7TH_AVENUE_FROM_SOUTHERN_AVENUE_TO_BROADWAY_ROAD_ROADWAY_DESIGN.pdf

PDF 196 KB Posted

Attached to
7TH AVENUE FROM SOUTHERN AVENUE TO BROADWAY ROAD ROADWAY DESIGN
Solicitation number
ST85100459
Issued by
Maricopa County, Phoenix City, Arizona

About this file

This Request for Qualifications (RFQ) is issued by the City of Phoenix, Arizona Office of the City Engineer for professional design services on the 7th Avenue from Southern Avenue to Broadway Road Roadway Design project. The City seeks a qualified consultant team to provide final design services for a roadway widening project with an estimated construction cost of $8.6 million. The project scope includes roadway widening on the west half of 7th Avenue, construction of 5-foot-wide sidewalks, installation of curb and gutter, drainage infrastructure improvements, street lighting, bus stop reconstruction, utility coordination, driveway retrofits to meet ADA standards, a new signalized intersection at Sunland Avenue and upgrades to the existing intersection at Roeser Road, and public outreach coordination. A pre-submittal meeting is scheduled for 9:00 a.m. on Friday, November 20, 2026, at the Gecko Conference Room in Phoenix and via Microsoft Teams. The deadline for submitting Statements of Qualifications is 12:00 p.m. on Friday, December 11, 2026, through the City's Procurement Portal. Selection notification is anticipated in early January 2027, with a scope meeting scheduled for mid-January 2027.

The RFQ employs a qualifications-based selection process with evaluation criteria weighted as follows: Design Experience of the Prime Firm (225 points, 22%), Design Experience of Key Personnel and Subconsultants (225 points, 22%), Project Understanding and Approach (425 points, 41.6%), Staffing Information for Key Personnel (125 points, 12.2%), and Reference Checks (21 points, 2.1%), for a total of 1,000 points. Firms must demonstrate experience with at least three similar projects completed within the past five years and provide detailed project descriptions, their roles, original and final contract values, and completion dates. A critical requirement is that the project must be federally reviewed and obligated prior to May 2029. Submissions are limited to 12 pages and must be submitted electronically in PDF format through the City's Procurement Portal. The City reserves the right to reject any or all submissions and will enter into negotiations with the selected team for contract execution upon City Council approval. No specific set-asides, pricing terms, or funding sources are identified in this RFQ.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CITY OF PHOENIX, ARIZONA

OFFICE OF THE CITY ENGINEER

DESIGN AND CONSTRUCTION PROCUREMENT

REQUEST FOR QUALIFICATIONS

7TH AVENUE FROM SOUTHERN AVENUE TO BROADWAY ROAD

ROADWAY DESIGN

PROFESSIONAL SERVICES

OPENGOV ID NO. ST85100459

RFQ Rev. 1/25 Page | 2

The City of Phoenix is seeking a qualified consultant team to provide Professional services for the 7th Avenue from Southern Avenue to Broadway Road Roadway Design project. The project involves roadway widening primarily on the west half of 7th Avenue to the ultimate roadway cross sections. Improvements include sidewalk, curb and gutter, drainage infrastructure, landscaping, street lighting, a new signalize intersection, upgrades to an existing intersection, pavement restoration and Americans with Disabilities Act (ADA) improvements. Services will include final design services. This project is located along 7th Avenue between Southern Avenue and

Broadway Road. The estimated construction cost is $8.6 million.

Project Description

7th Avenue: Southern Avenue to Broadway Road is a roadway widening project designed to improve corridor safety and security of pedestrian, bicyclists, transit riders, and drivers by adding sidewalks and streetlighting of the west side, as they currently do not exist. This is intended to promote safe and efficient mobility by prioritizing ADA-compliant sidewalks, curb ramps, driveway entrances, and upgraded signalized intersections.

