This is a Fiscal Year 2024-2026 Bipartisan Infrastructure Law (BIL) Work Plan and Long-Term Plan document prepared by the Coastal & Heartland National Estuary Partnership (CHNEP), a cooperative decision-making entity comprised of federal agencies, state departments, regional planning councils, water management districts, universities, and local governments across a 5,416-square-mile area in Southwest Florida. The work plan outlines how CHNEP will expend approximately $2.73 million in EPA BIL funding ($909,800 annually for three years) to implement projects addressing climate resilience, water quality, habitat restoration, and environmental justice through fiscal years 2024-2026. Primary deliverables include six county-level Comprehensive Vulnerability Assessments (DeSoto, Hardee, Manatee, Sarasota, Glades, and Hendry Counties) totaling $1.2 million, maintenance and improvements to the CHNEP Water Atlas data management system ($285,000), staff travel ($30,000), and undetermined restoration and research projects ($1,214,400). The work plan establishes management structure through the Policy Committee, Management Committee, and Technical Advisory Committee, with monthly meetings and ongoing partner coordination required throughout the implementation period. No specific contract award date, site visits, or bidder conferences are identified in this planning document; rather, it represents CHNEP's internal allocation strategy for federal funds already received.
The $2,729,400 total budget is fully funded by EPA through the Bipartisan Infrastructure Law with no local matching funds required, though some projects indicate supplementary local funding may be provided. All projects prioritize alignment with CHNEP's 2019 Comprehensive Conservation and Management Plan and specifically target BIL priorities including tackling climate change through ecosystem restoration, resilience adaptation, and advancing environmental justice with a requirement that at least 40 percent of FY24-26 funding benefits disadvantaged communities. County vulnerability assessments will incorporate new elevation data, updated sea level rise projections, stormwater management analysis, and social vulnerability indices to develop Adaptation Action Areas meeting Florida Statutory requirements and positioning counties for additional state funding. The Water Atlas improvements include new Lake Okeechobee waterbody pages, basin-level summaries, enhanced climate change data integration, and real-time data incorporation from partner monitoring networks. Restoration and research project funding remains flexible and performance-based, with selection criteria requiring projects to address CCMP priority actions, include long-term conservation assurances, demonstrate public education components, and provide transferable restoration methodologies.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
FISCAL YEAR 2024-2026 BIPARTISAN INFRASTRUCTURE LAW
WORK PLAN AND LONG-TERM PLAN
Sunset views from the BIL-funded Tiki Point living shoreline project site in Punta Gorda. / Photo credit: Rhonda Paprocki
May 25, 2023
1050 Loveland Blvd.
Port Charlotte, FL 33980
(941) 833-6580 www.CHNEP.org
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 2 of 30
The Coastal & Heartland National Estuary Partnership (CHNEP) is comprised of citizens, elected officials, resource managers and commercial and recreational resource users working to improve water quality and ecological integrity of other natural resources in its boundaries. A cooperative decision-making process is used to address diverse resource management concerns in its 5,416-square-mile area.
Many of these partners also financially support the Partnership. The governmental entities in the CHNEP and its service area include:
U.S. Environmental Protection Agency
U.S. Fish & Wildlife Service
U.S. Army Corps of Engineers
U.S. Geological Survey
U.S. Department of Agriculture
National Oceanic & Atmospheric Administration
Florida Department of Environmental Protection
Florida Fish & Wildlife Conservation Commission
Florida Department of Economic Opportunity
Florida Department of Agriculture
Central Florida Regional Planning Council
Southwest Florida Regional Planning Council
Southwest Florida Water Management District
South Florida Water Management District
West Coast Inland Navigation District
Peace River/Manasota Regional Water Supply Authority
Florida Gulf Coast University
University of South Florida
University of Florida
Polk, Sarasota, Manatee, Lee, Charlotte, DeSoto, Hardee, Hendry, Highlands, and Glades Counties and the incorporated Cities and Towns of Dundee, Haines City, Auburndale, Lake Alfred, Lake Wales, Lake Hamilton, Lakeland, Winter Haven, Eagle Lake, Bartow, Fort Meade, Bowling Green, Wauchula, Zolfo Springs, Arcadia, Venice, North Port, Punta Gorda, Fort Myers, Fort Myers Beach, Cape Coral, Sanibel, Estero, LaBelle, Moore Haven, and Clewiston.
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 3 of 30
TABLE OF CONTENTS
BIPARTISAN INFRASTRUCTURE FUNDING FOR THE CHNEP
CCMP FOCUS IN FY2024-FY2026
FISCAL YEAR 2024, 2025 and 2026 ANNUAL BUDGET
Table 1: Fiscal Year 2024, 2025 and 2026 BIL Budget Overview
Table 2: Fiscal Year 2024 Travel Budget
CHNEP BIL FUNDED WORK PLAN TASKS
Task 1 Management Conference: Administration, Finance, Operations
Task 3 Research Coordination
Task 3.2 CHNEP Water Atlas
Task 3.7 DeSoto County Comprehensive Vulnerability Assessment
Task 3.8 Hardee County Comprehensive Vulnerability Assessment
Task 3.9 Manatee County Comprehensive Vulnerability Assessment
Task 3.10 Sarasota County Comprehensive Vulnerability Assessment
Task 3.11 Glades County Comprehensive Vulnerability Assessment
Task 3.12 Hendry County Comprehensive Vulnerability Assessment
Task 4 Watershed Coordination
Task 4.5 Restoration/Research TBD Projects
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 4 of 30
COASTAL & HEARTLAND NATIONAL ESTUARY PARTNERSHIP
Policy Committee
Mr. Brian Smith, Co-Chair Ms. Jennifer Carpenter, Co-Chair
US Environmental Protection Agency, Region 4 Florida Department of Environmental Protection
Hon. Sandy Meeks
Hardee County
Hon. Emory Howard
Hendry County
Hon. Scott Kirouac
Highlands County
Hon. Ray Sandelli
Lee County
Hon. James Satcher
Manatee County
Hon. Bill Braswell
Polk County
Hon. Mark Smith
Sarasota County
Hon. Ken Doherty
Charlotte County
Hon. Ashley Coone
Desoto County
Hon. Tony Whidden
Glades County
Hon. Robert Heine, Jr.
