linear Foot 2,750.0000 N Std
4" STANDARD PAVEMENT MARKINGS, TAPE, YELLOW INCLUDING MAINTAINING AND REMOVAL
4901-0346 O2, O3 Linear Foot 4,500.0000 N Std
6" STANDARD PAVEMENT MARKINGS, TAPE, BLACK INCLUDING MAINTAINING AND REMOVAL
4901-0347 O2, O3 Linear Foot 480.0000 N Std
8" STANDARD PAVEMENT MARKINGS, TAPE, BLACK INCLUDING MAINTAINING AND REMOVAL
4901-0350 O2, O3 Linear Foot 5,800.0000 N Std
4" STANDARD PAVEMENT MARKINGS, TAPE, WHITE INCLUDING MAINTAINING AND REMOVAL
April 30, 2026 14:52:34 PM Page 5 of 44
0901-0461 Q Each 4.0000 N
FULL-MATRIX CHANGEABLE MESSAGE SIGN WITHOUT TELECOMMUNICATIONS
0962-1000 O Linear Foot 3,120.0000 N
4" WHITE WATERBORNE PAVEMENT MARKINGS
0962-1001 O Linear Foot 360.0000 N
6" WHITE WATERBORNE PAVEMENT MARKINGS
0962-1005 O Linear Foot 3,120.0000 N
4" YELLOW WATERBORNE PAVEMENT MARKINGS
1001-1000 S9 Cubic Yard 99.0000 N
CLASS AAAP CEMENT CONCRETE
1001-1080 S2 Cubic Yard 118.0000 N
CLASS AA CEMENT CONCRETE
1002-0053 S7 Pound 47,526.0000 N
REINFORCEMENT BARS, EPOXY COATED
1018-0050 T1 Lump Sum 1.0000 N Proj
REMOVAL OF PORTION OF EXISTING BRIDGE
1019-0050 K2 Square Yard 579.0000 N
PROTECTIVE COATING FOR REINFORCED CONCRETE SURFACES (PENETRATING SEALERS, BRIDGE
SUPERSTRUCTURE)
1072-0200 X Lump Sum 1.0000 N
WASTE MANAGEMENT
1072-0300 V2 Lump Sum 1.0000 N
WORKER HEALTH AND SAFETY
9000-0213 S2 Dollar 15,000.0000 $1.00 Y Proj
UNFORESEEN REINFORCEMENT BARS, EPOXY COATED
9000-0222 S2 Square Foot 70.0000 N Proj
CONCRETE BRIDGE DECK UNDERSIDE REPAIR, TYPE 2
9000-0267 S2 Each 10.0000 N Std
RESET ROCKER BEARINGS
9000-0273 S2 Linear Foot 463.0000 N Std
SILICONE SEALANT FOR BRIDGE JOINT
9000-0282 S2 Dollar 25,000.0000 $1.00 Y Proj
UNFORESEEN FABRICATED STRUCTURAL STEEL REPAIRS
9000-0290 S2 Each 2.0000 N Std
REPLACE METAL EXPANSION BEARING ASSEMBLY
9000-0330 S2 Lump Sum 1.0000 N Std
JACKING BRIDGE SUPERSTRUCTURE
April 30, 2026 14:52:34 PM Page 6 of 44
9000-5103 X Lump Sum 1.0000 N Std
ELECTRONIC TICKETING (E-TICKETING) FOR CONSTRUCTION CONCRETE
April 30, 2026 14:52:34 PM Page 7 of 44
SPECIAL PROVISIONS
Special Provision: G50B - a00050 APPLICABLE DESIGNATED SPECIAL PROVISIONS (FEDERAL) Addendum:
Action:
Item(s) Associated:
Header:
APPLICABLE DESIGNATED SPECIAL PROVISIONS (FEDERAL)
Provision Body:
APPLICABLE DESIGNATED SPECIAL PROVISIONS. The following Designated Special Provisions are found in Appendix C and apply to this bid proposal.
DSP7. Disadvantaged Business Enterprise (DBE) Requirements for Federally-funded Construction Projects.
DSP8. F.A.R. - Required Contract Provisions Federal-Aid Construction Contracts FHWA-1273 (Revised October 23, 2023). Also attached to the Proposal/Contract.
DSP9. Special Supplement - Anti-Pollution Measures - August 26, 1999.
DSP12. Executive Order 11246, with Appendix A and B.
DSP13. Buy America.
DSP15. Commonwealth Standard Terms and Conditions.
DSP16. Lobbying Certification Form. (Form is located in ECMS File Cabinet and must be completed and uploaded to the Contractor Checklist in ECMS).
DSP17. Federal Audit Clause.
DSP19. The United States Department of Transportation (USDOT) Standard Title VI/Non-Discrimination Assurances.
DSP20. FAR 52.240-1 Prohibition on Unmanned Aircraft Systems Manufactured or Assembled by American Security Drone Act- Covered Foreign Entities.
