This document is a Request for Information (RFI) from the National Aeronautics and Space Administration (NASA) Glenn Research Center regarding the Commercial Development of Lunar Exploration Ground Sites (LEGS) Communications Ground Systems.

The RFI seeks responses with rough order of magnitude (ROM) budget and schedule estimates for establishing three LEGS communications ground stations, with one site located at White Sands, New Mexico, one site in South Africa, and a third site yet to be determined. NASA is providing the 20.2-meter antennas as government-furnished equipment (GFE) for the latter two sites, while the first site's antenna will be installed by the GFE provider. The RFI is focused on the baseband signal processing and delivery of the data to the mission operations center, which is in scope for respondents. NASA is open to inputs from companies, including international firms, and is seeking feedback on the feasibility of meeting the target operational readiness dates.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Request for Informa�on (RFI) Commercial Development of Lunar Explora�on Ground Sites (LEGS)

Communica�ons Ground Systems - Ques�on and Answers

Q: Is Western Australia fixed?

A: NASA is currently under-going site selec�on.

Q: Whose antennas are being GFE'd?

A: Any Government Furnished Equipment (GFE) will be the property of NASA.

Q: Is baseband signal processing in scope or out?

A: Baseband signal processing is in scope of this RFI.

Q: Who is the importer of record? Is it NASA or the contractor?

A: NASA is currently in the market research phase and no posi�on on the importer of record has been made for the poten�al future requirement.

Q: Is the base band equipment onsite?

A: No, the GFE antenna will deliver down converted IF via fiber, the rest of the system would poten�ally need to be delivered as part of the turn-key solu�on.

Q: At each site, the way the sites are connected would be the backbone. Are you providing a backbone network? Is this out of scope?

A: The data delivery to the Mission Opera�ons Center is not being provided by NASA for the purposes of this RFI, and thus it is in scope of this RFI.

Q: We are a Canadian company, will there be restric�ons?

A: NASA is currently in the market research phase; no eligibility restric�ons have been defined for the poten�al future requirement.

Q: What facili�es and infrastructure is included?

A: Each loca�on will have different requirements. See Appendix C.

Q: With the RFI are you looking for price quotes?

A: NASA is reques�ng ROM level budget and schedule es�mates as part of this RFI.

Q: Will the antennas be handled by NASA?

A: For the purpose of responding to the RFI, submiters should consider the antennas as GFE.

Q: Does the GFE include power and telecommunica�on infrastructure?

A: For the purpose of responding to the RFI, assume that the LEGS ground sta�ons will all be located within exis�ng facili�es that have basic infrastructure (roads, u�li�es, perimeter fence etc.).

Q: Is this a procurement for all three sites or three different contracts?

A: This is a request for informa�on only. NASA is reques�ng ROM level budget and schedule es�mates for all three sites as part of this RFI. Respondees may offer input on any site(s) or all three sites.

Q: Will it be only one antenna?

A: There will be one antenna per site, 20.2m diameter.

Q: Would an opera�ons cost need to be provided?

A: Opera�ons and Maintenance (O&M) es�mates for sites 2 and 3 are being sought.

Q: We perceive that Australia is open for considera�on. Is reloca�ng WSC and SANSA site a possibility?

A: White Sands and the South African loca�on are defined.

Q: The word turn-key is used prominently throughout the RFI. What exactly are you looking for in regards to “turn-key”?

A: Delivery of an opera�onal ground sta�on that meets the requirements specified in the RFI.

Q: Will NASA look for this RFI to help select the third site?

A: No, site selec�on is already underway and not associated with this RFI.

Q: What is the diameter for the antenna?

A: 20.2m.

Q: Are the Opera�onal Readiness dates in the RFP firm dates or are these no�onal for the purposes of the RFI response?

A: Those are target dates; NASA is seeking feedback on the feasibility of those dates and any high-level schedule drivers that may impact the ability to meet those dates.

Q: LEGS 3 Loca�on: Will this loca�on be provided as part of RFP or is NASA looking for inputs / recommenda�ons? Can the Government provide a list of LEGS-3 site loca�ons under considera�on?

A: NASA will select and provide the site at a later date.

Q: For LEGS-1, is there another Company/Govt providing Opera�ons and Maintenance, or should that effort be included in response to this RFI?

A: Per the RFI, NASA is only seeking O&M es�mates for LEGS 2 and 3.

Q: Appendix C LEGS 1-3 Site Responsibility Matrix: When WSC and S are responsible for providing facili�es items (such as civil works, fencing, power, space, cooling, and communica�ons infrastructure) does that mean they are performing the FULL design (Civil, Electrical, Mechanical) and permi�ng process, the construc�on, and the tes�ng/inspec�ons and there is no Contractor involvement?

A: Yes, White Sands is more mature and has facili�es. In South Africa, SANSA will be taking a large role.

The Australian site will depend on what is chosen.

Q: Can the Government provide clarifica�on on Contractor responsibility for PDU, UPS, frequency conversion equipment at LEGS-3? As currently worded in Appendix C, there is ambiguity on what NASA will or will not provide for LEGS-3.

A: The output of the antenna will be the downconverter IF, all elements from there forward are in scope.

Q: Can you please explain what is being provided for the GFE antenna along with the roles of the GFE vendor(s) versus role of the contractor?

A: For the purpose of responding to the RFI, the LEGS1 site will be installed by the GFE provider. The antenna is GFE for LEGS2/3 and will need to be installed by the contractor to include Site Acceptance Tes�ng (SAT). The Antenna assembly for LEGS 2 and 3 would be on the contractor to assemble and install.

Q: Can the Government provide insight into an�cipated antenna diameter (including radome if included) with load bearing and structural support pad dimension requirements? Does the antenna include a radome?

A: The antenna is 20.2 m. There will be no radome.

Q: Are spares provided with the GFE for the GFE?

A: If spares are needed for the GFE, they will be provided as GFE.

Q: Would NASA be willing to grant an extension to the RFI due date un�l the end of July in considera�on for the 4th of July holiday?

A: NASA will begin reviewing responses at the closing date; late submitals may be reviewed by the Government.