Responses for Questions Received After Pre-Proposal Telecon 2.doc
DOC document 29 KB Posted
- Solicitation number
- 7TF-09-0004
- Issued by
-
GSA Federal Acquisition Service
About this file
Responses for Questions Received After Pre-Proposal Telecon 2
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 04 -SF 30.pdf | ||
| Amendment 03 -SF 30.pdf | ||
| 7TF-09-0004 Section B - Price Schedules- 090826.xls | XLS spreadsheet | |
| Responses for Questions Received After Pre-Proposal Telecon.doc | DOC document | |
| Amendment 02 -SF 30.pdf | ||
| LSA-2 Pre-proposal Telecon Notes 090819.doc | DOC document | |
| Amendment 01 to 7TF-09-0004.pdf | ||
| 7TF-09-0004 Section B - Price Schedules.xls | XLS spreadsheet | |
| 7TF-09-0004 Sections B thru M.doc | DOC document | |
| 7TF-09-0004 SF-33 p 2 of 2.doc | DOC document | |
| 7TF-09-0004 SF-33 p 1 of 2.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS RELATED TO LOCAL SERVICES REQUISITION – 2 (LSA-2)
Please note, this question was received following the posting of the notes on FedBizOpps. The question and response posted were based on a previous post Pre-Proposal Teleconference question. The responses below serve as clarification. These questions with responses are included in the notes posted on FedBizOpps.
Previous Question
If the contractor wanted to propose new products due to the emerging technologies, how could they do it and still be in compliance with Section C.2, Service Platform outlined in the solicitation? The clause states, “the services offered shall be such as to obviate the need for the Government to purchase common service customer premise equipment.” With such new technology/products additional equipment is required to ensure complete functionality.
RESPONSE: This procurement, as with others in the past, is to meet current requirements. As new requirements have come along, the contracts have been modified to meet these requirements.
However, one thing GSA has always been mindful of is cost. With the limits on budgets received by GSA customers, how would new technologies be purchased within a budget year? Changing to new technologies often incurs a “capital investment” which almost always exceeds a single year’s budget. Agencies cannot obligate funds not yet approved, i.e. the budget for a future year(s). A good technology example may be VOIP. Most of the technologies offered for business involve the procurement of expensive CPE as well as transition charges and monthly recurring costs. A single annual budget would not cover the cost to transition. And, as far as VOIP, Region 7 would need approval to include it in a Regional service procurement.
Clarification Question
Does the answer to the question below mean that it is okay for a vendor to include VOIP in their response, however before a customer can procure it, GSA Region 7 would have to gain approval?
RESPONSE: VOIP will not be part of the LSA-2 award and should not be included in the offer because of the reasons in the previous response.
Clarification Question
Upon review of the revised pricing document it was found that revised pricing spreadsheet B.7.2.13.TX did not include the product or CLIN codes like the ones for OK and AR. It just shows "# Lines" and PRI. What we do not know is the type of line e.g. analog business line or Centrex line. Would it be possible for GSA to provide the revised spreadsheet with the appropriate information?
RESPONSE: "Unhide" the columns in the revised worksheet.
Clarification Question
To allow adequate time for the vendors to complete the pricing, would GSA consider at least a two week or longer extension?
RESPONSE: In accordance with amendment 03 to solicitation 7TF-09-0004, an extension until 4:30pm central standard time, Monday, October 5, 2009 is approved.