Project Specific Details:
Special Provision: G113B - a00113 CONTRACT PROVISIONS - RIGHT-TO-KNOW LAW Addendum:
CONTRACT PROVISIONS - RIGHT TO KNOW LAW
Provision Body:
April 30, 2026 14:52:34 PM Page 8 of 44
I. Contract Provisions – Right to Know Law 8-K-1532
a. The Pennsylvania Right-to-Know Law (RTKL), 65 P.S. §§ 67.101-3104, applies to this Contract.
b. If the Department needs assistance in any matter arising out of the RTKL related to this Contract, the Department will notify the Contractor using the legal contact information provided in this Contract. The Contractor, at any time, may designate a different contact for such purpose upon reasonable prior written notice to the Department.
c. Upon written notification from the Department that it requires assistance in responding to a request under the RTKL for information related to this Contract that may be in the Contractor’s possession, constituting, or alleged to constitute, a public record in accordance with the RTKL (“Requested Information”), the Contractor will:
1. Provide the Department, within 10 calendar days after receipt of written notification, access to, and copies of, any document or information in the Contractor’s possession arising out of this Contract that the Department reasonably believes is Requested Information and may be a public record under the RTKL; and
2. Provide such other assistance as the Department may reasonably request, in order to comply with the RTKL with respect to this Contract.
d. If the Contractor considers the Requested Information to include a request for a Trade Secret or Confidential Proprietary Information, as those terms are defined by the RTKL, or other information that the Contractor considers exempt from production under the RTKL, notify the Department and provide, within 7 calendar days of receiving the written notification, a written statement signed by a representative of the Contractor explaining why the requested material is exempt from public disclosure under the RTKL.
e. The Department will rely upon the written statement from the Contractor in denying a RTKL request for the Requested Information unless the Department determines that the Requested Information is clearly not protected from disclosure under the RTKL. Should the Department determine that the Requested Information is clearly not exempt from disclosure, provide the Requested Information within 7 calendar days of receipt of written notification of the Department’s determination.
f. Failing to provide the Requested Information within the time period required by these provisions, indemnify and hold the Department harmless for any damages, penalties, costs, detriment or harm that the Department may incur as a result of this failure, including any statutory damages assessed against the Department.
g. The Department will reimburse the Contractor for any costs associated with complying with these provisions only to the extent allowed under the fee schedule established by the Office of Open Records or as otherwise provided by the RTKL if the fee schedule is inapplicable.
h. The Contractor may file a legal challenge to any Department decision to release a record to the public with the Office of Open Records, or in the Pennsylvania Courts, however, indemnify the Department for any legal expenses incurred by the Department as a result of such a challenge and hold the Department harmless for any damages, penalties, costs, detriment or harm that the Department may incur as a result of the failure, including any statutory damages assessed against the Department, regardless of the outcome of such legal challenge. As between the parties, agree to waive all rights or remedies that may be available as a result of the Department’s disclosure of Requested information pursuant to the RTKL.
i. The Contractor’s duties relating to the RTKL are continuing duties that survive the expiration of this Contract and continue as long as the Requested Information remains in the Contractor's possession.
Special Provision: G401A - a00401 ADVANCE NOTICE OF TRAFFIC RESTRICTIONS
April 30, 2026 14:52:34 PM Page 9 of 44
Header:
ADVANCE NOTICE OF TRAFFIC RESTRICTIONS
Provision Body:
Notify the Engineer at least 4 calendar days in advance of the start of any operation which will affect the flow of traffic and provide the Engineer with details of the work to be done. After notification, the District Office will advise the public of these traffic restrictions and possible delays.
Special Provision: G901B - a00901 ALTERNATE EROSION AND SEDIMENT POLLUTION CONTROL
PLAN
Addendum:
ALTERNATE EROSION AND SEDIMENT POLLUTION CONTROL PLAN
Provision Body:
Comply with these requirements when submitting an alternate plan for accomplishing equal or better temporary and permanent erosion and sediment pollution control. Do not start work until the alternate erosion and sediment pollution control plan, schedules, and operation methods have been approved by the Department and the Department of Environmental Protection, or by the Department and the County Conservation District, as applicable.
Apply for any earth disturbance permits or permit amendments not included in the proposal documents that are required because of the nature of the contemplated construction procedures.
Prepare and furnish, with the applications, plans and documents that are required by the Department of Environmental Protection or the County Conservation District.
Provide simultaneously to the District Executive a copy of all plans and documents that affect the construction requirements.
Provide immediately to the District Executive any modifications that are made to the plans and documents that are required by the Department of Environmental Protection or the County Conservation District.
Obtain the approval of the Department and the permit from the Department of Environmental Protection prior to beginning any work when a permit is required, and the approval of the Department and the County Conservation District when a permit is not required.
Acquire areas outside of the right-of-way that are necessary for erosion and sediment pollution control. Proceed with the agreement procedure described in Section 105.14 (Borrow Areas and Waste Areas).