City of Arcadia
Hon. Steve Githens
City of Bartow
Hon. Jessica Cosden
City of Cape Coral
Hon. Fred Burson
City of Fort Myers
Hon. Bill Veach
Town of Fort Myers Beach
Hon. Bill Read
City of Lakeland
Hon. Alice White
City of North Port
Hon. Donna Peterman
City of Punta Gorda
Hon. Mike Miller
City of Sanibel
Hon. Steve Hickox
Desoto County
Hon. Nicolas Pachota
City of Venice
Mr. M. J. Carnevale
City of Winter Haven
Hon. Katy Errington
Village of Estero
Hon. Barbara Arnold
City of Fort Meade
Ms. Allie McCue
Florida Fish & Wildlife Conservation Commission
Mr. Chauncey Goss
South Florida Water Management District
Ms. Margaret Wuerstle
Southwest Florida Regional Planning Council
Mr. Jack Bispham
Southwest Florida Water Management District
Mr. Don McCormick
Southwest Florida Regional Planning Council
Ms. Jennifer Codo-Salisbury
Central Florida Regional Planning Council
Management Committee Co-Chairs Ms. Claire Jubb & Mr. David Hutchinson
Technical Advisory Committee Co-Chairs Mr. Ernesto Lasso de La Vega & Mr. Mark Walton
Citizens Advisory Committee Co-Chairs Mr. Harry Phillips & Ms. Debi Osborne
CHNEP Executive Director Ms. Jennifer Hecker
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 5 of 30
BIPARTISAN INFRASTRUCTURE FUNDING FOR THE CHNEP
On November 15, 2021, President Biden signed the Bipartisan Infrastructure Law (P.L. 117-58), also known as the “Infrastructure Investment and Jobs Act of 2021” (IIJA) or “BIL.” The law’s investment in water is nothing short of transformational. It includes $50 billion to the U.S. Environmental Protection Agency
(EPA) for water infrastructure, the single largest investment in water that the federal government has ever made. The BIL provides $132 million in funding for the 28 longstanding National Estuary Programs (NEPs) for fiscal years 2022 through 2026. This funding is being evenly distributed to the NEPs, annually providing each with approximately $909,800 in BIL funds. Importantly, NEP BIL funds are available until expended.
On July 26th, EPA issued a NEP BIL Funding Implementation Memorandum (memorandum), which applies to funding provided under the BIL and provides guidance on uses of funds, timeframes, how to award the funds, and tracking and reporting requirements. The memorandum describes the process for FY 2022 – FY
2026 BIL funds and may be supplemented by additional implementation memoranda as needed. Unless otherwise noted in this document, the FY 2021 – FY 2024 Clean Water Act §320 National Estuary Program
Funding Guidance also applies to BIL funding. It outlines the core goals of BIL funding are to:
1) “Tackle the Climate Crisis” by reducing emissions that cause climate change and accelerating resilience and adaptation to climate change impacts; and
2) “Take Decisive Action to Advance Environmental Justice and Civil Rights” by promoting EJ and protecting civil rights at the federal, state, and local levels.
As such, it states that NEP projects funded through BIL should seek to: (1) Accelerate and more extensively implement CCMPs, (2) Ensure that benefits reach disadvantaged communities – including that at least 40% of the BIL funding goes to projects benefitting such communities in FY24-26, and (3) Build the adaptive capacity of ecosystems and communities – including addressing climate change and using green and nature-based solutions to enhance resiliency.
It goes on to state that where possible and aligned with the priorities identified in their Comprehensive
Conservation and Management Plans (CCMPs), NEPs should engage and educate the public and private sectors on key climate-related vulnerabilities and solutions and provide technical and financial assistance to accelerate progress in response to a changing climate. NEPs should elevate climate efforts through BIL implementation including, but not limited to:
➢ Assessment and planning projects that involve climate change vulnerability assessments, community resilience and adaptation plans, or hazard mitigation plans
➢ Restoration, water infrastructure, green infrastructure, stormwater management, and nonpoint source projects that prioritize innovative climate adaptation, hazard mitigation, and resilience solutions
➢ Projects focused on climate-related research, including those that measure, monitor, and increase carbon sequestration
➢ Projects focused on climate-related outreach and education
As with annual appropriations distributed to NEPs to implement CWA §320, the funds distributed under the
BIL must implement the management conference and EPA-approved CCMP and Work Plan. Therefore, the
CHNEP is required to put forth a BIL Work Plan and Budget for each year - with CHNEP being allowed to combine the last three years (FY24-FY26). Due to the long-term nature of BIL funding, each NEP is also required to develop a BIL Long-Term Plan to submit no later than June 1, 2023.
Accordingly, CHNEP has drafted this BIL FY24-FY26 Work Plan and Long-Term Plan to outline how it plans to expend the last three years of Bipartisan Infrastructure Law funding to further resiliency in the
CHNEP area, including addressing climate-related factors that affect improving water quality, restoring hydrology, protecting fish, wildlife and their habitat and increasing public engagement as outlined in the four action plans in the 2019 CHNEP CCMP.
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 6 of 30
CCMP FOCUS IN FY2024-FY2026
The Fiscal Year 2024-2026 BIL Work Plan and Budget reflects the approved 2019 CCMP, which outlines the 5-year organizational strategic plan and has the following visions, goals, objectives, and strategies:
WATER QUALITY
VISION: Waters that meet their designated human uses for drinking, shellfish harvesting, or swimming and fishing, while supporting appropriate and healthy aquatic life.
