SATPC0033778 TAB 04 4 SOW R.pdf
PDF 228 KB Posted
- Attached to
- Additively Manufactured Oscillating Heat Pipes
- Solicitation number
- 80NSSC24856703Q
About this file
This statement of work outlines requirements for the fabrication of oscillating heat pipes for a National Aeronautics and Space Administration project. The contractor shall fabricate parts from Inconel 625 additive manufacturing material to the specifications provided in the drawings, delivering quantities of each part number listed by January 2024. The technical requirements specify the contractor's experience and certifications as well as fabrication standards for density, build method, stress relief, and removal from the build plate. Induction heating equipment will be provided by the government for quality checks. The period of performance is from December 2023 through final deliveries in January 2024.
View the file
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Fabrication of Oscillating Heat Pipes for Leading Edge Thermal Protection System (TPS) Materials
November 2023
National Aeronautics and Space Administration Ames Research Center Moffett Field, California
OHP Fabrication | OHPACA Project Version: Rev 1
Table of Contents
1.0 Background
2.0 Purpose and Scope
3.0 Project Structure
4.0 Contract Line Item Numbers
5.0 Applicable Documents
6.0 Task Description
7.0 Schedule
8.0 Government Furnished Equipment, Property, or Information
9.0 Travel
10.0 Period of Performance
11.0 Point of Contact (P.O.C) Information
1.0 Background
Requirements of next generation commercial Low Earth Orbit (LEO) and Department of Defense
DOD hypersonic vehicles, dictate the need for robust thermal management solutions. Recent advancements in refractory additive manufacturing technology make available novel integrated thermal management systems capable of operating at extreme temperatures. One such system, Oscillating Heat Pipes (OHP’s), are a potentially disruptive technology to a wide range of NASA applications. NASA Ames Research was recently selected to advance OHP’s for commercial leading-edge applications in partnership with Lockheed Martin through an Announcement of
Collaboration Opportunity (ACO). This project is called the Oscillating Heat Pipe for Aero-entry and Commercial Applications (OHPACA).
2.0 Purpose and Scope
The purpose of this Statement of Work (SOW) is to fabricate parts in support of OHPACA project.
3.0 Project Structure
The contractor shall provide all labor, materials, facilities, service, equipment, analysis and management necessary to fabricate hardware defined in section 4.0.
4.0 Contract Line-Item Numbers
The effort described by this SOW shall be completed when all subcontract Contract Line Item Numbers (CLINS), defined in Table 1, are complete. As shown in the drawings, there are also some post-AM details that we require – reaming/drilling/machining of the heater and fill tube holes.
Table 1: Contract Line-Item Numbers (CLINS)
Line Item #
Part Part # Qty.
Delivery
Date
1 ACB-L-2310-M100_ 101 REV_4 Inconel 625 6 Jan-2024
2 ACB-L-2310-M100-102 REV_4 Inconel 625 3 Jan-2024
3 ACB-L-2310-M100-103 REV_4 Inconel 625 1 Jan-2024
4 ACB-L-2310-M100-104 REV_4 Inconel 625 2 Jan-2024
5 ACB-L-2310-M100-105 REV_4 Inconel 625 1 Jan-2024
6 ACB-L-2310-M100-106 REV_4 Inconel 625 1 Jan-2024
7 ACB-L-2310-M100-107 REV_4 Inconel 625 1 Jan-2024
5.0 Applicable Documents
The documents for this IAA include the following listed below:
• Determination & Findings (D&F)
• Statement of Work (SOW)
• JA22 Ames Routing Slip
• NF 1707 Form
• Independent Government Cost Estimate (IGCE)
• Quote from vendors
• 7600A & 7600B
• NIPR Form
• Detailed design drawings ACB-L-2310-M100_REV_4
• Sole Source Justification
6.0 Description of Tasks and Technical Requirements
6.1 Description of Tasks
Vendor is to fabricate quantity of parts per drawings specified in Table 1. As shown in the drawings, there are also some post-AM details required. Specifically, reaming/drilling/machining of the heater and fill tube holes. It should also be noted that drawings are agnostic to build orientation. Necessary scaffolding, supports, or roof structures to channels can be added pending approval of the technical POC on the NASA side. Finalized drawings with modifications will be worked with vendor upon contract award.
6.2 Technical Requirements
Technical requirements are documented below:
• Vendor shall have previous experience with additively manufactured Inconel 625 heat pipe casings that have been demonstrated to be capable of being hermetically sealed.
• Vendor shall have previous experience removing powder from very high aspect ratio channels
• Vendor shall be certified to ISO 9001:2008, or better.
• Vendor shall fabricate parts above 99% density.
• Vendor shall fabricate parts in a single build
• Vendor shall stress relieve parts
• Vendor shall remove parts from the build plate after stress relief using EDM
• Vendor shall minimize restarts during the additive manufacturing process.
7.0 Schedule
Table 2. Schedule for Deliverables Activity Start Date Responsible
Fabrication and delivery of Parts in Table 1 December 2023 Subcontractor
8.0 Government-Furnished Property, Material, Equipment, or Information (GFP/M/E/I)
• Induction heater(s) or a suitable gauge pin for checking the machined features are GFE and can be delivered to the contractor at the start of the contract through Mcmaster- Carr.
9.0 Travel
No travel costs anticipated.
10.0 Period of Performance
The period of performance for this effort shall be from December 2023, to January, 2024.
• Address: Building 234 Room 117, NASA Ames Research Center, Moffett Field, CA 94035-
NASA Ames Contract Specialist:
• NASA Ames Contract Specialist:
• Email:
• Address:
File details come from the government source that posted it. Updated .