Scope of Work

The consultant will provide design services for the widening and reconstruction of 7th Avenue, including coordination with City Environmental, Right-of-Way, Utility, Public Outreach teams, outside agencies, and stakeholders. The scope includes, but is not limited to:

• Roadway typical section would utilize existing lane widths (10–11-foot travel lanes, 10-foot two-way left-turn lane, 5–6-foot bike lanes)

• Construction of 5-foot-wide sidewalks along the west side of 7th Avenue (5-foot landscape buffer) where it currently does not exist.

• Installation of new curb and gutter along the west side of 7th Avenue; currently, it does not exist

• New driveway construction along the west side of 7th Avenue to accommodate new curb and gutter

• New driveway/sidewalk retrofits along the west and east side of 7th Avenue to reconstruct existing driveways/sidewalk that do not meet current ADA standards (4-foot sidewalk wrap-arounds at existing driveways where required)

• Reconstruction of existing bus stops along the west side of 7th Avenue to provide bus shelter/accessory pad

• Drainage improvements along the west side of 7th Avenue, including catch basin relocations and storm drain.

• Street lighting improvements

• Utility coordination to identify potential utility conflicts and make design adjustments to avoid conflicts as possible.

Page | 3

• Coordinate with City Real Estate Division to prepare necessary documentation for right-of-way (ROW) acquisition.

• Addressing a traffic signal or HAWK for pedestrian crossing at Sunland Avenue and 7th

Avenue; upgrading the intersection and traffic signal at 7th Avenue and Roeser Road.

• Pavement preservation

• Conducting Public Outreach

• Signing and Striping

• Coordination with city staff to obtain federal clearances, environmental, utility, right-of-way, and meet federal requirements necessary to obligate the project and receive authorization to begin the construction phase

The Project Assessment for 7th Avenue from Southern Avenue to Broadway Road, including the

15% Conceptual Plans and other information are available for download at:

https://www.phoenix.gov/administration/departments/streets/initiatives/projects-studies/7thAve-

Southern-Broadway.html

The Project Assessment includes a recommended alternative, the City has decided to pursue a design that meets the recommendations outlined by Alternative 2.

Use of UNIFIER, an Application Service Provider (ASP) web-based project management database, may be required. The following information provides a guideline for utilization. Any questions related to the requirements of UNIFIER should be directed to the Project Manager.

• The Consultant will be required to maintain all project records in electronic format.

• The City provides an ASP web-based project management database which the Consultant will be required to utilize in the fulfillment of the contract requirements.

• The Consultant shall provide a computerized networked office platform with broadband internet connectivity.

• UNIFIER training will be provided through the City of Phoenix to firms under contract.

Pre-Submittal Meeting

A pre-submittal meeting will be held at 9:00 am, Phoenix time on Friday, November 20, 2026, at

Gecko Conference Room, 1034 E Madison St Phoenix, AZ 85034 AND via Teams. At this meeting, City staff will discuss the scope of work, general project requirements, and respond to questions from the attendees. It is strongly recommended that interested firms attend the pre-submittal meeting. Inquiries regarding the project scope outside of this pre-submittal meeting must be directed to the Contracts Specialist.

Pre-Submittal Meeting Teams Information:

Microsoft Teams meeting

Join: https://teams.microsoft.com/meet/244308119256231?p=rviyz96KR33bJUkVLX https://www.phoenix.gov/administration/departments/streets/initiatives/projects-studies/7thAve-Southern-Broadway.html https://www.phoenix.gov/administration/departments/streets/initiatives/projects-studies/7thAve-Southern-Broadway.html https://teams.microsoft.com/meet/244308119256231?p=rviyz96KR33bJUkVLX

Page | 4

Meeting ID: 244 308 119 256 231

Passcode: EB2oQ7WH

Statement of Qualifications Evaluation Criteria

A firm will be selected through a qualifications-based selection process based on the criteria below. Subcriteria are listed in order of importance in relation to project services. City of Phoenix project experience is not required.