GOAL: Water Quality Improvement.
OBJECTIVE: Meet or exceed water quality standards for designated uses of natural waterbodies and waterways with no degradation of Outstanding Florida Waters.
STRATEGY: Support comprehensive and coordinated water quality monitoring programs and projects and programs that reduce pollutants entering waterways.
WQ-1: Support a comprehensive and coordinated water quality monitoring and assessment strategy
▪ CHNEP will continue working with partners to collect water quality monitoring data and uploading it to the CHNEP Water Atlas for access by interested parties and the public.
▪ CHNEP will work with our partners to develop new information pages on the Water Atlas as needed.
▪ CHNEP will continue to fund and support the Coastal Charlotte Harbor Monitoring Network
(CCHMN).
WQ-2: Develop water quality standards, pollutant limits, and clean-up plans
▪ CHNEP will continue to support, providing technical comment as appropriate, the development and implementation of water quality standards, pollutant limits and clean-up plans.
WQ-3: Reduce urban stormwater and agricultural runoff pollution
▪ CHNEP will continue to provide public presentations and information on urban stormwater and agricultural runoff pollution.
▪ CHNEP will continue to support partners in the implementation of stormwater and agricultural runoff reduction projects.
WQ-4: Reduce wastewater pollution
▪ CHNEP will continue to support partners in the implementation of wastewater discharge reduction and reuse projects, as well as septic to sewer conversion projects.
WQ-5: Reduce harmful algae blooms
▪ CHNEP will continue to provide public presentations and information on harmful algae blooms and nutrient pollution, as well as research algae bloom remediation techniques.
HYDROLOGICAL RESTORATION
VISION: Natural freshwater flow across the landscape to the estuaries.
GOAL: Enhanced and improved waterbodies with more natural hydrologic conditions.
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 7 of 30
OBJECTIVE: Adequate aquifer recharge and freshwater volume and timing of flow to support healthy natural systems.
STRATEGY: Support data-driven watershed planning and hydrological restoration projects to preserve or restore natural flow regimes and provide sufficient fresh surface and groundwater to natural systems.
HR-1: Conduct data collection, modeling, and analyses to support hydrologic restoration
▪ CHNEP will continue to actively participate in gathering data and supporting modeling and analyses as well as fund integrated ground and surface water models to improve decision-making with regards to hydrological restoration projects. Currently, these include the South Lee County Watershed
Initiative and the Charlotte Harbor Flatwoods Initiative projects.
HR-2: Increase fresh surface water and groundwater availability to support healthy natural systems
▪ CHNEP will continue to promote water conservation and sufficient flows and levels of freshwater to support natural systems.
HR-3: Preserve and restore natural flow regimes
▪ CHNEP will work with partners to identify funding sources to facilitate capital programs that coordinate water storage, flood control, water quality and disaster planning.
▪ CHNEP will continue participating and providing technical assistance in Everglades’ restoration through project review, meeting participation and technical comment.
FISH, WILDLIFE & HABITAT PROTECTION
VISION: A diverse environment of interconnected, healthy habitats that support natural processes and viable, resilient native plant and animal communities.
GOAL: Natural habitat protection and restoration.
OBJECTIVE: Permanently acquire, connect, protect, manage, and restore natural terrestrial and aquatic habitats.
STRATEGY: Promote and facilitate permanent acquisition and effective protection and management of critical natural habitats including wildlife dispersal areas, movement and habitat migration corridors, wetlands, flowways, and environmentally sensitive lands and estuarine habitats.
FW-1: Protect, restore, and monitor estuarine habitats
▪ CHNEP will continue to work with Southwest Florida Estuarine Restoration Team (SWERT) partners on designing, permitting, and constructing seagrass, oyster, and other estuarine restoration projects in CHNEP area.
FW-2: Protect, restore, and monitor environmentally sensitive lands and waterways including critical habitat areas
▪ CHNEP will continue to share the Habitat Restoration Needs report and maps to support the conservation, management and enhancement of environmentally sensitive lands and critical habitat areas necessary for habitat resilience and migration.
▪ CHNEP will continue to offer grants to assist engaged citizens that promote the protection and management of public environmental lands and waterways.
▪ CHNEP will continue to directly engage in funding and project managing habitat restoration projects.
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 8 of 30
FW-3: Assess and promote the benefits of land, waterway, and estuary protection and habitat restoration
▪ CHNEP will continue to use its comprehensive regional Economic Valuation study to promote the economic return on investment from land, water and estuarine protection and restoration investments.
PUBLIC ENGAGEMENT
VISION: An informed, engaged public making choices and taking actions that increase protection and restoration of estuaries and watersheds.
GOAL: Public education and engagement.
OBJECTIVE: Increase the proportion of the population that supports and participates in actions to protect and restore estuaries and watersheds.
STRATEGY: Promote environmental awareness, understanding, and stewardship to the general public, new target audiences, and policymakers; and strengthen non-profit partner collaboration in education and engagement programs.
PE-1: Promote environmental literacy, awareness, and stewardship through expanded education and engagement opportunities for the general public
▪ CHNEP will continue to host routine volunteer events, as well as routinely host and participate in community events to provide environmental education and public engagement opportunities.
▪ CHNEP will continue to produce free educational materials and distribute them throughout the
CHNEP area.
▪ CHNEP will continue to disseminate information about public engagement opportunities through
Constant Contact, on social media, and on the www.chnep.org website.
PE-2: Expand reach of education and engagement opportunities to new target audiences
▪ CHNEP will continue to conduct educational workshops and events, including in underserved communities, as a way to introduce natural resource protection information to new target audiences in that area.
PE-3: Strengthen non-profit partner collaboration in education and engagement programs
▪ CHNEP will continue to administer a Conservation Grant program to foster community natural resource protection projects and initiatives that support CCMP implementation, including with non-profit partners.
