About this file

This document is a comprehensive technical specification file for the Milwaukee Ave. Reconstruction Project issued by the City of Lubbock, Texas. The project involves reconstructing and widening Milwaukee Avenue from 4th Street to the city limits, transforming it into a 5-lane section that will include curb and gutter, driveways, and 6'-10' sidewalks. Major work items include excavation, concrete pavement construction, mobilization, constructing detours, installing concrete curb and gutter, concrete sidewalks, roadway illumination, and electrical conduit work. The project has a total duration of 516 calendar days from the Notice to Proceed, with liquidated damages of $300 per day for exceeding the timeline and an additional $100 per day for incomplete punch list items.

The contract specifications outline detailed technical requirements for materials, installation methods, testing, and quality control. The estimated contract value is not explicitly stated, but the specifications indicate a comprehensive infrastructure improvement project. Funding appears to be from the City of Lubbock, with work to be performed according to City of Lubbock Engineering Minimum Design Standards and TxDOT specifications. The contractor will be responsible for all materials, labor, equipment, and compliance with local and state regulations. Key technical requirements include specific material specifications for pipe, concrete, electrical components, and installation procedures, with rigorous testing and quality assurance protocols throughout the project lifecycle.

View the file

Other files

Show all 12

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Milwaukee Ave. Section 01010 08/2025

Milwaukee Ave. Reconstruction

(4th St. to Marshall St.)

TECHNICAL SPECIFICATIONS

August 2025

Milwaukee Ave. Section 01010 08/2025

Seal Sheet

08/01/2025

Milwaukee Ave. Section 01010 08/2025

TABLE OF CONTENTS

CITY OF LUBBOCK

PROJECT TITLE

SECTION 01010: SUMMARY OF WORK

SECTION 01019: CONTRACT CONSIDERATIONS

SECTION 01027: APPLICATIONS FOR PAYMENT

SECTION 01028: CHANGE ORDER PROCEDURES

SECTION 01039: COORDINATION AND MEETINGS

SECTION 01140: WORK RESTRICTIONS

SECTION 01300: SUBMITTAL PROCEDURES

SECTION 01310: PROGRESS SCHEDULES

SECTION 01322: PHOTOGRAPHIC DOCUMENTATION

SECTION 01400: QUALITY REQUIREMENTS

SECTION 01410: TESTING LABORATORY SERVICES

SECTION 01576: WASTE MATERIAL DISPOSAL

SECTION 01600: PRODUCT REQUIREMENTS

SECTION 01700: CONTRACT CLOSEOUT

SECTION 01800: MOBILIZATION

SECTION 02050: REMOVAL, DEMOLITION AND SALVAGE

SECTION 02084: FRAMES, GRATES, RINGS, AND COVERS

SECTION 02221: REMOVING EXISTING PAVEMENTS

SECTION 02240: DEWATERING

SECTION 02257: CONTROLLED LOW STRENGTH MATERIAL – FLOWABLE FILL

SECTION 02260: EXCAVATION SUPPORT AND PROTECTION

SECTION 02317: EXCAVATION AND BACKFILL FOR UTILITIES

SECTION 02320: UTILITY BACKFILL MATERIALS

SECTION 02611: STEEL SPLIT CASING PIPE

SECTION 02665: WATER PIPING, VALVES, AND FITTINGS

Milwaukee Ave. Section 01010 08/2025

APPLICABLE TXDOT SPECIFICATIONS

ITEM 100 PREPARING ROW

ITEM 104 REMOVING CONCRETE

ITEM 110 EXCAVATION

ITEM 132 EMBANKMENT

ITEM 160 TOPSOIL

ITEM 162 SODDING FOR EROSION CONTROL

ITEM 164 SEEDING FOR EROSION CONTROL

ITEM 169 SOIL RETENTION BLANKETS

ITEM 247 FLEXIBLE BASE

ITEM 310 PRIME COAT

ITEM 354 PLANING AND TEXTURING PAVEMENT

ITEM 360 CONCRETE PAVEMENT

ITEM 400 EXCAVATION AND BACKFILL FOR STRUCTURES

ITEM 402 TRENCH EXCAVATION PROTECTION

ITEM 416 DRILLED SHAFT FOUNDATIONS

ITEM 432 RIPRAP

ITEM 450 RAILING

ITEM 462 CONCRETE BOX CULVERTS AND DRAINS

ITEM 464 REINFORCED CONCRETE PIPE

ITEM 466 HEADWALLS AND WINGWALLS

ITEM 467 SAFETY END TREATMENT

ITEM 479 ADJUSTING MANHOLES AND INLETS

ITEM 496 REMOVING STRUCTURES.

ITEM 502 BARRICADES, SIGNS, AND TRAFFIC HANDLING

ITEM 506 TEMPORARY EROSION, SEDIMENTATION, AND ENVIRONMENTAL CONTROLS

ITEM 508 CONSTRUCTING DETOURS

ITEM 529 CONCRETE CURB, GUTTER, AND COMBINED CURB AND GUTTER

ITEM 530 INTERSECTIONS, DRIVEWAYS, AND TURNOUTS

ITEM 531 SIDEWALKS

ITEM 536 CONCRETE MEDIANS AND DIRECTIONAL ISLANDS

ITEM 610 ROADWAY ILLUMINATION ASSEMBLIES

ITEM 618 CONDUIT

ITEM 620 ELECTRICAL CONDUCTORS

Milwaukee Ave. Section 01010 08/2025

ITEM 624 GROUND BOXES

ITEM 628 ELECTRICAL SERVICES

ITEM 644 SMALL ROADSIDE SIGN ASSEMBLIES

ITEM 658 DELINEATOR AND OBJECT MARKER ASSEMBLIES

ITEM 662 WORK ZONE PAVEMENT MARKINGS

ITEM 666 RETROREFLECTORIZED PAVEMENT MARKINGS

ITEM 672 RAISED PAVEMENT MARKERS

ITEM 677 ELIMINATING EXISTING PAVEMENT MARKINGS AND MARKERS

ITEM 680 HIGHWAY TRAFFIC SIGNALS

ITEM 682 VEHICLE AND PEDESTRIAL SIGNAL HEADS

ITEM 684 TRAFFIC SIGNAL CABLES

ITEM 686 TRAFFIC SIGNAL POLE ASSEMBLIES (STEEL)

