This is a Statement of Work (SOW) for the replacement of a hydraulic accumulator bank at NASA's Glenn Research Center Lewis Field facility.
The National Aeronautics and Space Administration (NASA) Glenn Research Center, located at Lewis Field in Cleveland, Ohio, requires creation, assembly, and delivery of a new replacement hydraulic GN2 (nitrogen) accumulator bank with panel. The accumulator bank serves as a backup means of pressurized medium to control critical facility valves in the event of hydraulic pump failure during testing operations at the propulsion systems laboratory. The contractor must use specified components detailed in the PSL Accumulator Panel Schematic and Parts List (attached reference document) and maintain contractor-branded components critical for compatibility with existing facility fitting standards. The period of performance requires completion within 16 weeks from procurement placement, with an estimated delivery target of February 2027 to allow adequate installation time between testing programs. The primary deliverable is the assembled accumulator bank with associated parts list and drawing. Warranty requirements include first-party warranty support from the vendor and general workmanship warranty coverage for the delivered hardware.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
FOR
Lewis Field Building 125 Outside Hydraulic Accumulator Bank Replacement, Version 1.0
NATIONAL AERONAUTICS AND SPACE ADMINISTRATION
GLENN RESEARCH CENTER
LEWIS FIELD NEIL A. ARMSTRONG TEST FACILITY
21000 BROOKPARK ROAD 3597 SCHEID ROAD
CLEVELAND, OHIO 44135 SANDUSKY, OHIO 44870
DATE: 10/21/2026
Lewis Field Building 125 Outside Hydraulic Accumulator Bank Replacement Version 1.0
Background In the event of a hydraulic pump failure during testing operations at the propulsion systems laboratory, nitrogen accumulator banks enable a backup means of pressurized median to control critical facility valves.
Reference Documents (e.g. drawings, NASA procedures, computer files, etc.)
PSL Accumulator Panel Schematic + Parts List [Attached]
Scope of Work Description
Creation, assembly, and delivery of a new replacement hydraulic GN2 accumulator bank with panel using specified contractor components in drawing. Contractor branded components deemed critical to maintain compatibility with existing and established fitting standard across facility.
Period-of-Performance: (list start & end dates; include any critical factors driving these dates)
Completion of creation, assembly and delivery of accumulator bank and panel within 16 weeks placement of procurement. Critical to receive hardware near this window to ensure adequate time to install in between testing programs.
ETA ~February 2027
Deliverables Accumulator bank with associated parts list and drawing.
Warranty [identify any desired warranty terms and conditions (e.g. hardware, workmanship, etc.)] First Party Warranty Support from Vendor General Workmanship Warranty
Lewis Field Building 125 Outside Hydraulic Accumulator Bank Replacement Version 1.0