▪ CHNEP will continue to seek and work with non-profit organizations on collaborative initiatives.
▪ CHNEP will continue to sponsor events that foster non-profit partner collaboration to educate and engage the public on issues relating to CCMP implementation.
PE-4: Increase outreach to policymakers to enhance understanding and support for CCMP implementation
▪ CHNEP will continue to meet and send information to local, state, and federal policymakers, explaining CHNEP’s role in supporting CCMP implementation.
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 9 of 30
FISCAL YEAR 2024, 2025 and 2026 ANNUAL BUDGET
Table 1: Fiscal Year 2024, 2025 and 2026 BIL Budget Overview
Revenue
Federal (EPA FY24 Bipartisan Infrastructure Law (BIL) Funding) $ 909,800
Federal (EPA FY25 Bipartisan Infrastructure Law (BIL) Funding) $ 909,800
Federal (EPA FY26 Bipartisan Infrastructure Law (BIL) Funding) $ 909,800
Total Revenue $ 2,729,400
Expenditures
Desoto County Comprehensive Vulnerability Assessment $ 200,000
Hardee County Comprehensive Vulnerability Assessment $ 200,000
Manatee County Comprehensive Vulnerability Assessment $ 200,000
Sarasota County Comprehensive Vulnerability Assessment $ 200,000
Glades County Comprehensive Vulnerability Assessment $ 200,000
Hendry County Comprehensive Vulnerability Assessment $ 200,000
CHNEP Water Atlas Maintenance & Improvements $ 285,000
Travel $ 30,000
Restoration Project(s) TBD $ 1,214,400
Total Expenditures $2,729,400
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 10 of 30
Table 2: Fiscal Year 2024 Travel Budget
Date Purpose
Staff Location
Length of Stay
Travel
Mode Reg. Fee
Estimated
Cost
October
RAE Living Shorelines Tech
Workshop 1 Galveston, TX 3 Air $ 150 $ 950
October
Grant Management Boot
Camp 1 Orlando, FL 3 Auto $ 500 $ 750
Nov. 2023 Coastal Estuarine Research
Federation Meeting 2 Portland, OR 5 Air $ 595 $ 3,900
Jan. 2024 Everglades Coalition 1 Coral Springs, FL 4 Auto $ 0 $ 1,300
Feb. 2024 American Water Resources 4 Fort Myers, FL N/A Auto $ 300 $ 200
Feb. 2024 Gulf of Mexico Conference 4 Tampa, FL 4 Auto $ 1,800 $ 4,000
Mar. 2024 NEP/EPA Spring Mtg. 1 Washington, DC 4 Air $ 300 $ 2,000
April 2024 League of Environmental
Educators in Florida 1 Ocala, Florida 2 Auto $ 150 $ 600
Oct. 2023 -
Sep. 2024
Local Meetings/ Mileage 6 Various Florida
Locations N/A Auto $ 300 $ 7,205
Subtotal $ 4,095 $ 20,905
Total $ 25,000
Note: $10,000 from EPA BIL and $15,000 from EPA 320
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 11 of 30
CHNEP BIL FUNDED WORK PLAN TASKS
The CHNEP projects are organized according to task. There are five tasks, as follows:
Task 1: Management Conference
1.1 Materials and Supplies
Task 2: Public Engagement
2.1 Conservation Grants
2.2 2025 Calendar and 2024 Harbor Happenings Magazines
2.3 Public Engagement Events
2.4 Sponsorships
Task 3: Research Coordination
3.1 Water Quality and Seagrass Monitoring and Mapping Programs
3.2 CHNEP Water Atlas
3.3 Charlotte County Comprehensive Vulnerability Assessment
3.4 Polk County Comprehensive Vulnerability Assessment
3.5 Highlands County Comprehensive Vulnerability Assessment
3.6 Lee County Comprehensive Vulnerability Assessment
3.7 DeSoto County Comprehensive Vulnerability Assessment
3.8 Hardee County Comprehensive Vulnerability Assessment
3.9 Manatee County Comprehensive Vulnerability Assessment
3.10 Sarasota County Comprehensive Vulnerability Assessment
3.11 Glades County Comprehensive Vulnerability Assessment
3.12 Hendry County Comprehensive Vulnerability Assessment
Task 4: Watershed Coordination
4.1 Submerged Aquatic Vegetation Restoration
4.2 Pine Island Flatwoods Preserve Wetland Habitat Enhancement
4.3 Myakka Headwaters Project
4.4 Tiki Point Harborwalk Living Shoreline Pilot Project
4.5 Restoration/Research Project(s) TBD
Task 5: Policymaker Education
5.1 Comprehensive Conservation & Management Plan Updating and Reprinting
Note that only those tasks and projects bolded above are funded with FY24-26 Bipartisan Infrastructure Law funding.
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 12 of 30
Task 1 Management Conference: Administration, Finance, Operations
Objective: Provide committee structure that supports the implementation of the CCMP; support administration of CHNEP; ensure compliance with grant and agreement requirements as awardee and awarder; and seek additional funding support for identified projects.
Description: The CHNEP office provides staff support to the Management Conference, furnishes operations and finance support, ensures compliance with Host Agency procedures, secures funding from partners, and assists partners seeking grants and contracts to implement the CCMP.
CCMP Elements Implemented: All
Outputs/Deliverables
▪ Management Conference committee meetings for 4 committees, 3x/yr.
