This Statement of Work (SOW) outlines non-personal services contract requirements for Real Property Master Planning (RPMP) support to the National Aeronautics and Space Administration (NASA) across all 10 NASA Centers. The contract deliverables consist of ten primary tasks: Center Vision Plan, Area Development Plans (ADP), Sustainability Component Plans (SCP), Center Design Guide, Center Development Plan (CDP), Master Plan Digest, Master Plan Website, Area Development Execution Plans (ADEP), Center Special Study, and Agency Special Study. These master planning products must be affordable, flexible, maintainable, and achievable based on NASA's mission requirements and long-term capital investment strategy. The contractor must incorporate NASA's strategic goals, including a 25% reduction in constructed asset holdings over 20 years and alignment with the Agency's anticipated budget and affordability targets as defined in Center Future Development Concepts.
The contractor shall provide all personnel, equipment, software, supplies, facilities, and transportation necessary to perform RPMP tasks, except for Government-furnished items including workspace for collaborative workshops accommodating up to 40 people and applicable publications provided by the Contracting Officer's Representative (COR). Key contractor responsibilities include developing and maintaining a quality assurance and control plan, conducting stakeholder interviews and collaborative workshops, performing facility site data collection and analysis, preparing alternative plans with life-cycle cost analysis, and delivering monthly status reports by the 5th of each following month. Special qualifications are mandatory: the Contractor Project Manager and primary facilitation team members must possess Federal Master Planning training, experience with Department of Defense Unified Facilities Criteria (UFC 2-100-01), procurement strategy knowledge, life-cycle cost analysis experience (preferably ECONPACK software), and professional certifications including AICP, RLA, RA, AIA, or equivalent. Additionally, contractors must complete at least three days of relevant Federal master planning training through the U.S. Army Corps of Engineers within 12 months following task award. All work must comply with NASA Procedural Requirements, NASA Policy Directives, and security requirements including NASA Personal Identity Verification (PIV) credentials following FBI fingerprint checks and National Agency Check and Inquiries (NACI) background investigations. The contract specifies use of approved software including Adobe Creative Suite, ArcGIS, AutoDesk, Bentley, ECONPACK, and Microsoft Office Suite, with contractor-furnished files to include GIS shapefiles, PDF files, PowerPoint presentations, Adobe Suite files, Excel spreadsheets, and CADD files upon final report delivery.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| 80NSSC27Q0008 RFI - NASA Real Property Master Planning Services.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
NASA Real Property Master Planning Support
GENERAL: This is a non-personal services contract to provide Real Property Master Planning (RPMP) for the National Aeronautics and Space Administration (NASA) to be completed over the contract period and include the following RPMP products for all 10 NASA Centers (see Attachment 2 for complete list of sites):
Task 1: Center Vision Plan Task 2: Area Development Plans (ADP) Task 3: Sustainability Component Plans (SCP) Task 4: Center Design Guide Task 5: Center Development Plan (CDP) Task 6: Master Plan Digest Task 7: Master Plan Website Task 8: Area Development Execution Plans (ADEP) Task 9: Center Special Study Task 10: Agency Special Study
1.1 DESCRIPTION OF SERVICES/INTRODUCTION: The Contractor shall provide all personnel, equipment, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform RPMP tasks awarded as defined in this Performance Work Statement except for those items specified as Government furnished property and services. The Contractor shall perform to the standards in this contract.
1.2. SCOPE: The types of services that are to be performed are non-personal RPMP services. The objective is for the Contractor to provide NASA with master planning products that are affordable, flexible, maintainable, and achievable based on NASA’s mission requirements and long-term capital investment strategy (the Government will provide). Task services include, but are not limited to: developing work plans, stakeholder coordination and interviews, facility site data collection and analysis, collaborative workshop facilitation (a workshop in which key stakeholders work together on various engaging activities to analyze problems, brainstorm ideas, generate solutions, make decisions, and/or create plans), alternative plan preparation, life-cycle cost analysis, business case assessments, master planning document preparation and submittals, status reports, and quality control. The Contractor is responsible for providing master planning services and products that incorporate a foundational understanding of both the Center and NASA’s overarching mission and supporting real property strategy.
