8-General Notices, Notes and Information.pdf

PDF 2 MB Posted

Attached to
ITB - Hydro-Insensitive High Density Polyurethane Foam Materials and Related Items for Harris County Precinct 3
Solicitation number
25/0390
Issued by
Harris County, Texas

About this file

This is a General Notices and Specifications document from Harris County, Texas, for an Invitation to Bid (ITB) for Hydro-Insensitive High-Density Polyurethane Foam Materials and Related Items for Precinct 3 (UPIN 26103MF3YN01). Harris County is soliciting bids for a one-year term contract with the option to renew for up to four additional renewal periods, beginning approximately February 1, 2026. The scope of work involves supplying hydro-insensitive high-density polyurethane foam material for concrete slab raising and undersealing operations at various Harris County Precinct 3 job sites. Material may be delivered to job sites on an F.O.B. Job Site basis or picked up from the vendor's plant(s) on an F.O.B. Plant basis. The bid specification package, including pricing and delivery information, scope of work, construction notes, special provisions, and special specifications, is available at https://harriscountytx.bonfirehub.com/portal/. Estimated bid quantities are contingent and provided solely for bid evaluation purposes, with actual payment based on a Purchase Order issued according to the Precinct's available budget and actual accepted work completed at unit prices bid.

Payment for the hydro-insensitive high-density polyurethane material is calculated by the pound for material furnished and injected, with the quantity paid based on actual usage at the contract unit price. All other labor, tools, equipment, and incidentals, including elevation control devices, hole drilling, and traffic control devices, are considered incidental to the work and are not separately compensated. Contractors must have a minimum of three years of full-time experience using high-density polyurethane for raising and undersealing concrete slabs, demonstrated by completed job references. Harris County law requires that a minimum of 25 percent of the work be performed by the bidder, and the original contract price on firm fixed-price contracts may not be increased by more than 25 percent or decreased by 18 percent or more without contractor consent. The contractor is required to use Harris County's internet-based e-Builder construction program management software at no cost, with system login and training provided by the County. All contractors must supply a list of suppliers and subcontractors with addresses and phone numbers prior to work commencing, and a one-year guarantee period applies from the date of placement for all work performed.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FOR:

On Call - Polyurethane Foam Material for

Harris County Precinct 3 - 2025

UPIN - 26103MF3YN01

PREPARER’S CERTIFICATION FOR

Specifications, Special Specifications, Special

Provisions, Estimate and Specification Data

Special Note:

The following items developed per the published Construction

Drawings have been verified and included in the Purchasing

Department’s Bid Specification Package, which can be located at https://harriscountytx.bonfirehub.com/portal/: The items include:

• Pricing/Delivery Information

• Scope of Work

• Construction Notes

• Special Provision to Standard

• Specifications Special Specifications

• Supplement to General Requirements

• Contract Time https://harriscountytx.bonfirehub.com/portal/

SCOPE OF WORK

Harris County is soliciting bids for a one (1) year term contract, with the option to renew for up to four (4) renewals, for the supply of Hydro-Insensitive High-Density Polyurethane Foam

Material for Precinct 3. The vendor shall furnish and/or deliver the material to various Harris

County job sites within Precinct 3 (F.O.B. Job Site), or the material may be picked up from the vendor's plant(s) by Harris County vehicles (F.O.B. Plant).

Estimated bid quantities are contingent and provided solely for bid evaluation purposes. A

Purchase Order will be issued based on the Precinct’s available budget. The Contractor will be paid for actual, accepted work completed at the unit prices bid and will not be entitled to additional payment for any differences between estimated and actual quantities.

May 2019

GENERAL NOTICE TO CONTRACTORS

In accordance with House Bill 1059, a minimum of 25% of the work to be performed on this project shall be performed by the Bidder.

Special Notice: By law, the original price on firm fixed price contracts may not be increased by more than 25%. The original price may not be decreased by 18% or more without the consent of the contractor. Please monitor additions to your contract -additions in excess of 25% will not be paid under any circumstances.

On public works projects, all contractors shall supply a list of all suppliers and subcontractors with addresses and phone numbers, prior to work commencing.

At the time of the scheduled preconstruction meeting, the successful bidder shall supply to the County a list of representatives signed by an Officer of the Company who are authorized to sign official documents, i.e., Purchase Orders, Change Orders, Final Estimates, etc.

In determining who is a responsible bidder, Harris County may take into account the past performance of the bidder on Harris County projects. Commissioners Court adopted a written definition and criteria for determining the performance of a contractor which may be considered in determining the responsibility of a bidder.