▪ Management Conference adoption of Annual Work Plan before June 1, 2023
▪ GPRA Reporting through EPA’s NEPORT, by September 14, 2023
Milestones
▪ Administration of Program Office operations and finances, ongoing
▪ Collaborate with partners on CCMP implementation, ongoing
▪ Compliance with Host Agency finance and procurement requirements, ongoing
▪ Compliance with Funders’ grant reporting requirements, ongoing
FY 24 Budget
EPA 320 Funds (FY24):
Personnel (Salaries & Benefits) $538,810
Staff Travel $ 15,000
Overhead Host Administrative Fees $184,869
Communications Software and Fees $ 9,000
EPA BIL (FY24):
Staff Travel $ 10,000
SWFWMD
Personnel (Salaries & Benefits) $ 56,000
FDEP
Personnel (Salaries & Benefits) $ 75,000
Note: Total personnel costs are $669,810
Local:
Meeting Support $ 7,000
Task 1 Total Budget $ 895,679
Note: $10,000 per year travel funded through BIL in FY25 and FY26 as well (for a total of
$30,000 of FY24-FY26 BIL funding)
Outcomes
▪ Fully informed and engaged CHNEP Management Conference
▪ Other federal, state, and non-profit grants obtained to funding CCMP implementation
▪ Increased participation, understanding and support of NEP mission by partners
▪ Continued commitment from partners to fund CHNEP and CCMP activities
▪ Funding opportunities and assistance provided to partners to implement initiatives and projects that further CCMP implementation
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 13 of 30
Estimated Timeline: FY24-FY26
Task 3 Research Coordination
Work Plan Objective: To ensure collection, reporting and access to consistent region-wide, technically sound water quality and biological data throughout the CHNEP area. To identify and resolve gaps in scientific data and address emerging research needs through partnerships and innovative research.
Description: CHNEP coordinates some water quality sampling as well as works with partners to identify and resolve gaps in water quality and biological data, specifically through refinements to the Monitoring
Strategy. In addition, CHNEP assists partners with compiling, analyzing, mapping, and conveying complex technical information in an understandable manner so it can be used to implement effective resource protection and restoration projects. The resulting data is used to assess resource status and trends, to be incorporated into resource management plans.
CCMP Elements Implemented: WQ-1, WQ-2, HR-1, FW-2, and PE-1.
Partners and Roles: outlined below in the respective subtasks
Outputs/Deliverables, Milestones
▪ CHNEP Water Atlas: Review and assess uploaded water quality sampling data
▪ Water Quality Monitoring: Monthly water quality data, quarterly RAMP participation, and CCHMN annual field audits and meetings
▪ Seagrass Monitoring: Annual seagrass data
▪ Seagrass Aerial Mapping: Biennial and 6-year seagrass aerial mapping
▪ Data Management: Biannual up-dates of water quality data
▪ Data Access: Ongoing access to water quality data, graphing and analyses and response to data requests
▪ Data Analysis and Use: Annual up-dates of water quality contour maps and, and periodic refinement of Research Needs Inventory and environmental indicators
FY 24 Budget
EPA 320 Funds: Staff Time
FDEP Funds (Staff Time): Staff Time
SWFWMD Funds (Staff Time): Staff Time
Estimated Total Budget: Staff Time
Outcomes
▪ Consistent region-wide, technically sound water quality and biological data needed to assess resource status, trends, and complex interactions
▪ Public access to water quality and seagrass data to partners via CHNEP Water Atlas
▪ Increased data analyses, maps, and graphs to enhance and evaluate protection and restoration efforts
▪ Increased collaboration of monitoring, mapping and management among resource managers and agencies from throughout the CHNEP Area
▪ Expanded used of data by partners to assess resource conditions, manage resources and implement effective and efficient management programs and restoration projects
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 14 of 30
Task 3.2 CHNEP Water Atlas
Project Objective: To ensure continuing access to technical information from throughout the CHNEP Study
Area to scientists, resource managers and users, elected officials and the public through a user-friendly web-based tool. The resulting data, maps and graphs are easily accessible for use to evaluate resource conditions, answer site and topic specific questions, and convey scientific information in an understandable manner to support effective management programs and restoration projects.
Project Description: CHNEP maintains and enhances the CHNEP Water Atlas, a web-based, data management and mapping system that provides historical information, scientific data, water resource maps, resource management actions, volunteer opportunities and current events from throughout the CHNEP area.
Tools are available to map, analyze and graph data related to specific locations and topics to assists partners with identifying, prioritizing, and implementing projects that address CCMP water quality, habitat, hydrology, and stewardship goals. CHNEP support includes maintenance, improvements, and enhancements of all the CHNEP Water Atlas components, including home page design and database updates. In addition to maintenance, the CHNEP works with USF to make upgrades and improvements on an annual basis. New
Water Atlas Features/Improvements planned for 2024 include:
▪ Lake Okeechobee Waterbody Page: This task is to develop a Lake Okeechobee waterbody page with the updated waterbody page design, linked to the common map that displays GIS layers for the four categories: water quality, habitat, hydrology, and climate change. The focus of the additions will be water quality (nutrients and salinity) and cyanobacteria (if available), as well as the ecological impacts to the Caloosahatchee Watershed of freshwater releases from Lake Okeechobee (shown in the Estuary Tracker). The Lake Okeechobee & Caloosahatchee Estuary Tracker will be incorporated into the page above the Water Quality section of the page.
▪ Improvements to Basin Pages: This task is to enhance the existing Basin pages to include summary information at the basin-level for water quality and hydrology, highlighted links to featured CHNEP projects, and a new “Climate Change” category in the Related Information section.
▪ Adding Real-Time Data Collected by Partners onto the CHNEP Water Atlas Real-Time Data
Mapper: This task is to pull in the Sanibel -Captiva Conservation Foundation (SCCF) River, Estuary and Coastal Observing Network (RECON) Data onto Real-Time Data Mapper.
CCMP Elements Implemented: WQ-1, WQ-2, HR-1, FW-1, FW-2, FW-3, PE-1, and PE-3.