ITEM 687 PEDESTAL POLE ASSEMBLIES

ITEM 688 PEDESTRIAN DETECTORS AND VEHICLE LOOP DETECTORS

ITEM 3076 DENSE-GRADED HOT-MIX ASPHALT

ITEM 3080 STONE-MIX APSHALT

ITEM 7114 WATER FILLED BARRIER

REFERENCES

City of Lubbock Engineering Minimum Design Standards and Specifications (2023)

TxDOT Standard Specifications for Construction and Maintenance of Highways, Streets and

Bridges (2014)

Milwaukee Ave. Section 01010 08/2025

SECTION 01010: SUMMARY OF WORK

PART 1 GENERAL

1.1 SUMMARY

A. This section covers the description of the Work to be completed under these Specifications.

B. The OWNER is the City of Lubbock.

(1) The Owner’s Representative is:

John Turpin, P.E.

City Engineer

City of Lubbock O: (806) 775-3397 jturpin@mylubbock.us

(2) The Project Manager is:

James Dean, P.E.

Civil Engineer

City of Lubbock

O: (806) 775-3254

JDean@mylubbock.us

C. Section includes:

(1) Definitions

(2) Project description

(3) Permits and licenses

(4) Access to site

(5) Contractor’s use of the premises

(6) Project schedule

(7) Security Procedures

(8) Coordination requirements

(9) Pre-construction meeting

(10) Warranty

1.2 DEFINITIONS

A. Furnish: To supply products to the project site, including delivering ready for unloading and replacing damaged and rejected products.

B. Install: To put products in place in the work ready for the intended use, including unloading, unpacking, handling, storing, assembling, installing, erecting, placing, applying, anchoring, working, finishing, curing, protecting, cleaning, and similar operations.

Milwaukee Ave. Section 01010 08/2025

C. Provide: To furnish and install products.

D. Indicated: Shown, noted, scheduled, specified, or drawn, somewhere in the contract documents.

1.3 PROJECT DESCRIPTION

A. The purpose of this project is to reconstruct and widen Milwaukee Ave. from 4th St. up to the city limits. to a 5-lane section which will include curb and gutter, driveways, and 6’-10’ sidewalk throughout the limits of the project

B. Major work items are:

(1) EXCAVATION

(2) CONC PVMT (CONT REINF - CRCP) (9")

(3) MOBILIZATION

(4) CONSTRUCTING DETOURS

(5) CONC CURB & GUTTER (TY A)

(6) CONCRETE SIDEWALS (4”)

(7) IN RD IL (TY SA) 40T-10 (250W EQ) LED

(8) CONDT (PVC) (SCH 40) (2")

(9) DENSE-GRADED HOT-MIX ASPHALT

C. The Contractor shall furnish all labor, equipment, and materials required for the complete construction of the work as shown on the drawings and specified herein.

D. All work shall be performed in accordance with the most recent City of Lubbock Minimum

Design Standards.

1.4 Work shall also include restoration or replacement of all removed or damaged pavement, curb, sidewalk, gutter, shrubbery, fence, sod or other disturbed surfaces or structures in a condition equal to that before the work began to the satisfaction of the Engineer.

1.5 PERMITS AND LICENSES

A. Contractor shall provide qualifications to the Owner upon request to display evidence of competency and authority to perform required work.

B. Contractor shall be responsible for obtaining all required permits.

C. Contractor shall submit copies of all permits, licenses, and similar permissions obtained, and receipts for fees paid, to the Owner.

1.6 ACCESS TO SITES

A. Contractor shall limit access to the site to authorized personnel only.

B. Contractor shall adequately barricaded open excavations and construction material and equipment as to prevent unauthorized personnel from accessing.

Milwaukee Ave. Section 01010 08/2025

C. The Owner shall locate and designate all manhole access points open and accessible for the work, and provide rights of access to these points.

D. Contractor shall coordinate with the City Solid Waste Services to maintain trash pickup schedules when working with in the alley right of way.

1.7 CONTRACTOR’S USE OF THE PREMISES

A. The space available to the Contractor for the performance of the work, either exclusively or in conjunction with others performing other construction as part of the project, is restricted to the area shown on the site plan of the contract drawings unless the Contractor makes arrangements to use additional space with the Owner.

B. The contractor shall ensure that any disturbed area is left in a condition equal to or better condition before finishing construction in the area.

1.8 PROJECT SCHEDULE

A. The Work summarized above shall be substantially completed within 516 calendar days from the date of the Notice to Proceed.

B. There will be a $300.00 per day liquidated damages for each day that exceeds the 516 day limit.

C. Within five (5) business days after the date of the Substantial Completion Certificate, the

Engineer shall issue a Final Punch List of items to be corrected prior to Final Completion.

D. Punch list items shall be complete within 30 calendar days from the date of the Final Punch

List. There shall be $100 day liquidated damages assessed for each day that exceeds the 30 day limit.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

3.1 SECURITY PROCEDURES

A. Contractor shall limit access to the site to persons involved in the work.

B. Contractor shall provide secure storage for materials for which the owner has made payments and which are stored on site.

C. Contractor shall secure completed work as required to prevent loss or damage.

D. Contractor shall secure sites by means of fencing, security guards, or other means to prevent damage, theft, safety hazards, or other problems on the site.

E. The use of security personnel shall be cleared with the Owner.

3.2 COORDINATION REQUIREMENTS

A. Contractor shall inform the Owner when coordination of the work is required.

Milwaukee Ave. Section 01010 08/2025

B. If necessary, inform each party involved, in writing, of procedures required for coordination;

include requirements for giving notice, submitting reports, and attending meetings.

