This Statement of Work (SOW) details the disassembly and relocation of a helium reliquefier system from the National Institute of Standards and Technology (NIST) Gaithersburg EBIT lab. The contractor is required to disconnect, disassemble, and package all equipment associated with the helium reliquefier located at the NIST Gaithersburg site, with the ultimate destination being the Goddard Space Flight Center (GSFC). The work is to be performed at NIST, 100 Bureau Drive Stop 1640, Building 301 Room B129 in Gaithersburg, MD, with a tight timeline of beginning on-site work within 5 weeks after order receipt and completing all tasks within 5 days of starting the work.

View the file

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

1. Objective/Requirements Disassemble helium reliquefier system at NIST Gaithersburg EBIT lab and prepare for shipment to GSFC.

2. Characteristics, Scope, and Specs The contractor shall perform the following duties:

disconnect, disassemble, and package all equipment associated with NIST EBIT helium reliquefier at NIST Gaithersburg site.

3. Place of Performance

NATIONAL INSTITUTE OF STANDARDS AND TECHNOLOGY

100 BUREAU DRIVE STOP 1640, BUILDING 301 ROOM B129

GAITHERSBURG, MD 20899

4. Period of Performance Technician will begin work on site within 5 weeks after receipt of order. Work will be completed within 5 days after start of work.