Partners and Roles: All entities creating publicly accessible water quality data
Outputs/Deliverables Milestones:
▪ Post and provide access to water quality data updates every 6 months
▪ Post and provide access to data analyses, maps and graphs as requested
▪ Annual Update of WBID Boundaries and NNC Values
▪ Conducting trend analysis on water quality data annually and providing in user friendly format
▪ Conducting analysis on seagrass and macroalgae data annually and providing in user friendly format
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 15 of 30
FY 24 Budget:
EPA BIL FY23 Funds: $95,000
Total Budget: $95,000 + Staff Time
Note: $95,000 per year Water Atlas funded through BIL in FY25 and FY26 as well, for a total of
$285,000 of FY24-26 BIL funding.
▪ Data publicly provided to public and resource managers to assess effectiveness of protection and restoration efforts
▪ Increased coordination on sampling and monitoring efforts amongst resource managers and agencies in the CHNEP area
BIL Priorities Supported:
1) Tackle the Climate Crisis” by reducing emissions that cause climate change and accelerating resilience and adaptation to climate change impacts through providing the public all accessible climate change data for the region in one place where they can readily view and utilize.
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 16 of 30
Task 3.7 DeSoto County Comprehensive Vulnerability Assessment
Project Objective: To identify local climate change impacts and vulnerabilities and present adaptation responses that can help reduce community vulnerability and/or increase resilience in DeSoto County, Florida.
Project Description: This project will use the climate adaptation planning process to conduct public workshops and data analysis to identify pre-existing conditions and climate stressors, including vulnerability modeling to develop recommended Adaptation Action Areas (AAA’s) for DeSoto County. The Consultant will gather and update the County’s vulnerability assessment utilizing new elevation data, updated sea level rise projections, shoreline information, capital project data, social vulnerability index, and stormwater management data. The updated vulnerability modeling with new elevation data will be used to determine infrastructure and habitat impacts as well as areas of increasing vulnerability for a 2030, 2060, and 2100 sea level rise assumption horizon. Using the best available data, the contractor will also incorporate an analysis of stormwater management and social vulnerability using best practices such as the Center for Disease
Control's Social Vulnerability Index or other evaluation strategy (identifying vulnerable populations and potential public health risks).That information and input will be synthesized into a summary of current and projected climate changes for the community. The contractor will then use these vulnerability assessments to develop proposed adaptation strategies. One of the foundational concepts of Fla Stat 380.093 and FEMA’s
CRS program is to assess the flood risk of a community using best available tools, data, and methodologies.
The larger goal of both programs is to capture multiple types of weather-related scenarios to project and model how various flood risks would affect the community. This project will produce a final Climate
Change Vulnerability Assessment for DeSoto County that meets all Florida Statutory requirements. This will qualify DeSoto County to access additional state funding sources.
CCMP Elements Implemented: Potentially all CCMP elements
Partners and Roles: CHNEP (Funder), DeSoto County
Outputs/Deliverables Milestones
▪ Data Collection and Analysis
▪ Vulnerability Modeling and Analysis (including stormwater, social, etc.)
▪ Summary of Current and Project Climate Changes
▪ Summary of Proposed Adaption Strategies and recommended Adaptation Action Areas
FY24 Budget:
EPA FY24 BIL Funds: $ 200,000
Total Budget: $ 200,000 + Staff Time
Outcomes
▪ Climate Change Vulnerability Assessment for DeSoto County that meets state Statutory requirements
BIL Priorities Supported:
1) “Tackle the Climate Crisis” by reducing emissions that cause climate change and accelerating resilience and adaptation to climate change impacts; in assisting restoration of wetlands that act as carbon sinks and restoration of freshwater hydrological flows that can mitigate saltwater intrusion from sea level rise.
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 17 of 30
2) “Take Decisive Action to Advance Environmental Justice and Civil Rights” by promoting EJ and protecting civil rights at the federal, state, and local levels to identify and address additional vulnerabilities that may affect disadvantaged communities in selected County.
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 18 of 30
Task 3.8 Hardee County Comprehensive Vulnerability Assessment
Project Objective: To identify local climate change impacts and vulnerabilities and present adaptation responses that can help reduce community vulnerability and/or increase resilience in Hardee County, Florida.
Project Description: This project will use the climate adaptation planning process to conduct public workshops and data analysis to identify pre-existing conditions and climate stressors, including vulnerability modeling to develop recommended Adaptation Action Areas (AAA’s) for Hardee County. The Consultant will gather and update the County’s vulnerability assessment utilizing new elevation data, updated sea level rise projections, shoreline information, capital project data, social vulnerability index, and stormwater management data. The updated vulnerability modeling with new elevation data will be used to determine infrastructure and habitat impacts as well as areas of increasing vulnerability for a 2030, 2060, and 2100 sea level rise assumption horizon. Using the best available data, the contractor will also incorporate an analysis of stormwater management and social vulnerability using best practices such as the Center for Disease
Control's Social Vulnerability Index or other evaluation strategy (identifying vulnerable populations and potential public health risks).That information and input will be synthesized into a summary of current and projected climate changes for the community. The contractor will then use these vulnerability assessments to develop proposed adaptation strategies. One of the foundational concepts of Fla Stat 380.093 and FEMA’s
CRS program is to assess the flood risk of a community using best available tools, data, and methodologies.
The larger goal of both programs is to capture multiple types of weather-related scenarios to project and model how various flood risks would affect the community. This project will produce a final Climate
Change Vulnerability Assessment for Hardee County that meets all Florida Statutory requirements. This will qualify Hardee County to access additional state funding sources.
CCMP Elements Implemented: Potentially all CCMP elements
Partners and Roles: CHNEP (Funder), Hardee County
Outputs/Deliverables Milestones
▪ Data Collection and Analysis
▪ Vulnerability Modeling and Analysis (including stormwater, social, etc.)
▪ Summary of Current and Project Climate Changes
Outcomes
▪ Climate Change Vulnerability Assessment for Hardee County that meets state Statutory resilience and adaptation to climate change impacts; in assisting restoration of wetlands that act as
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 19 of 30 protecting civil rights at the federal, state, and local levels to identify and address additional
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 20 of 30
Task 3.9 Manatee County Comprehensive Vulnerability Assessment
Project Objective: To identify local climate change impacts and vulnerabilities and present adaptation responses that can help reduce community vulnerability and/or increase resilience in Manatee County, Florida.
