SOW.pdf
PDF 268 KB Posted
- Attached to
- 2 RISER GASKETS.
- Solicitation number
- 80NSSC27948140Q
About this file
This is a Statement of Work (SOW) for the procurement of critical spare parts for the IOPSS Rainbird Gaskets supporting Artemis 3 processing and launch operations at Kennedy Space Center. The requirement specifies two riser gasket items: three units of part number KT09367-001 (RISER GASKET, 56-3/16 IN DIAMETER) and two units of part number KT09367-002 (RISER GASKET, 60-3/16 IN DIAMETER). These spares are designated as mission-critical due to shelf-life degradation of currently installed gaskets; their unavailability would halt all vehicle processing activities on the launch pad.
Performance is to occur at Launch PAD B at Kennedy Space Center with a required delivery date of February 1, 2027. The SOW emphasizes the operational criticality of these items, noting that any failure to provide them on schedule would result in a complete halt to mission processing capabilities.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
1. Objective/Requirements These items are required to support critical spares for the IOPSS Rainbird Gaskets that are needed for Artemis 3 processing and support. Without these spares, if at any point these were to break and currently the old ones installed are running out of shelf life, all processes with the missions will be at a halt and no vehicle processing can be done on the launch PAD. They are mission critical spares.
2. Characteristics, Scope, and Specs
Quantity OEM Part # Product Description
3 KT09367-001 RISER GASKET, 56-3/16 IN DIAMETER
2 KT09367-002 RISER GASKET, 60-3/16 IN DIAMETER
3. Place of Performance Launch PAD B at Kennedy Space Center
4. Period of Performance Need Date (2/1/2027)
File details come from the government source that posted it. Updated .