SATPC0036864 Tab 04 4 SOW_Redacted.pdf

PDF 36 KB Posted

Attached to
Suit simulators and test support related to the use of the suit simulators
Solicitation number
80NSSC25886192Q
Issued by

About this file

This document is a Statement of Work (SOW) for a federal contract opportunity to provide suit simulators and test support related to the use of the suit simulators. The contractor is required to provide two space suit simulators with size adjustability and half visors, as well as support teams for suit simulator sizing, emergency drills, and three test scenarios involving donning/doffing, suit tech support, and test readiness review preparation and participation. The performance period is from December 2, 2024, through December 6, 2024, and the place of performance is the Johnson Space Center. The contractor must also provide certification to NASA Safety that the technicians are qualified to perform various test-related duties. The related federal contract opportunity is a Special Notice with Solicitation Number 80NSSC25886192Q, issued by the National Aeronautics and Space Administration Shared Services Center.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

STATEMENT OF WORK

1. Objective/Requirements

This support provides the Pressurized Rover (PR) Project with suit simulators and test support related to the use of the suit simulators. This includes providing support for 1 Fit and Familiarization session and 3 tests with the simultaneous use of 2 suit simulators for the purpose of demonstrating volumetric impacts between the suit and the vehicle while handling cargo. This support is required for PR System

Requirement Review (SRR) part 2.

2. Characteristics, Scope, and Specs

The contractor shall perform the following duties:

• Two (2) space suit simulators with size adjustability and half visors.

• Support team for Suit Simulator Sizing session.

• Support team for Suit Simulator Emergency Drill.

• Support team for the duration of each of the three (3) scenarios:

o Don/Doff of the suits.

o Suit Tech support while testing takes place.

• Support the preparations for and participate at the Test Readiness Review.

• Provide certification to NASA Safety that the technicians in the field are certified to preform:

o Test Subject Fittings.

o Test Subject Donning and Doffing.

o Test Support (spotters as the subjects navigate mockups, emergency egress).

• Preform all shipping and handling of the suit simulators and related equipment.

3. Place of Performance

Johnson Space Center,

4. Period of Performance

Testing shall be performed December 2, 2024, through December 6, 2024.