NASA is responsible for advancing aeronautics technologies for use in air, space, and on the ground, developing cutting-edge science, technology, and human space exploration for the United States. NASA's focus has always been, and will always be, to discover, invent, and demonstrate new technologies, tools, and techniques that will allow our Nation to explore space while improving life on Earth.
At NASA Headquarters, the Office of Strategic Infrastructure (OSI) has overall responsibility for policies and oversight of real property management and collaboration with NASA Centers responsible for implementation. OSI’s strategy is to “renew and modernize its facilities to sustain its capabilities and accommodate those capabilities in the most efficient facilities set practical.” This is a challenging task as NASA's real property portfolio is predominantly owned (2,700 owned buildings totaling 45 million gross square feet (gsf) and fewer than 2 million gsf in facilities leased directly or from GSA) and over 80% of these facilities were constructed before 1978. As a result, NASA’s facilities and infrastructure have become inefficient and costly to operate and maintain. The Agency recognizes that its facilities costs, including the increasing obsolescence and degradation of older facilities, present a continually escalating risk to mission success. To address these issues, NASA is integrating innovative practices for prioritizing repair and replacement of facilities and has deployed updated footprint reduction and affordability goals to be addressed in all Center Future Development Concepts (FDC, developed in-house by Centers) and all Center RPMPs (developed in alignment with a Center’s FDC):
• Footprint Reduction: Centers shall plan a 25% reduction in constructed asset holdings into a 20-year RPMPs. Centers shall also illustrate a planned reduction of office space to conform with NASA Policy Requirement (NPR) 8800 if Center averages exceed current allowances.
• Affordability: Centers shall develop a 20-year RPMP that aligns with the Agency’s anticipated budget and the RPMP shall be updated every five years.
They should also include projections of non-NASA sources of funding and savings such as Enhanced Use Lease proceeds, other out-grant mechanisms, funding from reimbursable work, host-tenant arrangements, etc.
The Contractor shall ensure that all RPMP reports developed incorporate the Agency’s affordability goals and align with NASA’s facilities strategy. The Contractor shall work with Center master planners to help facilitate collaboration with NASA HQ, and alignment with relevant directives provided by NASA HQ and Center leadership. These include, but are not limited to the following NASA entities at NASA HQ and the Centers:
• NASA HQ Level: Mission Support Council (MSC), NASA’s program-oriented
Mission Directorates and the Mission Support Directorate (MSD), Capability Portfolio Managers
• Center Level: Center Director, Center Associate Director, Facility Utilization Review Board (FURB), Executive/Senior Council, and Center master planner(s)
Additionally, the Contractor shall incorporate information, and meet mandates, provided by the MSC and Congressional Briefings and reports, and in accordance with all other current applicable policies, regulations, and publications (see 1.8: Applicable Publications), and with the performance standards delineated in this contract. NASA’s standards for RPMP tasks are closely modeled after the Department of Defense’s (DoD) standards for master planning documents. The most up-to-date master planning DoD Unified Facilities Criteria (UFC) shall be referenced for details on standards beyond what is provided in the NASA Master Planning Support Statement of Work (SOW) and supporting tasks SOWs. The Contractor will follow all Center IT security and legal requirements regarding public information sharing.
The Contractor is responsible for ensuring that the Contractor project manager (PM) and all employees leading the facilitation of Agency and/or Center on-site activities possess Federal Master Planning training and experience with the DoD master planning UFC 2- 100-01, have experience with procurement strategies and in life-cycle cost analysis (preferably ECONPACK software), and those in leadership roles be AICP (American Institute of Certified Planners), RLA (Registered Landscape Architect), Registered Architect (RA), AIA (American Institute of Architects), or equivalent certified/licensed.
(see 1.4.7 Special Qualifications).