Special Provision: G1101B - a01101 CONSTRUCTION PROCEDURES - EROSION AND SEDIMENT
POLLUTION CONTROL
April 30, 2026 14:52:34 PM Page 10 of 44
Addendum:
CONSTRUCTION PROCEDURES - EROSION AND SEDIMENT POLLUTION CONTROL
Provision Body:
I. Observe the applicable following procedures during the entire period of construction as directed:
(a) Conduct all operations as specified in the erosion and sediment pollution control plan and in such a manner to minimize turbidity in streams. Do not discharge water containing sediments or pollutants into the streams.
(b) Direct flowing water away from project construction areas.
(c) Limit movement of equipment through the streambed in accordance with the approved plan so as to prevent unnecessary siltation or disturbance. Permit equipment to cross flowing channels only on rock roadways and/or bridges to prevent constant turbulency and siltation.
Construct rock crossings, causeways or cofferdams with rock having a minimum size of 75 mm (3 inches) or larger as directed; also, the surface may be choked with stone aggregate having a minimum size of 9.5 mm (3/8-inch). Do not use earth or other materials which may cause sedimentation, for any crossings, causeways or cofferdams.
(d) Seed and/or stabilize all stream banks immediately upon completion of grading.
(e) Seed all cut and fill slopes when they have reached a vertical height of 4.5 m (15 feet). On areas where permanent seeding will not be performed within a period of 20 days after the excavation or embankment operations have been completed place temporary seeding (annual Ryegrass) and mulching on all soil areas.
(f) Control the entire grading area at all times during construction by placing the erosion and sediment pollution control devices that can be installed prior to disturbing the earth and the stabilization devices as soon as the required earthwork has been performed.
(g) For any excavation material stockpiled more than 20 days, take interim stabilization measures to minimize erosion of the stockpile slopes.
(h) Clean the sedimentation structures during construction as specified in Section 861. Dispose of silt fencing and sediment removed from the project, as directed.
(i) Separate all water originating outside of the project from that originating within.
(j) During the life of the contract, be responsible for the maintenance of all erosion and sediment pollution control devices.
(k) Seed all borrow and waste areas in accordance with the approved plans and with item (e) above.
Special Provision: G1601A - a01601 E.E.O. COVERED AREA
April 30, 2026 14:52:34 PM Page 11 of 44
1.
2.
3.
4.
5.
6.
7.
8.
9.
10.
11.
12.
13.
Header:
E.E.O. COVERED AREA
Provision Body:
For the purpose set forth in the Executive Order 11246 the covered area for this contract is Clinton County, which is within the Economic Area of Williamsport as listed in Appendix B of Designated Special Provision 12 (DSP12) entitled “Executive Order 11246 (with Appendix A and B)” in Appendix C of Pub 408.
Special Provision: G2302A - a02302 Worker Protection and Investment
Worker Protection and Investment
Provision Body:
In accordance with the Governor’s Executive Order 2021-06, Worker Protection and Investment, contractors and grantees of the Commonwealth must certify they are in compliance with Pennsylvania’s Unemployment Compensation Law, Worker’s Compensation Law, and all applicable Pennsylvania state labor and workforce safety laws including, but not limited to:
Construction Workplace Misclassification Act Employment of Minors Child Labor Act Minimum Wage Act Prevailing Wage Act Equal Pay Law Employer to Pay Employment Medical Examination Fee Act Seasonal Farm Labor Act Wage Payment and Collection Law Industrial Homework Law Construction Industry Employee Verification Act Act 102: Prohibition on Excessive Overtime in healthcare Apprenticeship and Training Act Inspection of Employment Records Law
To ensure compliance with these statutes, Contractors and Grantees are required to submit the Worker Protection and Investment Certification Form (BOP-2201) in response to all ECMS procurement solicitations. The form is available in the ECMS File Cabinet (in References Tab). If assistance with the Form is needed, contact the ECMS Help Desk at 855-783-8330 or at 717- 783-8330. ECMS Help Desk assistance is available 24 hours a day, 7 days a week.
This form must be completed for the Prime Contractor and all subcontractors and/or services.
The Prime Contractor must email the completed BOP-2201 Form to workprotect@pa.gov or fax the Form to 717-265-7207, signed by an authorized representative of the Contractor, possessing sufficient knowledge to make the representations and certifications on the BOP-2201 Form by 3:00 P.M. prevailing local time within 7 calendar days after the bid opening. When the seventh (7th) calendar day after the bid opening falls on a day that the Department offices are closed, submit the BOP-2201 Form by 3:00 P.M. prevailing local time on the next business day. Failure or refusal to provide the BOP-2201 Form, or inclusion on any Pennsylvania Department of Labor and Industry Worker Protection and mailto:workprotect@pa.gov
April 30, 2026 14:52:34 PM Page 12 of 44
Labor Law Non-Compliance List, will be considered a refusal to comply with bidding requirements and may result in rejection of the bid, and other appropriate consequences.