Harris County is using an internet-based Construction Program Management Software, e-Builder to maintain consistent administrative and technical control for its projects throughout the County. The Contractor is required to use e-Builder on this project in accordance with procedures provided by the County.

At no cost to the Contractor, the County will provide system login account(s) and provide training for Contractor personnel. The Contractor must update e-Builder with any new or changed information within 24 hours of that information becoming known to Contractor. The Contractor must have access to a computer with internet access and a scanner to use eBuilder.

Harris County- Revised Precinct Boundaries

This map is a user generated static output from an Internet mapping site and is for reference only. Data layers that appear on this map may or may not be accurate, current, or otherwise reliable.

577,791

© Latitude Geographics Group Ltd.

18.2

THIS MAP IS NOT TO BE USED FOR NAVIGATION

Legend

1:

WGS_1984_Web_Mercator_Auxiliary_Sphere

Miles0 18.29.12 Notes Notes

Harris County Boundary Other Counties

Harris County

Commissioner Precincts 2021 Pct 1

Pct 2

Pct 3

Pct 4

World Street Map

NOTICE OF SPECIFICATIONS

For the construction of this project, the Contractor shall use the attached Special Provisions, Special Specifications, and Harris County Engineering Department (HCED) Specifications Book – Standard Specifications for the Construction of Road and Bridges by Harris County Engineering Department, effective date October 10, 2023. The current HCED specifications may be found at the HCED website: https://www.eng.hctx.net/ Portals/33/2023-Standard%20Specifications/HCED-EN0-SS-001-00-C_Standard% 20Specifications%2010.26.2023%20(Final).pdf?ver=GRDvtDMEWY-IlJTeDWV4Hw%3d% 3d

When applicable, the Contractor shall use the Harris County Flood Control District (HCFCD) 2005 Standard Specifications Book. The current HCFCD specifications may be found at the HCFCD website: https://www.hcfcd.org/Technical-Manuals/all-documents?folderId=8625& view=gridview&pageSize=10

When applicable, the Contractor shall also use the Texas Department of Transportation (TxDOT) 2024 Standard Specifications Book. The current TxDOT specifications may be found at the TxDOT website: https://www.txdot.gov/business/resources/txdot-specifications/2024-standard-specifications.html

When applicable, the Contractor shall also use the City of Houston (COH) Standard Specifications. The current COH specifications may be found at the COH website:

https://www.houstonpermittingcenter.org/office-city-engineer/design-and-construction-standards http://www.eng.hctx.net/Portals/33/Publications/professional-services/spec/2017/2017_HC_Stand_Spec.pdf http://www.eng.hctx.net/Portals/33/Publications/professional-services/spec/2017/2017_HC_Stand_Spec.pdf https://www.hcfcd.org/Technical-Manuals/all-documents?folderId=8625&%20view=gridview&pageSize=10 https://www.hcfcd.org/Technical-Manuals/all-documents?folderId=8625&%20view=gridview&pageSize=10 https://www.txdot.gov/business/resources/txdot-specifications.html https://www.txdot.gov/business/resources/txdot-specifications.html https://www.houstonpermittingcenter.org/office-city-engineer/design-and-construction-standards https://www.houstonpermittingcenter.org/office-city-engineer/design-and-construction-standards

SPECIAL SPECIFICATION

ITEM 8104

RAISING AND UNDERSEALING CONCRETE SLABS

( revised 1-23-2012 )

8104.1 Description. This item shall govern the raising and undersealing of concrete slabs.

8104.2 Material. The material used for raising concrete slabs shall be a hydro-insensitive high density polyurethane foam.

The hydro-insensitive high density polyurethane shall exhibit the following physical characteristics and properties:

A. Properties

Material Injected In-situ (after water injection)

Density, lbs/ft3 3.8

Tensile Strength, psi 88

Elongation, % 4.8

Compression Strength, psi (at yield point) 80

B. Applicable Documents

Type Test ASTM Designation Title Shear Strength C273 Test Method for Shear Properties of Sandwich Cores Materials Solvent Resistance D543 Standard Practices for Evaluating the Resistance of Plastics to Chemical Reagents

Coefficient of D696 Test Method for Coefficient Expansion of Linear Thermal Expansion of Plastics between –300C and 300C with a Vitreous Silica Dilatometer