1.2.2 Task 1 – Center Vision Plan. The Contractor will conduct stakeholders interviews and lead a collaborative workshop to gather and develop information to prepare and provide a Center Vision Plan. The Center Vision Plan shall be developed in accordance with the Agency Vision Plan and include an introduction (e.g. statement of the purpose, process and methodology, and relevant guidance); analysis (e.g. overall constraints and opportunities map(s) and precedent studies); a Center’s planning vision, goals, and objectives; a Developable Area Map; a Framework Plan identifying and prioritizing all planning districts across the entire Center; a land pattern matrix if applicable; and a summary Future Development Concept and preliminary Capital Investment Program Plan (CIPP). To establish a Center’s planning districts, geographic features, key transportation systems, Center boundaries, open space networks, existing land-use patterns, and any identified historic districts should be evaluated. The Vision Plan will guide the development of a Center’s planning district ADPs with the prioritization of design principles and alignment with relevant policy and guidance. The Contractor shall complete Center Vision Plans in accordance with all current applicable policies, regulations, and publications (see 1.8: Applicable Publications), and with the performance standards delineated in the attached Task 1 SOW document.
1.2.3 Task 2 – Center Area Development Plans (ADP). The Contractor will conduct stakeholder interviews and lead a collaborative workshop to gather and develop information to prepare and provide an Area Development Plan for each defined planning district within a NASA Center. The Contractor shall use multiple techniques to gather data including electronic source retrieval, interviews, document reviews, and a participatory workshop. Multiple ADP planning districts may be addressed during the same workshop as appropriate. The Contractor shall facilitate a stakeholder workshop to prepare a district specific vision and program, analyze the site (real property constraints, environmental constraints, and operational constraints) prepare development alternatives, analyze and select a preferred alternative, and detail the preferred alternative with an illustrative plan, regulating plan, and phasing plan. Street, building, and landscape standards will also be included. All of the efforts shall be documented in a comprehensive ADP report for each planning district at the Center including updates to the Future Development Concept and CIPP. The Contractor shall complete all ADPs in accordance with all current applicable policies, regulations, and publications (see 1.8:
Applicable Publications), and with the performance standards delineated in the attached Task 2 SOW document.
1.2.4 Task 3 – Center Sustainability Component Plans (SCP). The Contractor will conduct stakeholder interviews and lead a collaborative workshop to gather and develop information to prepare and provide a Sustainability Component Plan for each defined planning district within a NASA Center. An SCP can be completed for a planning district only after the Area Development Plan (ADP) has been completed for that district. The district SCPs will be developed to align with the Center’s Strategic Sustainability Performance Plan (SSPP) and all identified sustainability projects will be phased to align with the Center’s Capital Investment Program Plan (CIPP). The Center’s most recent SSPP and the CIPP will be provided by the Government COR. All SCP components and recommendations related to Sustainability, Energy, Water Conservation, Real Property, and GIS shall comply with NASA NPRs and each NASA facility’s procedural requirements. The Contractor shall complete SCPs in accordance with all current applicable policies, regulations, and publications (see 1.8: Applicable Publications), and with the performance standards delineated in the attached Task 3 SOW document.
1.2.5 Task 4 – Center Design Guide. The Contractor will conduct stakeholder interviews and lead a collaborative workshop to gather and develop information to prepare and provide a Center Design Guide. The Design Guide shall include Historic Preservation Standards, Building Envelope Standards, Interior Design Standards, Transportation Standards, and Landscape Standards. The Contractor shall use multiple techniques to gather data including electronic source retrieval, interviews, document reviews, and a participatory workshop. The Center Design Guide shall incorporate and compliment any Center-specific Engineering Standards that have been previously developed and released for use. The Contractor shall complete Center Design Guides in accordance with all current applicable policies, regulations, and publications (see 1.8:
Applicable Publications), and with the performance standards delineated in the attached Task 4 SOW document.
1.2.6 Task 5 – Center Development Plan (CDP). The Contractor will conduct information to prepare and provide a Center Development Plan. The CDP workshop shall be held after the Vision Plan, ADP, ADEP, and SCP (if applicable) workshops and draft reports have been completed. In the CDP workshop, the Contractor shall integrate Vision attributes and key components from completed ADPs, SCPs (if applicable), the Design Guide (if applicable) into a CDP report which prioritizes and phases the Center CIPP. The Contractor shall complete CDPs in accordance with all current applicable policies, regulations, and publications (see 1.8: Applicable Publications), and with the performance standards delineated in the attached Task 5 SOW document.