C. Coordinate shop drawings prepared by separate entities.

D. Show installation sequence when necessary for proper installation.

3.3 PRE-CONSTRUCTION MEETING

A. A pre-construction meeting will be held at City Hall within ten (10) days of the date of Notice to Proceed and prior to any construction taking place.

3.4 WARRANTY

A. Contractor shall warrant 100% of the project for one (1) year after the date of substantial acceptance of the work.

B. On the eleventh (11) month from the date of final acceptance, an Owner’s representative will schedule an inspection with the presence of the Contractor to inspect for defects and assessment of the work performed.

C. Any work that is considered defective by the Owner’s representative will be repaired.

D. The Contractor shall remedy any defects in workmanship, and pay for any and all damages of any nature whatsoever resulting in defects at no cost to the Owner.

END OF SECTION

Milwaukee Ave. Section 01019-10 08/2025

SECTION 01019: CONTRACT CONSIDERATIONS

A. This section covers the method for the Contractor to request payment for completed work.

B. Section includes:

(1) Schedule of Values

(2) Application for Payment

(3) Payment Retainage

1.2 SCHEDULE OF VALUES

A. Contractor shall submit a Schedule of Values on Engineer approved Contractor’s form within five (5) days after receiving the bid tabulation.

B. Revise schedule to include approved Change Orders, with each Application for Payment.

1.3 APPLICATIONS FOR PAYMENT

A. Submit two (2) copies of each application on Engineer approved Contractor’s form.

B. Utilize Schedule of Values for listing items in Application for Payment.

C. Monthly, submit application for payment on or about the 10th day of each month.

D. Include an updated construction progress schedule, materials received, and manifest with each Application for Payment

E. Submit the following along with the application for final payment:

(1) The documentation for the completed project.

(2) Signed affidavit from a Notary Public that all claims on this job have been settled and that all bills owed by the Contractor for the project including materials and labor have been paid.

(3) One (1) year Contractor Warranty for work performed, signed and sealed by a Notary Public.

1.4 PAYMENT RETAINAGE

A. The Owner will retain five (5) percent of each payment.

B. Retainage will be released as final payment, upon completion of the Final Punch List.

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used

Milwaukee Ave. Section 01019-11 08/2025

Milwaukee Ave Section 01027-12 08/2025

SECTION 01027: APPLICATIONS FOR PAYMENT

PART 1 GENERAL

1.0 RELATED DOCUMENTS

A. Drawings, Construction Contract Clauses, Supplementary Conditions and Division 1 - General Requirements apply to work of this section.

1.1 SECTION INCLUDES

A. Procedures for preparation and submittal of Applications for Payment.

1.2 RELATED SECTIONS

A. Agreement: Contract Sum/Price and unit prices.

B. General Conditions: Progress Payments and Final Payment.

C. Section 01020 – Measurement and Payment.

D. Section 01028 - Change Order Procedures: Procedures for changes to the Work.

E. Section 01330 - Submittal Procedures.

F. Section 01700 - Contract Closeout.

1.2 FORMAT

A. EJCDC No. 1910-8-E - Application for Payment including continuation sheets when required, or

Owner forms, or Owner-approved form of the Contractor.

B. For each item, provide a column for listing: Item Number; Description of work; Scheduled Value, Previous Applications; Work in Place; Authorized Change Orders; Total Completed; Percentage of Completion; Balance to Finish; and Retainage.

1.3 PREPARATION OF APPLICATIONS

A. Present required information in typewritten form or computer generated Excel Spreadsheet.

B. Execute certification by signature of authorized officer.

C. Use data from approved Schedule of Values. Provide dollar value in each column for each line item for portion of work performed and for stored products.

D. List each authorized Change Order as an extension on continuation sheet, listing Change Order number and dollar amount as for an original item of Work.

E. Prepare Application for Final Payment as specified in Section 01700.

1.4 SUBMITTAL PROCEDURES

A. Submit two (2) copies of each Application for Payment.

B. Submit an updated construction schedule, materials received, and manifest with each Application for Payment. Payment will not be made until an up-to-date schedule is received.

C. Payment Period: Monthly, submit application for payment on or about the 10th day of each month.

D. Submit the following along with the application for final payment:

Milwaukee Ave. Section 01027-13 08/2025

a. The documentation for the completed project.

b. Signed affidavit from a Notary Public that all claims on this job have been settled and that all bills owed by the Contractor for the project including materials and labor have been paid.

c. One (1) year Contractor Warranty for work performed, signed and sealed by a Notary

Public.

1.4 SUBSTANTIATING DATA

A. When Engineer requires substantiating information, submit data justifying dollar amounts in question.

B. Provide one copy of data with cover letter for each copy of submittal. Show Application number and date, and line item by number and description.

Milwaukee Ave. Section 01028-14 08/2025

SECTION 01028: CHANGE ORDER PROCEDURES

A. This section covers the procedures to be followed for a change in Contract price or time.

B. Section Includes:

(1) Submittals

(2) Documentation Of Change In Contract Sum/Price And Contract Time

(3) Change Procedures

(4) Construction Change Authorization

(5) Stipulated Price Change Order

(6) Unit Price Change Order

(7) Time And Material Change Order

(8) Execution Of Change Orders

(9) Correlation Of Contractor Submittals

1.2 SUBMITTALS

A. Submit the name of the individual authorized to receive change documents, and be responsible for informing others in Contractor’s employ or Subcontractors of changes to the Work.

B. Change Order Forms.

1.3 DOCUMENTATION OF CHANGE IN CONTRACT SUM/PRICE AND CONTRACT TIME

A. Contractor shall maintain detailed records of work done on a time and material basis.

B. Provide full information required for evaluation of proposed changes and to substantiate costs of changes in the Work.

C. Document each quotation for a change in a cost or time with sufficient data to allow evaluation of the quotation.

D. On request, provide additional data to support computations, including but not limited to:

(1) Quantities of products, labor, and equipment.

(2) Taxes, insurance, and bonds.

(3) Overhead and profit.

(4) Justification for any change in Contract Time.

(5) Credit for deletions from Contract, similarly documented.

E. Support each claim for additional costs, and for work done on a time and material basis, with additional information:

(1) Origin and date of claim.