Flexural Strength D790 Test Methods for Flexural

Properties of Unreinforced and

Item 8104 Page -2-

Reinforced Plastics and Electrical Insulating Materials

Compressive Strength D1621 Test Method for Compressive

Properties of Rigid Cellular Plastics

Density D1622 Test Method For Apparent Density of Rigid Cellular Plastics

Tensile Strength D1623 Test Method for Tensile and Tensile

Adhesion Properties of Rigid Cellular Plastics

Dimensional Stability D2126 Test Method for Response of Rigid

Cellular Plastic To Thermal and Humid Aging

Water Absorption D2842 Test Method of Water Absorption of Rigid

Cellular Plastics

Fungus Resistance G21 Standard Practice for Determining

Resistance of Synthetic Polymeric Materials to Fungi

8104.3 Equipment. A listing of lifting and undersealing equipment shall be submitted to the Engineer for review. The minimum list of equipment required shall be as listed below. The listing is a minimum and shall not preclude the use of additional equipment.

A. A pneumatic drill, capable of drilling 5/8-inch diameter holes.

B. A truck mounted pumping unit capable of injecting the high density polyurethane formulation between the concrete pavement and the subbase and capable of controlling the rate of rise of the pavement.

C. A laser leveling unit used to ensure that the concrete is raised to an even plane and to the required elevations.

8104.4 Contractor Experience. Contractor shall have three full years experience using high density polyurethane to raise and underseal concrete slabs as demonstrated by completed job references.

8104.5 Construction Methods.

Preparation. Prepare a profile of the street or road to determine where the concrete pavement needs to be raised.

Barricades. Before commencing work, the Contractor shall furnish, place and maintain adequate standard warning signs, lights and flagmen, if necessary, Page -3-in accordance with the "Manual for Uniform Traffic Control Devices". Where barricades are left on the site overnight, blinking lights shall be left on from sunset to sunrise. No separate payment shall be made for furnishing traffic control devices and flagmen. They shall be considered incidental to the work.

Drilling. The injection holes shall be drilled in the following manner. A series of 5/8" holes will be drilled at about six to eight foot intervals through the concrete. The exact location and spacing of the holes shall be determined by the Contractor. The drilling of the holes shall be considered incidental to this item.

Injecting. The hydro-insensitive high density polyurethane foam is then injected under the slab. As the hydro-insensitive high density polyurethane chemically reacts, it expands and hardens, exerting the necessary lifting forces. The amount of rise shall be controlled, using the pumping unit, by regulating the rate of injection of the hydro-insensitive high density polyurethane material. When the nozzle is removed from the hole, any excessive polyurethane material shall be removed from the area and the hole sealed with a non-expansive cementitous grout.

After the hydro-insensitive high density polyurethane material has set, the Engineer will test the surface of the pavement with a 10-foot straight edge placed parallel to the centerline. In no case shall the maximum ordinate from a 10-foot straight edge to the pavement be greater than 1/4-inch. A tight string line may be used to monitor and verify elevations for a slab length of 50 feet or less. For longer sections, a laser level will be used to monitor and verify elevations. Elevations can also be verified by flooding the area to confirm that the paving has been realigned properly.

The Contractor shall be responsible for any pavement blowouts, excessive lifting, and/or uneven pavement, that causes ponding, which is result of the raising of the pavement and shall repair or fix the damaged area to the satisfaction of the County Engineer, without additional cost to Harris County.

Set-time. The hydro-insensitive high density polyurethane foam used shall set and obtain 90% of its ultimate compressive strength within 15 minutes from injection.

Grade Control. Control the final elevations within ¼ in. of the proposed profile elevations. The Engineer may check the treated area to confirm that the pavement has been aligned properly to attain positive drainage.

8104.6 Guarantee. The Contractor agrees to replace, without additional cost to the

County, any Work found to be defective and to make good all damage or other Work caused by such improper placement. The guarantee period for the Work is one year from the date of placement.

8104.7 Measurement. The hydro-insensitive high density polyurethane material shall be paid for by the pound, which will include furnishing and injecting material.

Page -4-

8104.7 Payment. The quantity of material to be paid for shall be the quantity actually used, based on the contract unit price shown on the bid form.

Only Hydro-Insensitive High Density Polyurethane shall be paid for directly.

All other labor, tools, equipment and incidentals including furnishing and operating elevation control devices, drilling of holes; furnishing and installing traffic control devices necessary for the completion of the work shall not be paid for directly, but shall be considered incidental to this item.

The descriptions and units for this item are:

Hydro-Insensitive High Density Polyurethane (Raising/Undersealing Concrete Slabs) lbs

END OF ITEM 8104

Table of Contents
Scope of Work
General Notice to Contractors
General Notes
Notice to Contractors - TBPE Policy
Notice to Contractors - Material Hauling
Notice to Contractors - SWQ and Env Issues