1.2.7 Task 6 – Center Master Plan Digest (Digest). The Contractor will conduct information to prepare and provide a Center Master Plan Digest. The development of the Digest may be conducted concurrently with the development of the Center Development Plan. The Master Plan Digest should only be completed after the Center Vision Plan, all of the Area Development Plans (ADPs), and all of the Sustainability Component Plan (SCPs, if applicable) have been completed. It may be completed concurrently to the development of the Center Development Plan (CDP). The Digest is a comprehensive magazine style document to showcase key components from the completed Vision Plan, ADPs, SCPs (if applicable), and the CDP (may be completed concurrently). The Contractor shall complete Center Digests in accordance with all current applicable policies, regulations, and publications (see 1.8: Applicable Publications), and with the performance standards delineated in the attached Task 6 SOW document. See attached Task 6 SOW for additional details on task requirements.
1.2.8 Task 7 – Center Master Plan Website. The Contractor shall prepare and provide a Center Master Plan Website for the Center showcasing key components from all completed master planning products and work with the Center’s local IT specialists to make it compliant with accessibility, security, and other requirements. Provisions for internal (Center) access, Agency-wide access, and public access versions of the website shall be included where appropriate. The Contractor shall complete Center Master Plan Websites in accordance with all current applicable policies, regulations, and publications (see 1.8: Applicable Publications), and with the performance standards delineated in the attached Task 7 SOW document.
1.2.9 Task 8 – Center Area Development Execution Plans (ADEPs). The Contractor will conduct stakeholder interviews and lead a collaborative workshop to gather and develop information to prepare and provide an ADEP for each defined planning district within a NASA Center. The ADEP is intended to guide planning staff to efficiently execute projects in alignment with the Center’s planning vision and anticipated Construction of Facilities (CoF) and NASA Program funding. The Contractor shall complete ADEPs in accordance with all current applicable policies, regulations, and publications (see 1.8: Applicable Publications), and with the performance standards delineated in the attached Task 8 SOW document.
1.2.10 Task 9 – Center Special Study. The Contractor will prepare a Special Study for the Center. Additional details on the intent, scope, and deliverable requirements of the special study will be provided by the Center. The Contractor shall complete the Center Special Study in accordance with all current applicable policies, regulations, and publications (see 1.8: Applicable Publications), and with the performance standards delineated in the attached Task 9 SOW document.
1.2.11 Task 10 – Agency Special Study. The Contractor will prepare a Special Study for the Agency. Additional details on the intent, scope, and deliverable requirements of the special study will be provided by the Agency. The Contractor shall complete the
Agency Special Study in accordance with all current applicable policies, regulations, and publications (see 1.8: Applicable Publications), and with the performance standards delineated in the attached Task 10 SOW document.
1.2.12 Lessons Learned Report. Based on the lessons learned from applying the NASA Master Planning Handbook and applicable policies, regulations, and publications with the completed tasks outlined in this SOW, a Lessons Learned Report shall be prepared and provided by the Contractor as part of each task or integral set of tasks for which the overall cost exceeds $200,000. Although many achievements may be produced, the Report should also identify obstacles that may have constrained success. Understanding the nature of these achievements and obstacles may allow NASA to improve its ability to refine the NASA Master Planning Handbook.
1.2.13 Monthly Status Reports. The Contractor shall provide administrative services for the project including monthly status reports, and accounting. The monthly status reports shall be submitted to the Government COR no later than the 5th of the following month.
1.2.14 Final Report Deliverables. Printed and electronic copies of all Final report deliverables shall be submitted to the Agency or Center COR and to the OSI master planner. Once a Final report is verified as complete in writing by the Center COR and the OSI Planner, then the task contract is considered complete. The number of printed copies to be delivered will be determined by the Agency/Center. The Final Report includes the entire 95% Final Report, with changes and corrections based on input from the Government review, and an updated Comment Tracker (see task SOWs for additional details) in the appendix. Included in this submittal will be electronic files of all data produced and maintained including geographic information system (GIS) shapefiles, PDF files, PowerPoint file(s), all Adobe Suite Program files, Excel files, and computer aided drafting and design (CADD) files. The Center planning staff will determine appropriate distribution of this data.
1.3 PERIOD OF PERFORMANCE: Each task order will define the duration/period of performance separately.
1.4 GENERAL INFORMATION:
1.4.1 Quality Assurance and Control: The Contractor shall develop and maintain an effective quality assurance and control (QA/QC) plan (see section 1.6.2).