For Subcontractors/Services, the completed BOP-2201 Form must be attached with the Public Works Verification Act form and submitted in ECMS before a subcontractor request can be approved. A subcontractor/service identified on any Pennsylvania Department of Labor and Industry Worker Protection and Labor Law Non-Compliance List will not be approved.
The Pennsylvania Department of Labor and Industry has created a public list of businesses that have been found to be non-compliant with Pennsylvania state labor and workforce safety law which will be published on its public-facing website. The link to the Department of Labor and Industry’s website is: www.dli.pa.gov/Pages/Non-Compliance-List.aspx.
Questions regarding inclusion on the list should be directed to the appropriate bureau with the Department of Labor and Industry.
Special Provision: G4401C - a04401 UTILITIES--FOR USE ON PROJECTS WITH MINIMUM OR NO
EXCAVATION
Addendum:
UTILITIES--FOR USE ON PROJECTS WITH MINIMUM OR NO EXCAVATION
Provision Body:
Identify and contact all utilities having existing aerial and/or underground facilities located within the limits of work to arrange for marking of the field locations of these facilities before performing any excavation. Although no adjustments or relocations are anticipated, coordinate with utilities and/or municipalities within the project limits.
Special Provision: C164A - a07000 CHANGES TO SPECIFICATIONS: SECTION 106
CHANGES TO SPECIFICATIONS: SECTION 106
Provision Body:
SECTION 106—CONTROL OF MATERIAL
http://www.dli.pa.gov/Pages/Non-Compliance-List.aspx
April 30, 2026 14:52:34 PM Page 13 of 44
106.10(a) Buy America Provisions. Revise last paragraph to read as follows:
Products manufactured of foreign steel or iron materials may be used, provided the cumulative cost of such products as they are delivered to the project does not exceed 0.1% of the total contract amount, or $2,500, whichever is greater.
Add 106.11 BUILD AMERICA, BUY AMERICA ACT PROVISIONS.
106.11 BUILD AMERICA, BUY AMERICA ACT PROVISIONS—
(a) Build America, Buy America Act. The Federal Bipartisan Infrastructure Law (Public Law 117-58) includes the Build America, Buy America Act that requires all iron, steel, manufactured products, and construction materials used to be produced in the United States.
The term produced in the United States defined as:
1. Iron or Steel Products. All manufacturing processes from the initial melting stage through the application of coatings occurred in the United States according to Section 106.10(a).
2. Manufactured Product. Final assembly of all manufactured products permanently incorporated into the project must be manufactured in the United States.
2.a A manufactured product, not predominantly steel or iron, is defined as an article, material, or supply that has been processed into a specific form and shape, or combined with other articles, materials, or supplies to create a product with different properties than the individual articles, materials, or supplies.
2.b Predominantly steel or iron is defined as greater than or equal to 50 percent of the total cost of the manufactured product.
2.c Manufactured products that are predominantly steel or iron must comply with Buy America provisions according to Section 106.10(a).
2.d If an article, material, or supply meets this definition but could also be classified as an excluded material or other product category, that article, material, or supply is not a manufactured product.
2.e Mixtures of excluded materials delivered to a work site without final form for incorporation into a project are also not manufactured products.
2.f Manufactured products where the final assembly did not occur in the United States may be used, provided the cumulative cost of such manufactured products is no more than the lesser of $1 million or 5% of total applicable costs for the project.
3. Construction Materials.
3.a All manufacturing processes for construction materials occurred in the United States.
3.b Construction materials includes an article, material, or supply that is or consists primarily of:
non-ferrous metals, plastic and polymer-based products including polyvinylchloride, composite building materials, and polymers used in fiber optic cables, glass including optic glass, lumber, or drywall
Items that consist of two or more of the listed materials that have been combined together through a manufacturing process, and items that include at least one of the listed materials combined with a material that is not listed through a manufacturing process, should be treated as manufactured products, rather than as construction materials.
3.c Limitation with Respect to Aggregates. Shall not include cement and cementitious materials, aggregates such as stone, sand, or gravel, or aggregate binding agents or additives.
April 30, 2026 14:52:34 PM Page 14 of 44
3.d Construction materials where all manufacturing processes did not occur in the United States may be used, provided the cumulative cost of such construction materials is no more than the lesser of $1 million of 5% of total applicable costs for the project.
Special Provision: C166A - a07010 CHANGES TO SPECIFICATIONS: SECTIONS 107 AND 608
CHANGE TO SPECIFICATIONS: SECTIONS 107, AND 608
Provision Body:
SECTION 107—LEGAL RELATIONS AND RESPONSIBILITY TO THE PUBLIC
Section 107.28 EROSION AND SEDIMENT POLLUTION CONTROL PLANS AND PERMITS. Revise to read as follows:
107.28 EROSION AND SEDIMENT POLLUTION CONTROL PLANS AND PERMITS—Install and maintain erosion and sediment (E&S) pollution control devices as indicated or submit an alternate plan for accomplishing equal or better temporary and permanent erosion and water pollution control. If an alternate plan is submitted, do not start work until the plan is approved by the County Conservation District and the Department. If a National Pollutant Discharge Elimination System (NPDES) Permit is involved, do not start work until the plan is approved by the DEP or the authorized County Conservation District and the Department. Concrete clean out areas, either contractor designed or indicated within the contract documents, are incidental to the contract items.