(2) Dates and times work was performed, and by whom.

(3) Time records and wage rates paid.

Milwaukee Ave. Section 01028-15 08/2025

(4) Invoices and receipts for products, equipment, and subcontracts, similarly documented.

1.4 CHANGE PROCEDURES

A. Changes to Contract Sum/Price or Contract Time can only be made by issuance of an official Construction Change Authorization or Contract Change Order. Discussions in the field or by phone or email, without proper documentation, do not authorize Contractor to perform tasks outside the scope of Work. Changes must be authorized as described in this Section.

B. The Engineer will advise of minor changes in the Work not involving an adjustment to Contract Sum/Price or Contract Time as authorized by the Contract by issuing supplemental instructions by letter.

C. The Engineer may issue a Proposal Request which includes a detailed description of a proposed change with supplementary or revised Drawings and Specifications. The Contractor shall prepare and submit an estimate within seven (7) days, or as specified in the Proposal Request. Estimate shall include the proposed change’s full effect on the Work and the effect on the Contract Sum/Price and Contract Time, with full documentation and a statement describing the effect on Work by separate or other contractors.

D. The Contractor may request clarification of Drawings, Specifications, or Contract documents or other information by submitting a Request for Information to the Engineer. Engineer may request a Proposal Request in response to a Request for Information.

1.5 CONSTRUCTION CHANGE AUTHORIZATION

A. The Engineer may issue a document, signed by the Owner, instructing the Contractor to proceed with a change in the Work, for subsequent inclusion in a Change Order.

B. The document will describe changes in the Work, and will designate the method of determining any change in Contract Sum/Price or Contract Time.

C. The Contractor shall promptly execute the change in the Work.

1.6 STIPULATED PRICE CHANGE ORDER

A. Based on accepted Proposal Request.

1.7 UNIT PRICE CHANGE ORDER

A. For pre-determined unit prices and quantities, the Change Order will be executed on a fixed unit price basis.

B. For unit costs or quantities of units of work which are not pre-determined, execute Work under a Construction Change Authorization.

C. Changes in Contract Sum/Price or Contract Time will be computed as specified for Time and Material Change Order.

1.8 TIME AND MATERIAL CHANGE ORDER

A. Submit itemized account and supporting data after completion of change, within time limits indicated in the Conditions of the Contract.

B. The Engineer will determine the change allowable in Contract Sum/Price and Contract Time as provided in the Contract Documents.

C. Maintain detailed records of work done on Time and Material basis.

Milwaukee Ave. Section 01028-16 08/2025

D. Provide full information required for evaluation of proposed changes, and to substantiate costs for changes in the Work.

1.9 EXECUTION OF CHANGE ORDERS

A. The Engineer will issue Change Orders for signatures of parties as provided in the Conditions of the Contract.

1.10 CORRELATION OF CONTRACTOR SUBMITTALS

A. Promptly revise Schedule of Values and Application for Payment forms to record each authorized Change Order as a separate line item and adjust the Contract Sum/Price.

B. Promptly revise progress schedules to reflect any change in Contract Time, revise sub-schedules to adjust time for other items of work affected by the change, and resubmit.

C. Promptly enter changes in Project Record Documents.

Milwaukee Ave. Section 01039-17 08/2025

SECTION 01039: COORDINATION AND MEETINGS

A. Section Includes:

(1) Coordination

(2) Field Engineering

(3) Pre-Construction Meeting

(4) Progress Meetings

1.4 COORDINATION

A. Coordinate scheduling, submittals, and Work of the various Sections of the Project to assure efficient and orderly sequence of installation of interdependent construction elements, with provisions for accommodating items installed later.

B. Coordinate completion and cleanup of Work of separate Sections in preparation for Substantial Completion.

C. After Owner occupancy of premises, coordinate access to site for correction of defective Work and Work not in accordance with Contract Documents, to minimize disruption of Owner’s activities.

1.5 FIELD ENGINEERING

A. Locate and protect survey control and reference points.

B. Verify set-backs and easements; confirm drawing dimensions, and elevations.

C. Provide field engineering services.

D. Establish elevations, lines, and levels, utilizing recognized engineering survey practices.

E. Submit a copy of registered site drawing and certificate signed by Land Surveyor that the elevations and locations of the Work are in conformance with the Contract Documents.

1.6 PRE-CONSTRUCTION MEETING

A. Schedule meeting within ten (10) days of date of Notice to Proceed.

B. Procedures and processing of field decisions, submittals, and substitutions, applications for payments, RFIs, proposal request, Change Orders and Contract closeout procedures.

C. Tentative agenda:

(1) Use of premises by Owner and Contractor.

(2) Distribution of executed Contract Documents.

(3) Submission of list of Subcontractors, list of products and progress schedule.

(4) Designation of personnel representing the parties in Contract and the Engineer.

(5) Owner’s requirements.

(6) Construction facilities and controls provided by Owner.

(7) Survey and layout.

(8) Security and housekeeping procedures.

(9) Schedules.

(10) Procedures for testing.

(11) Procedures for maintaining record documents.

(12) Inspection and acceptance of products put into service during construction period.

Milwaukee Ave. Section 01039-18 08/2025

D. Record minutes and distribute copies within five (5) days after meeting to Engineer, participants, and those affected by decisions made.

1.7 PROGRESS MEETINGS

A. Schedule and administer meetings throughout progress of the Work at minimum monthly intervals.

B. Make arrangements for meetings, prepare agenda with copies for participants, and preside at meetings.

C. Attendance Required: Job superintendent, major Subcontractors and suppliers, Engineer, as appropriate to agenda topics for each meeting.

D. Tentative agenda:

(1) Review minutes of previous meetings.

(2) Review of Work progress.

(3) Field observations, problems, and decisions.

(4) Identification of problems which impede planned progress.

(5) Review of submittals schedule and status of submittals.

(6) Review of off-site fabrication and delivery schedules.

(7) Maintenance of progress schedule.

(8) Corrective measures to regain projected schedules.