1.4.2 Quality Surveillance: The Government COR shall evaluate the Contractor’s performance under this contract in accordance with the Agency’s and/or a Center’s Quality Surveillance Plan. This plan is developed by the Government and is primarily focused on what the Government must do to ensure that the Contractor has performed in accordance with the performance standards. It defines how the performance standards will be applied, the frequency of surveillance, and the minimum acceptable defect rate(s).
1.4.3 Government Holidays:
New Year’s Day Labor Day Martin Luther King Jr.’s Birthday Columbus Day President’s Day Veteran’s Day Memorial Day Thanksgiving Day Independence Day Christmas Day
1.4.4 Hours of Operation: Normal business hours for NASA sites are 8:00 AM through 4:00 PM Monday through Friday. Some NASA sites, participate in Super Flex Fridays (work a 9 day/80-hour work schedule) and hold normal business hours from 8:00 AM through 6:00 PM. The Contractor shall work with the COR for required NASA provided support.
1.4.5 Place of Performance: The work to be performed under this contract will be performed at the Contractor facility and, for workshops and data collection, at Government facilities. The Contractor will also be expected to attend at least quarterly meetings at Government facilities to deliver status updates. Frequency of on-site meetings will be determined by the Center. All major NASA Centers and component facilities are located within the contiguous United States. See Attachment 2.
1.4.6 Security Requirements: Contractor personnel performing work under this contract must adhere to the following requirements from NASA Procedural Requirements (NPR) 1600.4, NASA Policy Directive (NPD) 2542.1H, and NASA’s Security Assessment and Authorization: External Information Systems Handbook (ITS-HBK- 2810.02-05A):
1.4.6.1 Security Plan: In accordance with ITS-HBK-2810.02-05A and NPD 2542.1H, the Contractor must develop a Security Plan outlining intent, protocol, and conditions for processing, storing, and/or transmitting NASA information on non-government furnished and personally owned IT equipment, software, and media that must be approved by the Agency Chief Information Officer (CIO).
1.4.6.2 NASA PIV credentials will be issued only after completion of a FBI fingerprint check and submission of a background investigation, which will be a National Agency Check and Inquires (NACI) background investigation at a minimum. NASA PIV credentials will have an expiration date set for a period not to exceed five years from the Card Production Request (CPR) generation date.
NASA PIV credentials will not be issued to individuals holding a Federal PIV credential issued by another Federal entity or to individuals holding a PIV-I credential issued by an organization whose PIV-I credentials conform to the Federal PIV-I standard. Exceptions to this policy may be made only when the exception has been documented and approved by the Center CIO. The exception request will specifically explain why a non-NASA credential is not usable in the NASA ICAM services.
Additional safety, security, and badging requirements may exist at specific sites, facilities, and interior spaces around the Agency. The Contractor will coordinate with the PM for access to these areas.
1.4.6.3 Physical Security: The Contractor shall be responsible for safeguarding all Government equipment, information and property provided for Contractor use.
At the close of each work period, Government facilities, equipment, and materials shall be secured.
1.4.7 Special Qualifications: NASA has modeled its requirements on the DoD Unified Facilities Criteria for Installation Master Planning (UFC 2-100-01). The Contractor is responsible for ensuring that the Contractor PM and all employees leading the facilitation of Agency or Center on-site activities possess Federal Master Planning training and experience with the master planning UFC, have experience with procurement strategies and in life-cycle cost analysis (preferably ECONPACK software), and those in leadership roles be AICP (American Institute of Certified Planners), RLA (Registered Landscape Architect), Registered Architect (RA), AIA (American Institute of Architects), or equivalent certified/licensed.
The Contractor PM and all employees on the primary facilitation team for Agency or Center on-site activities shall have completed at least three (3) days of relevant Federal master planning training. Relevant training is available through the U.S. Army Corps of Engineers (USACE) at multiple locations across the Nation, including one or more of the following list of classes: Master Planning Principles (Prospect 25); Master Planning Practices (Prospect 241); Master Planning Advanced Techniques (Prospect 952); Master Planning Applied Skills (Prospect 326); Master Planning Energy and Sustainability (Prospect 258); Master Planning Historic Structures I and/or II (Prospect 392 and 163);
Vision and Installation Design Guide Practicum; Area Development Plan Practicum;
Installation Development Plan Practicum; and/or the Master Plan Digest Practicum. To complete this requirement, contractors would provide documentary evidence of registration for and satisfactory completion of identified courses through USACE (see http://www.dodmpi.org/courses.html for more information), or through a comparable Federal training provider, during the twelve (12) months following task award.
