ANHYDROUS AMMONIA CYLINDERS NEED TO BE SENT OUT FOR RECERTIFICATION AND REFILL
Solicitation number
80NSSC27949336Q
Issued by

About this file

This is a Statement of Work for the recertification of CMASS ammonia cylinders for the Artemis III+ program. The work involves five cylinders (OEM Part #79K40456, serial numbers: 692720, 692739, AF313682, AF313767, CX54986PS) that must be recertified and returned to Kennedy Space Center by December 28, 2026.

The scope of work includes removing surface corrosion per MPCV 70156 specifications, performing paint touch-up with Aqua-Shield or complete repainting if required following SSPC and NASA-STD-5008 standards with inorganic zinc coating at 4-6 mil dry film thickness, conducting a 5-year inspection and requalification per 49 CFR 180.209 and 180.215 and CGA Pamphlet C-6 or C-6.3, marking cylinders with requalification dates and hazard stickers, refilling with anhydrous ammonia meeting MPCV 70156 Table 3.5-4 requirements, and returning the cylinders to KSC. For any cylinders that fail recertification, the contractor must remove the dual valve assembly and dip tube and dispose of the cylinder. The place of performance is Boggs Gases. Required submittals include all quality documentation and personnel certifications, an inspection report in prescribed form documenting retest and inspection results, and a quote referencing the SOW, delivery timeframe, estimated period of performance, and pricing. The applicable specifications are MPCV 70156, 49 CFR 180.209, 49 CFR 180.215, and DOT Specification 4AA480.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

1. Objective/Requirements

Recertify CMASS Ammonia cylinders for Artemis III+

DESCRIPTION OF WORK

For each of the ammonia cylinders being sent out, perform the following:

1. Remove surface corrosion per MPCV 70156 TABLE C 1.0-1

2. Touch up areas of paint, as required, with Aqua-Shield and match the current color of the cylinders as a best effort basis. Area of touch up should be prepared and coating applied per manufacturer instructions.

2.1. If a full repaint of the cylinders are required: Prepare surface for corrosion control, and painting touch up paint per manufacturer’s instructions if that is not possible then, Prepare and paint carbon steel as follows: Degrease per SSPC-SP 1, mechanically clean per SSPC-SP 2 or SSPC-SP 3 and abrasive blast per SSPC-SP 10 to an anchor profile of 1.5-3.0 mils. All rust shall be completely removed from pits and depressions. Remove abrasive residue. Clean and dry the surfaces. apply a brush coating or stripe coating with an inorganic zinc coating on all cutouts and sharp edges. Apply a 4-6 mil dry film thickness inorganic zinc (IOZ) coating (conforming to paragraph 4.1.2.1 of NASA-STD-5008) from the approved products list of NASA-STD-5008 appendix a. The application of the coating to the thickness required shall comply with the manufacturer’s recommendations. NACE inspection is required for all surface preparations and coating applications per section 5.2 of NASA-STD-5008.

Paint cylinder surface to match best effort color match

3. Perform required 5-year inspection and requalification per 49 CFR 180.209, 49 CFR 180.215, and per CGA Pamphlet C-6 or C-6.3

4. Mark cylinders with Inspection requalification date, apply hazardous material sticker

5. Provide certificate of inspection, including RIN, provide an inspection report in prescribed form of the results of the cylinder retest and/or inspection.

6. Refill with anhydrous ammonia that meets the requirements of MPCV 70156 Table 3.5-4 “Ammonia” Procurement column.

7. Return cylinders to KSC.

For any cylinder that fails recertification perform the following:

1. Remove dual valve assembly with attached dip tube, neck rings and caps from cylinders and return to KSC.

2. Dispose of ammonia cylinder.

SUBMITTAL REQUIREMENTS

Work Schedule

Work must be complete in time to support Artemis III Orion processing.

Technical

The Subcontractor shall submit all quality documentation and certifications for personnel supporting the machining/fabrication tasks and for any material purchased and provided for the component(s).

Data Deliverables

The Subcontractor shall provide a quote referencing the SOW, delivery timeframe, estimated POP, and pricing.

Documentation

The subcontractor shall provide an inspection report in prescribed form of the results of the cylinder retest and/or inspection.

2. Characteristics, Scope, and Specs

Quantity OEM Part # Product Description

5 79K40456

Serial Numbers:

692720, 692739, AF313682, AF313767, CX54986PS

Applicable specification:

MPCV 70156, 49 CFR 180.209, 49 CFR 180.215

DOT Specification:

4AA480

3. Place of Performance Boggs Gases

4. Period of Performance Need returned and in service by 12/28/2026