When a general or individual NPDES Permit is involved:
At the preconstruction conference, submit a Preparedness, Prevention and Contingency (PPC) Plan and identify a licensed professional (Professional Engineer, Geologist, Land Surveyor or Landscape Architect) registered in the Commonwealth and if applicable, their designee to be present onsite and responsible for implementing critical stages of the
Do not start earth disturbance activities until an environmental preconstruction meeting is held with DEP or delegated
CCD.
Within 14 days of completing the construction of a stormwater control measure (SCM) as determined by the licensed professional or designee, submit a completed Chapter 102 SCM Construction Certification Form for each SCM to the Representative through PPCC. Form CS-102 has information required to complete the Chapter 102 Form(s). Ensure the General Project and SCM Information, Construction Information, and Licensed Professional Certification sections are completed by the identified licensed professional responsible for overseeing the critical stages of the approved PCSM plan.
Prepare an as-built (record) PCSM Plan to be sealed and signed by the identified licensed professional registered in the Commonwealth. All construction survey, plan preparation, and engineering required for the as-built (record) PCSM Plan will be incidental to the contract items. The as-built (record) PCSM Plan must accurately reflect deviations from the approved PCSM Plan including, but not limited to, plan locations, dimensions, inverts/elevations, materials used and grading. Update the as-built (record) PCSM Plan as construction of the project’s PCSM features progresses. Have the identified licensed professional immediately notify the Representative of all deviations from the approved PCSM Plan. Deviations to the approved PCSM Plan must be submitted for approval. Assist with the determination and documentation if the as-built deviations require a permit amendment or if the PCSM features must be removed and replaced as indicated on the PCSM Plan.
approved Post Construction Stormwater Management (PCSM) Plan.
April 30, 2026 14:52:34 PM Page 15 of 44
Assist the Representative in performing visual site inspections weekly and after each precipitation event greater than 0.25 inches to ensure the project's E&S Best Management Practices (BMPs) are functioning properly. Immediately initiate corrective actions, at no additional cost to the Department, upon notification by the Representative of noncompliance with the provisions of this section that the Representative has determined requires immediate corrective action under Department policies. For all other notifications of noncompliance, initiate corrective actions within 24 hours. Failure or refusal to promptly comply with such notice upon receipt may, at the Department’s sole discretion, result in: the withholding payment of estimates for work completed until the requirements of the E&S Plan are met, assessment of E&S noncompliance liquidated damages as specified in Section 108.07(d) or issuance of a written order stopping all or part of the work until the corrective action has been taken and the requirements of the E&S Plan are met. No claims for extension of time, costs, or damages arising from, related to, or based upon such notices of noncompliance or stop orders will be granted, paid, or considered.
Nothing in this Section is to be interpreted to relieve the Contractor of its obligation to fully and timely comply with all applicable laws and any permits for the project. The time periods set forth in this Section do not supersede any more stringent time periods required by applicable laws or permits for the project.
If corrective action or noncompliance with the provisions of this Section result from design errors/omissions or a precipitation event exceeding the design storm criteria as specified in applicable Department publications; the cost and/or time required for the performance of the corrective actions for noncompliance notices or stop work orders will be considered as specified in Section 110.03 and Section 108.06, as applicable.
Utilize Department, DEP, or other authorized agency’s form(s) included in the contract or project permits unless directed otherwise by the Representative, DEP, the County Conservation District or other authorized regulatory agency.
For the purpose of determining compliance with the provisions of this section, “substantial completion” will be considered to have been attained when all of the following project milestones have been reached:
Either a semi-final or final inspection has been performed, physical work is complete, and an Environmental Commitments and Mitigation Tracking System (ECMTS) Sheet has been executed if applicable to the project.
Earth disturbance activity has been permanently stabilized and sufficient vegetative growth has been achieved to meet permit conditions (uniform 70% perennial vegetative cover) and agreed to by DEP or delegated CCD.
Installation of PCSM SCMs have occurred if applicable. Upon completion of PCSM conversions and facilities, the County Conservation District must approve the removal of all remaining E&S BMPs.
Once a project with a general or individual NPDES Permit has reached substantial completion, submit to the Representative a DEP Notice of Termination (NOT) Form ensuring Sections 2, 3, 4, 7 and 8, are fully executed. The NOT is to be accompanied by the required as-built (record) PCSM Plan, the final certification by the licensed professional and the Contractor’s executed portion of the ECMTS Construction Tracking Signature Sheet.