1.4.8 Post Award Conference/Periodic Progress Meetings: The Contractor agrees to attend any post award conference convened by the contracting activity or contract administration office in accordance with Federal Acquisition Regulation Subpart 42.5.
The Contracting Officer, Contracting Officers Representative (COR), and other Government personnel, as appropriate, may meet periodically with the Contractor to review the Contractor's performance. At these meetings the Contracting Officer will apprise the Contractor of how the Government views the Contractor's performance and the Contractor will apprise the Government of problems, if any, being experienced.
Appropriate action shall be taken to resolve outstanding issues. These meetings shall be at no additional cost to the Government.
1.4.9 Contracting Officer Representative (COR): The Government COR will be identified by a separate letter and may be a different individual at each Center. At some http://www.dodmpi.org/courses.html
Centers, in addition to a COR, there may also be a Technical Monitor. The COR monitors all technical aspects of the contract and assists in contract administration. The COR is authorized to perform the following functions:
• assure that the Contractor performs the technical requirements of the contract;
• perform inspections necessary in connection with contract performance;
• maintain written and oral communications with the Contractor concerning technical aspects of the contract;
• issue written interpretations of technical requirements, including Government drawings, designs, specifications; monitor Contractor's performance and notifies both the Contracting Officer and Contractor of any deficiencies; coordinate availability of Government furnished property;
• and provide site entry of Contractor personnel.
A letter of designation issued to the COR, a copy of which is sent to the Contractor, states the responsibilities and limitations of the COR, especially with regard to changes in cost or price, estimates or changes in delivery dates. The COR is not authorized to change any of the terms and conditions of the task order.
1.4.10 Contractor Key Personnel: The following personnel are considered key personnel by the Government:
Program/Contract Manager -The Contractor shall provide a program/contract manager who shall be responsible for the performance of the work. The name of this person and an alternate who shall act for the Contractor when the manager is absent shall be designated in writing to the Contracting Officer. The Contract Manager or alternate shall have full authority to act for the Contractor on all contract matters relating to daily operation of this contract.
1.4.11 Identification of Contractor Employees: The Contractor is directed to comply with FAR Clause 52.204-9 Personal Identity Verification of Contractor Personnel.
1.4.12 Data Rights: The Government has unlimited rights to all documents/material produced under this contract. All documents and materials, to include the source codes of any software, produced under this contract shall be Government owned and are the property of the Government with all rights and privileges of ownership/copyright belonging exclusively to the Government. These documents and materials may not be used or sold by the Contractor without written permission from the Contracting Officer.
All materials supplied to the Government shall be the sole property of the Government and may not be used for any other purpose. This right does not abrogate any other Government rights.
1.4.13 Organizational Conflict of Interest: The Contractor and subcontractor personnel performing work under this contract may receive, have access to or participate in the development of proprietary or source selection information (e.g., cost or pricing information, budget information or analyses, specifications or work statements, etc.) or perform evaluation services which may create a current or subsequent Organizational Conflict of Interests (OCI) as defined in FAR Subpart 9.5. The Contractor shall notify the
Contracting Officer immediately whenever it becomes aware that such access or participation may result in any actual or potential OCI and shall promptly submit a plan to the Contracting Officer to avoid or mitigate any such OCI. The Contractor’s mitigation plan will be determined to be acceptable solely at the discretion of the Contracting Officer and in the event the Contracting Officer unilaterally determines that any such OCI cannot be satisfactorily avoided or mitigated, the Contracting Officer may affect other remedies as he or she deems necessary, including prohibiting the Contractor from participation in subsequent contracted requirements which may be affected by the OCI.
1.5. GOVERNMENT FURNISHED ITEMS AND SERVICES:
1.5.1 Facilities: The Government will provide the workspace for on-site collaborative workshops (see Section 1.2) for up to forty people, and for on-site meetings with NASA personnel during times agreed upon the Center COR and the Contractor.