No. Evaluation Criteria Scoring Method Weight (Points)

1. Design Experience of the Prime

Firm

Describe the experience and qualifications of the prime firm in providing design services for at least three similar projects in the past 5 years. Identify projects the submitting firm has completed. For each project listed, provide:

A. Description of the project including scope and project owner

B. Role of the firm and explain how this relates to the services being solicited

C. Project’s original contract value, final contract value, and reason for variance

D. Project’s start date and completion date

Points Based 225

(22% of Total)

Page | 5

2. Design Experience of the Key

Personnel and Subconsultants

Describe the experience and qualifications of the specific project team expected to be assigned to this project in providing design services for similar projects. For each key person identified, list their length of time with the firm. List each key person’s role in the projects provided. If a project selected for a key person is the same as one selected for the firm, provide just the project name and the role of the key person. For each project listed, provide:

A. Description of the project including scope and project owner

B. Role of the team or team member and explain how this relates to the services being solicited

C. Project’s original contract value, final contract value, and reason for variance

D. Project’s start date and completion date

Points Based 225

(22% of Total)

Page | 6

3. Project Understanding and

Approach

Describe your firm’s understanding of the City’s need for this project, including important considerations such as project issues and challenges. Describe the team’s approach to the project, including important considerations such as scope, schedule, and budget.

A. The project must be federally reviewed and obligated prior to May 2029.

Provide a detailed schedule to show how the Consultant intends to complete design and obligate this project by the deadline. Provide the project critical path and a discussion of what elements might prevent the project from meeting the deadline;

include potential solutions to keep the project on schedule.

B. Describe the firm’s approach to expediting the project delivery to meet the obligation deadline.

C. Describe the team’s approach to handling conflicting interests and comments from multiple stakeholders. Describe the process the team will take to arrive at a solution in an effective and efficient manner

D. The PA has identified potential right-of-way

Points Based 425

(41.6% of Total)

Page | 7

(ROW) impacts to various parcels, describe the team’s approach to address and mitigate ROW impacts.

4. Staffing Information for Key

Personnel

Provide the following:

A. Team’s availability and commitment to the project, including subconsultants

B. Team’s plan to maintain continuity of the proposed services

C. Organization chart showing key personnel, current professional licenses or certifications, and assigned roles for both Design and

Construction Administration and Inspection Services for the project

D. Identify the location of the lead firm’s principal office and the home office location of key staff on this project.

Points Based 125

(12.2% of Total)

5. Reference Checks

Use the form provided in the

Attachments section to obtain at least three references. It is preferred no more than one be a City of

Phoenix project. If your firm has not completed prior projects with other agencies, you will not be penalized.

It is recommended there be references outside the City of

Phoenix.

*These points are in addition to the

(1,000) points for the SOQ.

Points Based 21

(2.1% of Total)

Page | 8

Submittal Requirements

Electronic Submittal Process: Firms interested in this project must submit a Statement of

Qualifications (SOQ) electronically through the City's Procurement Portal at https://procurement.opengov.com/portal/phoenix.

Submittal requirements are as follows:

Vendor Information: All firms must be registered in the City’s Vendor Management System prior to submitting a proposal. The vendor number should be included on the cover of the

SOQ. Information on how to register with the City is available at:

https://www.phoenix.gov/financesite/Pages/EProc-help.aspx

If your firm is already registered with the City of Phoenix’s Procurement system, please visit https://procurement.opengov.com/portal/phoenix to login and access the electronic solicitation.

Submittals:

• Submit only one SOQ electronically, in .PDF format only, addressing all evaluation criteria. No hard copies will be accepted.

• Clearly display the firm legal name, vendor number, project title, and project number on the cover of the SOQ.

• A maximum of 12 pages is permitted to address all content in the SOQ submittal.

(Maximum page limit includes evaluation criteria and all additional content. It does not include information sheet.)