(9) Planned progress during succeeding work period.

(10) Coordination of projected progress.

(11) Maintenance of quality and work standards.

(12) Effect of proposed changes on progress schedule and coordination.

(13) Other business related to Work.

E. Record minutes and distribute copies within five (5) days after meeting to Engineer, participants, and those affected by decisions made.

PART 2 PRODUCTS

Not used

PART 3 EXECUTION

Note used

Milwaukee Ave. Section 01039-19 08/2025

PAGE LEFT INTENTIONALLY BLANK

Milwaukee Ave. Section 01140-20 08/2025

SECTION 01140: WORK RESTRICTIONS

A. Section Includes:

(1) Use Of Premises

(2) Special Scheduling Requirements

(3) Working Period

(4) Utility Cutovers And Interruptions

(5) Noise Restrictions

(6) Advance Notice

(7) Water For Construction

(8) Work Area Limits

1.2 USE OF PREMISES

A. Limit use of premises to work in areas indicated. Do not disturb portions of site beyond areas in which the Work is indicated.

B. Confine construction operations to within the limits of Right of Way, Alley Easements and Manhole locations, as shown on plans.

C. Keep driveways and entrances serving premises clear and available to tenants, residents and emergency vehicles at all times, except when construction is immediately at that vicinity. Do not use these areas for parking or storage of materials.

D. Schedule construction to minimize obstruction of driveways and entrances.

1.3 SPECIAL SCHEDULING REQUIREMENTS

A. Have materials, equipment, and personnel required to perform the work at the site prior to the commencement of the Work.

B. Permission to interrupt utility service shall be requested in writing a minimum of fourteen

(14) calendar days prior to the desired date of interruption.

1.4 WORKING PERIOD

A. Regular working hours shall be within an eleven (11) hour period between 7:00 a.m. and 6:00 p.m., Monday through Friday, and an eight (8) hour period between 9:00 a.m. and 5:00 p.m.

on Saturday.

(1) Saturday work shall be restricted to those activities that do not require observation by the Owner.

(2) The Owner reserves the right, at the Owner’s discretion, to disallow work when it interferes with holiday times and traffic.

B. No work shall be performed on the following holiday periods or days:

(1) New Year’s Day

(2) Good Friday Holiday

Milwaukee Ave. Section 01140-21 08/2025

(3) Memorial Day Holiday

(4) Independence Day Holiday

(5) Labor Day Holiday

(6) Thanksgiving Day Holiday plus the day before and the three days following Thanksgiving Day.

(7) Christmas Week. If Christmas Day falls on Saturday, this will be defined as the week leading to Christmas Day. If Christmas Day falls on Sunday, this will be defined as the week following Christmas Day plus the Friday and Saturday prior to Christmas Day.

C. Work outside regular working hours requires Owner’s approval.

(1) Make application twenty-one (21) calendar days prior to such work to allow arrangements to be made by the Owner for inspecting the work in progress, giving the specific dates, hours, location, type of work to be performed, contract number and Project Title.

(2) Based on the justification provided, the Owner may approve work outside regular hours.

(3) During periods of darkness, the different parts of the Work shall be lighted in a manner approved by the Owner. Lighting shall be such that it does not cause nuisance conditions.

D. The Drawings contain specific requirements that affect certain areas of the Work.

1.5 UTILITY CUTOVERS AND INTERRUPTIONS

A. Sanitary sewer flow shall not be interrupted upstream of the Work. Bypass pumping of sanitary sewer flow upstream of the Work shall be the responsibility of the Contractor.

B. Water service connections shall be re-connected in a timely manner following installation of the new water pipe.

1.6 NOISE RESTRICTIONS

A. 75 dB limit at face of nearest structure during normal daylight hours.

B. 65 dB limit at face of nearest structure during evening and nighttime hours in or near residential areas and for 24-hour working conditions that have received Owner approval.

Evening and nighttime hours shall be defined as 6:00 p.m. to 7:00 a.m.

C. The Contractor shall keep on-site a hand portable sound measurement device for both the Owner’s and the Contractor’s use for measuring noise levels.

1.7 ADVANCE NOTICE

A. The Contractor shall provide a minimum of five (5) days advance written notice of construction to businesses and residences along the construction route.

B. The advance written notice shall be in the form of a single page flyer to be placed by hand by the Contractor’s forces in mailboxes, door handles, or handed to applicable individuals at each route building.

C. The text for the advance written notice will be approved by the Owner.

D. Reproduction shall be at the Contractor’s expense.

E. Distribution shall be at the Contractor’s expense.

Milwaukee Ave. Section 01140-22 08/2025

F. Single page flyers shall be of a paper or post card color other than white to direct the recipient’s attention to the information.

G. The text shall contain the anticipated beginning date of inconvenience to the recipient and the anticipated duration of that inconvenience.

H. The dates shall encompass the duration of driveway inconveniences and potential noise to the recipients on a single city block (i.e., the dates and durations shall reflect the time that the city block of interest will be affected by non-trafficability).

1.8 WATER FOR CONSTRUCTION

A. Obtaining water for construction is the Contractor’s sole responsibility.

B. Water is available from the potable water system of the City of Lubbock for construction purposes.

(1) The Contractor is responsible for all charges and arrangements for water consumption from the potable water system.

(2) The Contractor shall make such arrangements directly with the City of Lubbock Water Utilities Department.

(3) The City will not furnish potable water free of charge for the construction work.

(4) The Contractor is responsible for any required metering and hauling.

C. Water from park area lakes shall not be used for construction.

D. This section does not preclude the Contractor from seeking other water sources for use in construction. Such water resources shall meet the purity requirements for the intended use.

Such arrangements for water from other sources are the responsibility of the Contractor.

