RFI Responses 9-11-25.pdf

PDF 91 KB Posted

Attached to
Marshall Exploration Facility (MEF) Federal contract opportunity
Solicitation number
80MSFC25R0015
Issued by
National Aeronautics and Space Administration Marshall Space Flight Center

About this file

This document is a Request for Information (RFI) attachment for RFQ 80MSFC25R0015, specifically addressing a NASA Phase I Design-Build Request for Qualifications. The RFI contains a question and response regarding the submission requirements for Amendment 0006, focusing on Factor 1 – Past Performance on Relevant Projects. The key clarification is that if an offeror does not change their previously submitted project(s), they do not need to have past customers resubmit the same Past Performance Questionnaires (PPQs) that were originally submitted for the phase I proposal due in April 2025. The government confirms that resubmittal is not necessary if the initial submittal complies with the Factor 1 Submission Requirements.

View the file

Other files for this federal contract opportunity

Other files attached to Marshall Exploration Facility (MEF), newest first.
File Type Posted
MEF RFQ 80MSFC25R0015 Amend 6.pdf PDF
RFI Responses 6-25.pdf PDF
Attachment 9 Project Labor Agreements.pdf PDF
MEF RFQ 80MSFC25R0015.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

RFQ 80MSFC25R0015

Attachment 5 Request for Information (RFI)

Submission of Questions

Item

Solicitation or Attachment Reference Question Government Response

1 NASA Phase I Design-Build Request for Qualifications

Paragraph II.E.1. Factor 1 – Past Performance on Relevant Projects

Regarding submission requirements for Amendment 0006, if an offeror does not change our submitted project(s) under Factor 1 – Past Performance on Relevant Projects, please confirm we do not need to have our past customers resubmit the same PPQs they already submitted for the original phase I proposal that was due in April 2025.

Resubmittal is not necessary if the initial submittal complies with the Factor 1 Submission Requirements.

File details come from the government source that posted it. Updated .