• Submit electronically the Statement of Qualifications by 12:00 pm, Phoenix time, on

Friday, December 11, 2026.

• Page size must meet requirements of 8½” x 11”.

• Font size must not be less than 10 point.

• Content count:

o Each side of a page containing evaluation criteria and additional content will be counted toward the maximum page limit noted above.

o Pages that have project photos, charts and/or graphs will be counted towards the maximum page limit noted above.

o Front and back covers, information sheet, Table of Contents pages, and divider (tab) pages will NOT be counted toward the maximum page limit noted above, unless they include evaluation criteria and additional content that could be considered by the selection panel.

Information Sheet: Provide an information sheet that includes project title, OpenGov ID number, legal firm name (not a trade name), address, phone number, vendor number, and the https://procurement.opengov.com/portal/phoenix https://www.phoenix.gov/financesite/Pages/EProc-help.aspx https://procurement.opengov.com/portal/phoenix

Page | 9 name, title, email address and signature of your contact person for the project. Do not include any additional information.

Evaluation Criteria: Address the SOQ evaluation criteria.

Note: All pages exceeding the specified maximum page limit will be removed from the submittal and not considered in evaluating a submitted SOQ.

Grounds for Disqualification

Please be advised that the following will be grounds for disqualification, and will be strictly enforced:

• Submitting a Statement of Qualifications for a different project.

• Violating the “Contact with City Employees” policy contained in this RFQ.

Selection Process and Schedule

Interested teams will submit a Statement of Qualifications (SOQ). The team will be selected through a qualifications-based selection process. A Selection Panel will evaluate each SOQ per the criteria set forth in Section 5 above.

The City will select a team based on the SOQ’s received; no formal interviews will be conducted.

The City may conduct a due diligence review on the team receiving the highest evaluation.

The City expects to create a final list of at least one, but not more than three teams for this project.

The City will enter into negotiations with the selected team and execute a contract upon completion of negotiation of fees and contract terms for City Council approval.

The following tentative schedule has been prepared for this project.

Pre-submittal Meeting 9:00 am on Friday, November 20, Last Date for Questions 4:00 pm on Wednesday, November 25, 2026

SOQ's Due 12:00 pm on Friday, December

11, 2026

Selection Notification Early January 2027

Scope Meeting Mid January 2027

If the City is unsuccessful in negotiating a contract with the best-qualified team, the City may then negotiate with the next most qualified team until a contract is executed, or the City may decide to terminate the selection process. Once a contract is executed with the successful firm, the procurement is complete.

Page | 10 https://procurement.opengov.com/portal/phoenix

The firm selected for this project will be notified directly by the City. Notification to all other firms on the status of a short list for this project will be posted on the City of Phoenix’s Procurement

Portal:

https://procurement.opengov.com/portal/phoenix

General Information

Citywide Capital Improvement Projects. Consulting and contractor services supporting the

City’s Capital Improvement Projects are procured under the authority of the City Engineer, currently located within the Street Transportation Department. Design and Construction

Procurement coordinates the citywide consulting and construction contracting procurement processes.

Changes to Request for Qualifications. Any changes to this Request for Qualifications

(RFQ) will be in the form of a Notification. The City of Phoenix shall not be held responsible for any oral instructions. Notifications are available on both the Current Opportunities and City's eProcurement Portal at https://procurement.opengov.com/portal/phoenix.

It shall be the responsibility of the registered RFQ holder to determine, prior to the submittal of the Statement of Qualifications, if a Notification has been issued. Registered

RFQ holders may refer to the web page or call Angela Aguilar Sanchez (602) 495-7065 to ascertain if a Notification has been issued for this project.

Alternate Format. For more information or a copy of this publication in an alternate format, contact the Contracts Specialist (listed above) - Voice or TTY 711. Requests will only be honored if made within the first week of the advertising period.