PART 1 PRODUCTS

PART 2 EXECUTION

2.1 WORK AREA LIMITS

A. Prior to any construction, the Contractor shall mark the areas that need not be disturbed under this contract.

B. Isolated areas within the general work area which are to be saved and protected shall also be marked or fenced.

C. Monuments and markers shall be protected before construction operations commence.

D. Where construction operations are to be conducted during darkness, the markers shall be visible at all times.

E. The Contractor’s personnel shall be knowledgeable of the purpose for marking and/or protecting particular objects.

Milwaukee Ave. 01300-23 08/2025

SECTION 01300: SUBMITTAL PROCEDURES

A. Section includes:

(1) Submittal Procedures

(2) Re-Submittal Requirements

(3) Action Submittals

(4) Proposed Products List

(5) Shop Drawings

(6) Information Submittals

(7) Contractor’s Review

(8) Owner And Engineer Action

1.2 SUBMITTAL PROCEDURES

A. Transmit each submittal with Contractor’s standard transmittal letter including Contractor’s name, address, and phone number.

B. Identify Project, Contractor, Subcontractors or Suppliers, pertinent Drawings sheet and detail number(s), and specification Section number, as appropriate.

C. Schedule submittals to expedite the Project and coordinate submission of related items.

D. The Owner and Engineer reserve the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

E. Submittals may be delivered to the Engineer at the following address:

Engineering CIP and Design

1314 Ave. K Lubbock, Texas 79401

F. Allow enough time for submittal review, including time for re-submittals, as follows:

(1) Time for review shall commence on the Owner or Engineer’s receipt of submittal.

(2) Allow fifteen (15) days for initial review of each submittal.

(3) Allow additional time if processing must be delayed to permit coordination with subsequent submittals.

(4) The Owner or Engineer will advise the Contractor when a submittal being processed must be delayed for coordination.

(5) If more than five (5) submittals are transmitted for review within any five (5) day period, the time allowed for review will be increased to twenty-one (21) days.

(6) Where concurrent review of submittals by the Engineer, Owner, or other parties is required, allow twenty-one (21) days for initial review of each submittal.

(7) If intermediate submittal is necessary, process it in same manner as initial submittal.

(8) Allow fifteen (15) days for processing each resubmittal.

Milwaukee Ave. 01300-24 08/2025

G. No extension of the Contract Time will be authorized because of failure to transmit submittals sufficiently in advance of the Work to permit processing.

H. Identify variations from Contract Documents and Product or system limitations which may be detrimental to successful performance of the completed Work.

I. Provide space for Contractor and Engineer review stamps.

J. Distribute copies of reviewed submittals to concerned parties. Instruct parties to promptly report any inability to comply with provisions.

K. Use only final submittals with mark indicating action taken by Owner or Engineer in connection with the construction.

L. Submittals not requested will not be recognized or processed.

1.3 RE-SUBMITTAL REQUIREMENTS

A. Revise initial submittal as required and re-submit to meet requirements as specified.

B. Identify all changes made since previous submittal.

C. Mark as RESUBMITTAL.

D. Re-use original transmittal number and supplement with sequential alphabetical suffix for each re-submittal (i.e. 0001-A).

2.1 ACTION SUBMITTALS

A. Prepare and submit Action Submittals required by individual Specification Sections.

B. Submit three (3) copies of each submittal, unless otherwise indicated.

(1) The three (3) copies will be retained by the Owner’s representative.

(2) Any additional copies that the Contractor may need for his operations will be in addition to the three (3) copies required.

2.2 PROPOSED PRODUCTS LIST

A. Within fifteen (15) days after date of Notice to Proceed, submit complete list of major products proposed for use, with name of manufacturer, trade name, and model or catalog designation, and reference standards.

B. For products specified only by reference standards, give manufacturer, trade name, model or catalog designation, and reference standards.

C. Collect information into a single submittal for each element of construction and type of product or equipment.

D. Mark each copy to identify applicable products, models, options, and other data. Supplement manufacturers’ standard data to provide information unique to this Project.

E. Include recommendations for application and use, compliance with specified standards of trade associations and testing agencies.

F. Include notation of special coordination requirements for interfacing with adjacent work.

G. After review, distribute in accordance with Article on Procedures above and provide copies for Record Documents described in Section 01700 – Contract Closeout.

Milwaukee Ave. 01300-25 08/2025

2.3 SHOP DRAWINGS

A. Prepare Project specific information, drawn accurately to scale.

B. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

C. Include the following information, as applicable:

(1) Dimensions

(2) Identification of products

(3) Fabrication and installation drawings

(4) Schedules

(5) Design calculations

(6) Compliance with specified standards

(7) Notation of coordination requirements

(8) Notation of dimensions established by field measurement

D. For drawings larger than 11 x 17 inches, submit in the form of one reproducible transparency and one opaque reproduction.

E. For drawings 11 x 17 inches and smaller, submit the number of opaque reproductions which Contractor requires, plus three (3) copies which will be retained by Engineer.

F. Drawing size shall be minimum of 8 ½ x 11 inches and a maximum of 24 x 36 inches.

G. Draw details to a minimum size of ½ inch equal to 1 foot.

H. After review, produce copies and distribute in accordance with SUBMITTAL PROCEDURES article above and for record document purposed described in Section 01700

– Contract Closeout.

2.4 INFORMATION SUBMITTALS

A. Manufacturer’s Instructions:

(1) When specified in individual specification Sections, submit manufacturers’ printed instructions for delivery, storage, assembly, installation, start-up, adjusting, and finishing, in quantities specified for Product Data.

(2) Identify conflicts between manufacturers’ instructions and Contract Documents.

(3) Indicate special procedures, conditions requiring special attention and special environmental criteria required for application or installation.

B. Manufacturer’s Certificates

(1) When specified in individual specification Sections, submit manufacturers’ certificate to Engineer for review, in quantities specified for Product Data.

(2) Indicate material or product conforms to or exceeds specified requirements. Submit supporting reference date, affidavits, and certifications as appropriate.

(3) Certificates may be recent or previous test results on material or Product, but must be acceptable to the Engineer.

C. Insurance Certificates and Bonds:

(1) Prepare written information indicating current status of insurance or bonding coverage.

(2) Include name of entity covered by insurance or bond, limits of coverage, amounts of deductibles, if any, and term of the coverage.

