This document is a Justification for Other Than Full and Open Competition (JOFOC) prepared by NASA's IT Procurement Office (ITPO) for a sole source award to Cine Design Group LLC.

NASA seeks to procure and implement 19 Cinedeck ZX4U Ultra video recorder setups with onsite commissioning for all 19 systems, and to upgrade 5 existing Cinedeck ZX2U systems to the ZX4U Ultra configuration. The anticipated cost is approximately [redacted]. This acquisition supports the Spaceport Command and Control System (SCCS) program, which operates ground equipment for launch of the Space Launch System rocket and Orion spacecraft at Kennedy Space Center. The requirement is justified under 10 U.S.C. 3204(a)(2) (unusual and compelling urgency) as implemented by FAR 6.103-2, based on NASA's critical timeline to return American astronauts to the lunar surface by 2028 as part of the Artemis campaign, which directly supports U.S. national interests in space exploration leadership and national security. The JOFOC emphasizes that delays resulting from full and open competition would jeopardize mission schedules and allow China to achieve its lunar landing goal before the United States. No market research was conducted due to the urgent nature of the requirement. The contracting officer has determined that Cine Design Group LLC is the only source capable of performing this requirement within the required timeframe based on previous competitive activities and consultation with knowledgeable government aerospace personnel. No public Requests for Information were issued, and no competing proposals were received. The contracting officer has determined the anticipated cost will be fair and reasonable, subject to proposal analysis and negotiation prior to contract execution.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

NATIONAL AERONAUTICS AND SPACE ADMINISTRATION

NASA IT Procurement Office (ITPO)

JUSTIFICATION FOR OTHER THAN FULL AND OPEN COMPETITION

(JOFOC)

UNUSUAL AND COMPELLING URGENCY

FOR Cinedeck Recorder Refresh - Cinedeck Upgrade for Artemis III

1. Federal Acquisition Regulation (FAR) 6.104-1(a)(1) – Identification of the agency and the contracting activity, and specific identification of the document as a “Justification for other than full and open competition.”

This document is a justification for other than full and open competition prepared by

National Aeronautics and Space Administration (NASA).

The procuring agency is NASA, and the contracting activity is NASA IT Procurement Office

(ITPO).

2. FAR 6.104-1(a)(2) – The nature and/or description of the action being approved:

This justification provides the rationale for contracting by other than full and open competition to award a sole source order – Cine Design Group LLC.

The general purpose of this order is to acquire Cinedeck 4-channel baseband video recorders and commissioning. This requirement is critical to NASA’s Artemis campaign and its overall mission to safely land humans on the lunar surface.

The Artemis campaign’s timeline, and its included mission dates, are a vital component of the government’s need. For reasons discussed below, delays to mission execution as a result of developmental challenges are likely to result in mission failure. This contract is necessary to ensure that development of a lunar landing capability is complete in time to support NASA’s Artemis missions.

a. The Artemis Campaign and National Strategic Interests.

The Artemis campaign consists of several interconnected NASA programs, encompassing multiple contracts and international efforts. Each component of the campaign is required to reach the agency’s end state of landing humans on the lunar surface. Among these programs are: the Space Launch System (SLS), NASA’s primary space launch capability; Orion, NASA’s solution for transport of crew from low-earth orbit to cis-lunar orbit; Extra- Vehicular Activity (EVA) suits and the Human Landing System (HLS). Each of these programs depends upon the timely development and success of the others to perform its role, and delays within one program have a cascading effect upon the others.

NASA’s Artemis campaign explores the Moon for scientific discovery, technology advancement, and to learn how to live and work on another world in order prepare for human missions to Mars. The Artemis campaign collaborates with commercial and international partners and establish the first long-term presence on the Moon. These efforts support several vital national strategic interests including national security, solidifying the United States’ leadership and influence in space, supporting scientific and technological development, and supporting space commercial development.

To support these interests and ensure continued American superiority in space exploration, it is critical that the United States return to the lunar surface before its global competitors. By completing a lunar landing mission in advance of our global competitors, the United States can shape rules, policy, priorities, and the overall geopolitical landscape of future space exploration. This will provide the United States with the initiative needed to best advance related national interests and maintain its role as the global leader in space exploration.

Falling behind our global competitors in this effort cedes this initiative, and our nation’s leadership in space exploration, to our global competitors. This will result in unacceptable impacts to the United States’ geopolitical position and its national security.

Currently, China is actively developing a human crewed Moon landing mission. China has recently experienced significant success in development of space exploration technologies, including launch and landing of the country’s first reusable orbital rocket in 2025. China’s significant space technology progress has established the country as a near-peer competitor to the United States for space exploration. China’s recent progress also includes significant developments in the country’s crewed lunar program, including successful liftoff and landing tests of a crewed lander. These developments place China on target to meet their current goal of landing two astronauts on the lunar surface before 2030.

It is critical to the national interests of the United States, and therefore to NASA’s mission, that the Artemis program return American astronauts to the Moon before China reaches this milestone and seizes the initiative and global leadership role in human space exploration.

NASA plans to launch its first mission to return humans to the Moon (currently titled “Artemis IV”) by 2028. This launch schedule is critical to NASA’s mission and the national interests it supports.

b. Spaceport Command and Control System (SCCS) Program Background

The Spaceport Command and Control System (SCCS) was developed by NASA’s Exploration Ground Systems to operate, monitor and coordinate the ground equipment for launch of the Space Launch System rocket and Orion spacecraft. The SCCS comprises a suite of complex software linking the launch team operators in Firing Room 1 inside the Launch Control Center at NASA’s Kennedy Space Center in Florida to the SLS rocket and Orion spacecraft in processing areas such as the Vehicle Assembly Building, Mobile Launcher and at Launch Complex 39B.