608 MOBILIZATION
Section 608.4(b)3. Revise to read as follows:
3. When all physical work has been satisfactorily completed and the following certificates and documents, as required, have been properly furnished, the final payment will be made as specified in Section 608.4(a):
Certified Payroll Records
Final DBE/DB payment amounts and, if necessary, shortfall justification
Material Certifications
Form CS-4225H, Highway Lighting In-Service Guarantee Notification
As built drawings for Design/Build projects
Form RW-397A, Right to Enter (a property) and Release Form from property owner, if applicable
Form CS-4345, Borrow and/or Waste Management
Contractor Evaluations of the design of the project; and
April 30, 2026 14:52:34 PM Page 16 of 44
Work Order Information (i.e. Force Account documentation)
Post Construction Stormwater Management As-built drawings and all documentation required for submission of the Notice of Termination for projects with NPDES permits.
Special Provision: C168A - a07015 CHANGES TO SPECIFICATIONS: SECTIONS 110, 404, AND 507
CHANGE TO SPECIFICATIONS: SECTIONS 110, 404, AND 507
Provision Body:
SECTION 110—PAYMENT
Section 110.06 MATERIAL STORED OR ON HAND. Revise to read as follows:
110.06 MATERIAL STORED OR ON HAND—
(a) Stored Material. The Representative may authorize payment for certain material, using Form CS-110, before its incorporation into the work. Upon the Contractor's request submitted through the PennDOT Project Collaboration Center’s (PPCC) Material-Stored Material (CS-110) workflow and the Representative's acceptance in PPCC, the Contractor may be paid 100% of the cost of the material, less the pro‑rata share of the retainage, if any; provided the quantity of stored material does not exceed the total estimated quantity required to complete the project and the cost is at least $1,000 but does not exceed 90% of the contract price of the applicable contract item or component item. Load-Transfer Units are only eligible for 90% of the cost of the material. The cost of the material is that amount to be paid by the Contractor as evidenced by invoices. Fabricated structural steel that is to receive a protective coating may be approved for prepayment at 75% of the contract price of the applicable contract item or component item, before application of the coating, provided the structure has been fully fabricated and preassembly of field connections has been made.
Payment for stored material will not be authorized until the material has been delivered to the project site or an approved location in the vicinity of the project, is inspected by the Representative to ensure the material is in a satisfactory condition and of sufficient quantity, is stored in an approved manner, and conforms to the requirements specified in this Section and Section 106.03. Identify stored material by project designation and set apart from other materials. Fabricated precast/prestressed bridge structure elements indicated on an S-number structure plan are eligible for prepayment when they are approved to ship. Other materials to be stored less than 30 days are not eligible for prepayment. In determining eligibility for prepayment, the beginning date for evaluating whether the required 30-day minimum storage period will be met will be the date the material is delivered to the project or approved storage location, or the date the invoice is submitted to the Department, whichever is the latter. Material originally determined to be ineligible for prepayment due to the minimum storage period requirement, that is then stored for more than 30 days, is eligible for prepayment on the next estimate, provided the invoice has been submitted to the Department. If the Representative determines, because of required fabrication at an off‑site location, that it is not feasible or practicable to store material in the vicinity of the project, the material may be stored at an approved location, which is not in the vicinity of the project, at the Contractor’s expense.
With the exception of structural steel to be incorporated into fabricated structural steel components for main bridge members, as specified in Section 110.06(a)1., only end product manufactured material or fully fabricated products that are awaiting installation and/ or incorporation into the finished work are eligible for prepayment. Ingredients of a finished product are not eligible for prepayment.
Aggregates, cements, and other bulk material are not eligible for prepayment. Beams containing precast components or secondary precast elements detailed on the structure component item schedule or both are eligible for prepayment. Living or perishable plant materials are not eligible for prepayment before planting.
Assume full control and responsibility for the protection of the stored material from the elements and against loss or damage by any cause. In the event any stored material becomes lost, stolen, impaired, or damaged while stored, the monetary value of the lost, April 30, 2026 14:52:34 PM Page 17 of 44 stolen, impaired, or damaged material as may have been paid for in a current estimate will be deducted from a subsequent estimate.
Retain the title to the prepaid material until issuance of the acceptance certificate.
Payment for acceptable stored material will be made on current estimates against the applicable contract item. The amount paid will be proportionately recouped as the material is incorporated into the work. The cost of surplus stored material previously paid on a current estimate but not ultimately incorporated in the final measured work will not be included in the final payment. Surplus stored material is the property of the Contractor. Remove surplus material from the project and dispose of in a satisfactory manner.
Pay the material provider the amount due, as shown on the invoices within 7 calendar days of receipt of payment from the Department. Provide evidence of payment upon request. Failure to make invoice payments as specified will cause the appropriate monies to be deducted from future estimates and will cause the disapproval of further prepayment requests.