Milwaukee Ave. 01300-26 08/2025

3.1 CONTRACTOR’S REVIEW

A. Review each submittal and check for compliance with the Contract Documents.

B. Note corrections and field dimensions.

C. Mark with approval stamp before submitting to the Owner or Engineer.

(1) Stamp each submittal with a uniform approval stamp.

(2) Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor’s approval, and statement certifying that the submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

3.2 OWNER AND ENGINEER’S ACTION

A. The Owner or Engineer will not review submittals that do not bear the Contractor’s approval stamp and will return them without action.

B. The Owner or Engineer will review each submittal, make marks to indicate corrections or modifications required, and return it.

C. The Owner or Engineer will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action taken, as follows:

(1) No exception taken

(2) Make correction noted

(3) Revise and resubmit

(4) Rejected

D. The submittal stamp by the Owner or Engineer will also contain the following:

(1) Checking is only for general conformance with the design concept of the project and general compliance with the information given in the Contract Documents.

(2) Any action shown is subject to the requirements of the plans and specifications.

(3) The Contractor is responsible for confirming and correlating all quantities and dimensions; selecting fabrication processes and techniques of construction; and performing the Work in a satisfactory manner.

E. The Owner or Engineer will review each submittal and will not return it, or will reject and return it, if it does not comply with the requirements.

Milwaukee Ave. Section 01310-27 08/2025

SECTION 01310: PROGRESS SCHEDULES

A. Section Includes:

(1) Format

(2) Content

(3) Revisions To Schedules

(4) Submittals

(5) Distribution

1.2 FORMAT

A. Sequence of Listings: The chronological order of the start of each item of Work.

B. Scale and Spacing: To provide space for notations and revisions.

C. Sheet Size: Minimum 8 1/2 x 11 inches

D. Submit only if requested by the Engineer or Owner at preconstruction or coordination meeting.

E. Maintain monthly updates to schedule.

1.3 CONTENT

A. Show complete sequence of construction by activity, with dates for beginning and completion of each element of construction.

B. Identify each item by specification Section number.

C. Provide sub-schedules to define critical portions of the entire Schedule.

D. Show accumulated percentage of completion of each item, and total percentage of Work completed, as of the first day of each month.

E. Provide separate schedule of submittal dates for shop drawings, product data, samples, and dates reviewed submittals will be required from the Engineer. Indicate decision date for selection of finishes.

1.4 REVISIONS TO SCHEDULES

A. Indicate progress of each activity to date of submittal, and projected completion date of each activity.

B. Identify activities modified since previous submittal, major changes in scope, and other identifiable changes.

C. Provide narrative report to define problem areas, anticipated delays, and impact on Schedule.

Report corrective action taken, or proposed, and its effect.

1.5 SUBMITTALS

A. Submit initial Schedules within ten (10) days after date established in Notice to Proceed.

After review, resubmit required revised data within ten (10) days.

Milwaukee Ave. Section 01310-28 08/2025

B. Submit revised Progress Schedules with each Application for Payment.

C. Submit the number of opaque reproductions which the Contractor requires, plus two (2) copies which will be retained by the Engineer.

1.6 DISTRIBUTION

A. Distribute copies of reviewed Schedules to project site file, Subcontractors, suppliers, and other concerned parties.

B. Instruct recipients to promptly report, in writing, problems anticipated by projections indicated in Schedules.

PART 1 EXECUTION

Milwaukee Ave. Section 01322-29 08/2025

SECTION 01322: PHOTOGRAPHIC DOCUMENTATION

A. RELATED DOCUMENTS

a. Drawings, Construction Contract Clauses, Supplementary Conditions and

B. SECTION INCLUDES

a. This Section includes administrative and procedural requirements for the following:

b. Preconstruction photographs.

c. Periodic construction photographs.

d. Preconstruction videotapes.

e. Periodic construction videotapes.

C. RELATED SECTIONS

a. Section 01330 - Submittal Procedures for submitting construction photographs.

D. SUBMITTALS

a. Submit two (2) complete sets of preconstruction photographs or videotape to

Engineer. All three sets will be retained by the Owner and the Engineer.

b. Identification: On back of each print, videotape, or CD, provide an applied label or rubber-stamped impression with the following information:

c. Name of Project.

d. Name and address of photographer.

e. Name of Engineer.

f. Name of Contractor.

g. Date photograph was taken.

h. Description of vantage point, indicating location, direction (by compass point), and elevation or story of construction.

i. Digital Images: Submit a complete set of digital image electronic files with each submittal of prints. Identify electronic media with date photographs were taken.

Submit images that have the same aspect ratio as the sensor, uncropped.

E. PHOTOGRAPHS, GENERAL

a. Field Office Prints: Retain one set of prints of preconstruction photographs in the field office at Project site, available at all times for reference. Identify photographs the same as for those submitted to Engineer.

F. CONSTRUCTION PHOTOGRAPHS

a. Preconstruction Photographs: Before starting construction, take color photographs of Project site and surrounding properties from different vantage points, or as directed by Engineer.

Milwaukee Ave. Section 01322-30 08/2025

b. Take photographs to show existing conditions adjacent to the property before starting the Work.

c. Take photographs of existing structures either on or adjoining the property to accurately record the physical conditions at the start of construction.

d. Periodic Construction Photographs: As needed to document damage either directly related to or inadvertently related to the Contractor’s operations, photograph the area in question and provide to Engineer.

G. CONSTRUCTION VIDEOS, GENERAL

a. Narration: Describe scenes on video by audio narration by microphone while video is recorded. Include description of items being viewed, recent events, and planned activities. Describe vantage point, indicating location, and direction (by compass point).

H. CONSTRUCTION VIDEOS

a. Preconstruction Video: Before starting construction, record video of Project site and surrounding properties from different vantage points, or as directed by Engineer.

b. Show existing conditions on and adjacent to Project site before starting the Work.

c. Show existing structures either on or adjoining Project site to accurately record the physical conditions at the start of construction.

d. Existing condition videos shall cover the entire project route.

e. Show protection efforts by Contractor.

f. Periodic Construction Documentation: As needed to document damage either directly related to or indirectly related to the Contractor’s operations, video the area in question and provide to Engineer.