1.5.2 Materials: The COR will provide the current Applicable Publications (see Section 1.8) and relevant Standard Operating Procedure documents required to complete the requirements of this SOW.
1.6 CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES:
1.6.1 General: The Contractor shall provide all personnel, equipment, software and programs, supplies, facilities, transportation, tools, materials, supervision, and other items and non-personal services necessary to perform RPMP tasks awarded as defined in this Performance Work Statement except for those items specified as Government furnished property and services (see Section 1.5).
1.6.2 Quality Assurance and Control Plan: The Contractor shall develop and maintain an effective quality assurance and control (QA/QC) plan to ensure services are performed in accordance with this SOW. The Contractor shall develop and implement procedures to identify, prevent, and ensure non-recurrence of defective services. The Contractor’s QA/QC plan is the means by which they assure the work complies with the requirements of the contract. The Contractor shall develop and provide to the Government a QA/QC Plan at the time of proposal and any updates after contract award.
Any update to the QA/QC Plan must be submitted by the Contractor PM and reviewed by the COR when changes are made thereafter. After acceptance of the QA/QC Plan the Contractor shall receive the Contracting Officer’s acceptance in writing of any proposed change to his QA/QC system.
1.6.3 Non-Disclosure Agreement:
1.6.4 Approved Software: The Contractor shall utilize the following approved software programs to create all task files and documents: Adobe Creative Suite, ArcGIS, AutoDesk Software, Bentley Software, ECONPACK, and Microsoft Office Suite.
Additional programs may be used by the Contractor to create task files and documents with the Center COR’s written approval.
1.7 APPLICABLE PUBLICATIONS (CURRENT EDITIONS): The Contractor must abide by the most recent published version of applicable master planning regulations, publications, manuals, and local policies and procedures.
• Mission Support Council (MSC) Decision Memo 2017-06-002, Reduce the Footprint
– Strategic Rightsizing Goal, June 1, 2017
• Agency Mission Planning Model (AMPM) FY17
• NASA Transition Authorization Act of 2017, March 21, 2017; see Section 837
• NASA Strategic Workforce Plan, October 31, 2016
• NASA Policy Directive (NPD) 8810.2 Master Planning for Real Property, December
9, 2009
• NPD 1001.0B, NASA Strategic Plan, March 12, 2014
• NPD 2540.1H, Personal Use of Government Office Equipment Including Information
Technology, February 24, 2016
• ITS-HBK-2810.02-05A Security Assessment and Authorization: External
Information Systems, February 4, 2016
• EC-2016-10-001 NASA Center Roles Revision B, October 31, 2016
• FY17 Agency Mission Planning Manifest (AMPM), February 9, 2016
• NASA Interim Directive (NID) 8000.104 Acquisition of Administrative Office Space
• NASA Procedural Requirements (NPR) 8810.1A Center Master Planning, February
10, 2013
• NPR 8800.15C Real Estate Management Program w/Change 1, February 24, 2015
• NPR 8810.1 Master Planning Procedural Requirements, February 13, 2013
• NPR 1600.4 Identity and Credential Management, April 08, 2016
• NPR 1620.3A Physical Security Requirements for NASA Facilities and Property, October 4, 2012. Note: NASA Anti-Terrorism/Force Protection (AT/FP) standards follow The Risk Management Process for Federal Facilities, published 01 November 2016, and all appendices. AT/FP requirements in the UFC 2-100-01 are not applicable.
• NASA Master Planning Handbook, 2013
• Installation Master Planning Unified Facilities Criteria (UFC) 2-100-01, 15 May
• NASA Office of Strategic Infrastructure (OSI) CIPP Template
1.8 ATTACHMENT/TECHNICAL EXHIBIT LIST:
1.8.1 Attachment 1/Technical Exhibit 1– NASA RPMP Products Overview
1.8.2 Attachment 2/Technical Exhibit 2 – List of NASA Centers
Attachment 1/Technical Exhibit 1 – NASA RPMP Products Overview
AGENCY VISION
TASK 1:
CENTER VISION PLAN
CENTER FUTURE
DEVELOPM ENT
CONCEPT (FDC)
MSC APPROVAL
TASK 2:
CENTER AREA DEVELOPM ENT PLANS (ADP)
TASK 3:
CENTER SUSTAINABILITY COMPONENT PLANS (SCP)
TASK 4:
CENTER DESIGN GUIDE
TASK 5:
CENTER DEVELOPM ENT PLAN (CDP)
TASK 6:
CENTER MASTER PLAN DIGEST
TASK 7:
CENTER MASTER PLAN WEBSITE
TASK 8:
CENTER AREA DEVELOPM ENT EXECUTION PLANS (ADEP)
AGENCY M ASTER PLAN
Attachment 2/Technical Exhibit 2 – List of NASA Centers
Spread out from coast to coast, NASA's Centers are diverse and specialized to meet its unique mission assignments.