1. Prepayment for Structural Steel. Structural steel to be incorporated into fabricated structural steel components for main bridge members may be approved for payment up to 60% of the contract price of the applicable contract item or component item; provided the quantity, cost, delivery, inspection, and storage requirements of Section 110.06(a) are met. The cost of the structural steel is that amount to be paid by the Fabricator as evidenced by invoices. Invoices for approved structural steel are to include the material quantity and Department project identification (i.e., ECMS number, SR & Section, and county), and must be accompanied by certification, as specified in Section 106.03(b)3., and proof of payment (e.g., a copy of a canceled check or receipt, or a certified letter from the structural steel supplier acknowledging receipt of payment).
Payment for approved structural steel will be made on current estimates against the applicable contract item. The amount paid will be proportionately recouped as the fabricated structural steel components are incorporated into the work. Pay the Fabricator the amount due, as shown on the invoices, within 7 calendar days of receipt of payment from the Department. When payment is made, the structural steel becomes the property of the Department. Have the Fabricator furnish a transfer of ownership document within 7 calendar days of receipt of payment and promptly submit the documentation to the Department.
Only approved structural steel to be incorporated into fabricated structural steel components for main bridge members is eligible for prepayment. Handling, transportation, and storage of structural steel materials including, but not limited to, any storage site rental, security, and weather protection, are to be borne by the Contractor and included in the contract price for the applicable contract item.
SECTION 404—EVALUATION OF ASPHALT PAVEMENT RIDE QUALITY AND PAYMENT OF INCENTIVE
Section 404.1 DESCRIPTION. Revise to read as follows:
404.1 DESCRIPTION. This work evaluates an asphalt pavement surface profile and determines the ride-quality incentive associated with the pavement surface profile.
(a) General Requirements. Determine the ride quality of finished pavement surfaces, including overlaid bridge approach slabs and overlaid bridge decks. At least two of the following construction operations must be indicated in areas included in ride-quality lot measurements:
Profile milling as specified in Section 492.
Asphalt Base course.
Asphalt Scratch course.
Asphalt Leveling course.
Asphalt Binder course.
Asphalt Wearing course.
In the presence of the Representative, measure the pavement surface profile according to PTM No. 428. Provide daily calibration results to the Representative before taking any measurements. Provide the raw unfiltered data files and a summary printout of the resultant International Roughness Index (IRI) data and Mean Roughness Index (MRI) values to the Representative within 24 hours of taking measurements. The Representative will determine payment for each ride-quality lot based on the MRI.
Measure the pavement surface of the following excluded areas separate from the pavement surface profile of ride-quality lots. The Representative will not include measurements from excluded areas to determine lot incentive payment.
Pavement surfaces not constructed as a full-depth overlay, as indicated, such as the vertical transition areas at the limits of paving and at the approaches to bridges.
Bridge decks unless overlaid.
April 30, 2026 14:52:34 PM Page 18 of 44
Ramps less than 1,500 feet in length and less than 12 feet wide.
Tapered pavements.
Shoulders, medians, and other pavement surfaces indicated.
Pavement from 5 feet before and up to 5 feet after any appurtenances such as water boxes, manholes, railroad tracks, and inlets extending out into the pavement.
Partial lots less than 100 feet
Roadways with a posted speed limit of 40 miles per hour or lower.
(b) Lot Size. A full lot is 528 feet of a single pavement lane. The Representative will designate lots starting at the beginning limit of paving and continuing to the ending limit of paving for each pavement lane and ramp that is 12 feet or wider. Do not include the length of excluded areas in the 528-foot lot.
The Representative will designate a partial lot at the ending limit of paving and at an excluded area, when the lot length is less than 528 feet. The Representative will evaluate a partial lot as a percentage of a full lot.
Section 404.3(a) Equipment and Operator. Revise to read as follows:
(a) Equipment and Operator. Provide pavement surface profile measuring equipment that has been verified by the Department according to PTM No. 428. In the presence of the Representative, calibrate the distance sensor and check the profile system calibration before each day’s testing.
Provide an operator that is Department certified according to PTM No. 428. The operator must carry their valid PennDOT certification card during pavement surface profiling.
Section 404.3(b) Testing. Revise to read as follows:
(b) Testing.
1. Lots. Provide the traffic control and station marking necessary to accommodate testing. Remove objects and equipment from the surface and sweep the surface as necessary to remove debris. For projects identified for verification as specified in Section 404.3(f), identify and delineate the profiling limits and excluded areas on the day of the verification. The Representative will verify the profiling limits are correct. Use traffic cones with reflective tape and reflective tape on the pavement at the beginning and end of each lane and excluded areas for triggering the start and stop locations of the profiler. In the presence of the Representative, determine the pavement surface profile for each lot according to PTM No. 428. At the completion of testing, immediately submit the lot IRI data and MRI values, according to PTM No. 428, to the Representative.