Project Description: This project will use the climate adaptation planning process to conduct public workshops and data analysis to identify pre-existing conditions and climate stressors, including vulnerability modeling to develop recommended Adaptation Action Areas (AAA’s) for Manatee County. The Consultant will gather and update the County’s vulnerability assessment utilizing new elevation data, updated sea level rise projections, shoreline information, capital project data, social vulnerability index, and stormwater management data. The updated vulnerability modeling with new elevation data will be used to determine infrastructure and habitat impacts as well as areas of increasing vulnerability for a 2030, 2060, and 2100 sea level rise assumption horizon. Using the best available data, the contractor will also incorporate an analysis of stormwater management and social vulnerability using best practices such as the Center for Disease
Control's Social Vulnerability Index or other evaluation strategy (identifying vulnerable populations and potential public health risks).That information and input will be synthesized into a summary of current and projected climate changes for the community. The contractor will then use these vulnerability assessments to develop proposed adaptation strategies. One of the foundational concepts of Fla Stat 380.093 and FEMA’s
CRS program is to assess the flood risk of a community using best available tools, data, and methodologies.
The larger goal of both programs is to capture multiple types of weather-related scenarios to project and model how various flood risks would affect the community. This project will produce a final Climate
Change Vulnerability Assessment for Manatee County that meets all Florida Statutory requirements. This will qualify Manatee County to access additional state funding sources.
CCMP Elements Implemented: Potentially all CCMP elements
Partners and Roles: CHNEP (Funder), Manatee County
Outputs/Deliverables Milestones
▪ Data Collection and Analysis
▪ Vulnerability Modeling and Analysis (including stormwater, social, etc.)
▪ Summary of Current and Project Climate Changes
Outcomes
▪ Climate Change Vulnerability Assessment for Manatee County that meets state Statutory resilience and adaptation to climate change impacts; in assisting restoration of wetlands that act as
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 21 of 30 protecting civil rights at the federal, state, and local levels to identify and address additional
Estimated Timeline: FY25-FY27
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 22 of 30
Task 3.10 Sarasota County Comprehensive Vulnerability Assessment
Project Objective: To identify local climate change impacts and vulnerabilities and present adaptation responses that can help reduce community vulnerability and/or increase resilience in Sarasota County, Florida.
Project Description: This project will use the climate adaptation planning process to conduct public workshops and data analysis to identify pre-existing conditions and climate stressors, including vulnerability modeling to develop recommended Adaptation Action Areas (AAA’s) for Sarasota County. The Consultant will gather and update the County’s vulnerability assessment utilizing new elevation data, updated sea level rise projections, shoreline information, capital project data, social vulnerability index, and stormwater management data. The updated vulnerability modeling with new elevation data will be used to determine infrastructure and habitat impacts as well as areas of increasing vulnerability for a 2030, 2060, and 2100 sea level rise assumption horizon. Using the best available data, the contractor will also incorporate an analysis of stormwater management and social vulnerability using best practices such as the Center for Disease
Control's Social Vulnerability Index or other evaluation strategy (identifying vulnerable populations and potential public health risks).That information and input will be synthesized into a summary of current and projected climate changes for the community. The contractor will then use these vulnerability assessments to develop proposed adaptation strategies. One of the foundational concepts of Fla Stat 380.093 and FEMA’s
CRS program is to assess the flood risk of a community using best available tools, data, and methodologies.
The larger goal of both programs is to capture multiple types of weather-related scenarios to project and model how various flood risks would affect the community. This project will produce a final Climate
Change Vulnerability Assessment for Sarasota County that meets all Florida Statutory requirements. This will qualify Sarasota County to access additional state funding sources.
CCMP Elements Implemented: Potentially all CCMP elements
Partners and Roles: CHNEP (Funder), Sarasota County
Outputs/Deliverables Milestones
▪ Data Collection and Analysis
▪ Vulnerability Modeling and Analysis (including stormwater, social, etc.)
▪ Summary of Current and Project Climate Changes
Outcomes
▪ Climate Change Vulnerability Assessment for Sarasota County that meets state Statutory resilience and adaptation to climate change impacts; in assisting restoration of wetlands that act as
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 23 of 30 protecting civil rights at the federal, state, and local levels to identify and address additional
Estimated Timeline: FY25-FY27
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 24 of 30
Task 3.11 Glades County Comprehensive Vulnerability Assessment
Project Objective: To identify local climate change impacts and vulnerabilities and present adaptation responses that can help reduce community vulnerability and/or increase resilience in Glades County, Florida.
Project Description: This project will use the climate adaptation planning process to conduct public workshops and data analysis to identify pre-existing conditions and climate stressors, including vulnerability modeling to develop recommended Adaptation Action Areas (AAA’s) for Glades County. The Consultant will gather and update the County’s vulnerability assessment utilizing new elevation data, updated sea level rise projections, shoreline information, capital project data, social vulnerability index, and stormwater management data. The updated vulnerability modeling with new elevation data will be used to determine infrastructure and habitat impacts as well as areas of increasing vulnerability for a 2030, 2060, and 2100 sea level rise assumption horizon. Using the best available data, the contractor will also incorporate an analysis of stormwater management and social vulnerability using best practices such as the Center for Disease
Control's Social Vulnerability Index or other evaluation strategy (identifying vulnerable populations and potential public health risks).That information and input will be synthesized into a summary of current and projected climate changes for the community. The contractor will then use these vulnerability assessments to develop proposed adaptation strategies. One of the foundational concepts of Fla Stat 380.093 and FEMA’s
CRS program is to assess the flood risk of a community using best available tools, data, and methodologies.