3. FAR 6.104-1(a)(3) – A description of the supplies or services required, to meet the

Agency’s needs (including the estimated value):

a. The requirement is to upgrade and modernize the existing Cinedeck recording infrastructure through the procurement and implementation of 19 Cinedeck ZX4U Ultra setups, onsite commissioning for all 19 systems, and the upgrade of 5 existing Cinedeck ZX2U systems to the ZX4U Ultra configuration. This effort will refresh existing equipment, enhance system performance and capability, and ensure all upgraded systems are fully configured and operational.

b. The anticipated cost for this action is expected to be approximately $

4. FAR 6.104-1(a)(4) – An identification of the statutory authority permitting other than full and open competition:

The statutory authority permitting other than full and open competition is 10 U.S.C.

3204(a)(2), as implemented by FAR 6.103-2, Unusual and compelling urgency.

5. FAR 6.104-1(a)(5) – A demonstration that the proposed contractor’s unique qualifications or the nature of the acquisition requires use of the authority cited:

The rationale supporting the use of 10 U.S.C. 3204(a)(2) is as described below.

The agency’s need for Cinedeck 4-channel baseband video recorders and commissioning is of such an unusual and compelling urgency that the Government would be seriously injured, both financially and in terms of significant negative impact to the national interests discussed herein, if it is not permitted to limit the number of sources from which it solicits proposals.

In order to return to the lunar surface before our global competitors and advance the United States’ national interests in space exploration and leadership, NASA must return American astronauts to the surface of the Moon as quickly as technological development will safely allow. Current Artemis mission timelines require a lunar landing mission by 2028, with capability demonstration mission milestones planned for Fiscal Year 2027.

Though this mission timeline places NASA close to the developmental timelines and mission goals of our global competitors, this timeline ensures that the Agency is able to support the country’s space policy objectives and related national interests. Further delay to this timeline would place the United States unacceptably close to ceding its leadership in space exploration to our global competitors – significantly harming the national interests of the United States, including national security, scientific advancement, technological maturation and superiority, and other critical Government priorities.

Allowing full and open competition would result in delays in resolving existing Cinedeck hardware failures, firmware issues, service compatibility concerns, or operating system problems, potentially reducing recording system availability and negatively affecting Artemis mission support. Due to the cutting-edge nature of the technology required for this capability, every day in the developmental timeline is absolutely vital for ensuring that a lunar landing capability is completed in time for NASA’s established mission dates. Each day added to this timeline – including the significant time that would be required for a full and open competition – places the United States closer to ceding its space exploration leadership to our global competitors.

6. FAR 6.104-1(a)(6) – A description of the efforts made to ensure that offers are solicited from as many potential sources as practicable, including whether a notice was or will be publicized as required by Subpart 5.1 and, if not, which exception under 5.101 applies:

The contracting officer has determined in accordance with FAR 5.101(b)(1) that this action is exempt from the notice required in FAR 5.101, because unusual and compelling urgency precludes competition to the maximum extent practicable and the Government would be seriously injured if the agency complies with the publicizing and response time periods specified in FAR 5.101(d).

7. FAR 6.104-1(a)(7) – A determination by the contracting officer that the anticipated cost to the Government will be fair and reasonable:

The contracting officer’s signature on this document indicates that the Contracting Officer has determined that the anticipated cost to the government will be fair and reasonable. The Contractor must be required to submit a proposal to be evaluated and negotiated by the Government. Prior to execution of the contractual instrument, a proposal analysis will be performed. The proposal analysis will ensure that the final agreed-to price for the contract action is fair and reasonable.

8. FAR 6.104-1(a)(8) – Description of the market research conducted, and the results, or a statement of the reasons market research was not conducted (e.g., urgent, and compelling requirement):

Based on the unusual and compelling urgency of NASA’s requirement and the authority of FAR 6.103-2(b), additional market research was not conducted. Through the use of previous competitive activities, including the already established market research, and consultation with knowledgeable individuals in Government relative to aerospace activities, the contracting officer has determined Cine Design Group LLC is the only source capable of performing this requirement in the required timeframe.

9. FAR 6.104-1(a)(9) – Any other facts supporting the use of other than full and open competition:

This action aligns with the Executive Order 14369, Ensuring American Space Superiority, directive to return humans to the lunar surface no later than 2028. It also supports national priorities to ensure American leadership in space exploration by returning humans to the lunar surface before our international competitors.

10. FAR 6.104-1(a)(10) – A listing of the sources, if any, that expressed an interest in writing in the acquisition:

Based on the unusual and compelling urgency of NASA’s requirement and the resulting use of NASA’s authority under 10 U.S.C. 3204(a)(2), the Agency did not conduct public Requests for Information and thus received no responses. NASA also did not receive any unsolicited proposals to support a different approach to the Agency’s requirements.

11. FAR 6.104-1(a)(11) – A statement of actions, if any, the agency may take to remove or overcome any barriers to competition before any subsequent acquisition for the supplies or services required:

NASA’s future approach to acquisitions related to human space exploration is intended to establish a robust, competitive space economy. NASA has engaged in a parallel developmental contract structure in part to ensure completion of future Artemis missions and to support a sustained contractor base for future competitive lunar transportation requirements.

The Agency will continue to examine the market in the future for alternative solutions or new sources before executing any subsequent acquisitions for the same requirements.