This is a mechanical plan document for the Putnam High School Chiller Replacement project located in Milwaukie, Oregon, prepared by System Design Consultants Inc. for the North Clackamas School District. The document provides detailed specifications for the demolition of existing mechanical equipment and the installation of new high-efficiency heating and cooling systems. The project scope includes demolition of an existing air-cooled chiller, associated chilled water and heating water pumps, and concrete housekeeping pads, with replacement of these systems using new air-cooled, high-efficiency equipment that maintains the same or smaller footprint as the existing chiller. New equipment includes base-mounted chilled water and heating water pumps with variable frequency drives (VFDs), an inline heating water pump with VFD, and new chilled water supply and return piping from the chiller to the point of connection. All work must comply with the 2021 Oregon Mechanical Specialty Code, 2019 Oregon Energy Efficiency Specialty Code (ASHRAE 90.1-2019), and 2021 Oregon Energy Code requirements for insulation and structural bracing.

The plan document establishes technical requirements for equipment installation, including provision of structural bracing, maintenance of required service access areas, and integration of new pumps into the existing direct digital control (DDC) system. The mechanical floor plan includes two detailed views—one showing the existing system configuration and one depicting the proposed new work layout in the boiler room (G31) and adjacent areas. The document references additional technical details contained on sheets M0.1 and M0.2, including equipment schedules and control diagrams. The plan is dated December 24, 2024, and was designed by JF and checked by SDC, with coordination required with North Clackamas School District regarding potential reuse of existing VFD components. No pricing, contract term, or response deadline information is contained within this technical specification document.

View the file

Other files

File Type Posted
Request for Proposals.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

GENERAL NOTES

PROVIDE STRUCTURAL BRACING ON ALL NEW EQUIPMENT AS REQUIRED BY THE

STRUCTURAL ENGINEER

REFERENCED CODES INCLUDE 2021 OREGON MECHANICAL SPECIALTY CODE AND 2019

OREGON ENERGY EFFICIENCY SPECIALTY CODE (ASHRAE 90.1-2019)

INSULATE ALL NEW CHILLED WATER PIPING AND HEATING WATER PIPING AS REQUIRED BY

2021 OREGON ENERGY CODE.

SHEET NOTES:

1 DEMO EXISTING CHILLER. DEMO PIPING BACK TO P.O.C. SHOWN. REFERENCE DETAIL 1 ON

SHEET M0.2.

DEMO EXISTING CHILLED WATER PUMP. REFER TO DETAIL 1 ON SHEET M0.2. DEMO

EXISTING 4" CONCRETE HOUSEKEEPING PAD.

DEMO EXISTING HEATING WATER PUMP. REFER TO DETAIL 2 ON SHEET M0.2. DEMO

EXISTING 4" CONCRETE HOUSEKEEPING PAD.

DEMO EXISTING INLINE HEATING WATER PUMP. REFER TO DETAIL 2 ON SHEET M0.2.

PROVIDE NEW AIR COOLED, HIGH EFFICIENCY CHILLER. FOOT PRINT OF CHILLER TO BE

THE SAME OR LESS THAN EXISTING CHILLER. REFERENCE EQUIPMENT SCHEDULEON

SHEET M0.1. MAINTAIN REQUIRED SERVICE ACCESS AREAS.

PROVIDE NEW BASE MOUNTED CHILLED WATER PUMP. INSTALL ON NEW 4" CONCRETE

HOUSEKEEPING PAD. PROVIDE WITH NEW VARIABLE FREQUENCY DRIVE. TIE NEW PUMP

INTO EXISTING DDC SYSTEM. REFERENCE CHILLED WATER PUMP CONTROL DIAGRAM ON

SHEET M0.1. REFERENCE EQUIPMENT SCHEDULE ON SHEET M0.1.

PROVIDE NEW BASE MOUNTED HEATING WATER PUMP. INSTALL ON NEW 4" CONCRETE

HOUSEKEEPING PAD. PROVIDE WITH NEW VARIABLE FREQUENCY DRIVE. TIE NEW PUMP

INTO EXISTING DDC SYSTEM. REFERENCE HEATING WATER PUMP CONTROL DIAGRAM ON

SHEET M0.1. REFERENCE EQUIPMENT SCHEDULE ON SHEET M0.1.

PROVIDE NEW INLINE HEATING WATER PUMP. PROVIDE WITH NEW VFD. COORDINATE WITH

NCSD IF EXISTING VFD CAN BE REUSED. TIE NEW PUMP INTO EXISTING DDC SYSTEM.

REFERENCE HEATING WATER PUMP CONTROL DIAGRAM ON SHEET M0.1. REFERENCE

EQUIPMENT SCHEDULE.

PROVIDE NEW CHILLED WATER SUPPLY AND RETURN PIPING FROM CHILLER TO POINT OF

CONNECTION. INSULATE PIPE AS REQUIRED BY OREGON ENERGY CODE.

BOILER

ROOM

G31

STORAGE

G32

EE

HWP-2

6" CHWR

HEAT EXCHANGER /

BOILER-1

BOILER-2

HW STORAGE TANK

CHWP-1

E

E

E

E

6" CHWS

E

6" HWS

6" HWR

E

6" HWR

2-1/2" HWR

HWP-1

E

E

E

EXISTING

EXPANSION

TANK

OUTDOOR

CHILLER

COURTYARD

E

E

E

E

EXISTING

CHILLER

6" HWS

6" HWR

HWP-1

6" CHWR

HEAT EXCHANGER /

BOILER-1

BOILER-2

HW STORAGE TANK

CHWP-1

E

E

EE

6" CHWS

BOILER

ROOM

G31

STORAGE

G32

E

E

E

E

HWP-2

6" HWR

2-1/2" HWR

EXISTING

EXPANSION

TANK

OUTDOOR

CHILLER

COURTYARD

E

E

E

E

E

E

E

E

MAINTENANCE

ACCESS AREA

CH-1

M1.0

JF

MECHANICAL FLOOR

PLAN

REVISIONS:

ISSUE DATE:

SDC JOB #:

DESIGNED BY:

CHECKED BY:

DRAWN BY:

SET TYPE:

R

EX

P U

TN

A

M H

IG

H

S C

H O

O L

C H

IL

LE

R R

EP

LA

C

EM

EN

T

N O

R

TH

C

LA

C K

A M

A S

SC

H

O O

L D

IS

T.

S E

R O

ET

H

E R

D M

IL

W

A U

K

IE

, O R

EG

O

N

SYSTEM DESIGN CONSULTANTS INC.

333 SE SECOND AVE

SUITE 100

PORTLAND OR

97214

503-248-0227

NCS2401

12/24/2024

SCALE: 1/4"=1'-0"

MECHANICAL SYSTEM DEMO PLAN1

M1.0

NORTH

59898

OREGON

EXPIRES: 12/31/25

PROFESS IONAL

DERETSIGER

NEERIGNE

9, 2 0 0 2

YLUJ

D. F A R L E Y

NHOJ

SCALE: 1/4"=1'-0"

MECHANICAL SYSTEM NEW WORK PLAN2

M1.0

NORTH

NB

NB

File details come from the government source that posted it. Updated .