Milwaukee Ave. Section 01400-31 08/2025

SECTION 01400: QUALITY REQUIREMENTS

A. Section Includes:

(1) Definitions

(2) Testing Requirements

(3) Submittals

(4) Quality Control

(5) Repair and Protection

1.2 DEFINITIONS

A. Quality Assurance Services: Activities, actions, and procedures performed before and during execution of the Work to guard against defects and deficiencies and ensure that proposed construction complies with requirements.

B. Quality Control Services: Tests, inspections, procedures, and related actions during and after execution of the Work to evaluate that completed construction complies with requirements.

1.3 TESTING REQUIREMENTS

A. Testing and inspecting services are required to verify compliance with requirements specified or indicated. These services do not relieve the Contractor of responsibility for compliance with the Contract Document requirements.

B. Specific quality control requirements for individual construction activities are specified in the sections that specify those activities. Requirements in those Sections may also cover production of standard products.

C. Specified tests, inspections, and related actions do no limit the Contractor’s quality control procedures that facilitate compliance with the Contract Document requirements.

1.4 SUBMITTALS

A. Qualification Data:

(1) For individuals employed by the Contractor who will perform testing as required by the various specification Sections, submit at least fourteen (14) days prior to being used on the project the capabilities and experience of such individuals and the types of tests that the individual will perform.

(2) For outside testing agency employed by the Contractor, submit at least fourteen (14) days prior to being used on the project the name, address, and manager of such testing agency and the types of tests that the agency will perform.

(a) Such testing agency shall be acceptable to the Owner prior to being used on the project.

B. Reports:

(1) Prepare and submit written reports within fourteen (14) days following the date of the test that include the following:

Milwaukee Ave. Section 01400-32 08/2025

(a) Date of issue

(b) Project Title and number.

(c) Name, address, and telephone number of testing agency. If the individual is employed by the Contractor, use Contractor’s name, address, and telephone number.

(d) Dates and locations of samples and test

(e) Names of individuals making tests

(f) Description of the work and test method

(g) Identification of material, product, and specification Section.

(h) Complete test or inspection data

(i) Test results and interpretation of test results

(j) Ambient conditions at time of sample taking and testing.

(k) Comments and opinion on whether tested Work complied with the Contract Document requirements and the applicable specification Section.

(l) Name and signature of individual performing the test if employee of the Contractor, or name and signature of testing agency responsible person.

(m) For failing tests, recommendations on retesting unless specification Sections provide procedure for retesting.

C. Professional Engineer Qualifications:

(1) Where a Professional Engineer is required in the specification Sections, this means a Professional Engineer who is legally qualified to practice in the jurisdiction where the project is located and who is experienced in providing engineering services of the kind indicated.

D. Test Agency Qualifications:

(1) An agency with the experience and capability to conduct testing indicated, as documented by ASTM E 548, and that has the capability and experience in the types of tests to be performed.

E. Preconstruction Testing:

(1) Testing agency shall perform preconstruction testing with specified requirements for performance and test methods.

(2) The Contractor shall not perform preconstruction testing except through a third party testing agency.

F. Testing Agency Responsibilities:

(1) Submit certified written report of each test and similar Quality Assurance service to the Contractor.

(2) Interpret tests and state in each report whether tested work complies with or deviates from the Contract Document requirements.

1.5 QUALITY CONTROL

A. Owner Responsibilities:

(1) Where quality control services are indicated as Owner or Engineer’s responsibility, such services may be performed by the Owner’s forces or by a qualified testing agency to perform these services.

Milwaukee Ave. Section 01400-33 08/2025

(2) The Owner or Engineer will furnish the Contractor with names, addresses, and telephone numbers of testing agencies engaged by the Owner.

B. Contractor Responsibilities:

(1) Provide quality control services required in the various specification Sections.

(2) Where third party testing is engaged by the Contractor, notify testing agency sufficiently in advance of the time and date when work that requires testing will be performed.

(3) The Contractor shall not engage the same testing agencies as the Owner, unless Owner agrees in writing to such engagement.

(4) Where testing is indicated as the Contractor’s responsibility, submit certified written reports in duplicate of each testing service, whether performed by the Contractor’s personnel or Contractor engaged testing agency.

(5) Such reports shall include failing tests and retests.

(6) Testing requested by the Contractor and not required by the Contract Documents are the Contractor’s responsibility.

(7) Where the Contractor’s personnel are performing tests, provide individuals with appropriate equipment to perform the tests in accordance with the test method requirements.

(8) Provide alternate equipment where the specified test method cannot be applied, and where alternative test methods and equipment must be employed to provide the necessary quality control.

C. Retesting:

(1) Regardless of whether original tests were the Contractor’s responsibility, provide quality control services, including retesting, for construction that revised or replaced work that failed to comply with requirements established by the Contract Documents.

D. Testing Agency Responsibilities:

(1) Cooperate with the Engineer and Contractor in performance of duties.

(2) Provide qualified personnel and necessary equipment to perform required tests and inspections.

(3) Notify the Engineer or Contractor promptly of irregularities or deficiencies observed in the work during performance of its services.

(4) Interpret tests and inspections and state in each report whether tested and inspected work complies with or deviates from the requirements.

(5) Submit a certified written report, in triplicate, of each test, inspection, and similar quality control service through the Contactor.

(6) Do not release, revoke, alter, or increase requirements of the Contract Documents or approve or accept any portion of the Work.

(7) Do not perform any duties of the Contractor.

E. Associated Services:

(1) Cooperate with agencies performing required tests, inspections, and similar quality control services, and provide reasonable auxiliary services as requested.

(2) Notify agency sufficiently in advance of operations to permit assignment of personnel.

Milwaukee Ave. Section 01400-34 08/2025

(3) Provide the following:

(a) Access to the Work.

(b) Incidental labor and facilities necessary to facilitate tests and inspections.

(c)…

This is the start of the file's text. The full file is on GovTribe.