The larger goal of both programs is to capture multiple types of weather-related scenarios to project and model how various flood risks would affect the community. This project will produce a final Climate
Change Vulnerability Assessment for Glades County that meets all Florida Statutory requirements. This will qualify Glades County to access additional state funding sources.
CCMP Elements Implemented: Potentially all CCMP elements
Partners and Roles: CHNEP (Funder), Glades County
Outputs/Deliverables Milestones
▪ Data Collection and Analysis
▪ Vulnerability Modeling and Analysis (including stormwater, social, etc.)
▪ Summary of Current and Project Climate Changes
▪ Climate Change Vulnerability Assessment for Glades County that meets state Statutory requirements resilience and adaptation to climate change impacts; in assisting restoration of wetlands that act as carbon sinks and restoration of freshwater hydrological flows that can mitigate saltwater intrusion from sea level rise.
2) “Take Decisive Action to Advance Environmental Justice and Civil Rights” by promoting EJ and protecting civil rights at the federal, state, and local levels to identify and address additional
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 25 of 30
Estimated Timeline: FY26-FY28
Task 3.12 Hendry County Comprehensive Vulnerability Assessment
Project Objective: To identify local climate change impacts and vulnerabilities and present adaptation responses that can help reduce community vulnerability and/or increase resilience in Hendry County, Florida.
Project Description: This project will use the climate adaptation planning process to conduct public workshops and data analysis to identify pre-existing conditions and climate stressors, including vulnerability modeling to develop recommended Adaptation Action Areas (AAA’s) for Hendry County. The Consultant will gather and update the County’s vulnerability assessment utilizing new elevation data, updated sea level rise projections, shoreline information, capital project data, social vulnerability index, and stormwater management data. The updated vulnerability modeling with new elevation data will be used to determine infrastructure and habitat impacts as well as areas of increasing vulnerability for a 2030, 2060, and 2100 sea level rise assumption horizon. Using the best available data, the contractor will also incorporate an analysis of stormwater management and social vulnerability using best practices such as the Center for Disease
Control's Social Vulnerability Index or other evaluation strategy (identifying vulnerable populations and potential public health risks).That information and input will be synthesized into a summary of current and projected climate changes for the community. The contractor will then use these vulnerability assessments to develop proposed adaptation strategies. One of the foundational concepts of Fla Stat 380.093 and FEMA’s
CRS program is to assess the flood risk of a community using best available tools, data, and methodologies.
The larger goal of both programs is to capture multiple types of weather-related scenarios to project and model how various flood risks would affect the community. This project will produce a final Climate
Change Vulnerability Assessment for Hendry County that meets all Florida Statutory requirements. This will qualify Hendry County to access additional state funding sources.
CCMP Elements Implemented: potentially all CCMP elements
Partners and Roles: CHNEP (Funder), Hendry County
Outputs/Deliverables Milestones
▪ Data Collection and Analysis
▪ Vulnerability Modeling and Analysis (including stormwater, social, etc.)
▪ Summary of Current and Project Climate Changes
Outcomes
▪ Climate Change Vulnerability Assessment for Hendry County that meets state Statutory
3) “Tackle the Climate Crisis” by reducing emissions that cause climate change and accelerating resilience and adaptation to climate change impacts; in assisting restoration of wetlands that act as
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 26 of 30 from sea level rise.
4) “Take Decisive Action to Advance Environmental Justice and Civil Rights” by promoting EJ and protecting civil rights at the federal, state, and local levels to identify and address additional
Estimated Timeline: FY26-FY28
Coastal & Heartland National Estuary Partnership FY24-FY26 BIL Work Plan Page 27 of 30
Task 4 Watershed Coordination
Work Plan Objective: To coordinate partner efforts around protection and restoration on a watershed scale.
Description: CHNEP to coordinate protection and restoration efforts including mapping, monitoring, reporting (including in the annual development of the Government Performance and Review Act (GPRA) report). Additionally, CHNEP staff will provide technical support in watershed initiatives such as: Southern
Water Use Caution Area (SWUCA) Recovery Strategy, Minimum Flows and Levels, Reasonable Assurance
Plans, Basin Management Action Plans, Southwest Florida Comprehensive Watershed Management Plan, Charlotte Harbor Flatwoods Initiative, Lehigh Watershed Initiative, South Lee County Watershed Initiative, and Caloosahatchee River Watershed Protection Plan. Southwest Florida Estuarine Restoration Team
(SWERT) facilitates region-wide estuarine habitat restoration that addresses endangered smalltooth sawfish critical habitat. CHNEP also participates in state and federal processes to identify landscape scale conservation corridors with public and private partnerships to provide habitat and species migration and climate change adaptation. Additionally, CHNEP participates in Everglades Restoration projects relevant to the CHNEP Study Area; this includes participating on the Science Coordination Group on behalf of
Southwest Florida. As opportunities arise, CHNEP also assists partners in conducting restoration activities.
CCMP Elements Implemented: All
Partners: CHNEP, Florida Gulf Coast University, Florida SeaGrant, Coastal Wildlife Club, Lee County
Parks and Recreation Department, Lee County Department of Natural Resources, Charlotte Harbor
Environmental Center, Sanibel-Captiva Conservation Foundation, Friends of Charlotte Harbor Aquatic
Preserves, Lee County Conservation 2020 Program, Calusa Land Trust, City of Fort Myers, Mote Marine
Lab, Sarasota Estuary Program, and Tampa Bay Estuary Program.
Outputs/Deliverables Milestones
▪ GPRA Report
▪ Technical support for Charlotte Harbor Flatwoods Initiative, Lehigh Watershed Initiative, & South
Lee County Watershed Initiative
FY 24 Budget
EPA 320 Funds: Staff Time
FDEP Funds: Staff Time
SWFWMD Funds: Staff Time
Total Budget: Staff Time
Outcomes
▪ Improved resource management
▪ Annual summaries of partners’ restoration activities through the GPRA report
▪ Increased…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .