This Statement of Work (SOW) describes contract requirements for operating and maintaining the HyperNav hyperspectral radiometric system to support system vicarious calibration (SVC) of the NASA Plankton, Aerosol, Cloud, Ocean Ecosystem (PACE) Ocean Color Instrument (OCI). The Contractor shall conduct eight HyperNav system deployments per year across three geographical sites—three deployments in Hawaii, three in Mo'orea, and two in Puerto Rico—with each deployment lasting approximately 60 days. The Contractor must maintain eight HyperNav radiometric systems and associated float platforms in rotational deployment, with at least one float operational at any given time and no more than two deployed simultaneously. Deployments shall be scheduled to optimize clear-sky conditions. The Contractor must deliver a minimum of 160 quality-assured in-situ SVC observations over the period of performance and conduct a minimum of nine sensor calibrations per year, with pre-deployment and post-deployment laboratory calibrations documented to meet NASA's resolution, accuracy, and uncertainty requirements.

The contract uses a firm-fixed-price milestone payment structure with compensation distributed across monthly operations and data delivery (30% total), Hawaii deployments (12% total), Mo'orea deployments (15% total), Puerto Rico deployments (8% total), sensor calibrations (18% total), annual program reviews and travel (7% total), and annual reporting and open science compliance (10% total). The Contractor must operate and refine HyperNav data processing streams to generate SVC-qualified radiometric products, deliver data daily to the NASA PACE team at the Ocean Ecology Lab, conduct OCI-HyperNav matchup analyses, coordinate with NASA for data quality review, and document calibration processes and quality control procedures. All source code must be made publicly available through version-controlled repositories under open-source licenses with stable releases archived in repositories providing persistent DOIs. The place of performance is the Contractor's facility and the HyperNav deployment sites, with scheduled travel to Washington DC, Hawaii, Mo'orea, and Puerto Rico for deployments and conferences.

View the file

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

System Vicarious Calibration (SVC) of the NASA Plankton, Aerosol, Cloud, Ocean Ecosystem) PACE Observatory Using

HyperNav

Statement of Work (SOW)

1. Scope of Work This contract provides for operation and maintenance of the HyperNav hyperspectral radiometric system to support system vicarious calibration (SVC) of the NASA Plankton, Aerosol, Cloud, ocean Ecosystem (PACE) Ocean Color Instrument (OCI).

2. Background The HyperNav system was developed under NASA contract 80GSFC22CA050 (ROSES 2019, entitled A.48 The Plankton, Aerosol, Cloud, Ocean Ecosystem (PACE) Mission System Vicarious Calibration). The purpose of the contract was to develop, implement, and deploy in situ SVC capabilities for the Ocean Color Instrument, the primary instrument on the PACE mission. System vicarious calibration combines satellite sensor data with in situ radiometric measurements to determine on-orbit calibration factors, requiring high-accuracy, hyperspectral-resolution measurements with bounded uncertainty.

HyperNav was successfully deployed in 2022 and collected pre-launch SVC measurements. The system has been deployed at four (4) different sites – Hawaii, Mo’orea, Crete, and Puerto Rico – using eight (8) HyperNav radiometric systems and eight (8) floats. These rotational deployments are approximately 60 days in duration.

Over the past year, HyperNav completed twenty (20) deployments, collecting over seven hundred fifty (750) radiometric profiles. This data is currently being used by the PACE team to determine the gain coefficients for the PACE OCI sensor.

3. Objective The objective of this contract is to sustain HyperNav operations and the collection of SVC-quality data in support of the validation of the PACE mission measurements and calibration of PACE OCI sensor products.

4. Technical Requirements The work to be performed under this SOW includes:

4.1 HyperNav System Deployments. The Contractor shall conduct eight (8) HyperNav system deployments per year across three (3) geographical sites over the period of performance. Deployments shall be distributed as follows: three (3) deployments at the Hawaii site, three (3) deployments at the Mo'orea site, and two (2) deployments at the Puerto Rico site. Each deployment shall have a nominal duration of sixty (60) days. The Contractor shall maintain eight (8) HyperNav radiometric systems and associated float platforms to support rotational deployment operations.

Deployments shall be scheduled to optimize clear-sky conditions and maintain at least one float operational at any given time, with no more than two floats deployed simultaneously.

4.2 Data Processing and Delivery. The Contractor shall operate, maintain, and refine HyperNav data processing streams to generate SVC-qualified radiometric products. The Contractor shall deliver the data to the NASA PACE team at the Ocean Ecology Lab (OEL). The Contractor shall deliver a minimum of one hundred sixty

(160) quality-assured in-situ SVC observations for HyperNav over the period of performance.

4.3 Data Analysis and Coordination. The Contractor shall analyze HyperNav data for SVC quality, conduct OCI-HyperNav matchup analyses, and evaluate hyperspectral consistency, radiometric stability, and sensitivity to atmospheric and surface conditions. The Contractor shall coordinate with NASA OEL to review data quality, discuss anomalous profiles, refine matchup selection criteria, and support interpretation of SVC gain estimates. The Contractor shall implement agreed-upon refinements to the processing stream as directed by NASA.

4.4 Sensor Calibration and Maintenance. The Contractor shall perform pre-deployment and post-deployment laboratory calibrations of all HyperNav radiometric systems to ensure measurement accuracy and traceability. The Contractor shall conduct a minimum of nine (9) calibrations of sensors per year to ensure optimal data quality. Calibration procedures shall be documented and shall meet the resolution, accuracy, and uncertainty requirements for PACE OCI system vicarious calibration as specified in the technical literature and as accepted by NASA OEL. The Contractor shall maintain all HyperNav systems, float platforms, and associated equipment in operational condition throughout the period of performance.

4.5 Documentation and Reporting. The Contractor shall document the HyperNav calibration and characterization processes, data processing stream and updates, quality control procedures, and global/site specific matchup analyses. Documentation shall clearly describe processing methods, quality control decisions, and algorithmic updates affecting delivered products. The Contractor shall disseminate results through agency reports and peer-reviewed publications and presentations at professional conferences. The Contractor shall make all source code publicly available through version-controlled repositories (e.g., GitHub) under open-source licenses, with stable releases archived in repositories providing persistent DOIs (e.g., Zenodo). The Contractor shall comply with NASA's Open Science and Data Management Plan requirements.

Table 2: Scheduled Travel

Name of Travel/Event # of Travelers Destination # of Days/Nights

Frequency

NASA PACE meeting 1 Washington, DC (or determined location)

3/2 1x year

HyperNav deployment - Hawaii

1 Hawaii 3/2 3x year

HyperNav deployment – Mo’orea

2 Mo’orea 7/6 2x year

HyperNav deployment – Puerto Rico

1 Puerto Rico 5/4 1x year

Ocean Optics or alike conference

2 TBD 5/4 1x year

7. Place of Performance

The place of performance shall be the Contractor’s facility and at the HyperNav deployment sites.

8. Information Technology, Security, and Records Management Requirements

8.1 IT Purchase Authorization

a. The Contractor shall ensure all IT products and services direct charged to the contract are approved through the OCIO's Commercial IT Request (CITR) Application. This includes, but is not limited to, FITARA, Supply Chain Risk Management (SCRM), IPv6, and 508 compliance. No purchases of commercial IT products or services shall be made prior to coordination and approval by the OCIO. The Contractor shall report purchases monthly utilizing DRD IT-02, Commercial IT Authorization Report (CITAR).

b. This contract shall only be used to purchase software, software maintenance, hardware, or hardware maintenance necessary for the performance of this contract. NASA shall own the license(s) or subscriptions for any software or applications purchased. All hardware shall be titled to NASA.

8.2 Section 508 Conformance

The contractor shall ensure that all products, platforms, services, and communications delivered as part of this work statement that are Information and Communication Technology (ICT) or contain ICT, conform to the Revised Section 508 of the Rehabilitation Act Standards, 36 C.F.R. § 1194.1 & Apps. A, C & D. The Standards may be found at https://www.access-board.gov/ict/.

8.3 Records Management

a. The Contractor shall maintain all records created for Government use or created in the course of performing the contract and/or delivered to, or under the legal control of the Government and must be managed in accordance with Federal law, including but not limited to, the Federal Records Act (44 U.S.C.

chs. 21, 29, 31, 33), NARA regulations at 36 CFR Chapter XII Subchapter B, as well as NASA records policies (NPD 1440.6, NASA Records Management Program, and NPR 1441.1, NASA Records Management Program Requirements).

b. The Contractor shall ensure that NASA-owned/Contractor-held records are segregated from contractor-owned records and from non-record materials and report holdings of NASA records.

c. The Contractor shall immediately notify the Contracting Officer and NASA Records Officer upon discovery of any inadvertent or unauthorized removal, defacing, alteration, or destruction of Federal records. Destruction of Federal Records is EXPRESSLY PROHIBITED unless in accordance with records retention schedules or as directed by the Contracting Officer.

d. All Contractor employees assigned to this contract who create, work with, or otherwise handle Federal Records are required to complete mandatory NASA-provided records management training. The Contractor shall ensure that training has been completed according to agency policies, including initial training and any required annual or refresher training.

e. The Contractor shall incorporate the substance of this clause, its terms and requirements including this paragraph, in all subcontracts under this contract, and require written subcontractor acknowledgment of same.

9. Milestone Payment Schedule

9.1 Payment Structure

Payment under this Firm-Fixed-Price contract shall be made upon completion and Government acceptance of the milestones specified in Table 3.

Table 3: Milestone Payment Schedule

Milestone

ID

Milestone Description

Success Criteria (Trigger for Payment)

SOW

Ref.

Frequency / Timeline

Payment Amount (% of Total FFP)

M-1.01 to M-1.12

Monthly Operations & Data Delivery

Routine maintenance, data processing streams, matchup analyses, and daily delivery of SVC data to the PACE OEL.

Verification by NASA OEL of continuous daily data stream delivery and monthly matchup analyses for the preceding month.

4.2, 4.3, Monthly (12 payments per year)

30% total (2.5% per month)

D-2.01 to D-2.03

Hawaii Deployments

Execution of 60-day rotational deployments in Hawaii.

Successful deployment of the float, establishment of data stream, and completion of the 60-day deployment cycle.

4.1 3x per year 12% total (4% per deployment)

D-3.01 to D-3.03

Mo'orea Deployments

Execution of 60-day rotational deployments in Mo'orea.

Successful deployment of the float, establishment of data stream, and completion of the 60-day deployment cycle.

4.1 3x per year 15% total (5% per deployment)

D-4.01 to D-4.02

Puerto Rico Deployments

Execution of 60-day rotational deployments in Puerto Rico.

Successful deployment of the float, establishment of data stream, and completion of the 60-day deployment cycle.

4.1 2x per year 8% total (4% per deployment)

C-5.01 to C-5.09

Sensor Calibrations

Pre-deployment and post-deployment

Submission and NASA acceptance of calibration documentation

4.4 9x per year 18% total (2% per calibration)

Milestone

ID

Milestone Description

Success Criteria (Trigger for Payment)

SOW

Ref.

Frequency / Timeline

Payment Amount (% of Total FFP) laboratory calibrations of radiometric systems.

detailing resolution, accuracy, and uncertainty limits.

R-6.01 Annual Program Reviews & Travel

Participation in the

NASA PACE

meeting and Ocean Optics (or similar) conference.

Completion of travel/attendance and submission of any associated meeting presentation materials or summaries.

6 Annually (Usually Q3 or Q4)

7% total

R-7.01 Annual Reporting & Open Science Compliance

Delivery of the annual progress report and publication of source code.

NASA acceptance of the Annual Progress Report sent to the agency directly, and submission of data from the HyperNav system into the designated repository (e.g., OB.DAAC).

4.5, 5 Annually (Month 12)

10% total

TOTAL

100%

9.2 Milestone Acceptance Process

(a) Submission of Invoice. The Contractor shall submit an invoice for each milestone upon completion of the work and satisfaction of the acceptance criteria specified in Table 3.

(b) Government Review Period. The Government shall have thirty (30) calendar days from receipt of the Contractor's invoice and supporting documentation to review the milestone completion and either:

• Accept the milestone and authorize payment; or

• Reject the milestone with written explanation of deficiencies.

(c) Deficiency Correction. If a milestone is rejected, the Contractor shall correct the deficiencies and resubmit within fifteen (15) calendar days. The Government shall have an additional fifteen (15) calendar days to review the resubmission.

(d) Supporting Documentation. Each invoice shall include sufficient documentation to demonstrate completion of the acceptance criteria, including but not limited to:

• Deployment reports with dates, locations, and status report of data transmission.

• Calibration dates and specifications of results.

• Meeting attendance and summary of presentation materials.

• Any other relevant information regarding Monthly Operations & Data Delivery.

9.4 Cumulative Data Requirements

Notwithstanding the monthly payment structure, the Contractor remains obligated to deliver a minimum of one hundred sixty (160) quality-assured in-situ SVC observations over the period of performance as specified in Section 4.2. Failure to meet this cumulative requirement may result in withholding of final milestone payment R-02 until the deficiency is corrected.

9.5 Payment Terms

Payment shall be made in accordance with the Prompt Payment Act. The Government shall make payment within thirty (30) days after:

• Receipt of a proper invoice; and

• Acceptance of the milestone deliverable(s).

9.6 Force Majeure

(a) Definition. For purposes of this contract, "Force Majeure" means an event or condition beyond the reasonable control of the Contractor that prevents or delays performance of contractual obligations, including but not limited to: acts of God, fires, floods, epidemics, pandemics, quarantine restrictions, strikes, freight embargoes, unusually severe weather including storms, acts of war or terrorism, civil disturbances, or acts of government in its sovereign capacity.

(b) Notice Requirement. If the Contractor is prevented from performing any obligation under this contract by Force Majeure, the Contractor shall:

• Notify the Contracting Officer in writing within five (5) business days of the occurrence or anticipated occurrence of the Force Majeure event;

• Describe the nature of the Force Majeure event and its expected duration;

• Explain the specific contractual obligations affected; and

• Propose mitigation measures or alternative performance methods.

(c) Effect on Performance. Upon receipt and verification of a Force Majeure notice, the Contracting Officer may, at the Government's sole discretion:

• Extend the time for performance of affected milestones without penalty;

• Modify the contract to accommodate alternative performance methods; or

• Terminate the contract for the convenience of the Government in accordance with

FAR 52.249-2.

(d) Limitations. Force Majeure shall not excuse the Contractor from performance if:

• The event was caused by the Contractor's negligence or willful misconduct;

• The event was reasonably foreseeable and the Contractor failed to take reasonable precautions;

• The Contractor fails to use reasonable efforts to mitigate the effects of the Force

Majeure event; or

• The event affects only the Contractor's economic circumstances (e.g., increased costs, market conditions, supplier pricing).

(e) No Additional Compensation. The Contractor shall not be entitled to additional compensation or price adjustment solely due to a Force Majeure event. Any contract modification shall be limited to schedule adjustments or scope modifications as determined appropriate by the Contracting Officer.