ACRO
Center
Planning Site
Location Adjacent Sites (adjacent
Federal sites) Land Area
(acres) Workforce (total personnel) Facilities (total buildings and structures) Facilities Total
Gross Square Feet
AFRC Armstrong Flight Research Center Armstrong Edwards, CA Edwards Air Force Base 883 1,000 300 1,400,000
ARC Ames Research Center Ames Mountain View, CA Moffett Federal Airfield 448 3,300 200 2,800,000
ARC Ames Research Center Moffett Mountain View, CA N/A 1,469 1,500 350 2,600,000
ARC Ames Research Center Camp Parks Dublin, CA U.S. Army Camp Parks 175 0 50 2,500
GRC Glenn Research Center Lewis Field Cleveland, OH N/A 312 3,000 250 2,300,000
GRC Glenn Research Center Plum Brook Sandusky, OH N/A 6,742 100 325 550,000
GSFC Goddard Space Flight Center Greenbelt Greenbelt, MD N/A 1,264 7,600 375 3,900,000
GSFC Goddard Space Flight Center Wallops Wallops Island, VA N/A 308 500 800 600,000
JPL Jet Propulsion Laboratory Goldstone Fort Irwin, CA Fort Irwin 0 150 150 200,000
JPL Jet Propulsion Laboratory Oak Grove Pasadena, CA N/A 155 6,500 300 2,600,000
JSC Johnson Space Center Johnson Houston, TX N/A 1,581 7,200 400 3,900,000
JSC Johnson Space Center Ellington Houston, TX N/A 51 500 75 600,000
JSC Johnson Space Center White Sands Las Cruces, NM White Sands Missile
Range 8,710 600 225 500,000
KSC Kennedy Space Center Kennedy Merritt Island, FL N/A 139,490 6,200 1,025 8,000,000
KSC Kennedy Space Center Cape Cape Canaveral, FL Cape Canaveral Air Force
Station 265 60 275 300,000
LaRC Langley Research Center Langley Hampton, VA Langley Air Force Base 764 3,600 500 3,000,000
MSFC Marshall Space Flight Center Marshall Huntsville, AL Redstone Arsenal 1,841 6,400 425 4,400,000
MSFC Marshall Space Flight Center Michoud New Orleans, LA N/A 829 2,500 200 3,700,000
SSC Stennis Space Center Stennis Hancock County , MS N/A 20,375 5,000 440 4,300,000
| NASA Real Property Master Planning Support |
| 1.4 GENERAL INFORMATION: |
| 1.4.3 Government Holidays: |
| 1.5. GOVERNMENT FURNISHED ITEMS AND SERVICES: |
| 1.6 CONTRACTOR FURNISHED ITEMS AND RESPONSIBILITIES: |
| 1.6.3 Non-Disclosure Agreement: |
| 1.8 ATTACHMENT/TECHNICAL EXHIBIT LIST: |
| Attachment 1/Technical Exhibit 1 – NASA RPMP Products Overview |
| CENTER VISION PLAN |
| CENTER AREA DEVELOPM ENT PLANS (ADP) |
| CENTER SUSTAINABILITY COMPONENT PLANS (SCP) |
| CENTER DESIGN GUIDE |
| CENTER DEVELOPM ENT PLAN (CDP) |
| CENTER MASTER PLAN DIGEST |
| CENTER MASTER PLAN WEBSITE |
| CENTER AREA DEVELOPM ENT EXECUTION PLANS (ADEP) |
| Attachment 2/Technical Exhibit 2 – List of NASA Centers |
File details come from the government source that posted it. Updated .