2. Excluded Areas. Provide the traffic control necessary to accommodate testing. Test the entire surface of each excluded area in stages using a 12-foot straightedge. At each stage, hold the straightedge in contact with the surface and parallel to the roadway centerline and, in successive positions, test the pavement surface profile from one side of the excluded area to the other. Advance the test location to the next stage by moving the straightedge along the roadway centerline not more than 6 feet.
Section 404.3(c)1. Lots. Revise to read as follows:
1. Lots. The Representative will compare the lot MRI to Table A in Section 404.4 to determine if the lot requires corrective action.
Additionally, perform corrective action on any individual bump (must grind) where the irregularity is more than 3/16 inch when tested with a 12-foot straightedge.
Section 404.3(d) Corrective Action. Revise to read as follows:
(d) Corrective Action. Do not produce a deviation, such as a ridge or valley with the adjacent pavement, of more than 1/8 inch when measured on the transverse profile. Correct a sufficient length of pavement to correct the pavement surface profile without producing additional high or low points. Retest the lots and excluded areas after completing corrective action. Perform additional measurements of the pavement surface profile, as necessary, for the Representative to determine which lots do not require additional corrective action. Correct surfaces to provide a uniform texture and positive cross slope so the pavement drains.
Perform all corrective action before testing for pavement depth. Use one or more of the following methods:
1. Carbide Grinding. Use carbide grinding for correcting areas 15 feet in length or less. Use grinders of the walk-behind type that have cutting heads of carbide tipped shackles, stars, or blades and have a locking depth control to produce a uniform pavement surface texture.
April 30, 2026 14:52:34 PM Page 19 of 44
Provide a pavement surface texture consisting of parallel grooves between 3/32 inch and 1/4 inch wide with a “land area” between grooves of 1/16 inch and 3/16 inch. Operate the grinder by making multiple passes, if necessary, with a maximum depth of any single pass of 1/8 inch. Grind longitudinally or transversely across the pavement surface.
2. Diamond Grinding. Section 514.3 and modified as follows:
(d) Tolerance. Delete this section.
Unless otherwise approved, grind the entire lane width.
3. Removal and Replacement. Remove the surface course of the entire pavement lane width by milling and replace at least the minimum layer depth of the specified surface course. Place more than the minimum layer depth if necessary to correct the pavement surface profile.
Section 404.3(f) Verification. Revise to read as follows:
(f) Verification. For Federally funded projects, the Department will perform smoothness verification testing at a minimum of one day and on at least 10% of the project’s lane miles being evaluated using the Department’s inertial lightweight profiler concurrent with smoothness acceptance testing. The Department may require smoothness verification testing for any smoothness acceptance testing.
Coordinate with the Representative at least 14 days in advance of smoothness verification testing to arrange for Department profiler testing and to schedule a virtual meeting with the Department’s Roadway Inventory and Testing Unit (RITU) to verify the smoothness verification testing procedures.
Ensure the Department’s smoothness verification testing occurs concurrently with smoothness acceptance testing. The smoothness acceptance test results will be compared to the Department’s smoothness verification test results. The smoothness acceptance test results will be used for incentive payment when the following tolerances are met:
The verification MRI does not exceed the acceptance MRI by more than 6.1 inches/mile on at least 90 percent of the 528 foot lots for each lane.
The average verification MRI does not exceed the average acceptance MRI by more than 6.1 inches/mile for all lots tested in each lane.
The difference in the length for all lots tested in each lane is less than 0.2 percent.
If the tolerances above are not met during smoothness verification testing, the Department will immediately review the testing procedures, equipment, and personnel used in the smoothness acceptance testing to determine if the test results are acceptable.
When the Contractor’s smoothness acceptance test results are not considered acceptable, the Department’s smoothness verification test results will be used for incentive payment, and the Contractor’s profiler certification will be suspended and must be recertified according to PTM No. 428. Contact the RITU within 10 business days to schedule the profiler for recertification. Recertify the profiler before use on all Department projects.
Section 404.4 MEASUREMENT AND PAYMENT. Revise to read as follows:
404.4 MEASUREMENT AND PAYMENT. Dollar
The proposal will include an item and a predetermined amount of money for Evaluation of Asphalt Pavement Ride Quality and Payment of Incentive. The contract item will have a unit of measure of DOLLAR, a unit price of $1.00, and a quantity equal to the predetermined amount.
Due to the incentive or bonus status of the payment being made, the provisions specified in Section 110.02(d) are not applicable to this item.
Measured and paid for, under the Evaluation of Asphalt Pavement Ride Quality and Payment of Incentive item as follows:
If the lot is not defective, Table A and the MRI for each lot will be used to determine the incentive payment for ride quality.
The incentive payment for a lot subjected to corrective action will be determined according to Table A and the MRI for the lot after the Contractor completes corrective action.
The incentive payment for a partial lot will be determined as a percentage of a full lot.
April 30, 2026 14:52:34 PM Page 20 of 44
After corrective action, the Contractor may leave a defective lot in place if the District…