Release of Project Information/Public Records Request. The City shall provide the release of all public information concerning the project, including selection announcements and contract awards. Those desiring to release information to the public must receive prior written approval from the City. To submit a Public Records Request, visit phoenix.gov/prr.

City Rights. The City of Phoenix reserves the right to reject any or all Statements of

Qualifications, to waive any informality or irregularity in any Statement of Qualifications received, and to be the sole judge of the merits of the respective Statements of Qualifications received.

Contact with City Employees. This policy is intended to create a level playing field for all

Proposers, assure that contracts are awarded in public, and protect the integrity of the selection process. OFFERORS THAT VIOLATE THIS POLICY WILL BE DISQUALIFIED.

Beginning on the date the RFQ is issued and until the date the contract is awarded or the RFQ withdrawn, all persons or entities that respond to the RFQ, including their authorized employees, agents, representatives, proposed partner(s), subcontractor(s), joint venture(s), member(s), or any of their lobbyists or attorneys (collectively the Proposer), will refrain from any direct or indirect contact with any person (other than the designated Contract Specialist) who may play a part in the selection process, including members of the evaluation panel, the City Manager, Assistant

City Manager, Deputy City Managers, Department heads, the Mayor and other members of the

Phoenix City Council. As long as the RFQ solicitation is not discussed, Proposers may continue https://procurement.opengov.com/portal/phoenix https://procurement.opengov.com/portal/phoenix https://procurement.opengov.com/portal/phoenix https://phoenix.gov/prr

Page | 11 to conduct business with the City and discuss business that is unrelated to this RFQ solicitation with City staff.

Commencing on the date and time a solicitation is published, potential or actual proposers

(including their representatives) will only discuss matters associated with the solicitation with the

Mayor, any members of City Council, the City Manager, any Deputy City Manager, or any department director directly associated with the solicitation (including in each case their assigned staff, except for the designated procurement officer) at a public meeting, posted under the Arizona

Revised Statutes, until the resulting contract(s) are awarded or all offers or responses are rejected and the solicitation is cancelled without any announcement by the procurement officer of the City’s intent to reissue the same or a similar solicitation.

Proposers may discuss their proposal or the RFQ solicitation with the Mayor or one or more members of the Phoenix City Council, provided such meetings are scheduled through the

Contract Specialist (listed above), conducted in person at 200 W. Washington, Phoenix, Arizona

85003, and are posted as open meetings with the City Clerk at least twenty-four (24) hours prior to the scheduled meetings. The City Clerk will be responsible for posting the meetings. The posted notice shall identify the participants and the subject matter, as well as invite the public to participate.

Conflict of Interest. The City reserves the right to disqualify any Proposer on the basis of any real or apparent conflict of interest that is disclosed by the proposal submitted or any other data available to the City. This disqualification is at the sole discretion of the City. Any Proposer submitting a proposal herein waves any right to object now or at any future time, before any body or agency, including but not limited to, the City Council of the City of Phoenix or any court.

Protest Procedures. Firms responding to disqualification or a procurement outcome are referred to the Code of the City of Phoenix Chapter 2, Article XII, Section 2-187 to 2-190.4, which governs protest procedures utilized throughout the selection process. The procedures may be reviewed through the City of Phoenix website at:

http://www.codepublishing.com/az/phoenix/

A copy of the Protest Policy is also available online at:

https://www.phoenix.gov/administration/departments/streets/careers/business-opportunities.html

Questions - Questions pertaining to this selection process or contract issues should be submitted via the Procurement Portal.

Vendor Questionnaire

*Response required http://www.codepublishing.com/az/phoenix/ https://www.phoenix.gov/administration/departments/streets/careers/business-opportunities.html

REQUEST FOR QUALIFICATIONS
Project Description
Scope of Work
Pre-Submittal Meeting
Statement of Qualifications Evaluation Criteria
Submittal Requirements
Grounds for Disqualification
Selection Process and Schedule
General Information
Vendor Questionnaire

File details come from the government source that posted it. Updated .